32
1 | Page A REPORT ON INDUSTRIAL TRAINING ON (SWITCHGEAR & PROTECTION SYSTEM) AT 220kV GSS Kotputli Jaipur Under the guidance of Mr. Subhash Meena (A.En., RRVPNL)

Report

Embed Size (px)

Citation preview

Page 1: Report

1 | P a g e

A REPORT ON INDUSTRIAL TRAINING

ON

(SWITCHGEAR & PROTECTION SYSTEM)

AT

220kV GSS Kotputli

Jaipur

Under the guidance of

Mr. Subhash Meena

(A.En., RRVPNL)

Page 2: Report

2 | P a g e

Acknowledgement

This report is an outcome of the contributions made by some of the

peoples. Therefore, it is my sole responsibility to acknowledge them. I am

greatly thankful to the sincere efforts made by Mr. M.P. BADGUJAR,

X.En. (GSS, Kotputli) without whom this project would be abstract. I also

thank the staff of 220kV Grid Transmission Substation, Kotputli-Jaipur

who took out their precious time to tell me about the various equipments.

My special thanks is dedicated to Mr. Subhash Meena, A.En.

(maintenance).

SUNIL KUMAR YADAV

B. Tech (7th Sem)

Electrical Engineering

MALAVIYA NATIONAL INSTITUTE OF TECHNOLOGY

JAIPUR (RAJASTHAN)

Page 3: Report

3 | P a g e

DECLARATION

I hereby declare that this Industrial Training Report entitled ("switchgear

and protection systems") is an authentic record of my own work as

requirements of 45 days Industrial for the award of degree of B.Tech (Electrical Engineering), MNIT Jaipur.

(Signature of student)

(Name of Student) (Registration Number)

Date: 19 September,2016

Page 4: Report

4 | P a g e

ABSTRACT Training at 220 KV GSS Kotputli, Jaipur gives the insight of the real instruments

used. There are many instruments like transformer, CT, PT, CVT, LA, relay, PLCC,

bus bars, reactors, insulator, isolators, control room, etc. There are various problems

seen in substation while handling these instruments. There are various occasion when relay operate and circuit breaker open, load shedding, shut down of a feeder

in case of a fault , shutdown of total system, overheating of transformer, blasting of

current transformer in case of excessive current, transformer oil replacement, aging

of transformer oil, wireless communication, insulator classification as per current

rating, conductor requirement as per rating ,2 line and 3 line transmission, how to

put system on load and how to remove the system from load, automatic resetting of relay, isolator operation on off-load.

GSS is the mean of connection between generating station and consumer by

providing safety and reliability of system in case of fault. This sub-station step

down the incoming voltage power transmission to the required value and then is

supplied to the consumer feeder or GSS done by connecting auto transformer operation and requirement of various equipment have been include in detail, further

in case of report is the bus bar. Arrangement of different feeder level and switch

yards included information of bus bar arrangement of different level isolator and

growing substation also power transformer circuit breaker oil, filtration plant, and

compression protection control room and place are leveled.

The most important part of a G.S.S. is the battery room or most commonly known

as the heart of a G.S.S. without the battery system all the control panel, metering and

relay panel will not operate and therefore it will lead to failure of substation. As the

most important part of a GSS is battery room as control panel operate on this supply

it must be kept in spare as we have 220V DC supply and each battery supplies 2

volts hence 110 batteries will be kept in parallel to supply the same, hence always a backup of 110 batteries are always kept in storage room

Relay system is termed as the brain of the G.S.S. as it controls the circuit breaker

operations as it is very necessary to operate the circuit break operation in time, we

can take our time for closing on the circuit breaker but during fault circuit breaker

must be operated as soon as possible and arc must be quenched accordingly. To get insight of the substation, how things operate, how things are managed inside

a substation. Practical training as a whole proved to be extremely informative and

experience building and the things I learned here would definitely help a lot in

snapping the future ahead in a better way.

Page 5: Report

5 | P a g e

OBJECTIVE As a part of the engineering course curriculum every student has to go through a

minimum 45 days practical training from a premiere national level institute, this

training gives a chance to the student to really see how things are done practically

and how the problems are managed.

I decided to complete my training at 220 KV GSS, KOTPUTLI. As I am interested

in switchgear and protection systems a place better than G.S.S. could not have been

found.

My objective of training was to see how the equipment work in a proper manner,

how load is distributed, how power factor of system is improved, how fault is

measured with the help of megger(i.e. the potential difference between two lines) ,

how current transformers are installed , how logs are maintained, in what manner

earthing & protection system are installed, how cooling systems are operated.

Capacitor banks are really important in a substation as they help in improving the

power factor hence improving the voltage level in a system, because they supply

locally reactive power to the system and hence help in maintaining the tariff in limit.

As we all know that at a HV SUBSTATION we have assisting supplies also such a

motors and other loads also so to supply these we have an arrangement of stepping

down the voltage, this arrangement is really fascinating to me, to see this

arrangement was one of the main objective of the training.

As the most expensive and most important part of a substation is Transformer, so I

was really interested in seeing how the protection systems for transformers are

installed.

As the protection system includes C.T., RELAY & C.B., it was really important to

see the functioning of these instruments in co-ordination with each other.

While dealing with such equipments and at such a high voltage there is always a

possibility of accidental fires and water cannot be used to extinguish fire as current

is there in line, so fire extinguishing arrangement at a substation is really important

and I really wanted to see the extinguishing system.

Page 6: Report

6 | P a g e

INTRODUCTION

The "220 KV.GSS, RVPN Ltd. is ideally located at the KOTPUTLI, JAIPUR. GSS

is the medium of connection between generating station and consumers (Traction,

Industrial & Domestic etc.) by providing safety and reliability of whole system in

case of fault.

Steps of this sub-station are:- to step down the incoming voltage of power

transmission to a required value i.e. 220 KV to 132 KV, 132 KV to 33KV and then

supply to consumer's feeders of GSS done by connecting auto-transformer.

Operation requirement of various equipments have been included in detailed

manner further in report. There is one incoming line from ALWAR sub-station.

There are two 4 different outgoing line of 132kV, next we have 8 line of 33kV

outgoing feeder namely :

1. 33 kV PAOTA

2. 33 kV PANIYALA

3. 33 kV PANASIEA

4. 33 kV PATTAN CHALLA

5. 33 kV KOTPUTLI

6. 33 kV BEHROR II

7. 33 kV S. CEMENT

8. 33 kV PUTLI

We have 132 kV outgoing line to 4 different locations as:

1. 132 kV BEHROR

2. 132 kV NEEM KA THANA

3. 132 kV BANSUR

4. 132 kV SHAHPURA

Page 7: Report

7 | P a g e

INTRODUCTION OF RRVPNL

When India becomes independent its overall installed capacity was hardly 1900

MW. During first year plan (1951-1956) this capacity was only 2300 MW. The

contribution of Rajasthan state was negligible during 1&2 year plans & the

emphasis was on industrialization for that end it was considered to make the system

of the country reliable. Therefore, Rajasthan state electricity board came into

existence in July 1957.In India electrical power is generated at a voltage of 11KV

to 33 KV which is stepped up to the transmission level in the range of 66 KV to 400

KV. For transmitting power member of transmission and switching have to be

created. These are known as “SUB STATION”.

Along these transmission lines secondary substations are created where voltage is

further stepped down to sub transmission and primary distribution voltage.

A substation is an assembly of apparatus, which transform the characteristics of

electrical energy from one form to another say from one voltage level to another

level. Hence a substation is an intermediate link between the generating station and

consumer.

For economic transmission the voltage should be high so it is necessary to step up

the generated voltage for transmission and step down transmitted voltage for

distribution. For this purpose, substations are installed. The normal voltages for

transmission are 400kv, 220kv, 132kv and for distribution 33kv, 11kv etc.

Electricity boards are setup in all states of India which are responsible for

1.Generation

2.Transmission

3.Distribution

Page 8: Report

8 | P a g e

They also construct, install and maintain all the station made for these purpose.

In Rajasthan, R.R.V.P.N.L. is responsible for transmission and distribution of

electrical power all over Rajasthan. It has its own generating station and it’s also

gets power from various other stations also. It gets power from following stations:-

1. Badarpur

2. Bhakara Nangal Project (at sutlaj in Punjab)

3. Gandhi Sagar Dam Kota

4. Jawahar Dam Kota

5. Rana Pratap Sagar Dam Kota

6. Rajasthan Atomic Power Plant (RAPP) Kota

7. Kota Super Thermal Power Station (KSTPS) Kota

8. Anta Gas Power Plant Anta

9. Rajasthan share in Bhakara Beas Management Board (BBMB)

Power obtain from these stations is transmitted all over Rajasthan with the help of

grid stations. Depending on the purpose, substations may be classified as:-

1. Step up substation

2. Primary grid substation

3. Secondary substation

Page 9: Report

9 | P a g e

FUNCTIONS/ PROCESSES/ WORK DONE AT THE 220

KV GSS:

1.1 SUB STATION:

Electrical networks comprise the following region:

• GENERATING STATIONS

• TRANSMISSION SYSTEM

• RECEVING STATIONS

• DISTRIBUTUION SYSTEM

• LOAD POINTS

In all these regions, the power flow from generation station to final load point

takes place through electrical substation. A substation receives electrical power

from generating station via transformer incoming lines and delivers electrical

power via the outgoing transmission lines. A substation is an assembly of

electrical component including bus bars, switching, power transformer and

auxiliaries. Basically an electrical substation consists of number of incoming and

outgoing circuit connected to a common bus bar system. Bus bars are conducting

bars to which a no. of incoming and outgoing circuit are connected.

1.2 AN ELECTRICAL AUTHORITY AIMS AT THE

FOLLOWING:

1. Supply of electrical power to all the consumers continuously at all times.

2. Max coverage of the supply network over the given geographical area.

3. Max reliability of supply.

4.Minimum operation time of circuit breaker in fault duration.

5.Optimum efficiency of plants and the networks.

6.Supply of electrical power within specified voltage limits.

7.Supply of electrical energy to the consumers at the lowest cost.

Page 10: Report

10 | P a g e

1.3 THE TASK ARISES WITH THE MAJOR SUB STATION IN

THE TRANSMISSION AND DISTRIBUTION SYSTEMS ARE AS

FOLLOW :-

- Protection of transmission system

- Controlling the exchange of energy

- Ensuring the steady state and transient stability

- Load shedding and prevention of loss of synchronism maintaining the system

frequency within targeted limits.

- Voltages control, reducing the reactive power and tap changing

- Providing the adequate line capacity and facility for changing the transmission

paths

- Data transmission via power line carrier for the purpose of network monitoring,

controls and protection

- Determination the energy transfer through transmission lines and tie lines.

- Fault analysis and pin pointing the cause and subsequent improvement

- Established economic load distribution.

Page 11: Report

11 | P a g e

1.4 POWER SYSTEM DESIGN

In the power system design the following aspects have to be considered and studied

carefully.

(1) Land data, magnitude of rate of growth, Design of power station with details of

Equipment parts.

(2) Design of transmission lines and networks in the system for necessary load

transmission over a given distance with technical limitation and required

characteristics.

(3) Design of interconnections in the system.

(4) Design of distribution system.

(5) Choice of voltage, system control including voltage control, control of active and

reactive Load, system losses.

(6) Line compensation. System satiability studies and reliability studies.

(7) Bus - Bar arrangement.

(8) Power system protection, protection against fault protection against lighting.

1.5 E. H. V SUBSTATION DESIGN

(1) Types of substation and their classification.

(2) Choice of layouts & key diagrams.

(3) Selection of bus bar arrangements.

(4) Choice of BIL of equipment & main technical parameters, insulation cord.

(5) Selection of safety clearance.

(6) Design of ear thing system.

(7) Design of overhead shielding.

(8) Design of illumination system.

(9) Design of D.C supply.

(10) Design of fire protection.

(11) Design of communication system.

(12) Gas insulated substation.

(13) Design & selection of protective relaying system.

(14) Problems of operation & maintenance.

Page 12: Report

12 | P a g e

1.6 FOLLOWING ESSENTIAL EQUIPMENT:- 1.0 Main bus

2.0 Auxiliary bus

3.0 Insulators

4.0 Protective Relays

5.0 Circuit Breaker

6.0 Isolators

7.0 Power Transformers

8.0 Current Transformers

9.0 Potential Transformers

10.0 Lightning Arrestors

11.0 Relay and metering panels

12.0 Color Coding

13.0 Shunt capacitors and shunt reactors

14.0 Bus Coupler

15.0 Disturbance Recorder

16.0 Event Logger

17.0 On Load Tap Changer

18.0 No Load Tap Changer

19.0 Synchronoscope

As all the important and available equipment at the 220kv GSS are mentioned

above, explanation of each of the instrument available at the GSS are explained in

detailed and lucrative manner below:

2.0 BUS BARS

Bus Bars are the common electrical component through which a large no of feeders

operating at same voltage have to be connected. If the bus bars are of rigid type

(Aluminum types) the structure height are low and minimum clearance is required.

While in case of strain type of bus bars suitable ACSR(aluminum conductor steel

reinforced) conductor are strung/tensioned by tension insulators discs according to

Page 13: Report

13 | P a g e

system voltages. In the widely used strain type bus bars stringing tension is about

500-900 Kg depending upon the size of conductor used. Here proper clearance

would be achieved only if require tension is achieved. Loose bus bars would affect

the clearances when it swings while over tensioning may damage insulators. Even

the Clamps affect the supporting structures in low temperature conditions. The

clamping should be proper, as loose clamp would spark under in full load condition

damaging the bus bars itself. At 220 kV GSS Kotputli we have 2 main bus bars of

220 kv main bus-1 and main bus-2 ,also we have one auxiliary bus bar of 220 kv in

case of failure of one of the bus bar it can supply power hence increasing the

reliability of the system, apart from 220 kv bus bar we have one main bus bar of

132 kv namely main bus 1 and auxiliary bus of 132kv.

Various voltage levels and the suitable conductors used for them at the 220 kv GSS

are mentioned below:

220 kV Main Bus : Quadruple / Twin ACSR Zebra / Twin AAC Tarantulla

220 kV Auxiliary Bus : ACSR Zebra

220 kV equipment interconnection : Twin ACSR Zebra / Single ACSR Zebra

220 kV overhead bus & droppers in all bays : Twin ACSR Zebra / Single ACSR Zebra

132 kV Main Bus : ACSR Zebra

132 kV Auxiliary Bus : ACSR Panther

132 kV equipment inter connection : ACSR Zebra / ACSR Panther

132 kV overhead bus & droppers in all bays : ACSR Panther

33 kV Main Bus ACSR Zebra

33 kV Auxiliary Bus ACSR Zebra

Page 14: Report

14 | P a g e

3.0 INSULATOR

The insulator for the overhead lines provides insulation to the power conductors

from the ground so that currents from conductors do not flow to earth through

supports. The insulators are connected to the cross arm of supporting structure and

the power conductor passes through the clamp of the insulator. The insulators

provide necessary insulation between line conductors and supports and thus prevent

any leakage current from conductors to earth. In general, the insulator should have

the following desirable properties:

• High mechanical strength in order to withstand conductor load, wind load etc.

• High electrical resistance of insulator material in order to avoid leakage

currents to earth.

• High relative permittivity of insulator material in order that dielectric strength

is high.

• High ratio of puncture strength to flash over.

These insulators are generally made of glazed porcelain or toughened glass. Poly

come type insulator [solid core] are also being supplied in place of hast insulators

if available indigenously. The design of the insulator is such that the stress due to

contraction and expansion in any part of the insulator does not lead to any defect. It

is desirable not to allow porcelain to come in direct contact with a hard metal screw

thread.

Fig 1. Insulator

Page 15: Report

15 | P a g e

4.0 PROTECTIVE RELAYS

Relays must be able to evaluate a wide variety of parameters to establish that

corrective action is required. Obviously, a relay cannot prevent the fault. Its primary

purpose is to detect the fault and take the necessary action to minimize the damage

to the equipment or to the system. The most common parameters which reflect the

presence of a fault are the voltages and currents at the terminals of the protected

apparatus or at the appropriate zone boundaries. The fundamental problem in power

system protection is to define the quantities that can differentiate between normal

and abnormal conditions. This problem is compounded by the fact that “normal” in

the present sense means outside the zone of protection. This aspect, which is of the

greatest significance in designing a secure relaying system, dominates the design of

all protection systems.

Fig 2. Relay Panel

Page 16: Report

16 | P a g e

5.0 CIRCUIT BREAKER

The function of relays and circuit breakers in the operation of a power system is to

prevent or limit damage during faults or overloads, and to minimize their effect on

the remainder of the system. This is accomplished by dividing the system into

protective zones separated by circuit breakers. During a fault, the zone which

includes the faulted apparatus is de-energized and disconnected from the system. In

addition to its protective function, a circuit breaker is also used for circuit switching

under normal conditions.

Each having its protective relays for determining the existence of a fault in that zone

and having circuit breakers for disconnecting that zone from the system. It is

desirable to restrict the amount of system disconnected by a given fault; as for

example to a single transformer, line section, machine, or bus section. However,

economic considerations frequently limit the number of circuit breakers to those

required for normal operation and some compromises result in the relay protection.

Some of the manufacturers are ABB, AREVA, Cutler-Hammer (Eaton), and

Mitsubishi Electric,

Pennsylvania Breaker, Schneider Electric, Siemens, Toshiba, Končar HVS and

others.

Circuit breaker can be classified as "live tank", where the enclosure that contains

the breaking mechanism is at line potential, or dead tank with the enclosure at earth

potential. High-voltage AC circuit breakers are routinely available with ratings up

to 765,000 volts.

Page 17: Report

17 | P a g e

6.0 ISOLATORS

“Isolator" is one, which can break and make an electric circuit in no load

condition. These are normally used in various circuits for the purposes of Isolation

of a certain portion when required for maintenance etc. Isolation of a certain portion

when required for maintenance etc. "Switching Isolators" are capable of:

• Interrupting transformer magnetized currents

• Interrupting line charging current

• Load transfer switching

Its main application is in connection with transformer feeder as this unit makes it

possible to switch out one transformer, while the other is still on load. The most

common type of isolators is the rotating Centre pots type in which each phase has

three insulator post, with the outer posts carrying fixed contacts and connections

while the Centre post having contact arm which is arranged to move through 90` on

its axis.

Fig 3. Circuit Breaker

Page 18: Report

18 | P a g e

The following interlocks are provided with isolator:

a) Bus 1 and2 isolators cannot be closed simultaneously.

b) Isolator cannot operate unless the breaker is open.

c) Only one bay can be taken on bypass bus.

d) No isolator can operate when corresponding earth switch is on breaker.

Fig.4 Isolator

7.0 POWER TRANSFORMER

Distribution transformers reduce the voltage of the primary circuit to the voltage

required by customers. This voltage varies and is usually:

• 120/240 volts single phase for residential customers

• 480Y/277 or 208Y/120 for commercial or light industry customers.

• We have three transformers of total capacity 250 MVA namely:

1. BHEL transformer of 100 MVA capacity and 220/132kv

2. TELK transformer of 100 MVA capacity and 220/132kv.

Along with these transformers of 220/132 kv we have two more transformers of

132/33 kv capacity namely:

1.BBL transformer of 25 MVA capacity

2.TELK transformer of 25 MVA capacity

Page 19: Report

19 | P a g e

Three-phase pad mounted transformers are used with an underground primary

circuit and three single phase pole type transformers for overhead service.

Network service can be provided for areas with large concentrations of businesses.

These are usually transformers installed in an underground vault. Power is then sent

via underground cables to the separate customers.

Parts of Transformer: -

7.1 Windings:

Winding shall be of electrolytic grade copper free from scales & burrs. Windings

shall be made in dust proof and conditioned atmosphere. Coils shall be insulated

that impulse and power frequency voltage stresses are minimum. Coils assembly

shall be suitably supported between adjacent sections by insulating spacers and

barriers. Bracing and other insulation used in assembly of the winding shall be

arranged to ensure a free circulation of the oil and to reduce the hot spot of the

winding. All windings of the transformers having voltage less than 66 kV shall be

fully insulated. Tapping shall be so arranged as to preserve the magnetic balance of

the transformer at all voltage ratio. All leads from the windings to the terminal

board and bushing shall be rigidly supported to prevent injury from vibration short

circuit stresses.

Page 20: Report

20 | P a g e

Fig.5 Power Transformer

7.2 Tanks and fittings:

Tank shall be of welded construction & fabricated from tested quality low carbon

steel of adequate thickness. After completion of welding, all joints shall be

subjected to dye penetration testing.

At least two adequately sized inspection openings one at each end of the tank shall

be provided for easy access to bushing & earth connections. Turrets & other parts

surrounding the conductor of individual phase shall be non-magnetic. The main tank

body including tap changing compartment, radiators shall be capable of

withstanding full vacuum.

7.3 Cooling Equipment:

Cooling equipment shall conform to the requirement stipulated below:

7.3.1 Each radiator bank shall have its own cooling fans, shut off valves at the top

and bottom (80mm size) lifting lugs, top and bottom oil filling valves, air release

plug at the top, a drain and sampling valve and thermometer pocket fitted with

captive screw cap on the inlet and outlet.

Page 21: Report

21 | P a g e

7.3.2 Cooling fans shall not be directly mounted on radiator bank which may cause

undue vibration. These shall be located so as to prevent ingress of rain water. Each

fan shall be suitably protected by galvanized wire guard.

7.4 Temperature Indicators:

Most of the transformer (small transformers have only OTI) are provided with

indicators that displace oil temperature and winding temperature. There are

thermometers pockets provided in the tank top cover which hold the sensing bulls

in them. Oil temperature measured is that of the top oil, whereas the winding

temperature measurement is indirect

Fig.(6.1) OTI(temperature meter)

Page 22: Report

22 | P a g e

7.5 Silica Gel Breather:

Both transformer oil and cellulosic paper are highly hygroscopic. Paper being more

hygroscopic than the mineral oil The moisture, if not excluded from the oil surface

in conservator, thus will find its way finally into the paper insulation and causes

reduction insulation strength of transformer. To minimize this conservator is

allowed to breathe only through the silica gel column, which absorbs the moisture

in air before it enters the conservator air surface.

Fig.(6.2) Silica Gel Breather

8.0 CURRENT TRANSFORMER

As you all know this is the device which provides the pre-decoded fraction of the

primary current passing through the line/bus main circuit. Such as primary current

60A, 75A, 150A, 240A, 300A, 400A, to the secondary output of 1A to 5A.

When connecting the jumpers, mostly secondary connections is taken to three

unction boxes where star delta formation is connected for three phase and final leads

taken to protection /metering scheme.

Page 23: Report

23 | P a g e

Fig.7. Current Transformers

It can be used to supply information for measuring power flows and the electrical

inputs for the operation of protective relays associated with the transmission and

distribution circuit or for power transformer. These current transformers have the

primary winding connected in series with the conductor carrying the current to be

measured or controlled. The secondary winding is thus insulated from the high

voltage and can then be connected to low voltage metering circuits.

Page 24: Report

24 | P a g e

9.0 POTENTIAL TRANSFORMER

A potential transformer (PT) is used to transform the high voltage of a power line

to a lower value, which is in the range of an ac voltmeter or the potential coil of an

ac voltmeter.

The voltage transformers are classified

as under:

Capacitive voltage transformer or

capacitive type

Electromagnetic type.

Capacitive voltage transformer is being used more and more for voltage

measurement in high voltage transmission network, particularly for systems voltage

of 132KV and above where it becomes increasingly more economical. It enables

measurement of the line to earth voltage to be made with simultaneous provision

for carrier frequency coupling, which has reached wide application in modern high

voltage network for tele metering remote control and telephone communication

purpose.

10.0 LIGHTNING ARRESTOR

A lightning arrester (in Europe: surge arrester) is a device used on power systems

and telecommunications systems to protect the insulation and conductors of the

system from the damaging effects of lightning. The typical lightning arrester has a

high-voltage terminal and a ground terminal. When a lightning surge (or switching

surge, which is very similar) travels along the power line to the arrester, the current

from the surge is diverted through the arrestor, in most cases to earth.

In telegraphy and telephony, a lightning arrestor is placed where wires enter a

structure, preventing damage to electronic instruments within and ensuring the

safety of individuals near them. Smaller versions of lightning arresters, also called

Page 25: Report

25 | P a g e

surge protectors, are devices that are connected between each electrical conductor

in power and communications systems and the Earth. These prevent the flow of the

normal power or signal currents to ground, but provide a path over which high-

voltage lightning current flows, bypassing the connected equipment. Their purpose

is to limit the rise in voltage when a communications or power line is struck by

lightning or is near to a lightning strike.

If protection fails or is absent, lightning that strikes the electrical system introduces

thousands of kilovolts that may damage the transmission lines, and can also cause

severe damage to transformers and other electrical or electronic devices. Lightning-

produced extreme voltage spikes in incoming power lines can damage electrical

home appliances.

Potential target for a lightning strike, such as a television antenna, is attached to the

terminal labeled A in the photograph. Terminal E is attached to a long rod buried in

the ground. Ordinarily no current will flow between the antenna and the ground

because there is extremely high resistance between B and C, and also between C

and D. The voltage of a lightning strike, however, is many times higher than that

needed to move electrons through the two air gaps. The result is that electrons go

through the lightning arrester rather than traveling on to the television set and

destroying it.

A lightning arrester may be a spark gap or may have a block of a semi conducting

material such as silicon carbide or zinc oxide. Some spark gaps are open to the air,

but most modern varieties are filled with a precision gas mixture, and have a small

amount of radioactive material to encourage the gas to ionize when the voltage

across the gap reaches a specified level. Other designs of lightning arresters use a

glow-discharge tube (essentially like a neon glow lamp) connected between the

protected conductor and ground, or voltage-activated solid-state switches called

varistors or MOVs.

Lightning arresters built for power substation use are impressive devices, consisting

of a porcelain tube several feet long and several inches in diameter, typically filled

with disks of zinc oxide. A safety port on the side of the device vents the occasional

internal explosion without shattering the porcelain cylinder.

Page 26: Report

26 | P a g e

Lightning arresters are rated by the peak current they can withstand, the amount of

energy they can absorb, and the break over voltage that they require to begin

conduction. They are applied as part of a lightning protection system, in

combination with air terminals and bonding.

220 kV LIGHTNING ARRESTOR:

Manufacture: English electric company

No. of phase: One

Rated voltage: 360 kV

Nominal discharge current: (8×20µs) 10 kA

High current impulse: (4× 100µs) 100 kA

Long distribution rating: (200µs) 500 kA

Fig.8 Lightening Arrester on pole

Page 27: Report

27 | P a g e

11.0 CONTROL PANEL

Control panel contain meters, control switches and recorders located in the control

building, also called the dog house. These are used to control the substation

equipment to send power from one circuit to another or to open or to shut down

circuits when needed.

Fig 9. 220 KV GSS Kotputli Control Panel

Page 28: Report

28 | P a g e

12.0 COLOUR CODING

* 33KV GREEN

* 132 KV BLACK

* 220KV BROWN

* 440 VOLTS VOILET/INDIGO

* 110 VOLTS ORANGE

13.0 REACTOR It is used to lower the over excited capacitor. Capacitor bank is connected in shunt

over the reactor. Capacitors main purpose is to boost up the voltage. so when we

want to lower the voltage we use reactors. it is also use to stop the sudden change.

the commonly used reactor is NGR(Neutral ground reactor).

14.0 BUS COUPLERS It is used to equalize the load on both Bus bars.

15.0 DISTURBANCE RECORDER It records the distance & fault on graph with voltage w.r.t time.

Page 29: Report

29 | P a g e

16.0 EVENT LOGGER

It monitors as well as provides the details as a printed material.

These details may contain the sequence of operation, switching time, closing time

etc.

17.0 ON LOAD TAP CHANGER (OLTC)

In this method a number of tapings are provided on the secondary of the transformer.

The voltage drop in the line is supplied by changing the secondary emf of the

transformer through the adjustment of its number of turns by using transition

resistor which is placed in between each tapping.

Fig.10. Tap Changer

Page 30: Report

30 | P a g e

18.0 NO LOAD TAP CHANGER (NLTC)

In this we change the tap manually for which we have to shut down the transformer.

When the load increases the voltage across the primary drops but the secondary

voltage can be kept at the previous value by placing the movable arm on to a higher

stud. Whenever a tapping is to be changed in this type of transformer, the load is

kept off and hence the name off load tap-changing transformer.

19.0 SYNCHRONOSCOPE

A synchronoscope is used to determine the correct instance of closing the switch

with connect the new supply to bus bar the correct instance of synchronizing is

indicated when bus bar and incoming voltage

* are equal in magnitude

* are equal in phase

* have the same frequency

Page 31: Report

31 | P a g e

SUMMARY AND GAINS FROM THE TRAINING

A technician needs to have not just theoretical but practical as well and so every

student is supposed to undergo practical training session after 3rd year where I have

imbibed the knowledge about transmission, distribution, generation and

maintenance with economical issues related to it. During our 45 days training

session we were acquainted with the repairing of the transformers and also the

testing of oil which is a major component of transformer. At last I would like to say

that practical training taken at 220 kV GSS has broadened my knowledge and

widened my thinking as a professional.

Page 32: Report

32 | P a g e

REFERENCES

BOOKS:

[1] “A Course In Power Systems” by J.B. GUPTA(11th edition)

[2] “Modern Power System Analysis” by D.P. KOTHARI & I.J.

NAGRATH(4th edition)

ONLINE SOURCES

• http://www.alfredkim.co.in/bangalore/lightning-arrestor.html

• RVPNL HOME SITE :

• http://www.rvpn.co.in/aboutus/amis.shtml

• GATHERINGS DURING THE TRAINING PERIOD IN 220 KV G.S.S.

• Wikipedia

• REPORTS:

• Constructional manual of 220 kV GSS Kotputli(revised in 2008)