Moving from Wastewater Treatment to Resource Recovery Christopher S. Crockett, Ph.D., P.E.

Wastewater Plant to Resource Recovery Facility

Embed Size (px)

DESCRIPTION

A description of the Philadelphia Water Department's Energy Planning and Alternative Energy Program

Citation preview

Page 1: Wastewater Plant to Resource Recovery Facility

Moving from Wastewater Treatment to Resource Recovery

Christopher S. Crockett, Ph.D., P.E.

Page 2: Wastewater Plant to Resource Recovery Facility

Energy HistoryPWD has historically worked to address energy issuesOff peak operationsLoad sheddingEfficiency projects

Page 3: Wastewater Plant to Resource Recovery Facility

3

• Annual Energy Consumption – 260 GWh

• Deregulation at end 2010• Forecast 30+% cost increases• Culture of saving energy

PHILADELPHIA WATER DEPARTMENT’S CHALLENGE

WATER TREATMENT COLLECTION CSPS3.8% 1.5%

WASTEWATERTREATMENT

48.6%DRINKING WATERPUMPING

46.1%

Page 4: Wastewater Plant to Resource Recovery Facility

GoalsOrganizational

Balance core mission and organization managementEnsure organizational capacity to sustain energy

managementBusiness

Promote Innovation in Energy Management Integrate renewable energy into overall energy portfolioEstablish monitoring programs for energy management

TechnicalPromote Energy Conservation and Peak Demand

Management Optimize Operational Processes and Practices Implement Capital Initiatives that Positively Impact

Energy Conservation Financial

Define Cost Effective Procurement Options Develop Reliable Energy Cost Forecasting Mechanisms

Page 5: Wastewater Plant to Resource Recovery Facility

ORGANIZATIONAL STRUCTURE

5

ENERGY CHAMPION

ENERGY MANAGEMENT TEAM

ENERGY MANAGEMENT TEAM Finance Officer of Water Water Treatment

Wastewater Treatment Conveyance Collection

Planning & Research Design City Liaison

FACILITY LEADERS

ENERGY MANAGEMENT TEAM Baxter WTP Belmont WTP Queen Lane WTP

Northeast WPCP Southeast WPCP Southwest WPCP

Torresdale PS Load Control Flow Control

Bureau of Laboratory Services

ADHOCWORKING GROUPS

Page 6: Wastewater Plant to Resource Recovery Facility

Energy Use Facility Generation & Conservation

BHSPS

CSPS

QLRXPS

SEWPCP

BRPWS

QLRWPS

LPPS

TPS

NEWPCP

SWWPCP

0 0102030405060 10 20 30 40 50 60

Total

0 050100150200250300 50 100 150 200 250 300

Energy PW Value/Gwh

Gwh/year by Facility Gwh/year by Facility

PresentWorth Conservation-Generation Value Gwh

TBD58.4

52.6 TBD

30.1

29.4

26.3

20.1

18.7

12.1

3.3

2.7

45 6.2

34 4.4

5.31.6

3.1

2.4

0.31.2

1.3

3.5 0.2

253.7 60.3 120.7 9.1 79 108.5

Gwh/year by Facility Gwh/year by Facility

Drinking Water Distribution

Solar Energy*

Biogas Energy

Conservation

Legend

Wastewater Treatment and Pumping

*Solar Energy Generation Values are based on information obtained from PWD as of April 2010.

Energy Use Facility Generation & Conservation

BHSPS

CSPS

QLRXPS

SEWPCP

BRPWS

QLRWPS

LPPS

TPS

NEWPCP

SWWPCP

0 0102030405060 10 20 30 40 50 60

Total

0 050100150200250300 50 100 150 200 250 300

Energy PW Value/Gwh

Gwh/year by Facility Gwh/year by Facility

PresentWorth Conservation-Generation Value Gwh

TBD58.4

52.6 TBD

30.1

29.4

26.3

20.1

18.7

12.1

3.3

2.7

45 6.2

34 4.4

5.31.6

3.1

2.4

0.31.2

1.3

3.5 0.2

253.7 60.3 120.7 9.1 79 108.5

Gwh/year by Facility Gwh/year by Facility

Drinking Water Distribution

Solar Energy*

Biogas Energy

Conservation

Legend

Wastewater Treatment and Pumping

*Solar Energy Generation Values are based on information obtained from PWD as of April 2010.

Energy Planning

Conservation = 29.5 Gwh/yrGeneration = 79 Gwh/yr

Page 7: Wastewater Plant to Resource Recovery Facility

PWD Energy ActivitiesStrategic Energy PlanHydroelectric Power – studies & designsAirport Deicing Fluid to Biogas - ongoingSolar at SE – constructed/operatingSolar American Cities – Facility solar plan

completedSewer Geothermal – constructed/operatingNE Cogen – 5.6 MW facility under constructionFood Waste Co-digestion – under studyAlgae Biofuels – researchLighting Efficiency ProjectsLoad Demand Reduction ProgramsHigh Efficiency Pumps

Page 8: Wastewater Plant to Resource Recovery Facility

Sewer Thermal

Biogas CogenerationDe-icing Fluid RecyclingFood Waste

Solar

Page 9: Wastewater Plant to Resource Recovery Facility

PWD Potential Solar SitesExamined Solar at

PWD facilitiesLimiting Factors

Use behind the meter

Rooftop upgrade timing

Operational needs

Page 10: Wastewater Plant to Resource Recovery Facility

Solar Panel InstallationSoutheast WPCP

PWD’s first solar installation Installed August 2010Medium-sized Photovoltaic

System (PV)1014 panels250 kWp DC power300,000 kWh AC power

production per year$1.5 million project costPWD owns Solar Renewable

Energy Certificates (S-RECs) associated with solar energy generatedS-RECs earn 12

cents/kWhSimple pay back of 8 to 14

years with 25 year life cycle

Page 11: Wastewater Plant to Resource Recovery Facility

Solar Panel Installation - Southeast WPCP

Page 12: Wastewater Plant to Resource Recovery Facility

Aircraft De-icing Fluid (ADF)Southwest WPCP

PWD earns revenue from tipping fees paid by Airport:$351/truck$54/1000 gallons

Each truck delivers between 5,000 and 7,500 gallons of ADF per load.

• Aircraft deicing fluid (ADF) runoff from Philadelphia International Airport accepted at Southwest WPCP.

• Adding ADF to plant’s anaerobic digesters produces useful methane gas without any negative impacts on process.

Page 13: Wastewater Plant to Resource Recovery Facility

FY ADF Load (MG)

Revenue($)

09 1.9 $100,000

10 3.5 $190,000

11 2.9 $160,000

12 0.7 $42,000

Total 9.0 $490,000

Aircraft De-icing FluidRevenue from Tipping Fees

Page 14: Wastewater Plant to Resource Recovery Facility

Sustainable Food Waste Management EPA Hierarchy for

Managing FW Effectively- Improving upstream

production and distribution systems

- Smart purchasing and use of food

- Feeding people with leftover food

- Using a food waste disposer (FWD)

- Composting in the backyard, using green bins and maintaining community gardens

Page 15: Wastewater Plant to Resource Recovery Facility

Clean Kitchen, Green Community Installation of 100 FWDs throughout West Oak Lane and

Point Breeze neighborhoods Purpose of Program: To divert FW from landfills and to

assess howFWDs can help the City reach its Greenworks Philadelphia sustainability goals

• Collaboration between the Streets Dept, PWD and InSinkErator

• Streets Dept will conduct focused MSW study for West Oak Lane and Point Breeze neighborhoods

Page 16: Wastewater Plant to Resource Recovery Facility

Biogas Cogeneration FacilityNortheast WPCP

NE WPCP uses 51.5 million kWh/year

FY 13 energy budget ~$5 million

Facility will meet 85% of current NE WPCP demand

• PWD uses 270 million kWh/year• Facility will meet 15% of total PWD

demand• Facility will reduce greenhouse gas

emissions by ~28,000 tons CO2/year

Page 17: Wastewater Plant to Resource Recovery Facility

Biogas Cogeneration FacilityEnvironmental MetricsFacility will produce 4 x 1.44 MW = 5.67 MW

electricityOff-set: 27,870 tons of CO2 / yearThis is equivalent to

4,833 passenger vehicles

5,390 acres of pine or fir forests

132 railcars of coal

2,843,487 gallons of gasoline

Page 18: Wastewater Plant to Resource Recovery Facility

Biogas Cogeneration FacilityNortheast WPCPThe PWD is using a unique business approach

to accomplish Biogas Cogeneration project.Capital limitations prohibit PWD from

commissioning contract of required size.Federal tax incentives require that energy projects

be owned by taxable entities.Developer will finance, install, build,

commission, own, and maintain facility. City will lease facility from Developer for

sixteen year term and use generated electricity and thermal heat.

Project also qualifies for $3.9 million in State Act 129 funding “PECO’s Smart Ideas.”

Page 19: Wastewater Plant to Resource Recovery Facility

Biogas Cogeneration FacilityNortheast WPCP

Contract signed with Ameresco 12/23/2011.

NTP issued 2/92012.

Construction in progress.

Mechanical Completion 5/1/2013.

Final Completion 12/31/2013.

Page 20: Wastewater Plant to Resource Recovery Facility

Sewage Geothermal InstallationSoutheast WPCP

Page 21: Wastewater Plant to Resource Recovery Facility

NovaThermal Energy awarded Greenworks Pilot Energy Technology Grant to demonstrate its unique patented geothermal technology.

System extracts thermal energy in sewage to provide 40% of energy needed to heat Compressor Building at Southeast WPCP. Heat pump operates at 60 cooling tons/978,000

BTUs/hr.10°C temperature differential between inlet

and outlet streams.

Sewage Geothermal InstallationSoutheast WPCP

Page 22: Wastewater Plant to Resource Recovery Facility

Sewage Geothermal InstallationSoutheast WPCPSystem operational in

February 2012. First use of sewage for

heating purposes in the United States.

Important step forward for establishing energy neutral wastewater treatment plant operations.

Generating renewable energy to substitute purchased power reduces City’s exposure to volatile energy market.

Page 23: Wastewater Plant to Resource Recovery Facility

HydropowerFlat Rock Dam20 foot elevation changePWD maintains walls and

Manayunk CanalPotential for way to

offset maintenance costAccommodating

hydropower development in wall repair design

Construction 2014-2015

Page 24: Wastewater Plant to Resource Recovery Facility

10 Year VisionVision of the EMT and the Utility Wide Strategic Energy Plan

0

400000

800000

1200000

1600000

2000000

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022

Fiscal Year

En

erg

y F

oo

tpri

nt

Metered Usage Generation Efficiency Total Energy Use

Page 25: Wastewater Plant to Resource Recovery Facility

ConclusionsEnergy independence vs. net energy

producer depends on market and operational issues

Be prepared for opportunities and new technologies

Be flexible and responsive to changing markets and technologies

Organizational capacity, processes, and commitment are needed to make progress

Think beyond their facility when it comes to energy

Page 26: Wastewater Plant to Resource Recovery Facility

AcknowledgementsDebra McCartyLen Gipson Bob Ferguson - SEWPCPBob Lendzinski – NEWPCPJohn MuldowneyPaul KohlTeresa DiGenovaDebjani MalikKristin Sullivan

Page 27: Wastewater Plant to Resource Recovery Facility

Moving from Wastewater Treatment to Resource Recovery Christopher S. Crockett,

Ph.D., [email protected]