Page 1: SENIOR DESIGN PROJECT

Patriot, MA Office Park Development

Back Bay Engineering Group

Consultant: Tetra Tech Rizzo

Page 2: SENIOR DESIGN PROJECT

Project Overview Client: Office Parks, Inc. (OPI) Site Location: Patriot, MA 23.1 acres of wooded land Two 40,000 SF (footprint) office buildings Each building provides 120,000 SF of office space

and contains 3 stories OPI requires:

Concepts Permit Applications and Documents Engineering Documents Cost Effective Design

Page 3: SENIOR DESIGN PROJECT

EXISTING CONDITIONS

Site Boundary

Wetland

Littleton Rd.

Tree LineExisting Structures

Martin St.

Page 4: SENIOR DESIGN PROJECT

Challenges

Grading Existing Elevation Range: 206 – 257’ Minimize Net Cut/Fill

Fulfilling Parking Lot Requirements Large Impervious Area

High Flows of Runoff

Page 5: SENIOR DESIGN PROJECT

Guidelines

Existing conditions plan and wetland delineation

Patriot, MA local Zoning By-Law MA Wetland Protection Act and

Regulations MA DEP Stormwater Handbook ADA Accessibility Guidelines for

Buildings and Facilities (ADAAG) Guidelines set forth in the Request for

Proposal

Page 6: SENIOR DESIGN PROJECT

Three Conceptual Designs

Page 7: SENIOR DESIGN PROJECT

CONCEPTUAL #1

Page 8: SENIOR DESIGN PROJECT

CONCEPTUAL #2

Page 9: SENIOR DESIGN PROJECT

CONCEPTUAL #3

Page 10: SENIOR DESIGN PROJECT

Final Design

Page 11: SENIOR DESIGN PROJECT

Site Layout

Page 12: SENIOR DESIGN PROJECT

Requirements

Page 13: SENIOR DESIGN PROJECT

Grading

Minimize net cut/fill Maximum Slopes:

Driveways: 6.5% Parking Lot:

• < 100’ of Building: 2.0%• > 100’ of Building: 4.0%

Landscape:• 2 to 1 slope (50%) require retaining wall

Page 14: SENIOR DESIGN PROJECT

Grading

Page 15: SENIOR DESIGN PROJECT

Cut/Fill Analysis

Page 16: SENIOR DESIGN PROJECT

Cut/Fill Quantities

Net Cut: 5,560 cy Ledge: 376 cy

http://www.escocorp.com/markets/mining/images/excavator_lg.jpg

Page 17: SENIOR DESIGN PROJECT

Drainage

25 year storm design Determine Drainage Areas Pipe Sizing

Rational Method

Detention Pond Sizing SCS Method

Page 18: SENIOR DESIGN PROJECT

Drainage Plan

Page 19: SENIOR DESIGN PROJECT

Watershed Area

DB - 1

DB - 2

DB - 3

DB - 4

Page 20: SENIOR DESIGN PROJECT

Existing Conditions

Existing Condition

25 Year Storm

Qp = 14.98 CFS

Wetland Watershed - Existing Condition

Page 21: SENIOR DESIGN PROJECT

Detention Basin 1 Profile

Culvert to Detention Basin 2

Page 22: SENIOR DESIGN PROJECT

Detention Basin 1 Hydrograph

Qout Qin

Page 23: SENIOR DESIGN PROJECT

Detention Basin 2 Profile

Qp = 2.12 CFS

Weir to Detention Basin 3

Page 24: SENIOR DESIGN PROJECT

Detention Basin 2 Hydrograph

Qout Qin

Page 25: SENIOR DESIGN PROJECT

Detention Basin 3 Profile

Qp = 12.08 CFS

Culvert to Detention Basin 4

Page 26: SENIOR DESIGN PROJECT

Detention Basin 3 Hydrograph

Qout Qin

Page 27: SENIOR DESIGN PROJECT

Detention Basin 4 Profile

Qp = 13.00 CFS

Culvert to Wetlands Final Qp < Initial Qp

Page 28: SENIOR DESIGN PROJECT

Detention Basin 4 Hydrograph

Qout Qin

Page 29: SENIOR DESIGN PROJECT

Utilities Water

Water for both domestic and fire use is drawn from abutting Martin St.

An 8” PVC line ties into the building for domestic use

A 12” PVC line ties into the building for fire with 6” lines feeding each hydrant

Sewer Wastewater is drained from the site through 8”

PVC pipes utilizing gravity

Page 30: SENIOR DESIGN PROJECT

Utilities (continued)

Electrical Electrical connection to existing line on Littleton Road 4-5” PVC conduits carried in a 2’ duct bank to a transformer on

N.E. corner of site Secondary lines connect to mechanical rooms of each building

Telecommunications Lines connect to utility pole on Martin St. 6-4” conduits carried in a 2’-6” duct bank to each building

Gas A 4” PVC runs to each building from a connection on Martin St.

Page 31: SENIOR DESIGN PROJECT
Page 32: SENIOR DESIGN PROJECT

Construction Cost Estimate

Page 33: SENIOR DESIGN PROJECT

Permit

Massachusetts DEP WPA Form 5 –

Order of Conditions

Page 34: SENIOR DESIGN PROJECT