Hunter Mill Road and Sunset Hills Road Study

Community Meeting #5Progress Update

September 15, 2016

Kristin CalkinsFairfax County Department of Transportation

Page 2: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

2

Presentation Agenda• Project Objectives• Summary of Prior Community Involvement• Review of Alternatives Considered • Traffic Analysis Results • Detailed Evaluation of a 5-leg Roundabout• Evaluation of Sunset Hills Road Relocation• Next Steps• Questions and Answers

Page 3: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

3

Project Objectives• Address existing congestion• Plan for future traffic• Address queuing along Hunter Mill Road and

Sunset Hills Road• Improve access to the Dulles Toll Road by

minimizing congestion• Maintain Hunter Mill Road’s character by

applying context sensitive solutions

Page 4: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

4

Project Study AreaIntersection ID Intersection

CurrentIntersection Control Type

1Hunter Mill Road at Sunrise Valley Drive

Signalized

2Hunter Mill Road at

DTR EB RampsSignalized

3Hunter Mill Road at

DTR WB RampsSignalized

4Hunter Mill Road at

Sunset Hills RoadSignalized

5Hunter Mill Road at

Crowell RoadUnsignalized

(All-Way Stop)

6Hunter Mill Road at Hunting Crest Lane

Unsignalized(Two-Way Stop)

7Hunter Mill Road at

Lake Fairfax ParkUnsignalized

(Two-Way Stop)

7

6

5

4 32

1

Page 5: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

Project Background• Board of Supervisors authorized study as a follow-on study to

the Reston Phase I Plan Amendment• Meetings held on:

• December 8, 2014: Kick-Off • February 24, 2015: Existing & No-Build conditions and community

input on alternatives• May 20, 2015: Analysis Findings

• July 2015: Project put on hold at request of community to allow for new capacity analysis methodologies for roundabouts to be adopted by the Transportation Research Board

• Meeting held on: June 30, 2016: Roundabout capacity results

5

Page 6: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

Project ProcessKi

ck O

ff M

eetin

gEx

isting

Co

nditi

ons

Futu

re

Cond

ition

s

Com

mun

ity

Mee

ting #

2

Deve

lopm

ent o

f Al

tern

ative

s

Com

mun

ity

Mee

ting #

3

Proj

ect p

ut

on H

old

Com

mun

ity

Mee

ting

#4

Anal

ysis

of

Alte

rnati

ves

Com

mun

ity

Mee

ting #

5

Sele

ction

of

Pref

erre

d Al

tern

ative

Final

Repo

rt

Com

mun

ity

Mee

ting #

6

Inco

rpor

ation

into

Com

p Pl

an

24 MONTHS

6

We are Here

Page 7: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

Summary of Community Comments• Concern that traffic from Wiehle Avenue may be

diverted to Hunter Mill Road• Concern that the signal at Crowell Road may

increase delays in the off-peak• Maintain the character of Hunter Mill Road• Main goal of study is to improve Level of Service

(LOS) on Hunter Mill Road

7

Page 8: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

Summary of Community Comments (Cont.)• Roundabouts preferred at Dulles Toll Road ramps• Widen Hunter Mill Road from eastbound Dulles

Toll Road to Sunrise Valley Drive• Concern that improvements may attract more

development• Community wants an in-depth review of

roundabouts• There should be a mix and match of alternatives

8

Page 9: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

Alternatives Considered

9

Crowell Road

Sunset Hills Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

No-BuildCrowell Road

Sunset Hills Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

Alt. 1ACrowell Road

Sunset Hills Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

Alt. 1B

Roundabout

Signal Proffered

Page 10: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

Alternatives Considered (Cont.)

10

Crowell Road

Sunset Hills Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

No-BuildCrowell Road

Sunset Hills Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

Alt. 2Crowell Road

Sunset Hills Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

Alt. 3

Signal Proffered

Page 11: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

Alternatives Considered (Cont.)

11

Crowell Road

Sunset Hills Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

No-BuildCrowell Road

Sunset Hills Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

Alt. 4ACrowell Road

Sunset Hills Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

Alt. 4B

Signal Proffered

Page 12: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

Traffic Analysis Results

Traffic Analysis:• Performed for both 2030 and 2050• Consistent with VDOT Policies and Procedures • Used new Roundabout Methodology

12

Page 13: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

New Roundabout Methodology• New research resulted in:

• Re-assessment of Roundabout Capacity Models for the Highway Capacity Manual

• New methodology (adopted January 2016) resulted in an approximate 10-12% increase in roundabout capacity

• New model prioritizes movements with higher volumes• Resulting in improved LOS for heavier movements and overall

LOS• This study is an operational assessment, not an engineering design.

Roundabouts generally have greater ROW impacts• The best operating roundabout might have a tradeoff of a larger ROW

footprint

13

Page 14: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

2030 Traffic Analysis

• Utilized Future Year Projections from the Reston Phase I Plan Amendment.

• Included development potential associated with development of the Reston Transit Station Areas.

14

Page 15: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

2030 Traffic Analysis Results

15

Crowell Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

No-BuildCrowell Road

Sunset Hills Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

Alt. 1A (Roundabouts)Crowell Road

Sunrise Valley Drive

Hunt

er M

ill R

oad

WB DTR

EB DTR

Alt. 1B (Roundabouts)

Signal Proffered C C

D D

C E

C C

D D

E C

D D

B B

C D C D

B B

B D

C B

LOS: A, B, C

LOS: D

LOS: E

LOS: F

AM/PM LOS

Key for Levels of Service

Sunset Hills Road

Sunset Hills Road

24 sec./26 sec.

41 sec./53 sec.

29 sec./73 sec.

30 sec./25 sec.

38 sec./48 sec.

37 sec./18 sec.

45 sec./49 sec.

29 sec./47 sec.

17 sec./17 sec.

23 sec./12 sec.

14 sec./42 sec.

29 sec./47 sec.

17 sec./17 sec.

Page 16: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

2030 Traffic Analysis Results

16

Crowell Road

Sunrise Valley Drive

WB DTR

EB DTR

No-BuildCrowell Road

Sunset Hills Road

Sunrise Valley Drive

WB DTR

EB DTR

Alt. 2 (Signals)Crowell Road

Sunrise Valley Drive

WB DTR

EB DTR

Alt. 3 (Signals)

Signal Proffered C C

D D

C E

C C

D D

C C

C D

C C

D D

D C

D C

D D

C D

Sunset Hills Road

Sunset Hills RoadHu

nter

Mill

Roa

d

Hunt

er M

ill R

oad

Hunt

er M

ill R

oad

LOS: A, B, C

LOS: D

LOS: E

LOS: F

AM/PM LOS

Key for Levels of Service

22 sec./27 sec.

21 sec./45 sec.

55 sec./37 sec.

33 sec./31 sec.

39 sec./44 sec.

42 sec./34 sec.

19 sec./41 sec.

36 sec./35 sec.

35 sec./44 sec.

24 sec./26 sec.

41 sec./ 53 sec.

29 sec./73 sec.

30 sec./25 sec.

38 sec./48 sec.

B D

Page 17: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

2030 Traffic Analysis Results

17

Crowell Road

Sunrise Valley Drive

WB DTR

EB DTR

No-BuildCrowell Road

Sunset Hills Road

Sunrise Valley Drive

WB DTR

EB DTR

Alt. 4A (Roundabouts at Ramps)Crowell Road

Sunrise Valley Drive

WB DTR

EB DTR

Alt. 4B (Signals at Ramps)

Signal Proffered C C

D D

C E

C C

D D

C C

D D

B B

F F

E C

D C

C B

C D

Sunset Hills Road

Sunset Hills RoadHu

nter

Mill

Roa

d

Hunt

er M

ill R

oad

Hunt

er M

ill R

oad

LOS: A, B, C

LOS: D

LOS: E

LOS: F

AM/PM LOS

Key for Levels of Service

29 sec./47 sec.

45 sec./50 sec.

123 sec./143 sec.

29 sec./27 sec.

17 sec./17 sec.

23 sec./12 sec.

39 sec./32 sec.

66 sec./27 sec.

24 sec./26 sec.

41 sec./ 53 sec.

29 sec./73 sec.

30 sec./25 sec.

38 sec./48 sec.

Page 18: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

2030 Traffic Analysis Summary

18

LOS Standard = LOS D* Alt 2 in new location ** No Build includes the proffered signal at Crowell Road

IntersectionRoundabouts Signals Mix & Match

No Build Alt. 1A Alt. 1B Alt. 2 Alt. 3 Alt. 4A Alt. 4BOVERALL LOS AM (PM)

Hunter Mill Rd. @Crowell Rd. / Sunset Hills Rd. - - C (B) - D (C) - C (B)

Hunter Mill Rd. @Crowell Rd.** C (C) E (C) - C (C) - C (C) -

Hunter Mill Rd. @Sunset Hills Rd.* D (D) - - D (D) - - -

Hunter Mill Rd. @DTR WB Ramps & Sunset Hills Rd. - D (D) - - - D (D) -

Hunter Mill Rd. @DTR WB Ramps C (E) - B (D) C (D) B (D) - D (C)

Hunter Mill Rd. @DTR EB Ramps C (C) B (B) B (B) C (C) D (C) B (B) E (C)

Hunter Mill Rd. @Sunrise Valley Dr. D (D) C (D) C (D) D (D) C (D) F (F) C (D)

Page 19: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

2050 Traffic Analysis Results

19

Crowell Road

Sunrise Valley Drive

WB DTR

EB DTR

No-BuildCrowell Road

Sunset Hills Road

Sunrise Valley Drive

WB DTR

EB DTR

Crowell Road

Sunrise Valley Drive

WB DTR

EB DTR

Signal Proffered B C

C B

D C

E C

E D

F F

F F

D B

C C

F B

D B D B

D B

Sunset Hills Road

Sunset Hills RoadHu

nter

Mill

Roa

d

Hunt

er M

ill R

oad

Hunt

er M

ill R

oad

LOS: A, B, C

LOS: D

LOS: E

LOS: F

AM/PM LOS

Key for Levels of Service

50 sec./14 sec.

137 sec./58 sec.

82 sec./82 sec.

37 sec./13 sec.

104 sec./14 sec.

26 sec./35 sec.

37 sec./13 sec.

50 sec./14 sec.

17 sec./23 sec.

25 sec./17 sec.

42 sec./32 sec.

60 sec./21 sec.

58 sec./48 sec.

Alt. 1A (Roundabouts) Alt. 1B (Roundabouts)

Page 20: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

2050 Traffic Analysis Results

20

Crowell Road

Sunrise Valley Drive

WB DTR

EB DTR

No-BuildCrowell Road

Sunset Hills Road

Sunrise Valley Drive

WB DTR

EB DTR

Crowell Road

Sunrise Valley Drive

WB DTR

EB DTR

Signal Proffered B C

C B

D C

E C

E D

C B

D C

E C

C C

F C

E D

E D

E D

E C

Sunset Hills Road

Sunset Hills RoadHu

nter

Mill

Roa

d

Hunt

er M

ill R

oad

Hunt

er M

ill R

oad

LOS: A, B, C

LOS: D

LOS: E

LOS: F

AM/PM LOS

Key for Levels of Service

21 sec./14 sec.

71 sec./38 sec.

40 sec./29 sec.

58 sec./22 sec.

118 sec./24 sec.

34 sec./31 sec.

55 sec./22 sec.

59 sec./48 sec.57 sec./48 sec.

17 sec./23 sec.

25 sec./17 sec.

42 sec./32 sec.

60 sec./21 sec.

58 sec./48 sec.

Alt. 2 (Signals) Alt. 3 (Signals)

Page 21: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

2050 Traffic Analysis Results

21

Crowell Road

Sunset Hills Road

Sunrise Valley Drive

WB DTR

EB DTR

No-BuildCrowell Road

Sunset Hills Road

Sunrise Valley Drive

WB DTR

EB DTR

Crowell RoadSunset Hills Road

Sunrise Valley Drive

WB DTR

EB DTR

Signal Proffered B C

C B

D C

E C

E D

C B

F F

D B

D C

F B

F E

E C

D B

Hunt

er M

ill R

oad

Hunt

er M

ill R

oad

Hunt

er M

ill R

oad

LOS: A, B, C

LOS: D

LOS: E

LOS: F

AM/PM LOS

Key for Levels of Service

117 sec./57 sec.

22 sec./20 sec.

82 sec./82 sec.

37 sec./13 sec.

104 sec./14 sec.

39 sec./32 sec.

66 sec./27 sec.

50 sec./14 sec.

60 sec./21 sec.

42 sec./32 sec.

25 sec./17 sec.

17 sec./23 sec.

58 sec./48 sec.

Alt. 4A (Roundabouts at Ramps) Alt. 4B (Signals at Ramps)

Page 22: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

2050 Traffic Analysis Summary

22

IntersectionRoundabouts Signals Mix & Match

No Build Alt. 1A Alt. 1B Alt. 2 Alt. 3 Alt. 4A Alt. 4BOVERALL LOS AM (PM)

Hunter Mill Rd. @Crowell Rd. / Sunset Hills Rd. - - F (B) - F (C) - F (B)

Hunter Mill Rd. @Crowell Rd.** B (C) F (F) - C (B) - C (B) -

Hunter Mill Rd. @Sunset Hills Rd.* C (B) - - E (D) - - -

Hunter Mill Rd. @DTR WB Ramps & Sunset Hills Rd. - F (F) - - - F (F) -

Hunter Mill Rd. @DTR WB Ramps D (C) - C (C) D (C) C (C) - D (C)

Hunter Mill Rd. @DTR EB Ramps E (C) D (B) D (B) E (C) E (C) D (B) E (C)

Hunter Mill Rd. @Sunrise Valley Dr. E (D) D (B) D (B) E (D) E (D) F (E) D (B)

LOS Standard = LOS D* Alt 2 in new location ** No Build includes the proffered signal at Crowell Road

Page 23: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

23

Detailed Evaluation of 5-leg Roundabout • Intersection at Hunter Mill Road, Dulles

Toll Road (WB) and Sunset Hills Road• This evaluation is being done at the

request of the community• Designed per VDOT and FHWA standards• Evaluated for safe speeds, turning radii and

vehicle paths

Page 24: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

24

5-Leg Roundabout: Hunter Mill Defense League

Page 25: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

5-Leg Roundabout Summary: Hunter Mill Defense League

• Design:– Utilized Bypass lanes to limit circle size– No impact on toll plaza

• Concerns– Additional conflict points due to bypass lanes– Not designed to VDOT standards – Requires widening under the bridge

25

Page 26: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

26

5-Leg Roundabout: Elongated Oval

Page 27: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

5-Leg Roundabout Summary: Elongated OvalElongated Oval• Design:

– Minimized Impact on adjacent buildings– No impact on toll plaza

• Concerns– High speeds in circle– Reduced sight distance across circle– VDOT unlikely to approve design

27

Page 28: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

28

5-Leg Roundabout: Tight Circle

Page 29: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

5-Leg Roundabout Summary: Tight CircleTightest Circle• Design

– Smallest total footprint allowable– Provides minimal change to existing facilities

• Concerns– Impacts Dulles Toll Road Ramp Plazas – would require relocation– Considerable right-of-way impacts on the east side of Hunter Mill Road– Approach angles violate NCHRP 672 guidance

• Would not be considered an allowable and constructible design

29

Page 30: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

30

5-Leg Roundabout: Feasible Design

Page 31: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

5-Leg Roundabout Summary:Feasible DesignFeasible Design• Design is reflected in Alternatives 1A and 4A

– Only alternative that meets all VDOT and NCHRP design criteria– Minimizes impact on toll plaza

• Concerns– Impacts the Reston Presbyterian Church – Cultural and structural impacts associated with the design– Difficult Constructability

31

Page 32: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

32

5-Leg Roundabout: Alternatives 1A and 4A

Page 33: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

33

Sunset Hills Road Realignment

• Purpose of Sunset Hills Road Realignment:– To create distance from the Dulles Toll Road– To improve intersection efficiency along Hunter

Mill Road– Improve queuing conditions along Hunter Mill

Road

• Two potential alignments have been developed

Page 34: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

34

Realignment Option A

Page 35: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

35

Realignment Option B

Page 36: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

Sunset Hills Realignment Summary• Option A

– Most natural geometry– Longest natural queuing area at Hunter Mill Road– Most separation to the Dulles Toll Road– Closest alignment to Hunting Crest neighborhood

• Option B– Utilizes more of the existing facility– Provides back access to parcels along Hunter Mill Road– Has unusual curvature on breakaway point from existing– Less queuing area along straightaway at Hunter Mill Road– Separates school and soccer field

36

Page 37: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

37

Next Steps • Evaluate Community Feedback• Review Analysis Results• Select a Preferred Alternative based on:

• Community Feedback• Traffic Analysis• Impacts • Select the Best Performing, Least Impactful Alternative

• Final Recommendations and Report• Public meeting to present preferred alternative

• Thursday, November 17 (Location TBD)

Page 38: Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15, 2016

38

Question & Answers

30 MinutesPlease limit yourself to one question so others

have an opportunity to ask

[email protected]

http://www.fairfaxcounty.gov/fcdot/huntermillstudy.htm