A game to explore lean aspects, such as flow efficiency, batch sizes, waste in software development.

Citation preview

  • - or use the Flow Luke Peter Antman Based on h*p://www.netobjec4ves.com/system/les/DotGame_vas11_0.pdf
  • Illustrate Littles law Visualize why high resource utilization might be bad for flow efficiency Create an understanding that the most efficient way of getting flow is adapting to constraints Show how people in front of a bottleneck are actually causing problems when adding more work Show that its better not to work in many situations Show the effects of big batches Show that much work in progress adds waste and make it harder to fix and detect problems Show the value of customer collaboration Show the value of in process testing Purpose Peter Antman
  • Material 3x3 yellow post-its (300 post-its) Color dots Team of 8 persons and at least a couple of observers The game is played in 3 round 5 min pre 5 min running 10 min discussion Set up Peter Antman
  • From queuing theory The number of items in a system (WIP) equals the arrival rate (or throughout) times the average time an item spend in the system (lead time). WIP = TP * LT Littles law Peter Antman
  • We are a software shop, that produces this: Peter Antman
  • The group roles Business Analyst - Picks 6 post-its Technical Analyst - Puts on yellow dot Designer - Puts on red dot UI Developer - Puts on green dot Developer - puts on both blue dots Tester - discards anything of poor quality Project Manager - uses stopwatch Customer - receives the finished product Peter Antman
  • Workflow Business analyst peels of 6 post-its Technical analyst put yellow dot on Designer put red dot on UI designer put both green dots on Developer put both blue dots on Make those blue dots touch, but not overlap! Tester check against spec Puts in defect area, or give to customer Peter Antman
  • Its important that every one work on maximum capacity Everyone is a specialist We work in big batches (6) You hand of your work to the next inbox when finished You are not allowed to talk with each other Round 1 Peter Antman
  • Setup BA TA Design UI Dev Test Material PM Times 5 minute round Times rst batch Warns team 1 min before nish Customer Accepts deliveries Peter Antman
  • Dont accept anything where the blue dots are overlapping or not touching The dots in the corners should be fairly well spaced from the two sides Respond to people when asked, but dont volunteer information To customer Peter Antman
  • PM counts # of completed post-its # of accepted post-its # of post-its that are in progress (WIP) How long did the first batch take? Lead time? Throughput # of completed post-its/5 minutes Lead time (now) WIP/TP Debrief Round WIP Total Defects OK TP LT 60 18 16 2 3,6 16,7 Peter Antman
  • Only do work when the outbox is empty pull Once piece flow (not 6 post-its a time) Could you do in-place testing (test should not find any errors) PM measures several post-its lead time Customer answers questions Round 2 Peter Antman
  • PM counts # of completed post-its # of accepted post-its # of post-its that are in progress (WIP) How long did the first batch take? Lead time Throughput # of completed post-its/5 minutes Lead time (now) WIP/TP Debrief 2 Round WIP Total Defects OK TP LT 4 24 1 23 4,8 24s Peter Antman
  • Grab one post-it and work as a team Honor your specialties Discuss first how to organize team work Customer allowed to intervene Testing part of work Round 3 Peter Antman
  • Peter Antman