Department of Management 19 th Batch University of Dhaka Management Science (MGT-301) Pert & CPM Table of Contents 1 PERT & CPM ........................................................................................................................................................ 2 1.1 PERT ............................................................................................................................................................ 2 1.2 CPM ............................................................................................................................................................. 2 1.3 Differences between PERT & CPM............................................................................................................. 2 1.4 CRITICAL PATH ........................................................................................................................................ 2 1.5 Rules for drawing the network diagrams. .................................................................................................... 3 1.6 Network Representation: .............................................................................................................................. 3 1.7 Float (Slack) ................................................................................................................................................. 3 1.8 Examples ...................................................................................................................................................... 5 Courtesy of- Kamrul, Zonayed, and Fahad || Department of Management || University of Dhaka

Management science

Embed Size (px)

Citation preview

Page 1: Management science

Department of Management

19th Batch

University of Dhaka

Management Science (MGT-301) Pert & CPM

Table of Contents

1 PERT & CPM ........................................................................................................................................................ 2

1.1 PERT ............................................................................................................................................................ 2

1.2 CPM ............................................................................................................................................................. 2

1.3 Differences between PERT & CPM ............................................................................................................. 2

1.4 CRITICAL PATH ........................................................................................................................................ 2

1.5 Rules for drawing the network diagrams. .................................................................................................... 3

1.6 Network Representation: .............................................................................................................................. 3

1.7 Float (Slack) ................................................................................................................................................. 3

1.8 Examples ...................................................................................................................................................... 5

Courtesy of- Kamrul, Zonayed, and Fahad || Department of Management || University of Dhaka

Page 2: Management science

Management Science (MGT-301)

COURTESY OF- KAMRUL, FAHAD & ZONAYED || DEPARTMENT OF MANAGEMENT || UNIVERSITY OF DHAKA

2

1 PERT & CPM

1.1 PERT Program Evaluation & Review Technique – It is generally used for those projects where time required to

complete various activities are not known as a priori. It is probabilistic model & is primarily concerned for

evaluation of time. It is event oriented.

1.2 CPM Critical Path Analysis – It is a commonly used for those projects which are repetitive in nature & where one has

prior experience of handling similar projects. It is a deterministic model & places emphasis on time & cost for

activities of a project.

A project can be defined as a set of large number of activities or jobs (with each activity consuming time &

resources) that are performed in a certain sequence determined.

A network is a graphical representation of a project, depicting the flow as well as the sequence of well-

defined activities & events.

An activity (Also known as task & job) is any portion of a project which consumes time or resources and

has definable beginning & ending.

Event (Also known as node & connector) is the beginning & ending points of an activity or a group of

activities.

1.3 Differences between PERT & CPM PERT

CPM

It is a technique for planning scheduling & controlling

of projects whose activities are subject to uncertainty in

the performance time. Hence it is a probabilistic model.

It is a technique for planning scheduling & controlling

of projects whose activities not subjected to any

uncertainty and the performance times are fixed. Hence

it is a deterministic model

It is an Event oriented system. It is an Activity oriented system.

Basically does not differentiate critical and non-critical

activities.

Differentiates clearly the critical activities from the

other activities.

Used in projects where resources (men, materials,

money) are always available when required.

Used in projects where overall costs is of primarily

important. Therefore better utilized resources.

Suitable for Research and Development projects where

times cannot be predicted.

Suitable for civil constructions, installation, ship

building etc.

1.4 CRITICAL PATH Meaning: The longest path in a project network which determine the duration of the project is known as critical

path.

Determination of Critical Path

Step 1. List all the possible sequences from start to finish

Step 2. For each sequence determine the total time required from start to finish.

Step 3. Identify the longest path (Critical Path)

Page 3: Management science

Management Science (MGT-301)

COURTESY OF- KAMRUL, FAHAD & ZONAYED || DEPARTMENT OF MANAGEMENT || UNIVERSITY OF DHAKA

3

1.5 Rules for drawing the network diagrams.

In a network diagram, arrows represent the activities and circles represent the events.

The tail of an arrow represents the start of an activity and the head represent the completion of the activity.

The event numbered 1 denotes the start of the project and is called initial event.

Event carrying the highest number in the network denotes the completion of the project and is called

terminal event.

Each defined activity is represented by one and only arrow in the network.

Determine which operation must be completed immediately before other can start.

Determine which other operation must follow the other given operation.

The network should be developed on the basis of logical, analytical and technical dependencies between

various activities of the project.

1.6 Network Representation: Each activity of the project is represented by arrow pointing in direction of progress of project. The events of the

network establish the precedence relationship among different activities.

Three rules are available for constructing the network.

Rule 1. Each activity is represented by one & only one, arrow.

Rule 2. Each activity must be identified by two distinct events & No two or more activities can have the same tail

and head events.

Rule 3. To maintain correct precedence relationship, the following questions must be answered as each activity is

added to the network:

What activities must be immediately precede the current activity?

What activities must follow the current activity?

What activities must occur concurrently with the current activity?

There are two types of systems –

i. AOA system (Activity on Arrow system)

ii. AON system (Activity on Node system )

1.7 Float (Slack) Float (Slack) refers to the amount of time by which a particular event or an activity can be delayed without

affecting the time schedule of the network. Float (Slack) is defined as the difference between latest allowable and

the earliest expected time.

Event Float/Slack = LS – ES

Where LS = Latest start time

ES = Early start time.

1. Earliest start: Earliest start time is the earliest possible time by which the activity can be started. Denoted

as ‘ES’

2. Early finish time: Early finish time is the earliest possible time by which the activity can be completed.

Denoted as ‘EF’

3. Latest start time: Latest start time is the latest possible time by which the activity can be started. Denoted

as ‘LS’

4. Late finish time: Late finish time is the latest possible time by which the activity can be completed.

Denoted as ‘LS’

5. Total float (TF) / Total slack (TS): Total float of the job is the differences between its Late start and

Early start ‘or’ Late finish and Early finish. i.e.

TF (CA) = LS (CA) - ES (CA) or TF (CA) = LF (CA) - EF (CA)

CA = Current activity

Page 4: Management science

Management Science (MGT-301)

COURTESY OF- KAMRUL, FAHAD & ZONAYED || DEPARTMENT OF MANAGEMENT || UNIVERSITY OF DHAKA

4

6. Free float (FF) Free float is the amount of time a job can be delayed without affecting the Early start time

of any other job.

FF (CA) = ES (SA) – EF (CA)

CA = Current Activity

SA = Succeeding Activity

7. Independent Float (IF): Independent Float is the amount of time that can be delayed without affecting

either predecessor or successor activities.

IF = ES (SA) – LF (PA) - Duration of CA

ES = Early Start

LF = Late Finish

SA = Succeeding Activity

PA = Preceding Activity

CA = Current Activity

Page 5: Management science

Management Science (MGT-301)

COURTESY OF- KAMRUL, FAHAD & ZONAYED || DEPARTMENT OF MANAGEMENT || UNIVERSITY OF DHAKA

5

1.8 Examples Example-1

Develop the network for a project with following activities and immediate predecessors:

Activity Immediate

predecessors

A -

B -

C B

D A,C

E C

F C

G D,E,F

Solution

Example-2

Scheduling with activity time

Draw the net work

What is the critical path

Find out earliest start and earliest finish

Find out latest start and latest finish

Find out slack or free time

Page 6: Management science

Management Science (MGT-301)

COURTESY OF- KAMRUL, FAHAD & ZONAYED || DEPARTMENT OF MANAGEMENT || UNIVERSITY OF DHAKA

6

Solution

This information indicates that the total time required to complete activities is 51 weeks.

However, we can see from the network that several of the activities can be conducted

simultaneously (A and B, for example).

i. Network with ES & EF time

ii. Network with LS & LF time

iii. Activity schedule for our example

iv. Critical path activities: A, E, F, G, and I.

Page 7: Management science

Management Science (MGT-301)

COURTESY OF- KAMRUL, FAHAD & ZONAYED || DEPARTMENT OF MANAGEMENT || UNIVERSITY OF DHAKA

7

Example-3

PERT For Dealing with Uncertainty

Solution

i. Determination of Expected Value, Variance and Standard Deviation

Let m= most likely time estimate, mode.

a = optimistic time estimate,

b = pessimistic time estimate, and

Expected Value (TE) = (a + 4m + b) /6

Variance (V) = (( b – a) / 6 ) 2

Std Deviation (δ) = SQRT (V)

Page 8: Management science

Management Science (MGT-301)

COURTESY OF- KAMRUL, FAHAD & ZONAYED || DEPARTMENT OF MANAGEMENT || UNIVERSITY OF DHAKA

8

ii. The complete network

iii. The complete Network with critical path

iv. Critical Path Analysis (PERT)

v. Assume, Manager promised to complete the project in the fifty days. What are the chances of

meeting that deadline?

Calculate Z, where Z = (D-S) / V

D = 50 S (Scheduled date) = 20+15+8 =43; V = (4+25+4) =33

Z = (50 – 43) / 5.745

= 1.22

Page 9: Management science

Management Science (MGT-301)

COURTESY OF- KAMRUL, FAHAD & ZONAYED || DEPARTMENT OF MANAGEMENT || UNIVERSITY OF DHAKA

9

The probability value of Z = 1.22, is 0.888

vi. What deadline are you 95% sure of meeting

Z value associated with 0.95 is 1.645

D = S + 5.745 (1.645)

= 43 + 9.45

= 52.45 days

Thus, there is a 95 percent chance of finishing the project by 52.45 days.

Example-4

Construct the Network for the following Project and determine the following

Critical Path

ES,EF,LS,LF

TF,FF

Solution

i. Project Network

Page 10: Management science

Management Science (MGT-301)

COURTESY OF- KAMRUL, FAHAD & ZONAYED || DEPARTMENT OF MANAGEMENT || UNIVERSITY OF DHAKA

10

ii. Determination of ES,EF,LS,LF and TF,FF

Example-5

The following table lists the jobs of a network along with their time estimates.

i. Draw the project network.

ii. What is the probability that the job will be completed in 35 days?

iii. What due date has 90% chance of being met?

Solution

i. Construction of the Network

Page 11: Management science

Management Science (MGT-301)

COURTESY OF- KAMRUL, FAHAD & ZONAYED || DEPARTMENT OF MANAGEMENT || UNIVERSITY OF DHAKA

11

ii. Calculation of Expected time for all the activities

Expected Time ( te): ‘te’ can be calculated by the following formula

te = (to + 4tm + tp) / 6

iii. Determination of Critical Path

Expected Duration of the project Te = 32 days

iv. Probability of completing the project within a given date

Z = (TS – TE) / σ

= (35 – 32) / 6

= 0.5

From the Normal distribution Table, we get the probability of completing the project in

35 days is 69.15%

v. The due date for 90% chance of being met.

Probability of completing the project within a given date. The value of Z from the table for a 90%

probability is +1.28

TS =? (To be calculated),

TE = 32,

σ = 6

Z = (TS – TE) / σ

1.28 = (TS– 32) / 6

TS = 39.68 days