14
SUMMER TRAINING IN ON Suraj Bajpai M.E. (Polytechnic) MOTHERSON SUMI SYSTEMS LIMITED PRODUCTION PROCESS OF WIRING HARNESS

Ppt of training in MSSL

Embed Size (px)

Citation preview

Page 1: Ppt of training in MSSL

SUMMER TRAINING IN

ON

Suraj Bajpai M.E. (Polytechnic)

MOTHERSON SUMI SYSTEMS LIMITED

PRODUCTION PROCESS OF WIRING HARNESS

Page 2: Ppt of training in MSSL

Content

1. Company profile2. Wiring Harness3. LPC4. Assembly line5. Quality control

Page 3: Ppt of training in MSSL

Samvardhana Motherson Group is a global group which currently presence in 25 countries.This group is providing full systems solutions to automotive and other related industries.Samvardhana Motherson Group work in global manufacturing, global customer base and emerging markets

Page 4: Ppt of training in MSSL

Motherson Sumi Systems Limited is the flagship company of SMG.

And currently SMG have 45 group companies.

MSSL lucknow plant started from November 2011. and customer of lucknow is TATA moters.Product of lucknow – Wiring Harness

Page 5: Ppt of training in MSSL

What is Wiring Harness According to dictionary sources, the word "harness“ originally means the "fittings used for a horse and by which it is fastened to the cart, wagon, plough, etc. that it pulls". Then later, because of its general shape, a wiring assembly installed in automobiles was called "harness" or "wiring harness", in viewing the automobile in the same style as a wagon.

Page 6: Ppt of training in MSSL

What and function of w/h "Wiring Harness" could be termed in commonwords as an assembly of wires for automobiles.W/H is comprised of electrical circuits madeof low voltage wires by cutting them intorequired lengths and assembling them to makewiring (installation) inside the car An automobile Wiring Harness has to distributepower from the battery to devices located all over thecar (Ex: Headlamp, Horn, Radio, A/C…etc.)easy.

Page 7: Ppt of training in MSSL

LPC Process FLOW

. Cutting

, Crimping, Stripping

Before cri

mping

part fitting

Manua

l crimping

After cri

mping

part fitting

Middle

splicing

Joint cri

mping

Page 8: Ppt of training in MSSL

Automatic wire terminating machine

This machine have 10 sensors .This machine have 7 emergency stop push button and safety devices.

Page 9: Ppt of training in MSSL

Other units with C & C machine

1. Long wire receiving unit2. Interlayer paper winding unit3. Terminal overload detection unit4. Accumulator5. Micrometer6. Push-pull gauge

Page 10: Ppt of training in MSSL

Applicator

Applicator is the heart of C&C machine.1. Side feed applicator2. End feed applicator

Page 11: Ppt of training in MSSL

Assembly process flow

.

Circuits from charging

STA

RT

Circuit checking

Final assembly.

Parts fitting

END

Visual inspection.

Material feeding. Sub assembly.

Grommet fitting.

Page 12: Ppt of training in MSSL

Quality Control

Quality control department make the main role to achieve the goal of the company by these things.1. 6S2. 6R3. 3G4. FLAP

Page 13: Ppt of training in MSSL

Goal of the companySHINE TO WINS – SpeedH – HonestyI – ImproviseN – Not yet companyE – EvolversT – TrustO – Open to ideasW – Working togetherI – ImaginatorsN – Never give up attitude

Page 14: Ppt of training in MSSL

Thank you.