Runway Construction Sequence & Methods

© David H Moloney

Page 3: Heathrow 3rd Runway Construction

Runway Construction Methods

© David H Moloney

Earthworks Basecourse Ducts for ground lights

Asphalt Paving Line Marking Flight Check

Page 4: Heathrow 3rd Runway Construction

M25 Tunnel under Runway Construction Sequence & Methods

© David H Moloney

Page 5: Heathrow 3rd Runway Construction

Culvert under Runway Construction Methods

© David H Moloney

Earthworks Prepare Formation Floor

Walls Roof Backfill

Page 6: Heathrow 3rd Runway Construction

Heathrow Airport, 3rd Runway Construction

Introduction

This Presentation shows in a straightforward way how a runway

is constructed and how the progress, safety and quality is

monitored and controlled. Also the measures to ensure that

the site is environmentally friendly.

The Presentation can be used to engage Stakeholders and to

get the Site Teams commitment to the programme. Also can be

used as a way to capture and share knowledge.

Presentation can be used for safety and induction Training for

apprentices from the nearby communities that will be

employed on the new infrastructure. The Presentation shows

what to expect prior to stepping onto site and is currently used

for Training in Safety Compliance in airside operations to avoid

safety incidents and accidents

© David H Moloney

Page 7: Heathrow 3rd Runway Construction

Project Execution Plan for Runway Construction Details of how a Runway is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly.

David H Moloney

10th August 2016

Brief Description

The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Runway .

This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.

Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.

High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)This Video Presentation is innovative and has many beneficial uses.

http://www.slideshare.net/DavidHMoloney/runway-construction-project-execution-plan

Film at https://youtu.be/yCKLPzrDztw

© David H Moloney

Page 8: Heathrow 3rd Runway Construction

Table of Contents

© David H Moloney

Page 9: Heathrow 3rd Runway Construction

Runway Construction

© David H Moloney

Page 10: Heathrow 3rd Runway Construction

Runway Construction Sequence & MethodsR

oads &

Pavin

gs

© David H Moloney

Page 11: Heathrow 3rd Runway Construction

Excavate & Load Tipper Trucks

© David H Moloney

Page 12: Heathrow 3rd Runway Construction

Trench Excavation with Stepped Faces

© David H Moloney

Page 13: Heathrow 3rd Runway Construction

Trench Excavation with Battered Faces

© David H Moloney

Page 14: Heathrow 3rd Runway Construction

Spreading & Compaction Clay fillE

art

hw

ork

s

Page 15: Heathrow 3rd Runway Construction

Tipper Trucks Unloading

Page 16: Heathrow 3rd Runway Construction

Spreading & Compaction Clay fillE

art

hw

ork

s

Page 17: Heathrow 3rd Runway Construction

Backfill TrenchE

art

hw

ork

s

Page 18: Heathrow 3rd Runway Construction

Dozer Pushing ClayE

art

hw

ork

s

Page 19: Heathrow 3rd Runway Construction

Dozer Ripping GroundE

art

hw

ork

s

Page 20: Heathrow 3rd Runway Construction

Excavator with Hydraulic RockbreakerE

art

hw

ork

s

Page 21: Heathrow 3rd Runway Construction

Rock - Excavability

The excavability of rock depends mainly on the rock strength and the layer thickness. This diagram shows excavation methods for rock of various strengths and thicknesses, with a free face.

ⓒ David H Moloney

Page 22: Heathrow 3rd Runway Construction

CABC ( Crushed aggregate base course )E

art

hw

ork

s

Mixing Plant

Testing Compaction

Site Trial

Page 23: Heathrow 3rd Runway Construction

Mixing CABCE

art

hw

ork

s

Page 24: Heathrow 3rd Runway Construction

Spreading & Compaction CABC ( Crushed aggregate base course )E

art

hw

ork

s

Page 25: Heathrow 3rd Runway Construction

Spreading & Compaction CABC ( Crushed aggregate base course ) E

art

hw

ork

s

Page 26: Heathrow 3rd Runway Construction

Spreading & Compaction CABC ( Crushed aggregate base course )E

art

hw

ork

s

Page 27: Heathrow 3rd Runway Construction

Runway Asphalt PavementR

oads &

Pavin

gs

Brief Description

Sequence, plant and methods to construct a runway

Page 28: Heathrow 3rd Runway Construction

Prime Coat Site TrialsR

oads &

Pavin

gs

Bituminous Prime Coat shall

consist of supplying and applying

bituminous material to a previously

prepared and approved base

course in accordance with the

Specification to ensure a bond

between this surface and the

overlying course.

Page 29: Heathrow 3rd Runway Construction

Runway Asphalt Pavement - Prime CoatR

oads &

Pavin

gs

Page 30: Heathrow 3rd Runway Construction

Runway Asphalt PavementR

oads &

Pavin

gs

Page 31: Heathrow 3rd Runway Construction

Runway Asphalt PavementR

oads &

Pavin

gs

Page 32: Heathrow 3rd Runway Construction

Runway Asphalt PavementR

oads &

Pavin

gs

Page 33: Heathrow 3rd Runway Construction

Runway Asphalt PavementR

oads &

Pavin

gs

Page 34: Heathrow 3rd Runway Construction

Runway Asphalt Pavement - 4 Pavers working togetherR

oads &

Pavin

gs

Page 35: Heathrow 3rd Runway Construction

Runway Asphalt Pavement - 4 Pavers working togetherR

oads &

Pavin

gs

Page 36: Heathrow 3rd Runway Construction

Cutting JointR

oads &

Pavin

gs

Page 37: Heathrow 3rd Runway Construction

Runway Asphalt Pavement - Line & Level R

oads &

Pavin

gs

Checking asphalt level by Dip measurements

String line used for Level & line reference

Page 38: Heathrow 3rd Runway Construction

Runway Asphalt PavementR

oads &

Pavin

gs

Page 39: Heathrow 3rd Runway Construction

Runway Pavement - MarkingR

oads &

Pavin

gs

Page 40: Heathrow 3rd Runway Construction

Runway Pavement – Cleaning surface with rotating water jetsR

oads &

Pavin

gs

Page 41: Heathrow 3rd Runway Construction

Runway Pavement – Cleaning surface with rotating water jetsR

oads &

Pavin

gs

Page 42: Heathrow 3rd Runway Construction

Runway Pavement – Test for Skid Resistance

Roads &

Pavin

gs

Page 43: Heathrow 3rd Runway Construction

Runway Pavement R

oads &

Pavin

gs

Using the Douglas Mu-Meter continuous friction measuring equipment

Page 44: Heathrow 3rd Runway Construction

Runway Pavement – Test for Smoothness using Rolling Straight Edge

Roads &

Pavin

gs

Page 45: Heathrow 3rd Runway Construction

Runway Pavement – Test for Texture by Sand Patch testR

oads &

Pavin

gs

Page 46: Heathrow 3rd Runway Construction

Airfield Ground Lights Ducts & ChambersM

isce

llan

eo

us

Page 47: Heathrow 3rd Runway Construction

Airfield Ground Lights M

isce

llan

eo

us

Page 48: Heathrow 3rd Runway Construction

Airfield Ground Lights Ducts & ChambersM

isce

llan

eo

us

Page 49: Heathrow 3rd Runway Construction

Airfield Ground Lights Excavate Trench in CABCM

isce

llan

eo

us

Page 50: Heathrow 3rd Runway Construction

Airfield Ground Lights – Concrete DuctsM

isce

llan

eo

us

Page 51: Heathrow 3rd Runway Construction

Airfield Ground Lights – Surface Inset LightsM

isce

llan

eo

us

Page 52: Heathrow 3rd Runway Construction

Airfield Ground LightsM

isce

llan

eo

us

Jig to Level Pot

Page 53: Heathrow 3rd Runway Construction

Airfield Ground Lights - Core drill for Inset LightM

isce

llan

eo

us

Page 54: Heathrow 3rd Runway Construction

Airfield Ground Lights Fit Pot with JigM

isce

llan

eo

us

Page 55: Heathrow 3rd Runway Construction

Airfield Ground Lights M

isce

llan

eo

us

Page 56: Heathrow 3rd Runway Construction

Precast Yard - Chambers M

isce

llan

eo

us

Page 57: Heathrow 3rd Runway Construction

Delivery of Precast Chambers M

isce

llan

eo

us

Page 58: Heathrow 3rd Runway Construction

Airfield Ground Lights M

isce

llan

eo

us

Jointing HDPE Ducts Jointing HDPE Ducts

Precast Chamber Grouting Inset Light Pot

Page 59: Heathrow 3rd Runway Construction

ILS Localiser Antenna & Approach LightsM

isce

llan

eo

us

Provides lateral radio guidance to an aircraft approaching and landing on a runway

Page 60: Heathrow 3rd Runway Construction

Approach LightsM

isce

llan

eo

us

Page 61: Heathrow 3rd Runway Construction

Approach LightsM

isce

llan

eo

us

Used by the pilot to align the aircraft visually with the runway centreline.

Page 62: Heathrow 3rd Runway Construction

ILS Glide Path AntennaM

isce

llan

eo

us

Provides radio vertical guidance to an aircraft approaching and landing on a runway

Page 63: Heathrow 3rd Runway Construction

DVOR Ground StationM

isce

llan

eo

us

Omni Directional Radio Range (VOR) is a radio navigation system for aircrafts, so an aircraft can determine their position and stay on course.

Page 64: Heathrow 3rd Runway Construction

Airfield Lights - SubstationM

isce

llan

eo

us

Contains switchgear, protection and control equipment

Page 65: Heathrow 3rd Runway Construction

Airfield Lights - SubstationM

isce

llan

eo

us

Contains switchgear, protection and control equipment

Page 66: Heathrow 3rd Runway Construction

Airfield Lights – Taxi Guidance SignsM

isce

llan

eo

us

Taxi guidance signs provide direction and information to taxiing aircraft.

Page 67: Heathrow 3rd Runway Construction

Concrete Slipform PavingR

oads &

Pavin

gs

Brief Description

Horizontal slip forming for concrete pavement. The process

consists of placing and spreading low slump concrete on the

ground in front of a paver that slips over the concrete and

extrudes strips of slabs.

Slipform Concrete PaverSpreader

Texturing & Curing

Page 68: Heathrow 3rd Runway Construction

Concrete Slipform Paving – Texturing MachineR

oads &

Pavin

gs

Page 69: Heathrow 3rd Runway Construction

Concrete Slipform Paving - Slipform MachineR

oads &

Pavin

gs

Page 70: Heathrow 3rd Runway Construction

Concrete Slipform Paving – Placer / Spreader MachineR

oads &

Pavin

gs

Page 71: Heathrow 3rd Runway Construction

Concrete Slipform Paving R

oads &

Pavin

gs

Page 72: Heathrow 3rd Runway Construction

Concrete Slipform Paving R

oads &

Pavin

gs

Page 73: Heathrow 3rd Runway Construction

Concrete Slipform Paving R

oads &

Pavin

gs

Page 74: Heathrow 3rd Runway Construction

Concrete Slipform Paving R

oads &

Pavin

gs

Page 75: Heathrow 3rd Runway Construction

Concrete Slipform Paving – Drilling holes for dowelsR

oads &

Pavin

gs

Page 76: Heathrow 3rd Runway Construction

Concrete Slipform Paving – Drilling holes for dowelsR

oads &

Pavin

gs

Page 77: Heathrow 3rd Runway Construction

Runway Concrete PavementR

oads &

Pavin

gs

Page 78: Heathrow 3rd Runway Construction

Milling / Planing MachineR

oads &

Pavin

gs

Used to remove part of the surface of a paved area

Page 79: Heathrow 3rd Runway Construction

Cable LayingP

ipe

wo

rk

Brief Description

132 kVa Cable laying .

Page 80: Heathrow 3rd Runway Construction

Cable Laying P

ipe

wo

rk

Page 81: Heathrow 3rd Runway Construction

Cable Laying P

ipe

wo

rk

Page 82: Heathrow 3rd Runway Construction

Cable Laying P

ipe

wo

rk

Page 83: Heathrow 3rd Runway Construction

Cable Laying ⓒ David H Moloney

Cable Drum Stand Cable pulled on rollersCable Winch

Cable Drum Unloading Cable on rollers Cable Testing prior to Backfilling

Mis

ce

llan

eo

us

Page 84: Heathrow 3rd Runway Construction

Horizontal Directional DrillingP

ipe

wo

rk

Brief Description

Horizontal Directional Drilling under a taxiway.

Process

1. A pilot hole id drilled to the designed profile

2. A reamer is pulled back through the hole to enlarge it

3. A pipe string is pulled into the hole.

Page 85: Heathrow 3rd Runway Construction

Horizontal Directional DrillingP

ipe

wo

rk

Page 86: Heathrow 3rd Runway Construction

Micro TunnellingT

un

ne

ls

Page 87: Heathrow 3rd Runway Construction

Micro Tunnelling Sequence David H Moloney

ⓒ David H Moloney

Tu

nn

els

Page 88: Heathrow 3rd Runway Construction

FencingM

isce

llan

eo

us

Brief Description

Fencing.

Sequence of construction;

1. Clear and grade the ground.

2. Fix corner and straining posts.

3. Fix intermediate posts.

4. Fix line wire, chain-link and razor wire.

5. Construct concrete ground beam

Page 89: Heathrow 3rd Runway Construction

FencingM

isce

llan

eo

us

Page 90: Heathrow 3rd Runway Construction

FencingM

isce

llan

eo

us

Page 91: Heathrow 3rd Runway Construction

FencingM

isce

llan

eo

us

Page 92: Heathrow 3rd Runway Construction

FencingM

isce

llan

eo

us

Page 93: Heathrow 3rd Runway Construction

Fencing DeliveryM

isce

llan

eo

us

Page 94: Heathrow 3rd Runway Construction

Article on Muscat Airport Runway Link http://www.ccc.me/pdf/bulletins/bulletin103.pdf

Page 95: Heathrow 3rd Runway Construction

Runway Construction Pavement Details & Mixes

Runway Asphalt Runway Ends Concrete

Page 96: Heathrow 3rd Runway Construction

Concrete Delivery Order - RecordC

on

cre

te Brief Description

It is important to record orders for

concrete deliveries.

The form can be adapted for

other materials e.g.

reinforcement.

Page 97: Heathrow 3rd Runway Construction

Flight CheckTe

sts

Brief Description

Aircraft performing flight checks

on new Instrument Landing

System

Page 98: Heathrow 3rd Runway Construction

Concrete

Page 99: Heathrow 3rd Runway Construction

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Co

ncre

te

Brief Description

The sequence to construct a reinforced concrete wall is as

follows:

Tie the reinforcement.

Erect stop-ends and the wall shutters.

Pour and vibrate the concrete mix.

Remove the shutters after the concrete has hardened.

.

Cycle Time Pour per Day

Page 100: Heathrow 3rd Runway Construction

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Co

ncre

te

Page 101: Heathrow 3rd Runway Construction

Culvert ConstructionC

on

cre

te

Brief Description

Sequence to construct culvert

with head walls.

Page 102: Heathrow 3rd Runway Construction

Culvert ConstructionC

on

cre

te

Page 103: Heathrow 3rd Runway Construction

Oil InterceptorM

isce

llan

eo

us

Used to capture oil / fuel from leaks or spillages that are washed down drains every time it rains.

Page 104: Heathrow 3rd Runway Construction

Oil InterceptorC

on

cre

te

Page 105: Heathrow 3rd Runway Construction

Excavation for Underground Pump stationE

art

hw

ork

s

Brief Description

Faces of excavation Stepped &

Well-point Dewatering used.

Page 106: Heathrow 3rd Runway Construction

Concrete MixG

en

era

l It

em

s

A concrete mix contains 5 major

elements: cement, water, coarse

aggregates, fine aggregates (sand) and

air in different proportion. Additional

elements such as pozzolanic materials (fly

ash, silica fumes or slag) and chemical

admixtures can also be incorporated to

the mix to increase its properties.

Page 107: Heathrow 3rd Runway Construction

Vibrating Concrete

ⓒ David H Moloney

Co

ncre

te

Page 108: Heathrow 3rd Runway Construction

Airside Restrictions

Page 109: Heathrow 3rd Runway Construction

Stakeholders Engagement

Method of Work Plan (MOWP)

A Method of Working Plan (MOWP) is prepared when the normal operation of an aerodrome is

disrupted through aerodrome works and the risk to aircraft operations is increased. Stakeholders

likely to be significantly affected by the proposed works will be given the opportunity to participate

in the planning process.

The MOWP will clearly set out the following: • the scope of work and the stages of carrying out

the work; • how the works are to be carried out and the restrictions on the works organisation; •

how the aircraft operators and pilots will be told, through NOTAM, of the restrictions to aircraft

operations at each stage of the work; • identify any changes necessary to aerodrome markings

and lights as the works progress; • drawings to illustrate work arrangements and changes to

declared distances, taxiing routes, etc.; and • identify persons responsible for the works and those

accountable for ensuring safety of the aerodrome facilities to aircraft operations.

Airport Stakeholders

Operations G.M.

Technical Services G.M

Senior Aviation Manager

Chief Fire Officer

Project Manager

Sr. Maintenance Manager

Operations Reediness Team Leader

Certification & Compliance Manager

Airfield Duty Manager

Airport Duty Manager

HSE Specialist

DGSAS, Director of Airports

DGSAS, Aerodrome Certification

CAA Air Traffic Control –Tower

CAA Chief of Tower

Police

Ground Handling Agent

Airport Refueller Companies

Page 110: Heathrow 3rd Runway Construction

Airplane Wingtip ClearanceM

isce

llan

eo

us

Brief Description

Regulation distances shown

for wingtip clearance.

Page 111: Heathrow 3rd Runway Construction

Airplane Wingtip ClearanceM

isce

llan

eo

us

Page 112: Heathrow 3rd Runway Construction

Taxiway Reconstruction AirsideM

isce

llan

eo

us

Brief Description

Regulations regarding working adjacent to

a live runway.

Page 113: Heathrow 3rd Runway Construction

Taxiway Reconstruction AirsideM

isce

llan

eo

us

Page 114: Heathrow 3rd Runway Construction

Working Airside to Upgrade Taxiway

Asphalt Pavement Laid on Existing Concrete Pavement Temporary Gate and Fence

Excavation Planing at Runway tie-inFill –Crushed Aggregate Rake sealant out of Joints

Page 115: Heathrow 3rd Runway Construction

Taxiway Reconstruction AirsideM

isce

llan

eo

us

Page 116: Heathrow 3rd Runway Construction

Contractors Temporary Facilities

Page 117: Heathrow 3rd Runway Construction

Temporary Contractors Site Facilities

ⓒ David H Moloney

Brief Description

Site Offices, Camp Accommodation for 1,250 workers, Canteen, Recreation, Fabrication shops, Stores, Plant Yard. In five locations along the route.

Page 118: Heathrow 3rd Runway Construction

Welfare Facilities

ⓒ David H Moloney

Ge

ne

ral It

em

s

Toilets – Washing

Canteen, Drying Room, Toilet & Generator

Page 119: Heathrow 3rd Runway Construction

Site Hoarding examples

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 120: Heathrow 3rd Runway Construction

Temporary Fence type 1

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Examples of temporary security fences that are higher than the usual

Page 121: Heathrow 3rd Runway Construction

Temporary Fence type 1

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 122: Heathrow 3rd Runway Construction

Temporary Fence type 2

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Temporary fence on precast beam for airport.

Page 123: Heathrow 3rd Runway Construction

Temporary Fence type 2

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 124: Heathrow 3rd Runway Construction

Dewatering

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Construction dewatering is the removal or drainage of

groundwater and or surface / rain water usually by

pumping to keep the works dry.

Page 125: Heathrow 3rd Runway Construction

Dewatering

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Construction dewatering is the removal or

drainage of groundwater and or surface /

rain water usually by pumping to keep the

works dry.

Page 126: Heathrow 3rd Runway Construction

Dewatering

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 127: Heathrow 3rd Runway Construction

Wheel Wash Drive-through

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 128: Heathrow 3rd Runway Construction

Wheel Wash Drive-throughG

en

era

l It

em

s

Page 129: Heathrow 3rd Runway Construction

Temporary Electricity Supply & Tower Lights

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 130: Heathrow 3rd Runway Construction

Asphalt Batching YardG

en

era

l It

em

s

Page 131: Heathrow 3rd Runway Construction

Asphalt Batching YardG

en

era

l It

em

s

Page 132: Heathrow 3rd Runway Construction

Asphalt Batching YardG

en

era

l It

em

s

Page 133: Heathrow 3rd Runway Construction

Concrete Batching Yard 3 Nr MixersG

en

era

l It

em

s

Page 134: Heathrow 3rd Runway Construction

Concrete Batching Plant David H Moloney

ⓒ David H Moloney

Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production

Page 135: Heathrow 3rd Runway Construction

Concrete Batching Yard 3 Nr MixersG

en

era

l It

em

s

Page 136: Heathrow 3rd Runway Construction

Crushed Aggregate Batching PlantG

en

era

l It

em

s

Page 137: Heathrow 3rd Runway Construction

Crushed Aggregate Batching PlantG

en

era

l It

em

s

Page 138: Heathrow 3rd Runway Construction

Quarry & Aggregate ProductionG

en

era

l It

em

s

Page 139: Heathrow 3rd Runway Construction

Quarry & Aggregate ProductionG

en

era

l It

em

s

Page 140: Heathrow 3rd Runway Construction

Reinforcement Cutting & Bending Yard David H Moloney

ⓒ David H Moloney

Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine

Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site

Page 141: Heathrow 3rd Runway Construction

Reinforcement Cutting & Bending

ⓒ David H Moloney

Co

ncre

te

Page 142: Heathrow 3rd Runway Construction

Setting out & Surveying

Page 143: Heathrow 3rd Runway Construction

Setting out & Surveying

Page 144: Heathrow 3rd Runway Construction

Setting out & Surveying

Page 145: Heathrow 3rd Runway Construction

Safety & Environmental

Page 146: Heathrow 3rd Runway Construction

Emergency Phone Numbers & Response

Page 147: Heathrow 3rd Runway Construction

HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of

current HSE Issues and historical trends

Page 148: Heathrow 3rd Runway Construction

Site Safety Posters examples

Page 149: Heathrow 3rd Runway Construction

Safety Precautions

Page 150: Heathrow 3rd Runway Construction

Personal Protective Equipment (PPE)H

ealth,

Safe

ty &

Envir

onm

ent

Personal protective equipment (PPE) is protective clothing, helmets, goggles, or other garments or equipment designed to protect the wearer from injury or infection

Page 151: Heathrow 3rd Runway Construction

Existing Underground Utilities

ⓒ David H Moloney

Ea

rth

wo

rks

Brief Description

Before digging

establish the location

and route of

underground utilities.

Locator to find Utilities

Spray Paint to mark pavement

Page 152: Heathrow 3rd Runway Construction

Existing Underground Utilities & Overhead Cables - Safety Measures

ⓒ David H Moloney

Ea

rth

wo

rks

Page 153: Heathrow 3rd Runway Construction

Trench - Safety Measures H

ealth,

Safe

ty &

Envir

onm

ent

Page 154: Heathrow 3rd Runway Construction

Trench - Safety Measures

ⓒ David H Moloney

Health,

Safe

ty &

Envir

onm

ent

Page 155: Heathrow 3rd Runway Construction

Safety Training on Site M

isce

llan

eo

us

The purpose of safety training is to provide the knowledge necessary to

perform a job safely

Page 156: Heathrow 3rd Runway Construction

Safety Training Matrix M

isce

llan

eo

us

The purpose of safety training is to provide the knowledge necessary to

perform a job safely

Page 157: Heathrow 3rd Runway Construction

Emergency Response Drill H

SE

Drills and exercises are used to rehearse anticipated emergency scenarios

Page 158: Heathrow 3rd Runway Construction

Safety DocumentsH

ealth,

Safe

ty &

Envir

onm

ent

Safe System of Work.

To provide a safe system of work is a legal requirement. What this means is that before you ask an employee to do a

job. You ensure that he has received training, has the appropriate personal protective equipment, the work area is safe

and he is unlikely to be injured or cause damage by carrying out the assigned task.

Project Management Plan for Health, Safety, Security and Environment. also Known as (HSSE Plan)

The Project HSSE Management Plan details how safety on site will be managed.

Project Procedures for Health, Safety, Security & Environment

Details the safe way to undertake a task

Methods Statements

Are prepared in advance of starting work, to plan a Safe System of Work on site for all activities that carries a risk. The

contents of a Method Statement, typically include:- Scope & Location of the Works, Programme, Roles & Responsibilities

of Staff. Resources, Work Methodologies and Risk Assessment.

Slide 1 of 2

Page 159: Heathrow 3rd Runway Construction

Safety DocumentsH

ealth,

Safe

ty &

Envir

onm

ent

Safety Risk Assessments

Are prepared to identify and evaluate risks, to adopt control measures to reduce or eliminate risks.

COSHH Sheet

The purpose of the Control Of Substances Hazardous to Health sheet is to identify how to prevent or adequately control

workers exposure to hazardous substances.

Permit to Work.

Is a management system used to control high risk activities by ensuring safety measures are in place prior to starting

work.

Types of work for which permits will be required include:

Excavation and the digging of trenches.

Working at height, including on roofs.

Working in confined spaces, for example entering a manhole.

Hot work, which is welding, soldering or cutting steel with angle grinders or by gas torch.

Slide 2 of 2

Page 160: Heathrow 3rd Runway Construction

Environmentally Friendly Site Air, Noise, Water & Soil Pollution

Page 161: Heathrow 3rd Runway Construction

Hazardous Substances Symbols H

ealth,

Safe

ty &

Envir

onm

ent

COSHH stands for the Control of Substances Hazardous to Health

Shown are the new hazard symbols

Page 162: Heathrow 3rd Runway Construction

Water Pollution PreventionG

en

era

l It

em

s

Page 163: Heathrow 3rd Runway Construction

Segregation of Waste H

ealth,

Safe

ty &

Envir

onm

ent

Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe.

Colour Code for Skips & Bins

Page 164: Heathrow 3rd Runway Construction

Putting Waste Concrete to use

ⓒ David H Moloney

Health,

Safe

ty &

Envir

onm

ent

Precast bases for signs and hoarding, Precast blocks for walls.

Page 165: Heathrow 3rd Runway Construction

Administration

Page 166: Heathrow 3rd Runway Construction

Organogram

Brief Description

Shown are the line and

lateral relationships

between the various team

members and their relative

position in the site

organisation.

Page 167: Heathrow 3rd Runway Construction

Staff Responsibility Matrix

Page 168: Heathrow 3rd Runway Construction

Staff Directory

Brief Description

List of staff and their

contact details

Page 169: Heathrow 3rd Runway Construction

Daily Work Record

Brief Description

Daily Work Records showing the

allocation of resources, materials and

work activities carried out daily.

Page 170: Heathrow 3rd Runway Construction

Quotations Comparison Sheet

Page 171: Heathrow 3rd Runway Construction

Filing System

Page 172: Heathrow 3rd Runway Construction

Quality Assurance

Page 173: Heathrow 3rd Runway Construction

Quality Assurance Dashboard Dashboard is a single page, graphical representation of

current statistics and historical trends

Page 174: Heathrow 3rd Runway Construction

Runway Asphalt Pavement - TestsR

oads &

Pavin

gs

Page 175: Heathrow 3rd Runway Construction

Quality Assurance Tests

Page 176: Heathrow 3rd Runway Construction

Runway Concrete Pavement - TestsR

oads &

Pavin

gs

Page 177: Heathrow 3rd Runway Construction

Runway LaboratoryR

oads &

Pavin

gs

Page 178: Heathrow 3rd Runway Construction

Laboratory

ⓒ David H Moloney

Asp

ha

lt P

avin

g

Page 179: Heathrow 3rd Runway Construction

Programme & Progress Monitoring

Page 180: Heathrow 3rd Runway Construction

Progress Monthly, Monitoring & Reporting - DashboardDashboard is a single page, graphical representation of current

progress and historical trends

Page 181: Heathrow 3rd Runway Construction

Histogram Charts for Resources & Outputs

Manpower per Discipline

Concrete per Location

Man-hours for each month of the Project

Quantity for each month of the Project

ⓒ David H Moloney

Brief Description

Histograms shows resources etc. for each month of a project.

Page 182: Heathrow 3rd Runway Construction

Plant & Equipment List & Worker’s Job Titles

ⓒ David H Moloney

Page 183: Heathrow 3rd Runway Construction

Programme for Construction

Gantt Charts to plan and schedule projects

Page 184: Heathrow 3rd Runway Construction

Primary Substation-

Chiller Plant

Pump House

IRRIGATION WATER TANKS

Irrigation Pump House-

POTABLE/FIRE WATER TANK

Programme using Timeline & 3D Images

Airport Central Utility Yard

Page 185: Heathrow 3rd Runway Construction

Pump House

Piling

Page 186: Heathrow 3rd Runway Construction

Primary Substation

Chiller PlantPump House

Irrigation Pump House

Page 187: Heathrow 3rd Runway Construction

Primary Substation-711

Chiller Plant-714Pump House-715

Irrigation Pump House-716

Page 188: Heathrow 3rd Runway Construction

Primary Substation-711

Chiller Plant-714Pump House-715

IRRIGATION WATER TANK

Irrigation Pump House-716

Page 189: Heathrow 3rd Runway Construction

Primary Substation-711

Chiller Plant-714Pump House-715

IRRIGATION WATER TANK

Irrigation Pump House-716

Page 190: Heathrow 3rd Runway Construction

Primary Substation-711

Chiller Plant-714Pump House-715

IRRIGATION WATER TANK

Irrigation Pump House-716

Page 191: Heathrow 3rd Runway Construction

Primary Substation-711

Chiller Plant-714Pump House-715

IRRIGATION WATER TANK

Irrigation Pump House-716

Page 192: Heathrow 3rd Runway Construction

Primary Substation-711

Chiller Plant-714Pump House-715

IRRIGATION WATER TANK

Irrigation Pump House-716

POTABLE/FIRE WATER TANK

Page 193: Heathrow 3rd Runway Construction

Miscellaneous

Page 194: Heathrow 3rd Runway Construction

Structural Steel

Page 195: Heathrow 3rd Runway Construction

Airport Roof Truss

ⓒ David H Moloney

Str

uctu

ral S

tee

l

Brief Description

Roof Truss 190 tonne in weight. Sections welded together on

trestles and the truss is lifted into position.

Page 196: Heathrow 3rd Runway Construction

Airport Roof TrussS

tru

ctu

ral S

tee

l

Roof Truss Sections Roof Truss Sections assembled on trestles

Trusses weigh 190 tonnes Crane Demag CC 8800

Page 197: Heathrow 3rd Runway Construction

Airport – Roof Section Mock-up S

tru

ctu

ral S

tee

l

Page 198: Heathrow 3rd Runway Construction

Airport Piers Roof Frames S

tru

ctu

ral S

tee

l

Sections assembled on trestles

Page 199: Heathrow 3rd Runway Construction

Pedestrian Boarding Bridges & Bridge House S

tru

ctu

ral S

tee

l

Page 200: Heathrow 3rd Runway Construction

Pedestrian Boarding Bridges & Bridge HouseS

tru

ctu

ral S

tee

l

Page 201: Heathrow 3rd Runway Construction

Pedestrian Boarding Bridges & Bridge HousesS

tru

ctu

ral S

tee

l

Mock-up

Page 202: Heathrow 3rd Runway Construction

Airport Roof TrussS

tru

ctu

ral S

tee

l

Page 203: Heathrow 3rd Runway Construction

Airport Roof TrussS

tru

ctu

ral S

tee

l

Page 204: Heathrow 3rd Runway Construction

Piers ConstructionS

tru

ctu

ral S

tee

l

Page 205: Heathrow 3rd Runway Construction

Piers ConstructionS

tru

ctu

ral S

tee

l

Page 206: Heathrow 3rd Runway Construction

Roof Covering

ⓒ David H Moloney

Str

uctu

ral S

tee

l

Brief Description

Sequence is

Fix bottom sheet

Fix Vapour barrier

Fix Top Hat section and clips

Fit Insulation

Fix top sheet

Page 207: Heathrow 3rd Runway Construction

Roof Covering

ⓒ David H Moloney

Str

uctu

ral S

tee

l

Page 208: Heathrow 3rd Runway Construction

Roof Covering

ⓒ David H Moloney

Str

uctu

ral S

tee

l

Page 209: Heathrow 3rd Runway Construction

Roof Covering

ⓒ David H Moloney

Str

uctu

ral S

tee

l

Page 210: Heathrow 3rd Runway Construction

View from ATC TowerM

isce

llan

eo

us

Page 211: Heathrow 3rd Runway Construction

View from ATC TowerM

isce

llan

eo

us

Page 212: Heathrow 3rd Runway Construction

View from ATC TowerM

isce

llan

eo

us

Page 213: Heathrow 3rd Runway Construction

Tower ConstructionC

on

cre

te

Brief Description

Air Traffic Control Tower constructed

using a jump-up shutter system.

Page 214: Heathrow 3rd Runway Construction

ATC Tower CladdingC

on

cre

te

Page 215: Heathrow 3rd Runway Construction

Production by David H Moloney

My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ