Case studies from around the world help explain what is working in the world of Hadoop, real time analytics and internet connected devices.
IBM delivers a significant data warehouse modernization programme to General Motors
Toby Woolfe, Big Data Industrial and Automotive Solutions Leader, IBM Europe
[email protected] +44 7795 328 742
© 2014 IBM Corporation2
A New Era of Smart
We are on the precipice of awareness of, and adoption of, internet connected devices far beyond the Smartphone...
Devices: 145 actuators, 70 on-board computers, 4700 relays and 70 sensors, including radar, sonar, accelerometer, camera, rain sensors.
433MB per minute1 car year = 1TB
Plus existing enterprise data, social media data, 3rd party suppliers,...etc
© 2014 IBM Corporation3
A New Era of Smart
3
But how fast does information currently get delivered?
Monthly reporting?Based originally on the lunar cycle, the Julian Calendar was introduced by Julius Caesar in 46BC
Quarterly reporting?Celebrated by Druids for centuries, the four seasons result from the yearly revolution of the earth around the sun and the tilt of the earth’s axis relative to the plane of revolution.
Annual reporting?In temperate and polar regions, the seasons are marked by changes in the intensity of sunlight that reaches the Earth's surface, variations of which may cause animals to go into hibernation or to migrate, and plants to be dormant
Weekly reporting?Recorded in Babylonian carvings dated 6th
century, the origin of the 7 day week was probably based on a quarter of the lunar cycle (though inaccurate)
© 2014 IBM Corporation4
A New Era of Smart
4
“GM Opens New Data Center Modeled on Google, Facebook”CIO Randy Mott launched a new $130
million data center
Chief Executive Dan Akerson said ”If we are going to win, we must turn IT into a competitive advantage and not treat it as something that is just a utility,”
The IT Operations and Command Center in the $130-million Enterprise Data Center at the General Motors Technical Center in Warren, Michigan.
© 2014 IBM Corporation5
A New Era of Smart
5
GM’s people, process and technology evolution
GM has hired about 1,500 software developers and engineers, up from “close to zero” just one year ago, according to Tim Cox, CIO of GM global development services
About 70% of the 10,000 IT staff will be focused on innovation
Until recently, GM was using 23 different data centers. Now the company is moving to two
The site in Warren has the capacity to hold more than 10,000 ‘pizza box’ size servers, as well as smaller-size servers and larger mainframes
The data warehouse incorporates both the cutting edge IBM BigInsights for Hadoop technology as well as more traditional Massively Parallel Processing technologies historically used for data warehousing
Source/thanks to
© 2014 IBM Corporation6
A New Era of Smart
6
General Motors wiki
Business profile
Global vehicle sales leader for 77 consecutive years from 1931 – 2007
212,000 staff in 157 countries
Business problem
GM has issued 45 recalls in 2014 involving 28 million cars worldwide
The cost of one recall due to faulty ignition switches, which has been linked to at least 13 deaths, is $1.3 billion
IT transformation
General Motors (GM) is in the process of constructing a single global information warehouse that will become the foundation for all business analytics and decision support across the enterprise.
The business objectives are – to reduce operating expenses for data warehouses by 25-30%– deliver 10x the measurable business value– double IT project capability– and integrate existing data warehouse systems with new technology to offload
data, reduce latency, reduce costs and improve performance.
© 2014 IBM Corporation7
A New Era of Smart
7
Abstract: IBM delivers a significant data warehouse modernization programme to General Motors
High performance and continuously available data management environment
329,000 users with a 10% concurrency rate
Grow to approximately one petabyte in size over three years
IBM proposed a centralized enterprise architecture leveraging a traditional data warehouse matched with IBM Big Insights Hadoop technology for big data analytics
Data types:• Inventory control of parts• Manufacturing equipment and
assembly line data• Warranty and services data from
dealers• Telemetry data from vehicles • Customer services and social
media data
© 2014 IBM Corporation8
A New Era of Smart
8
Big data = disparate data!
© 2014 IBM Corporation9
A New Era of Smart
9
Probabilistic matching
© 2014 IBM Corporation10
A New Era of Smart
10
Analyst validation of key IBM technologies....
....and Analyst validation of IBM potential future phase technologies....
© 2014 IBM Corporation11
A New Era of Smart
11
Capabilities required1. Efficient data protocols2. Real time analytics3. Capture all data to a landing zone4. High performance analytics platform5. Application Platform6. Data governance & integration
© 2014 IBM Corporation12
A New Era of Smart
12
IBM conclusions applicable to enterprise data warehouse modernisation learned from work with GM
GM’s objectives published in WSJ: –Reduce operating expenses for data warehouses by 25-30%–Deliver 10x the measurable business value–Double IT project capability–Integrate existing data warehouse systems with new technology
to offload data, reduce latency, reduce costs and improve performance
Educate enterprise architecture staff on the new disruptive technology capabilities delivered from Hadoop, and its integration into existing data architectures
Engage in a revue of data warehouse architecture to harness the cost savings, speed advantages and business focus that new technologies such as IBM BigInsights for Hadoop brings to market
Experiment with new data asset/business objective combinations with IBM’s Big Data experts
© 2014 IBM Corporation13
A New Era of Smart
13
For a volume production car fleet using telematics data, IBM correctly predicted warranty codes/claims 43 days out with 86% accuracy and only 1% false positives
For a new electric car model, IBM predicted warranty claims 60 days out with 96% accuracy and 1% false positives on 619 vehicles using Big Data and analytics technology
Case study illustrates the hidden value of machine data
© 2014 IBM Corporation14
A New Era of Smart
14
Broad range of role based visualisation and analytical capabilities
SPSS Predictive analytics R Script support Integration with Cognos BI
Data scientist Business person
Spreadsheet visualisation of data 360 degree view of machine/client/location
Delivered using the BigInsights wizard to accelerate the use of Hadoop data
© 2014 IBM Corporation15
A New Era of Smart
15
BigInsights visualisation examples
2 - Sort, filter etc.
1 –Hadoop raw data in spreadsheet format
© 2014 IBM Corporation16
A New Era of Smart
16
...and onto many kinds of analytical capability using Cognos
© 2014 IBM Corporation17
A New Era of Smart
How is Big Data Being Used in Industry?
Connected Vehicle V2V, V2C, V2I, V2X Automotive Telematics Real-time Alerts
Geospatial Analytics Predictive Failsafe Analytics
Driver Specific Predictive Analytics Condition Based Monitoring
After Sales Fraud Analytics
Regulatory Analytics Social Media Analytics Warranty Analytics Customer 360 Next Best Action
Marketing & Sales Social Media Analytics
Text Analytics Customer 360
Actionable Customer Intelligence
Next Best Action
Patent Analytics Social Media Analytics
Text Analytics Quality & Warranty Analytics
Product Development & Engineering
Manufacturing & Quality
Predictive Maintenance Quality Early Warning Operational Efficiency Supply Chain Analytics
© 2014 IBM Corporation18
A New Era of Smart
18
Experiment with Hadoop
© 2014 IBM Corporation19
A New Era of Smart
Suggested next action:
Create an inventory of your structured and unstructured data and assess where business value will be found
Inte
rnal
Exte
rnal
Structured Unstructured
Relatively easy to acquire Difficult to
acquire
Complaints
MDMCustomer
Data
FinancialData
Txn History
PaymentHistory
Warranty History
WorkflowData
CallRecordings
Maintenance records
Activities
Emails
WebTraffic
Shipping schedule
data
TelematicData
Machine failure data
GeolocationData
GoogleAlerts
CatastrophicData
MachinePerformance
Data
Social MediaData
© 2014 IBM Corporation20
A New Era of Smart
20
17TH ~ 18th NOV 2014MADRID (SPAIN)