40
Corporate Presentation The 2 nd Qtr 2012 Operating Performance Opportunity Day 5 September 2012 1

TRC Oppday Q255

Embed Size (px)

DESCRIPTION

20120905 trc http://vihybrid.wordpress.com

Citation preview

Page 1: TRC Oppday Q255

Corporate Presentation

The 2nd Qtr 2012 Operating Performance

Opportunity Day 5 September 2012

1

Page 2: TRC Oppday Q255

2

Agenda

Company Overview

On going and Future Developments

Key Financial Highlights

Q&A Session

Page 3: TRC Oppday Q255

3

Company Overview

Vision To become the leading contractor of Thailand delivering projects in respect of standard

and safety for both natural gas pipeline, petrochemical industry and energy fields

along with its sustainable growth.

Mission 1. To enhance the company’s consistent growth with the good conduct of the corporate governance

practice for highly benefit of the company and its shareholders.

2. To recognize human dignity by treating all employees on fairly basis with disregard of race , class, complexion

or religion.

3. To emphasize human development through rendering knowledge gain, skill and expertise trainings as well as

required knowledge in concerned areas for the company’s sustainable growth.

4. To strive toward teamwork performance , passing on skill and knowledge including experience from one

generation through another.

5. To emphasize design engineering works, encourage learning participation and utilize new technology in

cooperation with both domestic and international alliances to develop Thai engineers’ capability to be identical

with the international ones.

6. To reward society and community.

Page 4: TRC Oppday Q255

4

2005 - 2008

• EPC Turnkey • Pipeline / Small & Medium Process Plant / Modular Fabrication • Civil work / infrastructure • Project Management Consulting (PMC)

Construction

2009 - 2012

• Greenfield / Brownfield Project Development Capability •Conceptual Design • Basic Engineering • Feasibility Study • Advisory Services

Project Development

• Engineering Capability

Commissioning / Testing

2012+

• Operating & Maintenance Services • Investment through our investment arms - TRC International Ltd. - TRC Investment Ltd.

Commercial Operation Date

Leading Turnkey Solution Provider Company

Page 5: TRC Oppday Q255

5

Key Corporate Milestone

• Established with experience group of engineers undertaking small pipeline projects

1998 2005

• Listed in MAI with Baht 1.70 IPO price • Successfully JV with CPP (China) for 2,100 MB pipeline project

2007

• EPC capability for Biodiesel Processing Plant

2008 • Project Development & Investment Division established

2009

• Successfully landed in Oman • Undertaking PTT Gas Separation Plant Project

2010 • Awarded by Gulf JP a EPC Pipeline Package of THB 2,016 MB + 21.09 Mil USD

2011 • Awarded for EPCC of Ethanol Project

Songkhla Transmission Pipeline Project (562 MB)

• Lump Sum Turnkey Bangchak Bio Diesel Plant Project (757 MB)

Nigeria Project

• Wang Noi-Kaeng Khoi Cross Country Gas Pipeline

• TRC is equipped capability of EPC and undertake Large Scale Project

• EPC for Flowline Project in Oman • Consortium with Siemens for OCS#1

Oman Project

Revamp OCS#1

• Ubon Boi-Ethanol Project of 2,134 MB • Group backlog reached 4,452 MB

• Acquired Sahakarn Wisavakorn Co., Ltd. as subsidiary

Page 6: TRC Oppday Q255

Our Core Business

6 Fabrication- Pressure vessel, piping,

Steel structure (ASME U&S Stamp)

Small to Medium Process and

Industrial Plant EPC Pipeline Engineering and Construction

Project Development and Investment

Page 7: TRC Oppday Q255

7

Key Success Factors

Competent and

experienced

professional

management team

& operation personnel

“Provide service excellence and maintain the highest level of customer satisfaction”

Strong risk

management

and solid

liquidity

management

to enables

financial flexibility

Continuously

growing

sustainable

revenue and

profit stream

while creating

loyal and

engaged customers

Establishing strong

strategic alliances

and focus on high

margin projects with high barriers to entry

Page 8: TRC Oppday Q255

8

TRC Group Structure

Paid-up Capital 336.59 MB

99.99% 100%

100%

60% 70%

TRC Engineering

(Sultanate of Oman)

Paid-up Capital OMR 250,000

Co., Ltd.

(Thailand)

(Thailand)

Paid-up Capital OMR 150,000

TRC International Ltd.

(Hong Kong)

Paid-up Capital HKD 10

TRC & Al-Ghalbi LLC

(Sultanate of Oman)

TRC Construction

Public Company Limited

Sahakarn Wisavakorn TRC Investment Ltd.

(Mauritius)

Paid-up Capital 200 MB Paid-up Capital USD 1

Page 9: TRC Oppday Q255

Our Quality, Health, Safety and Environmental Promises

9

Page 10: TRC Oppday Q255

Our Reputable Clients

10

Page 11: TRC Oppday Q255

11

Agenda

Company Overview

On going and Future Developments

Key Financial Highlights

Q&A Session

Page 12: TRC Oppday Q255

TRC Revenues Growth

12

• Core Businesses On-going

• Gulf SPP and IPP Package

• Ubon Bio Ethanol Project

• PTTAR-IRPC Multiproduct Pipeline

• Green ABS VI Project

• GUT Pipeline Project *

• Expansion in Oman

• PTTEP Oman

• EPCC and O&M in oil & gas sector and

petrochemical industry

• Investment Scheme

• Energy projects in neighboring countries • Natural resources project

EPC

* Note: New project acquired in Aug 2012

Page 13: TRC Oppday Q255

13

On-going Core Business: Gulf JP Pipeline Project

Gulf SPP and IPP Pipeline Package

Owner: Gulf JP Co., Ltd Group

TRC’s Work Value: THB 2,016 million +

USD 21.09 million

Scope of Work:

Gas Pipeline EPC Package for Natural Gas Transmission Pipeline Construction Work and Metering and Regulation Station for 7 SPP Projects and 1 IPP Project in Saraburi, Chachoengsao, Rayong and Prathumthani Province

% of Completion as at 30 Jun 12: 54%

Page 14: TRC Oppday Q255

14

On-going Core Business: Ethanol Processing Plant

Ubon Bio Ethanol Project

Owner : Ubon Bio Ethanol Co., Ltd.

SKW’s Work Value: THB 2,134 million

Scope of Work:

Plant Out Side Battery Limit (“OSBL”) EPCC Package for Ethanol Processing Plant with a capacity of 400,000 liter per day utilizing dry and fresh cassava as raw material

% of Completion as at 30 Jun 12: 73%

Page 15: TRC Oppday Q255

15

Page 16: TRC Oppday Q255

16

On-going Core Business: PTTAR-IRPC Multiproduct

PTTAR-IRPC Multiproduct Project

Owner: IRPC Public Company Limited

TRC’s Work Value: THB 723 million

Scope of Work:

Multiproduct pipeline installation between IRPC Tank to PTTAR Refinery

% of Completion as at 30 Jun 12: 61%

Page 17: TRC Oppday Q255

17

On-going Core Business: Green ABS VI Project

Green ABS VI Project

Owner : IRPC Public Company Limited

SKW’s Work Value: THB 280 million

Scope of Work:

Construction of Concrete Steel Buildings, Steel Structure and Infrastructure

Project location at inside IRPC plant, Rayong Province

% of Completion as at 30 Jun 12: 38%

Page 18: TRC Oppday Q255

18

GUT Gas Pipeline Project

Owner: Gulf JP UT Company Limited

TRC’s Work Value: THB 1,547 million

Scope of Work:

EPC of 28 inches diameter Natural Gas Pipeline length approximately 21 km. and two block valve stations and one metering station for GUT Power Plant (IPP)

Project located in Rojana Industrial

Park 3, Ayutthaya Province

Work Period: Approximately 23 months

New Acquired Project: GUT Gas Pipeline Project

Page 19: TRC Oppday Q255

19

Expansion in Oman: Petrogas Rima (Extension Contract)

Pipeline Project

Owner: Petrogas Rima LLC

(1-year extension contract

+ 1-year potential extension)

Construction Period: May 2012 – Apr 2013

Type of Contract: EPC Contract

Scope of Work:

Engineering, Procurement and Construction of production flow lines and water injection flow lines connecting the drilling wells together.

Up to date, TRC has achieved its services for connecting about 80 drilled wells which increasing the oil production of Rima Small Fields from about 2,200 bopd in 2009 to nearly 14,000 bopd today.

Page 20: TRC Oppday Q255

20

Expansion in Oman: PTTEP Oman

Pipeline Project

Owner : PTTEP Oman Company Limited

TRCE’s Work Value: Approximately

THB 125 million

Additional Work: THB 36 million to be completed within the end of 2012

Scope of Work:

Project location: Block 44 concession area of PTTEP in the northwest of Oman;

Shams-16 flowline and its related equipment & facilities;

Munhamir-1 and Munhamir-2 flowline and its related equipment & facilities;

Munhamir crude export pipeline

Page 21: TRC Oppday Q255

21

Expansion in Oman: EPCC and O&M in Oil & Gas and Petrochemical Sectors

EPCC and O&M in Oil & Gas and Petrochemical Sector

New opportunity in Oman to be explored and committed by TRC and its strategic partner

Scope of Work:

Engineering, Procurement, Construction Commissioning and Operating & Maintenance focusing on oil & gas sector and petrochemical industry

Target: To be awarded the project value THB 150 million within 2012 for the above scope of work

Page 22: TRC Oppday Q255

22

Investment Scheme: Focusing on Energy and Natural Resources in ASEAN Countries

Energy Projects in Neighboring Countries

Natural Resources Development Project

Objectives:

To explore and capture business opportunity focusing on energy sector and natural resources in ASEAN neighboring countries such as Myanmar, Cambodia and Lao;

To retain some fixed income portion of TRC group; and

To be ready for ASEAN Economic Community (AEC) in 2015

Page 23: TRC Oppday Q255

23

List of Potential Projects

Project Name

Approximate

Project Value

(MB)

Construction

Period

A. Natural Gas Pipeline

A.1 Provincial Gas Transmission Pipeline (as Subcontractor) 2,000 – 3,000 2013 - 2015

A.2 IPP* (TRC awarded GUT Project , 1,557 MB in Aug 2012.) Awarded 2013 - 2014

A.3 SPPs 500 2013 - 2014

A.4 Distribution Pipelines 500 2012 onwards

A.5 Construction Call Off Services n/a 2013 onwards

B. Processing Plant

B.1 Waste Heat Recovery 1,300 2013 - 2014

B.2 Waste to Energy 2,000 2013 - 2014

B.3 Ethanol Plant 1,700 2013 - 2014

B.4 CBG for NGV 70 2012

C. Two Projects in Sultanate Oman 700 2013 - 2016

Total Approximate

9,770

Page 24: TRC Oppday Q255

24

Agenda

Company Overview

On going and Future Developments

Key Financial Highlights

Q&A Session

Page 25: TRC Oppday Q255

1st Qtr 2nd Qtr 1st Qtr 2nd Qtr 1st Qtr 2nd Qtr 1st Qtr 2nd Qtr 1st Qtr 2nd Qtr 6-Month

Services Income & Sales 490.25 515.16 403.85 471.69 58.24 19.73 49.86 52.93 1,002.20 1,059.51 2,061.71

Interest Income 1.59 1.04 1.06 1.26 0.00 0.00 0.00 0.00 2.35 2.29 4.64

Other Income 4.74 2.80 5.36 2.08 0.00 1.24 0.00 0.00 10.21 5.89 16.10

Total Revenues 496.58 519.00 410.27 475.03 58.24 20.97 49.86 52.93 1,014.76 1,067.69 2,082.45

Cost of Services & COGS -412.55 -438.80 -377.39 -436.30 -48.64 -20.15 -44.72 -55.23 -877.04 -950.24 -1,827.28

Gross Profit (Loss) 77.70 76.36 26.47 35.38 9.60 -0.42 5.14 -2.30 125.16 109.27 234.43

SG&A and Finance Cost -29.43 -31.38 -6.09 -6.07 -6.47 -6.83 -4.42 -6.66 -47.36 -50.53 -97.89

Profit before Tax 54.59 48.83 26.80 32.65 3.13 -6.01 0.71 -8.95 90.35 66.93 157.28

Tax -12.53 -10.88 0.00 -1.94 -0.09 0.09 0.00 0.00 -12.61 -12.74 -25.35

Net Profit (Loss) 42.07 37.94 26.80 30.71 3.05 -5.93 0.71 -8.95 77.74 54.19 131.93

Less: Minority Interest

(40% for TRCA, 30% for

TRCE) -1.43 5.05 3.62

Net Profit Attributable to

Equity Holders of the

Company

76.31 59.24 135.55

EPS (Baht/Share) 0.23 0.18 0.40

Gross Profit (Loss) 15.85% 14.82% 6.55% 7.50% 16.48% -2.12% 10.30% -4.34% 12.49% 10.31% 11.37%

Net Profit Margin 8.47% 7.31% 6.53% 6.47% 5.23% -28.26% 1.43% -16.91% 7.52% 5.55% 6.51%

Consolidated FS

(Unit: Million Baht)

(Oman) (Oman)

TRC Sahakarn TRC & Al-Ghabi TRC Engineering

The 1st and 2nd Qtr 2012 Performance of TRC Group

25

Sahakarn’s tax shield of 87 MB was completely utilized from 2011 to the 1st half of 2012.

Page 26: TRC Oppday Q255

1,814 1,724

1,567

2,262

254

1,014

3,500 – 4,000

532

1,068

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

2008 2009 2010 2011 6-M 2011 6-M 2012 2012 (F)

1st Qtr 2nd Qtr

Total Revenue

Total Rev Growth 165%

26

(MB)

2,082

786

Page 27: TRC Oppday Q255

Services Income & Sales Break-Down

Pipeline Process & Plant Civil Other Services 27

6-M 2012

(2,062 MB)

Pipeline 58.5%

Process & Plant 40.5%

Civil 0.5% Others 0.5%

Year 2011

(2,228MB)

Year 2009

(1,695 MB)

Year 2010

(1,452 MB)

Others

1.0%

Civil

2.8%

Page 28: TRC Oppday Q255

127

-166

183

149

12

76

18

59

-200

-100

0

100

200

300

2008 2009 2010 2011 6-M 2011 6-M 2012

1st Qtr 2nd Qtr

Net Profit

Net Profit Growth 353%

28

30

135

(MB)

Page 29: TRC Oppday Q255

Gross Profit & Net Profit Margin

29

19.6%

16.4%

25.9%

14.6% 14.5%

11.4%

7.0%

-9.6%

12.0%

6.6%

3.8%

6.5%

-15.0%

-10.0%

-5.0%

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

2008 2009 2010 2011 6-M 2011 6-M 2012

Gross Margin Net Profit Margin

Low Net Profit Margin due to SKW’s loss

Page 30: TRC Oppday Q255

0.38

-0.50

0.55 0.45

0.09

0.40

2.17

1.53

2.05

2.39

1.93

2.66

-1.00

-0.50

-

0.50

1.00

1.50

2.00

2.50

3.00

2008 2009 2010 2011 6-M 2011 6-M 2012

Weighted Average EPS & Book Value per Share

EPS BVPS

EPS & Book Value

(Baht/Share)

30

Nearly to the whole of 2011

Page 31: TRC Oppday Q255

0.80 0.83

0.60

1.98 2.06

1.83

0.00

0.50

1.00

1.50

2.00

2.50

2008 2009 2010 2011 30 Jun 2011 30 Jun 2012

Debt to Equity Ratio

(Time(s))

0.84 0.94

Calculated from (Total Liabilities – Advances from Customers – Unearned Construction Revenue)/ Total Equity

31

0.95

Page 32: TRC Oppday Q255

32

Dividend Payout Summary

0.031

0.285

0.15

0.06

0.15

0.12

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

2007 2008 2009 2010 2011

0.318

(Baht/Share)

Dividend/ Net Profit after Legal Reserve 92.56% 34.43% N/A 50.66% 83.73%

Stock Dividend

Cash Dividend

Dividend policy: 40% of net profit after legal reserve (Only TRC’s Performance)

Net Loss 46 MB

Page 33: TRC Oppday Q255

33

Paid-up Capital

150

329.99 330.67 333.56 336.59

(MB)

1.11

471.50

133.80

Registered Capital

General Mandate

Expired ESOP Warrants

336.59

Total exercised ESOP shares Sep 2010-Jun 2012 = 6.59 MB

Paid-up Capital

Page 34: TRC Oppday Q255

1,357 1,186

607

1,092

2,835

1,838

284 315

32

1,352

806

627

359

265

230

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

5,000

2007 2008 2009 2010 2011 30 Jun 2012

GUT Project

Oman Subsidiaries

SKW

TRC

1,501 1,266

1,451

4,452

TRC Group Backlog

34 Note: 1. Oman subsidiaries consist of TRC & Al Ghalbi LLC and TRC Engineering LLC which TRC International Ltd.

invested 60% and 70%, respectively. 2. Backlog is shown the outstanding work value of total projects.

1,641

1,547

4,421

New GUT Project

Acquired in Aug 2012

(MB)

Page 35: TRC Oppday Q255

Project Name

Type

of

Works

Project Owner/

Client

Work Value

(MB)

Uncompleted

Work Value

(MB) Project Period

1. Gas Pipeline Construction Work for Gulf JP’s IPP

Project (The Project value 1,185 MB and USD 16.345

Million)

E, P, C Gulf JP Company Limited 1,693.24 1,044.74 Oct 11 Jun 13

2. PTTAR-IRPC Multiproduct Pipeline E, P, C IRPC Public Company Limited 722.50 284.30 Jul 11 Dec 12

3. - 8. Gas Pipeline Construction Work for

Gulf JP’s 7 Small Power Plant (SPP) Projects

(Total 6 contract, the project value 831 MB and USD

4.745 million)

E, P, C Gulf JP Company Limited 975.47 198.37

Oct 10 Sep 13

9. Schedule of Rate Period Contract for HDPE Natural

Gas Pipeline Distribution Project

E, P, C PTT Natural Gas Distribution

Company Limited 144.00 127.40 Nov 11 Oct 13

10. N/G pipeline to OTS&PRS E, P, C AMATA Natural Distribution

Company Limited 76.00 76.00 Jun 12 Dec 12

11. Dismantle and Construction structure steel and piping

on piperack from BST

E, P, C Bangkok Synthetics PCL. 56.00 56.00 Jul 12 Oct 12

12. Schedule of Rate Period Contract for HDPE Natural

Gas Pipeline Distribution

E, P, C AMATA Natural Gas Distribution

Company Limited 58.00 38.05 Nov 11 Oct 13

13. Additional Work E, P, C Bangkok Synthetics PCL. 4.80 4.80 Aug 12 Oct 12

14. PTTNGD-N/G gas Pipeline to Thai Abika E, P, C PTT Natural Gas Distribution

Company Limited 4.00 4.00 Feb 12 Sep 12

15. REP-Propylene Glycol (PG) Pipeline E, P, C Rayong Engineering Company

Limited 28.50 1.86 Dec 11 Jul12

16. I1 and PTT Piperack Modification Project E, P, C Glow SSP3 Company Limited 23.08 1.15 Nov 11 Jul 12

TRC’s Backlog as at 30 June 2012

35

Page 36: TRC Oppday Q255

Project Name

Type

of

Works

Project Owner/

Client

Work Value

(MB)

Uncompleted

Work Value

(MB) Project Period

17. TPP Piperack Extension (State#1) E, P, C - Bangkok Industrial Gas Company

Limited

- Thai Industrial Gases Public

Company Limited

- Vinythai Public Company Limited

15.71 0.79 Sep 11 Dec 12

18. Relocate pipe to GKP1 E, P, C

PTT Public Company Limited 3.60 0.72 Jun 12 Jul 12

Total 18 Projects 3,804.90 1,838.18

TRC’s Backlog as at 30 June 2012

36

Project Name

Type

of

Works

Project Owner/

Client

Work Value

(MB)

Uncompleted

Work Value

(MB) Project Period

GUT Gas Pipeline Project E, P, C

Gulf UT Company Limited 1,547.01 1,547.01 Aug 12 Jul 14

Total 1 Project 1,547.01 1,547.01

New Project Acquired in August 2012

Page 37: TRC Oppday Q255

SKW’s Backlog as at 30 June 2012

Project Name

Type

of

Works

Project Owner/

Client

Work Value

(MB)

Uncompleted

Work Value

(MB) Project Period

1. The Construction and Commissioning of 400,000 LPD

Cassava-Based Fuel Ethanol Plant Project

E, P, C Ubon Bio Ethanol Company Limited 2,134.10 560.63 Mar 11 Sep12

2. Civil works for Green ABS VI Project E, P, C Thai ABS Company Limited 280.00 173.71 Jan 12 Oct 12

3. Water Treatment Plant E, P, C Electricity Authority of Thailand 20.36 20.36 Sep 11 Oct 13

4.-10. 7 Civil Work Projects (Bride & Road Construction) E, P, C Department of Rural Roads

58.91 51.35 Completed in

Sep-Oct 2012

Total 10 Projects 2,493.37 806.05

37

Page 38: TRC Oppday Q255

TRC & Al-Ghalbi’s Backlog as at 30 June 2012

Project Name

Type

of

Works

Project Owner/

Client

Work Value

(MB)

Uncompleted

Work Value

(MB) Project Period

Construction of Flow Lines Rima Satellites Small Fields (The project value approximately OMR 1.80 million)

E,P,C Petrogas Rima LLC Sultanate of Oman

145.56 145.56 May 12 Apr 13

Total 1 Project 145.56 145.56

Project Name

Type

of

Works

Project Owner/

Client

Work Value

(MB)

Uncompleted

Work Value

(MB) Project Period

1. Shams-16 Munhamir-1&2 flow Line and Munhamir Crude Export Pipe Line Project (The project value approximately OMR 1.99 million)

E,P,C PTTEP Oman Company Limited 161.09 54.74 Aug 11 Dec 12

2. Well Casing Cathodics Protection (The project value approximately OMR 0.67 million)

P,C German Cathodics Protection GmBH

53.82 29.45 Apr 11 May 12

Total 2 Projects 214.91 84.19

TRC Engineering’s Backlog as at 30 June 2012

38

Page 39: TRC Oppday Q255

TRC Group

No. of

the Projects

Remaining

Work Value (MB)

TRC Construction Plc. 14 1,838

Sahakarn Wisavakorn Co., Ltd. 10 806

TRC & Al-Ghalbi LLC (Oman) 1 145

TRC Engineering (Oman) 2 85

Total Backlog as at 30 June 2012 27 2,874

Backlog Conclusion as at 30 Jun 2012

39

Add: New GUT Project 1 1,547

Total Backlog 28 4,421

Page 40: TRC Oppday Q255

40

Agenda

Company Overview

On going and Future Developments

Key Financial Highlights

Q&A Session