24.11.2009
1
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Agile Planning
Artem Marchenko
AgilDays.ru, December 9, 2009
Artem Marchenko - background
© 2003–2009 Artem Marchenko and Mountain Goat Software®
24.11.2009
2
© 2003–2009 Artem Marchenko and Mountain Goat Software®
What’s a good plan?
• A good plan is one that supports reliable decision-making
• Will go from
• We’ll be done in the third quarter
• We’ll be done in August
• We’ll be done August 18th
© 2003–2009 Artem Marchenko and Mountain Goat Software®
What makes planning agile?
Is more focused on
planning than the plan
Encourages change
Results in plans that
are easily changed
Is spread throughout
the project
24.11.2009
3
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Starting assumptions
• We have a product backlog (prioritized feature
list)
• Items on the product backlog (user stories is my
preference) have been estimated in story points
or ideal days
• We have a team with a known velocity
• We’ll relax this assumption shortly
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Sprint 2
Sprints 3-4
An example with velocity=14
Sprint 1Story A
5
Story E
1
Story D
5
Story G
1
Story I
5
Story J
8
Story H
13
Story C
3
Story B
8
Story F
5
24.11.2009
4
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Release and sprint planning
Release Plan
Sprint
1
Sprint
2
Sprint
3
Sprints 4–7
8 hoursTask A
16 hoursTask B
5 hoursTask C
8 hoursTask D
© 2003–2009 Artem Marchenko and Mountain Goat Software®
•Sprint planning
•Estimating velocity
•Release planning
•Contracting on fixed-date
& fixed-scope projects
Agenda
24.11.2009
5
© 2003–2009 Artem Marchenko and Mountain Goat Software®
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Two approaches
• Velocity-driven sprint planning
• Commitment-driven sprint planning
24.11.2009
6
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Velocity-driven sprint planning
• “We finished 15 story points last time, let’s plan
on 15 story points this time.”
• Very unreliable in what will be accomplished
during an iteration
• Velocity is mostly useful over the long term
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Commitment-driven sprint planning
• Discuss the highest priority item on the product backlog
• Decompose it into tasks
• Estimate each task
• Ask ourselves, “Can we commit to this?”
• If yes, see if we can add another backlog item
• If not, remove this item but see if we can add another smaller one. Possibly by splitting the original story
24.11.2009
7
© 2003–2009 Artem Marchenko and Mountain Goat Software®
It looks something like this
• Code the abc class (8 hours)
• Code the user interface (4)
• Write test fixtures (4)
• Code the xyz class (6)
• Update performance tests (4)
As a user, I want ...
2
• Prototype the UI (8 hours)
• Demo UI to 3 outside users (3)
• Code new UI (12)
• Update documentation (3)
As a user, I want ...
3
Team can commit, so they continue...
26
26
© 2003–2009 Artem Marchenko and Mountain Goat Software®
time
1
2
time
24.11.2009
8
© 2003–2009 Artem Marchenko and Mountain Goat Software®
© 2003–2009 Artem Marchenko and Mountain Goat Software®
How to estimate velocity
Use historical values
Don’t, until you’ve run
a sprint or two
Forecast it
1
2
3
24.11.2009
9
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Forecasting velocity
• Just like commitment-driven sprint planning
• Estimate available hours for the sprint
• Repeat until full:
• Pick a story, break into tasks, estimate each task
© 2003–2009 Artem Marchenko and Mountain Goat Software®
An example
• Estimating available hours
Person Hours per Day Hours per Sprint
Sergey 4-6 40-60
Kimmo 5-7 50-70
Jarmo 2-3 20-30
Total 110-160
24.11.2009
10
© 2003–2009 Artem Marchenko and Mountain Goat Software®
... 20
... 50
8
6
12
Code the UI
Write test fixture
Code middle tier
Write tests 5
An example
As a frequent flyer, I
want to...3
As a user, I want to... 5
As a vacation planner,
I want to...5
As a frequent flyer, I
want to...2
Code the ... 12
Do the... 8
Document the... 8
Test the... 8
Analyze the... 4
Document ... 8
48 31
50
20
At 110-160 available hours per
sprint, what is the team’s velocity?
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Put a range around it
• You’re unlikely to have precisely forecasted the
exact velocity the team will average
• So, put a range around your velocity estimate:
Known team, domain,
technology
+5%
−10%
Unknown team,
domain, technology
+25%
−50%
+10%
−25%
†Numbers based on PMI advice on progressive
accuracy of estimates.
24.11.2009
11
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Expressing velocity as a range
200 ÷ 20 = 10
Estimated velocity
= 18
20
14
1.10
.75 200 ÷ 14 = 15
“Right now, before we start this project,
our best estimate is that it will take
between 10 and 15 sprints.”
Adjustments
from prior page
or intuition
Total of
estimates on
product
backlog
© 2003–2009 Artem Marchenko and Mountain Goat Software®
24.11.2009
12
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Create a range from historical
data
Sprints
Mean (Worst 3) = 28
Mean (Last 8) = 33
Mean (Best 3) = 37
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Predicting where we finish
At our long-term average we’ll finish here (5×33)
At our slowest velocity we’ll finish here (5×28)
At our best velocity we’ll finish here (5×37)
24.11.2009
13
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Planning on contracted projects
Fixed-date projectsFixed-scope projects
• There are times you need to do this
• So let’s look at some good techniques
• Better though is try for a collaborative
relationship with your customer
• “You’ll have this team for each sprint, can
direct them at the start of each, and stop
when you have enough”
A caveat
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Fixed-date planning
1. Determine how many sprints you have
2. Estimate velocity as a range
3. Multiply low velocity × number of sprints
• Count off that many points
• These are “Will Have” items
4. Multiply high velocity × number of sprints
• Count off that many more points
• These are “Might Have items”
How much can I get by <date>?
24.11.2009
14
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Fixed-date planning: an example
Desired
release date30 June
Today’s Date 1 January
Number of
sprints6 (monthly)
Low
velocity15
High
velocity20
6×15
6×20
Will have
Might
have
Won’t have
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Fixed-date contracting
6×15
6×20
Will have
Might
have
Won’t have
•You won’t likely win the contract
•But you’ll probably make money if
you do
If you write a contract
for just the will haves:
•You will likely win the contract
•But probably not make money on it
If you write a contract that
includes the might haves:
It’s a risk issue
Where do you want to be?
24.11.2009
15
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Fixed-scope planning
1. Sum all the backlog items the customer needs
2. Estimate velocity as a range
3. Divide total story points by high velocity
• This is the shortest number of sprints it could
take
4. Divide total story points by low velocity
• This is the “most” sprints it could take
When will all of this be done?
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Fixed-scope planning: an example
Total story points desired 120
Low velocity 15
High velocity 20
120÷20=
120÷15=
24.11.2009
16
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Fixed-scope contracting
•You’ll likely win the contract
•But may not make any money
If you write a contract
for the short duration:
•You probably won’t win the contract
•But will make money if you
If you write a contract
for the long duration:
It’s a risk issue
Where do you want to be?
© 2003–2009 Artem Marchenko and Mountain Goat Software®
Ranges
• Notice in both cases we had a range
• For a fixed date project, use a scope range:
• “By that date you’ll have all of these features and
some of these.”
• For a fixed-scope project, use a date range:
• “It will take us between 5 and 8 sprints to deliver all
of those features.”
24.11.2009
17
© 2003–2009 Artem Marchenko and Mountain Goat Software®