Design and technique Product description Gyptone edge D1 is a pre-painted, de- mountable suspended acoustic ceiling, mounted in a concealed grid system (T-24). Gyptone ceilings can be used for many applications, like schools, offices and com- mercial settings. Gyptone edge D1 is fully demountable and gives good opportuni- ties for inspection in the cavity above the ceiling. Gyptone edge D1 is available with perforated and non- perforated surfaces. Thickness is 12,5 mm and the format 600 x 600 mm. Plenum height Min and max plenum heights with T-grid system can be found on page 5. Surfaces Gyptone ceiling tiles with edge D1 is paint- ed from the factory. The color used is white (NCS0500) with a gloss value of 5-9 accord- ing to ISO 2813. Further painting is to be done with a shorthaired paint roller as spray painting will impair the acoustic performance. Grid system Gyptone edge D1 is installed on a Quick- Lock T-24 grid system. The system is sus- pended and should be installed with suitable hangers. Gyptone edge D1 must be installed according to this installation manual as well as the general specifica- tion of the project. Fire resistance A2-s1, d0. Load The max point load for each tile, with a deflection of max 2 mm is 1 kg. If higher load is needed the installations needs to be fixed to the slab above with dedi- cated suspensions. Max point load for the grid is 0,5 kg. Max load equally spread on the main beams is 2 kg/m for T24 grid system. Stability Gyptone edge D1 is to be installed and used in rooms with relative humidity not permanently exceeding 70% or tempera- tures exceeding 45 degrees Celsius. Weight Non perforated Gyptone edge D1 = 9 kg/m² Perforated Gyptone edge D1 = 8 kg/m² Cleaning Can be cleaned with a damp cloth. Do not use detergents. Always use clean gloves when installing Gyptone edge D1. Maintenance If damages on edges or surfaces occurs, It is recommended to replace the damaged tile. Gyptone edge D1™ system Installation manual Gyproc A/S is not to be held responsible for any typographical errors and reserves the right to change range and product technology without prior notice.

Gyptone edge d1 installation manual

Embed Size (px)

Citation preview

Design and technique

Product descriptionGyptone edge D1 is a pre-painted, de-mountable suspended acoustic ceiling, mounted in a concealed grid system (T-24). Gyptone ceilings can be used for many applications, like schools, offices and com-mercial settings. Gyptone edge D1 is fully demountable and gives good opportuni-ties for inspection in the cavity above the ceiling. Gyptone edge D1 is available with perforated and non- perforated surfaces. Thickness is 12,5 mm and the format 600 x 600 mm.

Plenum heightMin and max plenum heights with T-grid system can be found on page 5.

SurfacesGyptone ceiling tiles with edge D1 is paint- ed from the factory. The color used is white (NCS0500) with a gloss value of 5-9 accord- ing to ISO 2813. Further painting is to be done with a shorthaired paint roller as spray painting will impair the acoustic performance.

Grid systemGyptone edge D1 is installed on a Quick- Lock T-24 grid system. The system is sus- pended and should be installed with suitable hangers. Gyptone edge D1 must be installed according to this installation manual as well as the general specifica-tion of the project.

Fire resistanceA2-s1, d0.

LoadThe max point load for each tile, with adeflection of max 2 mm is 1 kg. If higherload is needed the installations needsto be fixed to the slab above with dedi-cated suspensions. Max point load for the grid is 0,5 kg. Max load equally spread on the main beams is 2 kg/m for T24 grid system.

StabilityGyptone edge D1 is to be installed andused in rooms with relative humidity notpermanently exceeding 70% or tempera-tures exceeding 45 degrees Celsius.

WeightNon perforated Gyptone edge D1 = 9 kg/m²Perforated Gyptone edge D1 = 8 kg/m²

CleaningCan be cleaned with a damp cloth. Do notuse detergents. Always use clean gloves when installing Gyptone edge D1.

MaintenanceIf damages on edges or surfaces occurs,It is recommended to replace thedamaged tile.

Gyptone edge D1™ systemInstallation manual

Gyp

roc

A/S

is n

ot t

o be

hel

d re

spon

sibl

e fo

r any

typ

ogra

phic

al e

rror

s an

d re

serv

es t

he

righ

t to

ch

ange

ran

ge a

nd

prod

uct

tec

hn

olog

y w

ith

out

prio

r not

ice.

Gyptone edge D1 – Installation manual 2

The placement of the wall angle is marked with a bubble level/chalk line and mounted with a flat headed screw suitable for the wall per max. 300 mm. The first screw should be no more than 50 mm from a corner. The wall angles should not be shorter than 300 mm. Cut the wall angles in close mitre at the corner joints. If the wall is uneven, mount a thin wooden list behind the wall angle.

Hangers for the main beam are placed in rows per 600 mm. The first main beam 200 - 600 mm from the wall. First hanger in main beam max 100 mm from the wall. Other hangers per max 1200 mm. See illustration on page 4. The hook of the hanger must be squeezed together with a pair of nippers.

Gyptone edge D1™ systemInstallation of T-grid systemWe recommend reading the manual thoroughly prior to installing the ceiling

When mounting the cross tees, always place the hook in the right side of the slot seen from the mounting side. Cross tees are mounted at each 1200 mm, see illustration on page 4. The cross tee is placed by the first hanger. The length of the cross tee closest to the wall is adjusted. The grid system is adjusted to the accurate height. Every 5th main beam and all cross tees against the wall, are fixed to the wall with wall brackets.

At the longitudinal assembly of the main beams the couplings should be pushed together until they click. Adjust the hangers to ensure all main beams are in level with the wall angle. The main beam should not be rested on the wall angle, but placed approx. 15 mm over the wall angle.

300 mm

A B

DC15 mm

Distance between profiles

Gyptone edge D1 – Installation manual 3

Gyptone edge D1™ systemMounting of Gyptone edge D1 ceiling tilesWe recommend reading the manual thoroughly prior to installing the ceiling

GYPTONE

GYPTONE

When mounting the Gyptone tiles, use cotton gloves. The tiles are lifted perpendicular into the grid system. The J-profile is slid over the edge of the main beam, and the tile is placed in position with the Z-profile resting on the opposite main beam. Slide/push the tiles in place in the direction of the main beam. Be careful not to damage the tiles. Mounting of tiles should always be started from the center of the room. All installations should be completed before mounting the tiles.

Adjusting the frieze tiles against the wall: The front of the tile is marked. The Z and J profile on the back is shortened with a hacksaw or similar. Turn the tile and cut the tile cardboard. Frieze tiles should not be cut with an undersize of more than max 5 mm.

E

Gyptone edge D1 installed in concealed T-24 grid system.

H

F

When mounting the friezes against the wall, place 2 wall springs per tile. The short side of the spring is squeezed between the wall angle and the wall.

G

J-profile

Z-profile

Gyptone edge D1 – Installation manual 4

Gyptone edge D1™ systemMounting of T-grid system and Gyptone edge D1 tilesWe recommend reading the manual thoroughly prior to installing the ceiling

Dimensions T24 grid system

Estimated consumption installation of suspended grid system

Grid system

Product Term T24 Length mm cc mm Usage/m²

1 Main beam 4810181 3000 600 1.67 m

2 Cross tee D1 4849111 600 1200 0.83 m

3 Wall angle 4133301 3000 24x24 Measurement

4 Adjustable hanger - - 1200 1.39 pcs

5 Wall spring 4133301 3000 24x24 3.3 pcs per m wall angle

2415

38 38

Max. 100 mm

Max. 1200 mm

Min. 200 mm

600 mm

Min. 200 mm

1

2

4

5

3Main beamL: T-24 3600 mm

Wall angleL: 3000 mm

Cross tee D1L: 600 mmcc 1200 mm

1

2

3

Adjustable hangersfor lengths between90-1500 mm

5

Wall spring4

19

24

24

2415

38 38

1512

25

5

2415

38 38

19

24

241512

25

5

2415

38 38

19

24

241512

25

5

2415

38 38

19

24

241512

25

5

2415

38 38

19

24

241512

25

5

NB! Gyptone cross tee must always be used. Cross tees should always be placed next to a hanger.

Gyptone edge D1 – Installation manual 5

The height is measured without any Gyptone tiles and with-out attachment to the slap above the ceiling. The distance is from the top of the hanger to the bottom of the grid system.

T-grid system with adjustable hangers

Min

. 100

mm

To ensure easy mounting of the tiles in the grid system, the distance between the lower surface of the grid and the above element of building should be min 100 mm.

Gyptone edge D1, suspension of grid system

Gyptone edge D1, frieze solutions

Gyptone edge D1™ systemMounting of T-grid system and Gyptone edge D1 ceiling tilesWe recommend reading the manual thoroughly prior to installing the ceiling

T24 Adjustable 9-12 Min. height 100 mm Max. height 130 mm

T24 Adjustable 12-20 Min. height 130 mm Max. height 210 mm

T24 Adjustable 18-30 Min. height 190 mm Max. height 310 mm

T24 Adjustable 30-60 Min. height 310 mm Max. height 610 mm

T24 Adjustable 60-100 Min. height 610 mm Max. height 1010 mm

T24 Adjustable 100-125 Min. height 1010 mm Max. height 1260 mm

T24 Adjustable 125-150 Min. height 1260 mm Max. height 1510 mm

Max. 300 mm. Max. 300 mm.

25

Max. 300 mm.

5

5

7 8

10

11

4

2

9

11

7 7

6 4

2

1

2

3

4

5

6

7

8

9

10

11

24 mm main beam 4810181, c/c distance 600 mm.

24 mm cross tee D14149111, c/c distance 1200 mm.

Adjustable hanger, c/c distance 1200 mm.

Gyptone ceiling tile edge D1.

Wall angle GK-C, fixed to wall every 300 mm.

Main beam GK 1.

Adjusted main beam GK-1, c/c distance 400 mm.

Connecting bracket GK 21.

Hanger GK 26-25, c/c distance 900 mm.

Gyproc Kortplank, GKP 13 (recessed edge from factory).

Gyproc screw QS 25.

Learn more on www.gyptone.com

1

2

3

4

5

6

7

24 mm main beam 4810181, c/c distance 600 mm. (every 5th main beam is fixed to the wall).

24 mm cross tee D1 4149111, c/c distance 1200 mm.

Adjustable hangerc/c distance 1200 mm.

Gyptone tiles edge D1.

Corner profile H 50/50, fixed to wall every 400 mm, use screws with pan-head.

15,5 mm fitted plasterboard GFKP 15 (Recessed edge from factory) (Jointing supporters with steel base plate and filters/screw).

Gyproc screw QS 25.

Learn more on www.gyptone.com

1

1

6

3

3

Gyptone edge D1 – Installation manual 6

Min. 24 mmInstallation of light fitting in Gyptone D1 ceiling – detail

Installation of light fitting in Gyptone D1 ceiling

Installation of light fitting in Gyptone D1 ceiling.

Gyptone edge D1™ systemInstallation of light fitting in Gyptone D1 ceilingWe recommend reading the manual thoroughly prior to installing the ceiling

Installation of light fitting in Gyptone D1 ceiling – detail.

Min. 24 mm

Min. 24 mm

Min. 24 mm

Gyptone Edge D1 – Installation manual 7

Gyptone edge D1™ systemGyptone edge D1 – Good advice

Corners with wall angle

Butt joint Mitre joint Overlap joint

How to handle the tile boxes on site

Placing the first hanger and cross tee Max. 1 kg load per tile

Placing the wall springs Use the appropriate cross tees

Gyptone D1

Gyptone D1

Gyptone D1

Gyptone D1

Max. 2 mm air

Max. 100 mm.

Main beam is raised 15 mm above the wall angle

Gyp

tone

D1

Gyp

tone

D1

Gyptone Edge D1 – Installation manual 8

Gyproc A/SHareskovvej 12DK-4400 KalundborgPh: +45 59 57 03 30e-mail: [email protected] www.gyptone.com

ISO and OHSASGyproc A/S has a quality management system, which iscertified by BVQI Denmark A/A according to the demandsin ISO 9001, 14001 and OHSAS 18001

Humidity in the room should not exceed 70% during installation or usage

Fix wall angles to the wall with a max of 300 mm distance between the screws

Hangers should be at every 1200 mm. First hanger should be max. 100 mm from the wall

Main beams are placed with a cc distance of 600 mm and cross tees with a cc distance of 1200 mm. Cross tees should always be placed next to a hanger

Main beams and cross tees against the wall should be held 15 mm above the wall angle

Always use the specified D1 cross tees for mounting Gyptone D1 ceilings

All cross tees against the wall should be fixed to the wall

Use 2 wall springs per tile facing the wall

Gyptone edge D1 tiles have a max load capacity of 1kg

Gyptone edge D1™ systemChecklist for mounting of T-grid system and Gyptone edge D1 ceiling tilesWe recommend reading the manual thoroughly prior to installing the ceiling