Beth Vogelsang's presentation from October 4th, 2013 at the Colorado APA Conference in Vail regarding high speed rail and its interface with stations and land uses.
Citation preview
1
Stations: Balancing HSR and Community
Fewer stations means retaining higher speeds; better travel times; stronger ridership
Accommodate regional travel Interface with local transit/transportation
HSR Station Parameters
2
9 Stations from Fort Collins to Pueblo including the Denver Metro area:
Fort Collins North Suburban DIA/Union Station South Suburban West Suburban Monument Colorado Springs (2) Pueblo
Front Range Stations
3
Mountain Stations -6 Stations: Idaho Springs, Silverthorne, Breckenridge, Vail, Beaver Creek, Eagle County Airport
4
15 system stations
15 acres of new development per station; Developable square footage 9 million Potential value over $2 billion Likely funding element of implementation
Benefits?
5
Functionality of the system Potential for development regionally Potential economic return statewide
Station Siting important to..
6
7
Where do we site these stations?
9
San Jose Diridon Station –
Today
San Jose Diridon Station –
Future
10
Public Personal Rapid Transit Consortium
SkyTran
Swift Tram, Inc
Technology Choice
Common Elements
11
◦ Platform◦ Parking
◦ Traffic circulation◦ Transit interface ◦ Passenger Drop-off
◦ Bicycle and PedestrianStation example California HSR
12
Typical Station
13
Platform Requirements
14
Parking Lot or Structure
15
Roadway infrastructure
16
Transit Connection
17
Development and Structured Parking options
1. Optimize Location for access/ridership2. Minimize Sprawl – Promote Infill
◦ Limit demand on resources◦ Leverage current investments
3. Maximize Connectivity ◦ Increase bicycle, pedestrian, transit◦ Consider first mile/last mile connections◦ Minimize parking footprint
18
Community Considerations
Anticipated level of ridership activity at station and operability needs
Origin or Destination? Collector or Distributor station
Role of parking vs. transit at the station
Potential for development surrounding site
Station acreage varies and depends on:
19
Concept Stations
20
station concept – 10 acre
21
22
6-8 acres
2-3 acres
4 acres
23
4 Story Structure - 150 spaces/deck acre 600 spaces
transit interface & passenger drop-off
24
pedestrian plaza
25
station concept – 20+ acres
26
27
10-12 acres
28
6 Story Structure - 150 spaces/deck acre 2 acres - 1500 spaces
transit interface – separate from passenger drop-off
29
30
Transit Distribution from Silverthorne Station
31
32
33
34
35
36
80’ envelope, 600-1000’ platform, 15 acre
site
37
Idaho Springs
Urban Design and Context
38
Are cities willing to implement policies, station area plans and eventual rezoning to achieve
higher density residential and commercial development? Light freight?
Historic relevance
Community character
Compatible with surrounding land use? Compatible with regional plans?