Upload
prabhash-gokarn
View
38
Download
1
Embed Size (px)
Citation preview
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 1 of 14
Abstract
Tata Steel operates Manganese mines at Joda in Odisha producing Manganese ore which is sent to
the Ferro Alloy Plant at Joda and converted to Ferro Manganese. This Ferro Manganese is sent to
Tata Steel’s Steel Plants at Jamshedpur and Kalinganagar; as well as sold to customers across the
world.
The Ferro Alloy Plant at Joda was commissioned in 1958 and is in continuous operation since. It
currently produces 50,000 MTPA of HC Ferro Manganese in two Submerged Arc Furnaces.
Gas Cleaning Plant (GCP) slurry generated in wet venture scrubbers is collected in slurry pits inside
the plant for drying and subsequent disposal. Because of space constraints, and in order to recycle
the water used in the wet venture scrubbers, Tata Steel is upgrading its GCP slurry handling process
by the installation of a GCP slurry dewatering plant.
Construction of large structures within an operating plant, without affecting operations is always a
challenge. The job is even more challenging, since the plant is 58 years old, with many unmarked
structures, pipes, and cables lying underneath.
This paper discusses how new and unexpected challenges are tackled during the construction of the
Slurry Dewatering Plant without compromising on safe working.
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 2 of 14
Background
Manganese is the fourth most widely used metal after iron,
aluminium and copper. While it is used for various
applications, almost 90% is used in the manufacture of steel
for refining and as an alloying element.
In nature, Manganese occurs as oxidized or carbonated
mineral deposits (ores). Manganese Ores occurs as ferruginous
deposits in the Bonai-Keonjhar synclinorium region contiguous
with iron ore.
Manganese is usually added to steel as a ferro-alloy, i.e. a low
melting eutectic compound of Manganese with iron, carbon
and other elements. The two most common ferro alloys are high carbon ferro manganese & silico
manganese. The Ferro Alloy Plant at Joda currently produces high carbon ferro manganese from
Manganese Ores found locally.
Ferro Alloy Plant Joda and the Ferro Alloy Making Process
The Ferro Alloy Plant at Joda was
commissioned in 1958 to supply
manganese alloys to Tata Steel’s plant
at Jamshedpur.
It is India’s (and possibly the world’s)
oldest continuously operating Ferro
Alloy Plant.
It currently has two submerged arc
furnaces, one 9MVA and another
15MVA and produces 50,000 MTPA of
High Carbon Ferro Manganese through
carbo-thermic reduction of manganese
ore as shown in the accompanying
diagram.
Gas Cleaning Plant
The flue gases released during production contain manganese dust and other solid particles which
need to be cleaned before being released into the environment.
This is done by passing the flue gases through a Gas Cleaning Plant containing wet type venture
scrubbers; which use water to coalesce dust particles and let out the cooled and cleaned gases into
the environment.
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 3 of 14
Current Process of Slurry Management
The resultant slurry is thickened and transported to sludge pits via a pipeline. The sludge from the
Gas Cleaning Plant is then collected in sludge cleaning pits. Water from the sludge pits percolates
into the ground and contaminates ground water.
As sludge has been declared a hazardous waste by Odisha State Pollution Control Board (OSPCB); its
percolation into the ground needs to be avoided. Moreover, in the process, complete recycling of
water is not possible as a significant amount of water from the sludge pit is lost by this percolation.
Hence, we are in the process of installing a state of the art, Solid Liquid Separation Process plant at
FAP Joda in order to :
a. Meet the statutory norms of State Pollution Control Board, Odisha and compliance to the
conditions laid in the Consent to Operate.
b. Recycle & reuse water
c. Eliminate ground and surface water contamination and the expenditure on account of
impervious lining
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 4 of 14
Solid Liquid Separation Plant for Slurry Management
We are setting up a Mechanized de-watering plant with a High Rate Thickener and a Press Filter. The
Plant has the following equipment, :
a. Filter press with accessories,
b. Installation of High rate thickener with accessories
c. Process Automation supplied by the vendor
d. Chemical dosing system with accessories
e. Compressors and related electro-mechanical equipment
f. Standard attachments and accessories.
and, meets the three requirements from OPCB, namely :
a. Cooling water will be completely recycled through recycling from the mechanized dewatering
system (Figure 5 shows the water conservation that will be achieved).
b. The mechanized dewatering system will result in the dry sludge, which can safely be dumped
inside the plant in a manner which would not contaminate ground water. A retaining wall is to
be constructed in sludge dump area.
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 5 of 14
Construction Difficulties and How They Were Tackled
Since the plant has had to be retro-fitted to an existing, working plant, there is very little space for
accommodating all the facilities planned. After a lot of deliberations at site and design
improvements, the plant was designed so that it could fit in the space available; between the old
dump hopper and the old thickener. This in itself increased challenges during construction.
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 6 of 14
Site Safety Challenges
1. Old Dump Hopper – This Dump hopper building is a very old structure and situated at left of
pit excavated for the new thickener. Due to lack of space, we had to cut the slope vertically
(at almost 90o), so that the thickener base foundation, at a depth of 4 m could be fitted. The
lateritic soil becomes very weak once it rains. As remedial measure, strong shoring was done
to hold the soil slope. We also drilled hollow pipe sections into the ground to ensure stability
of the super structure, the old Dump Hopper Building.
2. Old GCP Thickener area - The structure is also very old and situated at the right of the
excavated pit of new thickener area. By the side of the structure is an old brick walled slurry
trench. The slurry lines in the trench take the thickened slurry from old thickener to the sludge
pits, with no alternate route. Dismantling of the brick walled drain would result in stopping of
the plant operations and a huge production loss. To avoid the loss, we first placed a strong
hollow pipe as an alternate route; then stabilize the trench and created a safe and working
environment for excavating pits for the foundation of the Thickener and Filter Press Buildings.
3. Existing pipe trench for slurry lines to the old slurry pit – Because the slurry trench passed
almost through the middle of the proposed area for setting up major structures of the new
plant; i.e. the new Thickener, the Filter Press and the DG Building; and the leakage of slurry
over the years from the old slurry pipes; the soil bearing capacity of the area was far lower
than the average. Hence, the foundations had to be built deeper, to a level of 4m to reach soil
stratum of good bearing capacity. This deep excavation posed difficulties in slope stabilization
which was tackled through proper shoring with pipe & steel sheet supports to the walls.
4. Live Cables through Project Site – The Ferro Alloy Plant at Joda plant is almost six decades
old and due to a lot of space available then, underground electrical cables have been laid in
an unplanned manner and without proper marking. Old drawings, if available were also lost.
To mitigate the risk of hitting live cables during excavation, we used a live cable detector to
mark the cable path before excavation.
Technical Challenges
1. Very Deep Excavation : Due to the issues cited above, the design team specified a RCC
foundation depth for the thickener & filter press area of 4m. Excavation to a depth of 4m in
soil that is of a reddish-brown lateritic type, mixed with ferruginous nodules, pebbles, gravel
etc. was challenging due to the widely varying soil hardness.
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 7 of 14
2. Water seepage : There was frequent water seepage from the top as well as from an
underground aquifer which submerged the excavated pit frequently, requiring frequent
dewatering. Because complete dewatering could not be done, rod binding, pouring concrete
etc. was very challenging!
3. Side Slope Unstable : Due to the water seepage problem, stability of pit slope was of prime
concern. Proper shoring, barricading was done to stabilize the slope and create a safe
working environment.
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 8 of 14
Safety Challenges during the Execution and How They Were Tackled
Making the Site Safe from Normal Operations
A. The Jigging Plant
The jigging plant was situated in the old thickener area, where the Solid Liquid Separation plant is
being constructed. The old jigging pit had a very thick RCC foundation. It took a lot of effort and time
to shift the jigging plant to a new location, including re-making the thick RCC foundation to start the
construction work.
B. Various Pipes & Cables
As mentioned earlier, in the almost 60 year old Ferro Alloy Plant, there were many unmarked
underground electrical cables and pipes in the construction area, which needed to be shifted. By
keeping the construction area separate from normal operations, it was possible to reroute the
cables without affecting operations which greatly increased safety during construction.
C. Weather Proofing : A major challenge has been working through the very heavy monsoon period
(June-16 to September-16). To ensure safe working we ensured that no foundation work
(excavation, making of columns etc), electrical work (HT cabling etc.) or erection work was
scheduled during the monsoon period.
Similarly, we ensured that during the very hot period from mid-March to mid-June, when heat
induced incidents are common, there was adequate supply ORS, cold water etc. as well as
rescheduled the work time, as per statutory guidelines, to avoid working between 11am and 3pm
when the temperature peaks.
D. Lack of space, mentioned earlier, has also meant that the work that could have been carried out
in parallel in any other site, has per-force had to be sequenced because of safety and other
execution. Keeping the stores at a different location, away from working area improved safety.
Site Safety
No job is so urgent that we cannot take the time to perform it safely
Mike Shavers, President, Mountain V Oil & Gas Inc
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 9 of 14
Safety is not negotiable, and we at Tata Steel, through years of training, efforts and learning from
incidents have made safe working almost second nature.
We jointly develop safe working SOPs, HIRA and training of workmen during the execution of the
job.
Inadequate planning and sequencing of jobs are major causes for onsite incidences; which we
avoided by proper planning & scheduling along with our contractor TENOVA India.
Timely and regular safety audit in the initial stages by external teams helped us greatly in identifying
hazards. Post the audits, we developed many safety protocols, some of them being :
a. Site Safety In-charges from Tata Steel, the engineering consultant and two site safety in-
charges from the execution partners were appointed for the project.
b. Daily tool box meeting conducted at site before start of job where the work to be done, along
with the possible hazards are discussed with each workman. This meeting is attended by the
Project Team from Tata Steel, the Engineering Team and all members of the execution team
of the Contractor and Sub-Contractor.
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 10 of 14
c. SOPs (Standard/Safe Operating Procedures) made for each activity. All workmen are trained
on these SOPs as required before start of job during the Tool Box meeting.
d. Check List for daily checking of all equipment : Grinding Machine, Dumpers, Cranes, JCBs, Fire
Extinguishers, Welding Machines, etc. made and followed on a daily basis.
e. Authorized entry ensured at site – with Proper Safety Training and issuing Gate Pass from
security as per norms.
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 11 of 14
f. Work permit system implemented at site – Identification of 6 directional Hazards and
Mitigation is a part of the work permit.
g. Use of Personal Protective Equipment (PPEs), as per nature of job is ensured at the site.
h. Labour shed with all facilities (separate kitchen, drinking water, toilets etc.) was the first
structure constructed. A further provision of designated rest areas, with drinking water
facilities, was also provided at site post the audit.
i. Protocols for movement of Dumpers, JCBs, Cranes and other heavy moving vehicles
developed. We have designed the layout in a systematic manner to ensure that all the
activities can be carried out during construction without unwanted hindrances from other jobs
being carried out in parallel.
j. MSDS for all chemicals, including fuel at site and following the listed precautions.
k. Emergency Response Plan displayed at all key locations.
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 12 of 14
l. Fire Safety : location of fire extinguishers such that they are easily approachable, having
regular mock drills etc., are also safe behavior that must be implemented at any construction
site.
m. Regular and Frequent Safety Inspections : The first safety truth relates to volume, with
studies showing injuries decrease as observations increase. Hence, we encouraged everyone
to audit the construction site and make observations of hazards, unsafe practices and suggest
improvements which we rigorously ensured were acted upon. We also instituted a system of
inspections in the night (on the rare occasions when work had to be done till late, due to a
casting for example).
n. Inspections by people from very diverse fields : The second safety truth involves the diversity
of observers. Involving observers with different skill sets allows risk to be better identified and
managed. Hence, by encouraging people from diverse fields (including those from “desk” jobs
like HR & Accounts) and different levels (new entrants & trainees to people with many years
of experience) we received feedback which was more comprehensive than if we restricted
making of observations.
o. Driving Ownership : this was one of the most difficult tasks. With identified safety officers
from Tata Steel, the Contractor and the Sub-Contractor, there was a tendency to view that
these safety professionals as owning the safety process, instead of safety being a group effort
which was tackled through regular communication in tool box meetings and review meetings.
p. Encouraging recording of both ‘safe’ and ‘unsafe’ observations : Projects with a high
frequency of all safe inspections are generally at a very high risk for injuries. The reasons
observers may falsely indicate nothing is wrong vary from not knowing how to determine
what is unsafe to fear of reprisal from management or fear that unsafe observations are
perceived as poor job performance. If error, including human error, is viewed as a criminal act
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 13 of 14
with penalty, no one would volunteer this information. Hence, we have tried to encourage a
culture of discovery in which we routinely are engaged and empowered to find and fix unsafe
activities, as well as address the causal factors that allowed them to occur in the first place.
q. Recording near misses is again a vital but very difficult task. Near misses have been defined as
unplanned behaviors or events that did not result in injury, illness or damage, but had the
potential to do so. We have recently started a system of reporting and acting on near misses.
r. Ensuring every observation is acted upon and closed is the cornerstone of ensuring safety in
the project site.
Conclusion
Ralph Waldo Emerson, the noted American Poet and Essayist once said, “Shallow men believe in
luck. Strong men believe in cause and effect.” He could be defining construction & process safety.
Having an incident in the workplace is always unplanned, and frequently seems to have occurred
due to a freak coincidence of many events; an accident. However, it is not. Safety is ensured only as
a result of hard work, proper planning, setting up of protocols for safe behaviour, including SOPs;
regular safety audits with attention paid to closing of observations, etc.
We have been both lucky and have worked hard at making the Solid Liquid Separation Plant
construction site safe. Much has been done, but still many lose ends remain. Safety is truly an on-
going journey. We are nowhere near mastering safe construction practices, we remain students.
With this article, we hope that by sharing our experiences and by reading about the experiences of
others in this safety journey, we will remain on the safety improvement path.
Safety Challenges in Construction of a Large Water Recovery Plant at India’s Oldest Ferro Alloy Plant
Page 14 of 14