Strategic Action Planning for Revival of Bangalore Lakes

Presentation by

Chairman, KSPCB

04-04- 2013Hotel Taj West End

Bangalore

Page 2: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Lakes/Tank Rejuvenation initiatives Series of Stakeholders consultation meets on Rejuvenation of lakes/tanks Insisting Industries/Developers to take up Tanks for improvement under

Corporate Social Responsibility

2

View of Stakeholders consultation-Hennagara Gram Panchayat

Page 3: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Criteria for lake rejuvenation projects• Lake should be small.• Lake should be situated in semi urban areas.• It should have less litigation & encroachments.• There shall not be entry of sewage.• The rejuvenation budget should be small

approx 50Lakhs• It should be possible to complete in 6 months• The ownership of the lake will be with ULB’s• There will be a board of the sponsorers

3

Page 4: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Finance for Lake Rejuvenation Projects

• Karnataka State Pollution Control Board Cess Funds

• Industries, Developers & other stakeholders as a part of Corporate Social Responsibilities

• Donors from different organizations of the society

4

Page 5: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Action taken with BWSSB & Suggestion given

• Collected water cess arrears and amount will be invested in the projects taken by BWSSB for rejuvenation of lakes.

• Insisted to discharge sewage water into lake after treatment.

• A proposal for pumping of treated water to Bangalore University campus.

• Initiated action on diversion of waste water from open drain to manhole, which ultimately joins to nearest treatment system, then to lakes.

5

Page 6: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Construction of silt trap in stages will reduce the flow of sewage in the drain gradually.

Action not yet taken to utilise the full capacity of V.Valley STP(only 30% being used).

Entire BBMP area has to be covered by the BWSSB and any direct discharge from the erstwhile CMC area into any lakes has to be prevented.

BWSSB has to enter into an agreement with horticulture Department, Forest Department, BDA for programmes such as stone pitching, beautification by gardening, making walkway etc.

Sewage in its septic condition to the tune of about 12 to 15 MLD (Peenya and other area) is bypassed from Madavara lake and the same further joins T.G.Halli Catchment. The same can be uploaded into Nagasandra STP which is operating at 30% its capacity.

The sewage treatment/diversion at V.Valley region is below par.

Page 7: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Lakes/Tank Water Quality improvement interventions

Taken up issue of arresting sewage flow into lakes with BWSSB –Inflow to STPs reached 63% as on 28-2-2013 of installed capacity (721 MLD)

Improved sewage inflow into K.R.Puram STP by diverting sewage from the near by open drain thereby augmenting flow from 6 MLD to 10 MLD

• Diversion Dyke made of SSM-Sewage flowing into STP

(1 ft depth trench beneath has been made)

7

Page 8: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Lakes/Tank Water Quality improvement interventions

• Date of Completion 22-01-2013

• Board adopted policy not to permit discharge of treated effluent into water body & to promote use of same for agriculture /Recycle for the secondary purpose

• Board is monitoring water quality of 66 lakes in Bangalore

8

View of Clear Treated Sewage

Entering the K.R.Puram lake

Page 9: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Lakes/Tank Water Quality improvement interventions

9

View of Clear Treated Sewage

Entering the K.R.Puram lake

Page 10: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

B.Hosahalli lake Before & After Rejuvenation

10

Page 11: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Bisleri International

Lake and Lake Type Borewell Recharging Unit

Page 12: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Status of Pushkarni’s at Chitradurga

12

Page 13: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Status of Pushkarni’s at Chitradurga

13

Page 14: Strategic Action Planning for Revival of Bangalore Lakes_KSPCB

Thank You