Upload
ecofys
View
300
Download
0
Embed Size (px)
Citation preview
by Felix von Blücher
September 15, 2016
Germany’s opening of the EEG
Cross-border renewables auctions
© ECOFYS | |
Background – Why cooperate on renewables support?
Gains from cooperation:
> Cost efficiency: RES deployment where potential is high
> Using regional synergies/portfolio effects (e.g. diversification of RES)
> More competition (especially for small Member States)
> Policy/knowledge transfer
Felix von Blücher15/09/20162
© ECOFYS | |
Background – Why cooperate on renewables support?
Source: “Cooperation between EU MemberStates under the RES Directive”, Klessmann et al. (2014)
Felix von Blücher15/09/20163
© ECOFYS | |
Background – EU Commission versus Member States
Felix von Blücher15/09/2016
> Internal energy market
> Harmonisation of energy
policy
> EU-Quota/Harmonisation of
RES support
> Energy mix under national
sovereignty
> Member States are reluctant
to coordinate their policies
> Fragmented national RES
support instruments
EU Commission Member Statesversus
No European solution for challenge of transforming the energy system
Potential gains of policy coordination remain untapped
4
© ECOFYS | |
Content
I. A new push for renewables cooperation in Europe
II. Germany’s opening of the EEG
1. Implementing “reciprocity”
2. The German-Danish test case
III. Challenges of conducting cross-border auctions
1. Deviating market conditions
2. Differing preferences for support systems
IV. Conclusions
Felix von Blücher15/09/20165
© ECOFYS | |
Ecofys‘ expertise in renewables auctions and cross-
border cooperation
Ecofys has a strong track record in designing renewables cooperation and
renewables support policies:
> Supporting the set-up and design of cooperation:
– The Federal Ministry for Economic Affairs and Energy
– European Commission: “Cooperation between EU Member States under the
Renewable Energy Directive and interaction with support schemes”
(http://res-cooperation.eu/)
> Supporting the implementation of auctions for renewable energy support:
– The Federal Ministry for Economic Affairs and Energy
– European Commission: AURES (AUctions for Renewable Energy Support)
(http://auresproject.eu/)
Felix von Blücher15/09/20166
© ECOFYS | |
Renewables Cooperation in Europe
> The EU Renewable Energy Directive (Directive 2009/28/EC) introduced
three cooperation mechanisms:
– Statistical transfer
– Joint projects
– Joint support schemes
> Primary aim: facilitate achievement of 2020 renewables targets through
financing RES generation in Member States with lower-cost RES
potential
> Very limited use of cooperation mechanisms so far:
– Joint support scheme between Sweden and Norway
– Some countries explore statistical transfer
Felix von Blücher15/09/20168
© ECOFYS | |
Reasons for limited use
> Political barriers:
– Public acceptance
– Uncertainty on continuity of the RES framework beyond 2020
> Technical barriers:
– Uncertainty on costs and benefits
– Uncertainty on design options of cooperation mechanisms
– Lacking transmission infrastructure and market integration
> Legal barriers:
– Potential incompatibility of cooperation mechanisms with national legislation
Felix von Blücher15/09/20169
© ECOFYS | |
RES cooperation is gaining momentum
> State Aid Guidelines for Environmental Protection and Energy 2014-
2020:
– Several Member States are being forced to open their support (non-
discrimination of foreign RES electricity, Art. 30/110 TFEU)
– Strong push for convergence of national support schemes based on auctions
(default by 2017)
> Cooperation may be key element of the new EU Energy framework:
– Council Conclusions 2014: 2030 governance system shall “facilitate
coordination of national energy policies and foster cooperation”
– New Renewable Energy Directive may contain further provisions
Felix von Blücher15/09/201610
© ECOFYS | |
Agreement between Germany and EU Commission
> State aid clearance for EEG 2014:
– As of 2017: Germany to open 5% of the newly installed capacity („partial
opening“) = 250 MW per year
> In 2016: „Pilot Opening” Auction For Ground-Mounted PV:
– Developing a concept for the opening
– Test case: carrying out first cross-border auctions of up to 100 MW
– Lessons learned will help to set the rules for opening up auctions for other
renewable technologies (partial opening)
Felix von Blücher15/09/201612
© ECOFYS | |
Requirements for the opening
Three requirements for the opening
(§88, section 2-4 EEG 2014):
1. Principle of reciprocity
2. ‘Physical’ import or comparable effect
3. Cooperation agreement
Felix von Blücher15/09/2016
Requirements for the opening:
1. ‘Physical’ import (electricity delivered to DK)
2. Cooperation agreement
Obligation to open 5% as of 2017
= 250 MW pa
Pilot 2016 = up to 100 MW
Obligation to open 6% of the
tendered capacity in 2015 & 2016
= 2,4 MW in 2016
13
© ECOFYS | | 14
II. Germany’s opening of the EEG
1. Implementing “reciprocity”
15/09/2016 Felix von Blücher
© ECOFYS | |
Reciprocity – Basic models to open an auction
1. „Unilateral opening“ – Only one country opens its support
scheme; the partner country contributes to the support
payments.
2. „Mutual opening“ – The cooperation countries both open their
domestic auction schemes to another.
3. Joint auction with separate support scheme – The
cooperation countries set up a joint auction, awarded projects
are then assigned to one country’s support scheme.
4. Joint auction with joint support scheme – The cooperation
countries set up a joint auction and a joint support scheme
In
ten
sit
yo
f co
op
erati
on
Felix von Blücher15/09/201615
© ECOFYS | |
Reciprocity – Basic models to open an auction
1. „Unilateral opening“ – Only one country opens its support
scheme; the partner country contributes to the support
payments.
2. „Mutual opening“ – The cooperation countries both open their
domestic auction schemes to another.
3. Joint auction with separate support scheme – The
cooperation countries set up a joint auction, awarded projects are
then assigned to one country’s support scheme.
4. Joint auction with joint support scheme – The cooperation
countries set up a joint auction and a joint support scheme
Option 2 and 3 shall be tested in the German pilot opening
Felix von Blücher15/09/2016
In
ten
sit
yo
f co
op
erati
on
16
© ECOFYS | |
Reciprocity – Basic models to open an auction
1. „Unilateral opening“– Only one country opens its support
scheme; the partner country contributes to the support
payments.
2. „Mutual opening“ – The cooperation countries both open their
domestic auction schemes to another.
3. Joint auction with separate support scheme – The
cooperation countries set up a joint auction, awarded
projects are then assigned to one country’s support
scheme.
4. Joint auction with joint support scheme – The cooperation
countries set up a joint auction and a joint support scheme
Germany and Denmark will conduct “mutually-opened” auctions
Felix von Blücher15/09/2016
In
ten
sit
yo
f co
op
erati
on
17
© ECOFYS | |
Mutual opening – Basic concept
> Mutually-opened auction:
– Two countries each open their separate auction to bids from the
partner country
– Relatively easy because each country sets out the conditions for its
own auction
– Agreement necessary on basic parameters but not on the details
– Large flexibility for each auction design
Felix von Blücher15/09/201618
© ECOFYS | | 19
II. Germany’s opening of the EEG
2. The German-Danish test case
15/09/2016 Felix von Blücher
© ECOFYS | |
Danish-German Test Case
> Danish-German test case:
– First of its kind
– Test case character: single pilot auction
– Intensive exchange on conditions, auction design, information exchange etc.
– Involved: Ministries, agencies, regulators and TSOs
> Cooperation agreement signed summer 2016:
– Sets the basic conditions of the cooperation
– Data exchange
– Cross-border payment of support
– Accounting of RES production for national target achievement
Felix von Blücher15/09/201620
© ECOFYS | |
Danish-German Test Case
> Danish-German auctions:
– Technology: DE: PV (only ground-mounted)
DK: PV
– Volume: DE: 50 MW, all is auctioned cross-border
DK: 20 MW, up to 4.799 MW auctioned cross-border
– Physical import: direct interconnection
– Accounting of
RES production: towards funding country
Felix von Blücher15/09/201621
© hydyl/Thinkstock
© ECOFYS | |
Which rules apply?
> Starting point: national auction design of each cooperating state
> Agreement on some basic parameters (volume, etc.)
> Basically: each country sets out the support conditions for its own auction
(market premium, etc.)
> Deviations from national auction design necessary in case rules are not
applicable in cross-border context (material pre-qualification criteria, etc.)
or against interests of cooperating country
> Bidders must know all conditions up front
> Rights and duties should be the same for all bidders, however no
alignment of exogenous conditions
Felix von Blücher15/09/201622
© ECOFYS | | 23
III. Challenges of conducting cross-border auctions
1. Deviating market conditions
15/09/2016 Felix von Blücher
© ECOFYS | |
Challenge: Deviating market conditions
> Market conditions are more heterogeneous in cross-border auctions
> In auctions, only the lowest bids will receive support
> Challenge: public acceptance problems if all successful bidders come from
only one of the participating countries (trade-off between efficiency and
acceptance)
To what extent do we need to „level the playing field“ by aligning
framework conditions to ensure a balanced auction result?
Felix von Blücher15/09/201624
© ECOFYS | |
Conditions that influence LCOE
LCOE/
Minimum bid level
Project specific factors
Investment costs, planning processes, etc.
Natural potential
Solar radiation, available sites, etc.
Economic and energy-economical conditions
Market prices and values, interest rates, etc.
Regulatory conditions
Auction design elements, Location-specific conditions: taxes, planning regulation, site restrictions, etc.
Felix von Blücher15/09/201625
© ECOFYS | |
Conditions that influence LCOE
Felix von Blücher15/09/2016
LCOE/
Minimum bid level
Project specific factors
Investment costs, planning processes, etc.
Natural potential
Solar radiation, available sites, etc.
Economic and energy-economical conditions
Market prices and values, inflation, interest rates, etc.
Regulatory conditions
Auction design elements, Location conditions: taxes, planning regulation, site restrictions, etc.
Different regulatory conditions can lead to distortive effects.
26
© ECOFYS | |
Levelling the playing field for auction bidders
Do regulatory conditions have to be aligned to ensure an efficient allocation of support payments?
> No general answer
> Detailed analysis of the relevance of distortive effects required, e.g. through cash-flow model:
> Pragmatic approach towards creating a level playing field:
– Not all differences lead to (strong) distortive effects
– Not all regulations can be harmonised in the short term
Felix von Blücher15/09/201627
e.g. 1% higher business tax = 0,05% higher LCOE
Inte
rest
rate
Investm
ent
costs
Busin
ess
tax
Full
load
hours
Stronginfluence
Lowinfluence
Stronginfluence
© ECOFYS | | 28
III. Challenges of conducting cross-border auctions
2. Differing preferences regarding support systems
15/09/2016 Felix von Blücher
© ECOFYS | |
Differing national preferences
Issue of aligning rules:
> National regulations are tailored to national policy goals and market
conditions.
> Cooperating countries need to develop an understanding of how much
they want to deviate from the national regulations / auction design to level
the playing field for bidders.
> Necessary degree of adapting or even alignment of regulation depends
on:
– Distortive effect
– Whether or not it is part of:
● auction design, or
● location-specific conditions defined outside of the auction
– The model of cooperation:
● Mutual opening
● Joint auctions
Felix von Blücher15/09/201629
© ECOFYS | |
Adapting the rules
Felix von Blücher15/09/2016
Mutually-opened auctions
Joint auctions
Auction Design Element
Member States may draft auction designs
individually(partial aligment)
Single auction design required
Local Specific Condition
Rules and conditions of the country apply in which the installation is to be implemented
30
Mutually-opened auctions – deviations from
national design only partly necessary
Joint auctions – require alignment
© ECOFYS | |
Auction design elements of pilot cross-border auctions
Felix von Blücher15/09/201631
Design element German auction Danish auction
Volume 50 MW 20 MW (only 2,4 MW opened)
Bid size 10 MW 2,4 MW
Market premium Floating premium based on local market value
Fixed premium
Guarantees of origin
Not allowed Allowed
Self-consumption Excluded Excluded
Material Pre-qualification
None(location specified)
None(location specified)
Financial Pre-qualification
70 €/kW 24 €/kW
Transferability Restricted Not possible
Member States draft auction designs individually, deviations
from national design only partly necessary
© ECOFYS | |
Location-specific conditions of pilot cross-border auctions
Felix von Blücher15/09/201632
Location-specificconditions
Bidders from Germany Bidders from Denmark
Permitted sites German site restrictions (only ground-mounted) for all bidders
Danish site restrictions for all bidders
Exception: roof-top PV excluded for DE-supported projects
Compensation during curtailment
Yes Yes
Remunerationduring negative prices
Yes, 6 h-rule applies to all bidders in German auction
No remuneration for all bidders in Danish auction
Rules and conditions of the country apply in which the
installation is to be implemented
© ECOFYS | |
Alignment of design elements in case of a joint auction
Felix von Blücher15/09/201633
Designelement
German auction Danish auction
Volume 50 MW 20 MW (only 2,4 MW opened)
Bid size 10 MW 2,4 MW
Market premium Floating premium based on local market value
Fixed premium
Guarantees of origin
Not allowed Allowed
Self-consumption Excluded Excluded
Material Pre-qualification
None(location specified)
None(location specified)
Financial Pre-qualification
70 €/kW 24 €/kW
Transferability Restricted No possible
Cooperating countries need to agree on a single auction design
in order to avoid distortive effects
© ECOFYS | |
Alignment of location conditions in case of a joint auction
Felix von Blücher15/09/201634
Location-specificconditions
Bidders from Germany Bidders from Denmark
Permitted sites German site restrictions (only ground-mounted)
Danish site restrictions for all bidders
Exception: roof-top PV excluded for DE-supported projects
Compensation during curtailment
Yes Yes
Remunerationduring negative prices
Yes, 6 h-rule No remuneration
Rules and conditions of the country apply in which the
installation is to be implemented
© ECOFYS | |
Conclusions – I
Gains from cooperation:
> Cooperation bears a lot of potential to reduce support expenditures
> Win-win: cooperation gains must be visible for all partners
Setting the rules:
> Setting up cross-border auctions requires looking into the details
> Pragmatic approach: no perfect level playing field, no perfect allocation of
costs and benefits
> Trade off: efficiency gains versus political acceptability
Felix von Blücher15/09/201636
© ECOFYS | |
Conclusions – II
Varying intensity of cooperation:
> Necessity to align the rules depends on the model of cross-border auctions
> Choice of model allows for custom-made solutions
Cooperation is easier to implement when:
> Countries have similar power systems and energy policies, especially for
renewables support
> Countries are neighbours (direct interconnection)
“Regional” cooperation is easier to implement than “EU”-wide cooperation,
or cooperation between dissimilar countries.
Felix von Blücher15/09/201637
© ECOFYS | |
Thank you!
> For further information or in case of questions, please contact us:
Felix von Blücher Malte Gephart Corinna Klessmann
[email protected] [email protected] [email protected]
38 15/09/2016 Felix von Blücher