31
DEPARTMENT OF CONSTRUCTION MANAGEMENT PROJECT COVER SHEET STUDENT NAME: STUDENT NUMBER: C 123 COURSE/ YEAR DT117/4 SUBJECT: Health and Safety Management 2 PROJECT TITLE: Alphen aan den rijn crane salvage LECTURER: FOR OFFICE USE ONLY: DATE DUE: 22 nd October 2015 DATE RECEIVED: RECEIVED BY: REPEAT PROJECT? MARKS:

Health and safety management 2

Embed Size (px)

Citation preview

Page 1: Health and safety management 2

DEPARTMENT OF CONSTRUCTION MANAGEMENT

PROJECT COVER SHEET

STUDENT NAME:

STUDENT NUMBER: C 123

COURSE/ YEAR DT117/4

SUBJECT: Health and Safety Management 2

PROJECT TITLE: Alphen aan den rijn crane salvage

LECTURER:

FOR OFFICE USE ONLY:

DATE DUE: 22nd October 2015

DATE RECEIVED:

RECEIVED BY:

REPEAT PROJECT?

MARKS:

Page 2: Health and safety management 2

C123 Alphen ann den rijn crane salvage 2

Contents

INTRODUCTION TO COMPANY’S AIMS AND OBJECTIVES .............. 3

ACCIDENT SUMMARY REPORT ............................................................................................................................. 3 SITE LOCATION ................................................................................................................................................... 6

SCOPE OF WORKS .......................................................................................... 7

SITE SPECIFIC SAFETY PLAN ..................................................................... 8

SITE SECURITY .................................................................................................................................................... 8 SITE RULES & EMERGENCY PROCEDURES ............................................................................................................ 8 WELFARE FACILITIES & FIRST AID ...................................................................................................................... 9 SIT ACCESS .......................................................................................................................................................... 9 TRANSPORT ....................................................................................................................................................... 10

TRAFFIC MANAGEMENT PLAN................................................................ 11

REQUIRED PLANT AND EQUIPMENT ..................................................... 12

MOBILE WELDING UNIT ..................................................................................................................................... 12 GRINDER ........................................................................................................................................................... 12 LIFE JACKETS & HARNESS ................................................................................................................................ 13 BARGE HEBO P12 ............................................................................................................................................ 13 FLOATING BUCK ................................................................................................................................................ 14 THE CRANE WILL BE HIRED FOR THE DURATION OF THE PROJECT. THIS CRANE IS AN EXCELLENT CHOICE FOR

THIS PROJECT AS IT HAS SLEWING CAPABILITIES AND CAN TRAVEL WITH A LOAD. THIS FEATURE OFFERS A LOT

MORE MOBILITY AS IT WILL BE LOCATED ON THE RIVER WHICH TAKE UP A LOT OF THE LIMITED, AVAILABLE

SITE SPACE THAT IS NOT BEING USED. ITS LONG SPAN OVER THE BARGE AND THE FALLEN CRANES WILL ALLOW

EXTRA REACH AND CAN LIFT HEAVY LOADS OF UP TO 300 TONES ..................................................................... 14 TELESCOPIC CRANE MAMMOET .................................................................................................................... 15

RISK ASSESSMENT ....................................................................................... 16

WHAT IS A RISK ASSESSMENT? ......................................................................................................................... 17 RISK ASSESSMENT AIMS ................................................................................................................................... 17 WHAT ARE CONTROL MEASURES ...................................................................................................................... 17 THE PROCESS OF RISK ASSESSMENT .................................................................................................................. 18 RISK ASSESSMENT CLASSIFICATION .................................................................................................................. 18

METHOD STATEMENT ................................................................................ 19

INTRODUCTION ..................................................................................................................................................... 20 PERMIT TO WORK SYSTEMS (PTWS) ................................................................................................................. 20 CRANE OPERATIONS OF LIFTING PLAN .............................................................................................................. 25 CONCLUSION ..................................................................................................................................................... 26 REFERENCES ..................................................................................................................................................... 27 RICHARD L. KRABBENDAM, HEAVY LIFTS SPECIALIST, DETAILS ON CRANE (ONLINE) LINK:

HTTP://WWW.HEAVYLIFTSPECIALIST.COM/AUTHOR/RICHARD/ .......................................................................... 28 (ACCESSED 7TH OCTOBER 2015) ........................................................................................................................ 28

TOOLBOX TALKS TO BE CARRIED OUT .. ERROR! BOOKMARK NOT

DEFINED.

Page 3: Health and safety management 2

C123 Alphen ann den rijn crane salvage 3

Page 4: Health and safety management 2

C123 Alphen ann den rijn crane salvage 4

Introduction to company’s aims and objectives

As the Health & Safety Manager for the crane company. I’m here by required to do a detailed

report for the Dutch Health and Safety authority listing all the sequential steps taken by

following the accident.

This document will provide a detailed Risk Assessment and Method Statement explaining how

our company is going to remove cranes from the water and buildings with minimum impact to

all local shops and residence. Main objective of this report is to analyse specific construction

related safety problems and identify the key issues to be addressed in the solution of such

problems.

Alphen aan den Rijn on the 3rd of August 2015

Accident summary report

20 people were injured in the town of Alphen aan den Rijn after two cranes lifting a bridge

section toppled on to three houses, clothing store and art and drawing supplies store. The cranes

that were working from barges, were renovating the Queen Juliana Bridge, the two tower

cranes on a barge began to shift and toppled over on to a row of houses, slamming through the

buildings and sending a cloud of dust. Following images will show technical drawings of the

barges and cranes before the accident.

Figure 0.1Image presenting The barge that the cranes was placed on

Page 5: Health and safety management 2

C123 Alphen ann den rijn crane salvage 5

Figure 0.2 The angels the crane was sitting on before the fall.

Figure 0.3 Showing the estimate dimensions of the positioned cranes, bridge and barge.

Page 6: Health and safety management 2

C123 Alphen ann den rijn crane salvage 6

Page 7: Health and safety management 2

C123 Alphen ann den rijn crane salvage 7

Site location

The proposed removal of the cranes is positioned in the Westside of the Ouede Rijn in Alphen

ann rijn , Nederland’s.

Figure 1. The location of the accident site as seen from google maps

Figure 1. The location of the accident site as seen from google maps

Page 8: Health and safety management 2

C123 Alphen ann den rijn crane salvage 8

Scope of works

Site investigation - walk the site, check if qualifications of operatives are valid and

appropriate to the works to be carried out on site’ and obtain all necessary permits and

establish traffic management plan.

Divert pedestrian traffic via a temporary pedestrian crossing to the west, east and north.

Site setup – Erect traffic barriers, fencing, signage, get required plant and equipment

to site and establish welfare and storage facilities.

Establish Crane positions for the removal by means of anchors points, best structural

stability and ordering of the Main boom of 700 tons Terex AC700 lifted onto pontoon.

Barge will be hired to provide a working platform on the water for the duration of the

works for attaching the necessary cables for lifting the crane.

Two telescopic mobile cranes will arrive and be fixed to the fallen cranes first as they

lay on top of the bridge section and will be attached

In order to carry out this operation the existing barge will be used for lowering the

pieces of crane on stable position out of the water.

The crane will then begin the operation of lifting the cranes out by pieces. Starting with

the steam of the fallen cranes and then the vehicle.

Upon completion Structural Engineer will inspect lifting of the bridge section that is

associated with works;

Cranes will be dispatched off site

Bridge section will be lifted and positioned on the built barge structure as before the

accident that will be located where the fallen barges used to sit.

Houses supported by shoring / demolish dangerous buildings.

Make good road and footpath.

All materials and equipment will be removed from site.

Site clean-up and removal of site facilities and fencing and other associated equipment.

Client Inspection/snags.

Handover.

Page 9: Health and safety management 2

C123 Alphen ann den rijn crane salvage 9

Site specific Safety Plan

Site Security

It is proposed to fence off Site area with fencing with crash barriers facing the road this

measure is to provide protect site operatives and members of the public by segregating traffic

from site operations; Details of which will be in our traffic management plan for the project.

In addition, 24 hour site security will be provided for the duration of the project given the

location of the site and its proximity to the river and vehicular traffic in the area. The security

officer will ensure that no unauthorised personnel may enter the work area during the clean-

up and that all visitors to site sign in at the site office at that stage they will be accompanied

to the works area with authorised personnel.

A security hut will be positioned at the main entrance to the site. The security officer’s roles

will include:

Ensuring that only permitted personnel and deliveries are allowed access to the site.

Maintain detailed records of all people entering and leaving the site.

Communicate all site hazards with personnel entering the site and make them aware of

the risks associated with the works in progress.

Security of the site against theft and vandalism.

Ensure adequate lighting and appropriate safety signage is in place.

Ensure that plant and equipment is secured where applicable.

Site rules & emergency procedures

Designated Safe assembly areas will be provided for emergencies. All personnel will be

required to attend site specific induction training prior to working on site.

During the induction training they will be advised on any safety issues and site specific hazards.

Page 10: Health and safety management 2

C123 Alphen ann den rijn crane salvage 10

Welfare facilities & First aid

Welfare facilities will be provided on-site to meet the requirements of HAS authority

Specific items that will be included are:

Potable drinking water;

Porta-loos (given the lack of useable site space);

Canteen/meeting/induction room;

Changing facilities/Drying room.

A designated First Aiders will be appointed to deal with minor accidents on site. If the First

Aider is unable to deal with an injury, the emergency services will be contacted.

Operatives will be made aware of the Site First Aider on site and the location of first aid

equipment which will include a defibrillator in accordance with company policy.

Sit access

It is proposed to liaise with the local authorities when planning deliveries of heavy plant,

equipment or materials to site, this measure is to provide a safe passage for operatives and to

ensure the safety of pedestrians and other road users.

This will entail lane and footpath closures for the duration of the works, Warning signage on

approach to the site entrance, additional lighting after dark and road supervision when required,

during peak periods, to allow safe movement of traffic.

A designated set-down area for staff vehicles will be provided for off lading of tools and

equipment but parking will not be provided given the lack of useable site space.

Page 11: Health and safety management 2

C123 Alphen ann den rijn crane salvage 11

Transport

Hazards associated with traffic and transport will be controlled in the form of liaison with local

authorities.

Other issues that require attention in order to insure a safe passage to site include:

A route survey will be carried out to ensure the safe passage of oversized loads to the

site such as the delivery of the cranes;

To avoid any major disruption, experienced banks persons will be used. These

personnel will exercise proper signalling techniques during the deliveries of large loads

to Site.

Road preparation such as marking realignment will be carried out as required in

accordance with the traffic management plan.

Date & time of deliveries will be check against local events.

Consultation and notification of possible road closure/diversion strategies will be put

in place in advance for delivery of any large loads.

A temporary Pedestrian crossing will be set up to divert pedestrian traffic approaching the site.

Pedestrians will be diverted across the road safety at a temporary level crossing which will be

sign posted accordingly.

Crash barriers and fences will be erected around site to protect members of the public from site

operations and site personnel form vehicular traffic.

Page 12: Health and safety management 2

C123 Alphen ann den rijn crane salvage 12

Traffic management plan

Page 13: Health and safety management 2

C123 Alphen ann den rijn crane salvage 13

Required plant and equipment

Mobile welding unit

This will be used when the fallen cranes stem will have to be removed from the main vehicle.

Also if necessary welded on supports will be placed on cranes for to lift them safely. This is

the preferred choice for this site.

Only qualified, competent personnel will operate this machine. A check will be carried out to

determine when it was last tested/serviced and a visual inspection will be caries out to check

for damage or wear on any cabling and to safety devices are working.

Grinder

Electric grinder will be selected as to remove the steam from the fallen crane vehicle. Also if

found necessary the cables that have been stranded under the bridge section will have to be

removed.

Some of the safety devices the grinder must provide are:

Anti kick back;

Restart protection - Prevents the grinder restarting after a power cut;

Anti rotation guard - Prevents the guard moving should a disc shatter;

Vibration control;

Start current limitation or soft start.

Page 14: Health and safety management 2

C123 Alphen ann den rijn crane salvage 14

Life jackets & Harness

These will be worn by all other operatives and visitors on site due to the sites proximity to the

water.

Certification will be checked on all life jackets and on each harness. In addition, the harness

will be checked for grease on the linings and will be inspected routinely for damage and wear

along with the other life jackets.

Barge HEBO P12

Will be hired so that the cranes can be transported off site and for the duration of the works. It

will access the cranes from the north as seen in figure 3. It will allow to have a safe platform

for workers to grind and weld off the crane stem from a stable and adjustable platform when

installing the fixing points, to the fallen crane.

Page 15: Health and safety management 2

C123 Alphen ann den rijn crane salvage 15

Floating buck

The Crane will be hired for the duration of the project. This crane is an excellent choice for this

project as it has slewing capabilities and can travel with a load. This feature offers a lot more

mobility as it will be located on the river which take up a lot of the limited, available site space

that is not being used. Its long span over the barge and the fallen cranes will allow extra reach

and can lift heavy loads of up to 300 tones

Length 41,54 m

Breadth working (incl. side

pontoons)

17,85 m

Max. draught (ballast tanks filled +

max. load)

3,10 m

Airdraught sheerlegs and flyjib laid

down forward on pontoon

6,00 m

Airdraught sheerlegs laid down

backwards (seapassage)

17,00 m

Gross tonnage 676 T

Max. Capacity Mainblock 2x150 T

Main Runner 1x5 T

Fly-jib Runner 1x5 T

Page 16: Health and safety management 2

C123 Alphen ann den rijn crane salvage 16

Telescopic Crane MAMMOET

The Crane three cranes will be a for the duration of works on site that will be located on land.

Their main purphose will be to assist the Barge crane and for the banksman to direct the cranes.

Telescopic craneoffers a lot more mobilityaround the site and has sufficient ground to stand on

thee crane, requires a solid base to operate safely. This is provided by the existing roadway

that, as part of the contract, will be re-surfaced upon completion of the works.

Page 17: Health and safety management 2

C123 Alphen ann den rijn crane salvage 17

Risk assessment

Page 18: Health and safety management 2

C123 Alphen ann den rijn crane salvage 18

What is a Risk assessment?

Risk assessments are an essential tool for the implementation of good health and safety

management. Risk Assessment is where the severity of the Hazard and its potential outcomes

are considered in conjunction with other factors including the level of exposure and the

numbers of persons exposed and the risk of that hazard being realised.

Additionally, all employers regardless of the size of the business are required to carry out a risk

assessment at their place of work and to keep a written record of the risk assessment for each

job for the purpose of possible inspection by the Health and Safety Authority.

Risk Assessment aims

The Aim of a Risk Assessment is to demonstrate the company’s ability to identify hazards in

the workplace or those that are associated with a particular task and in turn assess the risk and

outline the recommended control measures to be adopted. These findings are presented in a

written format, in simple language, in order for them to be fully understood by those who are

going to carry out the task.

‘Risk’ is defined as the likelihood that a person may be harmed or suffers adverse health effects

if exposed to a hazard

What are control Measures

Page 19: Health and safety management 2

C123 Alphen ann den rijn crane salvage 19

The process of risk assessment

In carrying out risk assessments employers must look closely at what or what activities could

cause harm to their employees, visitors and members of the public and in determine the

appropriate control measures to be implemented to reduce or minimise the risk.

Risk Assessment classification

The following table indicates the classification of a ‘Hazard’ and a ‘Risk’.

Assessment of hazard (Severity) Assessment of risk (likelihood)

HIGH

Fatality/ major injury or illness causing long

term disability

HIGH

Certain or near certain

MEDIUM

Illness or injury causing short term

disability

MEDIUM

Reasonably likely to occur

LOW

Other minor injury

LOW

Very seldom

Severity Fatality Medium High High Very High Very High

Major Injury Medium Medium High High Very High

Reportable

injury

Low Medium Medium High High

Lost Time

Injury

Low Low Medium High High

Minor Injury Low Low Low Medium High

MAMMOET Matrix

guide

Improbable Remote Possible Probable Likely

Probability

Page 20: Health and safety management 2

C123 Alphen ann den rijn crane salvage 20

Method statement

Page 21: Health and safety management 2

C123 Alphen ann den rijn crane salvage 21

Introduction

A method statement is a way of documenting the hazards involved in carrying out specific

tasks and in turn communicating the risk and precautions required to all personnel involved.

The statement should not be complicated or longer than necessary to achieve these objectives.

Method Statements are for the benefit of those carrying out the work and their immediate

supervisors therefore they should be clear and written in simple language suited to those

carrying out the operations and should not be over complicated.

Equipment needed for safe working should be identified and made available before work starts.

The Method Statement should be updated as the work proceeds and personnel should be

informed and trained if their required work methods need to be changed.

Permit to work systems (PTWS)

PTW systems set out systematically the works to be carried out, the hazards involved and the

precautionary measures to be employed.

Situations where PTWS are necessary include:

1. Hot works such as Welding and the use of a grinder.

2. Working in confined spaces. Such as Excavations.

3. Crane Operations.

4. Working at heights.

The employer should document in the safety statement what work activities require a permit to

work system and details of which will be noted on the site specific Method Statement.

Employers must also need to consider the associated regulations and codes of practice related

to the task.

The Method Statement for the Salvage crane and bridge section are details of the following:

• The Project (location, duration etc.).

• Personnel Involved.

• The required Key Plant, Tools and Equipment.

• Specific Identified Residual Hazard.

• Specific staff training and details of permits to work.

• Sequence of operations.

• Access, Egress and Traffic management.

• Fall protection procedures.

• Hazardous substances and storage of same.

• PPE First Aid & Hospital Information.

Page 22: Health and safety management 2

C123 Alphen ann den rijn crane salvage 22

Name:

(site manager)

Address:

Bolton street

22, Dublin

Ireland

Telephone:

E-mail:

Project name: Alphen aan den rijn salvage

Description of

the task

Alphen aan den rijn crane and bridge section salvage in Netherlands

Site address/

location

Hooftstraat 128-132, 2406 GN

Alphen aan Den Rijn,

Netherlands

Start date: 3rd August 2015

Finish date: 10th October 2015

Personnel

Involved

Name Role/ trade

N. Walshe General Operative

W. Gadimough General Operative

C. McGregor Telescopic Crane Driver (GOB)

P. Higgins Telescopic crane operative

H. Hogan Crane Banks man

S. Nolan Welder

B. Marshe Barge crane operative

C. Burns Barge Crane operative

P. McKena Grinder

C. Doharty Security

C. Smith Safety Officer

J. Casey Barge operative

Site

supervisor

Telephone

086-0264545

Site officer Shane O’Carrol Telephone 085-1233022

Key Plant &

Tools:

Mobile welding unit/Generator

Grinder

Drill

Floating barge crane

Three Telescopic cranes

Barge for removal

Harnesses

Life jackets

Elevated work platform

Key materials Crane, Barge.

Page 23: Health and safety management 2

C123 Alphen ann den rijn crane salvage 23

Other

Essential

Equipment:

Fencing, crash barriers, signage, temporary traffic lights, two way radios, Fall protection

to the canal wall and Barge for duration of works.

Specific

Identified

Residual

Hazards:

or refer to the

task specific

risk

assessment

All Hazards, insofar as reasonably practicable, are identified with the appropriate control

measures outlined, in the accompanying Risk assessment.

Hazards Include:

Working at the water’s edge (drowning), heights and crane in operation.

1. Exclusion zone in effect when crane is in operation- Banks man and site manager

have control;

2. Life jackets to be worn;

3. Barge in addition, attached two points of contact under a permit to work in buddy

pairs on river Bank;

4. Rescue plan to be implemented for Barge and working on the river bank.

5. Loose building material

Specific staff

training

Safe Pass & Manual Handling, training for carnage operations, hot works, manual

handling & toolbox talks before the commencement of each task on site as deemed

necessary.

Personnel only authorised to operate Barge for duration of works.

Sequence of operations

1. Check all permits are obtained, traffic management plan and qualifications of

operatives before works commence on site.

2. Divert traffic in accordance with traffic management plan provided with signage

of diverted traffic.

3. Set up temporary fencing

4. Construction of a temporary pedestrian crossing.

5. Site establishment (welfare facilities and site accommodation).

6. The existing dangerous buildings will need to be shored or demolished. If

necessary remove asbestos and transported for recycling off site.

7. Delivery and erection of Barge crane MAMMOETH lift 7

8. Delivery of HEBO P12 barge.

9. Positioning the barge and anchor it to the bank of the river as per drawings.

10. Setting up of the space needed for the salvage cranes to be positioned on the

barge.

11. Delivery and unloading of welding units and grinders

12. The fixing points of the salvage cranes will be established by means of structural

and stability.

13. Lifting supervisor will carry out toolbox talk with all personnel involved in the

lifting operation. When this has been completed all involved in the lifting

operation must sign the register.

14. Crane to reverse into position under the control of banksman.

15. Crane the operator will telescope the main boom out.

16. Hook of crane hoisted on to the body of the fallen crane at its established points

as in step 11.

17. The weight of the salvage cranes body will be lifted slightly.

Page 24: Health and safety management 2

C123 Alphen ann den rijn crane salvage 24

18. The beam of the salvage crane will be detached using welding units and grinders

by operatives standing on barge.

19. Banksman will now instruct operator to hoist salvage crane just clear of the barge

to position it to the left.

20. Lift Supervisor will now check for correct slinging and adjust.

21. Once positioned instructions will be made to operator to lower off all weight of

lifted item.

22. Lifting hooks will now be released from item.

23. Operations (15-22) inclusive will be repeated until all salvage cranes have been

lifted and placed into position.

24. The salvage cranes are to be taken off site using barge for further inspections and

investigations.

25. Salvage bridge section hoisting bracket on barge is to be placed at the right side

of the river for loading of the bridge.

26. The bridge section will be attached to existing points using two telescopic cranes

and barge crane. It will then be levelled in upright position.

27. Bridge section will then be lowered on to the bracket.

28. Crane hooks will be removed.

29. The bridge section is to be transported on the barge to a storage area.

30. Once all lifting has been completed crane operator to lower hook block to

ground.

31. Lifting tackle will be removed from hook block and stowed away.

32. Cranes will move off site.

33. Subcontracted demolition will take place.

34. Clearing of the site.

Temporary Supports and Props needed to facilitate the works:

The existing buildings will need propping as it is classified dangerous.

Method of Access and Egress to the work area:

1.Vehicular traffic will pull into delivery staging area to the east and enter site when

instructed by the site manager via the gate policeman;

2. Pedestrian traffic will enter by swipe access at secure gate to west at the welfare

facilities.

Fall Protection Measures:

1. All personnel working on/ near the barge must wear the approved life jacket with

incorporated harness;

2. Report equipment defects;

3. Ensure fall arrest equipment is fit for purpose i.e. will hold weight of operative.

Fall arrest system to have two points of contact (reduce pendulum effect);

4. Ensure a suitable rescue plan is in place should an operative fall both from river

bank and Barge;

5. No operative will work alone in a harness;

6. Inertia reel to be set to the required length to prevent operatives entering the

water from the bank;

7. Ensure trained rescuers are on standby in case of a fall;

8. Wear suitable PPE in addition to site requirements

Page 25: Health and safety management 2

C123 Alphen ann den rijn crane salvage 25

Hazardous Substances: (Attach MSDS if required)

Applicable:

Yes

Diesel &

Oils

Yes

Diesel &

Oils

No Yes

Diesel

& Oils

No Yes

Diesel &

Oils

No

Hazardous substances and storage arrangements:

1. Diesel and oils will be stored in approved containers in designated storage area.

Details of permits to work:

Hot Works, use of abrasive wheel, crane operating, plant operating, abrasive wheel

operating, working on Barge.

Safe working load

1. Barge crane Hebo lift 7 - self tonnage - 672 – max lifting - 300 tonne

2. Mobile telescopic crane Hebo (Mammoet) - max lift 100 tone

3. Mobile telescopic crane Hebo (Mammoet) - max lift 100 tone

4. Mobile telescopic crane Hebo (Mammoet) – max lift 40 tone

Required personnel protective equipment

Safety

boots

Hard

Hats Safety

gloves

Hearing

protectio

n

Eye

Protectio

n

Fall

Protecti

on

Other:

High Vis

Life Jackets

Harness

Respiratory

protection

Emergency procedures

Notify the site manage

Call ambulance at 999 or 112

Call coastguard – 113

First aid facilities:

On Site First aider:

First aid box location: Site offices on the east of the site

On Hebo P12 barge

On barge lift 7

Location of the nearest

hospital:

Meteoorlaan 4, 2402 Alphen aan Den Rijn, Netherlands

rijnland.nl

+31 172 467 467

-999

-112

Site welfare requirement

Site office, Canteen, Changing room/drying room, WC’s.

Page 26: Health and safety management 2

C123 Alphen ann den rijn crane salvage 26

Services supplied by Others:

Barge Crane Hire: by HEBO

Barge for the removal of bridge and crane sections.

Traffic Management

As seen in the traffic management plan it is proposed to fence off with crash barriers

employed for the duration of works. Signage will be erected on and around site for the

information of personnel and members of the public. A temporary pedestrian crossing

will divert pedestrians across the road. A construction vehicle staging area will be

located to the east at site vehicle entrance. Vehicles, after being security cleared will

reverse into site and upon completion of delivery/collection will exit via same entrance.

Pedestrian entrance will be to the west beside accommodation area.

Crane Operations of lifting plan

The project supervisor will ensure that all members of the appointed crane team employed to

salvage the section on site are fully aware of their roles and duties, and that each person has

sufficient knowledge, training and experience to carry out their work safely. Records of

training and experience will be verified and their details will be retained in the site safety file.

Lift supervisor will supervise and co-ordinate all lifting activities in accordance with the Lift

Plan. This person will brief all lifting team members i.e., crane operators, slingers and

appointed banks person on each lift. Project supervisor will be responsible for the planning,

risk control measure and safe lifting procedure before they commence the lifting operation.

The Lift supervisor will ensure that a permit is issued by the project manager before he instructs

his team to carry out any lifting operation on site. The Lift supervisor will brief the lift team

members on the Lift Plan before commencement of any lifting operation and can stop the lifting

operation.

Crane beam detached and lifted on to prepared barge Crane body remove from beam and lifted on barge

Page 27: Health and safety management 2

C123 Alphen ann den rijn crane salvage 27

Bridge section lifted in bracket using 3 cranes. Salvage cranes being transported off site.

Conclusion

The crane and bridge section should go smoothly as all risks have been identified and the

likelihood that a person may be harmed or suffers adverse health effects being eliminated in

this statement.

All employers are required to carry out a risk assessment at the site and to keep a written record

of that risk assessment for each job. The main reasons why risk assessments are carried out are

to prevent financial costs associated, moral/ ethical and the legal reasons.

Carrying out a risk assessment, preparing a method statement and their implementation are

required by law under the Safety, Health and Welfare at Work Act 2005.Risk assessments are

an essential tool for the implementation of good health and safety management. In carrying out

Risk assessments the severity of the Hazard and its potential outcomes are considered in

conjunction with other factors, these include, the level of exposure and the numbers of persons

exposed and the risk of that hazard being realised.

Risk Assessments are to demonstrate the company’s ability to identify hazards in the workplace

or such that are associated with a particular task and, in turn outline the recommended control

measures to be adopted. These findings are presented in a written format, in simple language

appropriate to the persons who are to carry out the task.

After identifying the risk or hazards, employers must adopt control measures to reduce or

remove the potential of an operative’s exposure to a particular Hazard or reduce the likelihood

of the risk of the exposure to that hazard being realised.

Page 28: Health and safety management 2

C123 Alphen ann den rijn crane salvage 28

A method statement is a way of documenting the hazards involved in carrying out specific

tasks and in turn communicating the risks and precautions required to all personnel involved

in the work. The statement should again, not be complicated and be written in simple language

appropriate to the personnel whom are carrying out the tasks.

In line with the Method statement, Equipment needed for safe working should be identified

and made available before work starts. The Method Statement should be updated if necessary,

as the work proceeds and Personnel should be informed if their work methods need.

Permit to work systems are written systems to protect workers in dangerous areas. They set out

systematically the works to be carried out, the hazards involved and the precautionary measures

to be employed.

References

Alex Dahm, KHL Magazines - 10 Aug 2015 Accident summary report (online). Link:

http://www.khl.com/magazines/international-cranes-and-specialized-

transport/detail/item110371/Work-resumes-at-Dutch-crane-crash-bridge

(Accessed 20 September 2015)

Mubarakmarine. Scope of Works. (online) Link: http://mubarakmarine.com/mubarak/wp-

content/uploads/2012/05/vessels-work-History.pdf

(Accessed 20 September 2015)

Authority, H.S.A., 2006. SMP20 Site specific safety plan (online) Link:

http://www.hsa.ie/eng/Your_Industry/Construction/Construction_Safety_Partnership/SMP_2

0/SMP20_Update_Pack_Download_Revision_1.pdf

(Accessed 7 October 2015)

Golndustry Dove bid 2015, Mobile welding unit. (online) Link: http://www.go-

dove.com/en/auction/view?id=9319610

(Accessed 7 October 2015)

References on Slideshare. References (online) Link: http://www.slideshare.net/pierdole/task-

description

(Accessed 7 October 2015)

Page 29: Health and safety management 2

C123 Alphen ann den rijn crane salvage 29

Richard L. Krabbendam, Heavy lifts specialist, details on crane (online) Link:

http://www.heavyliftspecialist.com/author/richard/

(Accessed 7th October 2015)

Heavy lift news, Position of cranes and removal process (online). Link:

http://www.heavyliftnews.com/accidents/salvage-plan-mammoet-hebo-presented-and-

salvage-operation-finally-on-its-way-

(Accessed 14 October 2015)

Alphen ann den rijn, Access to all methos statements and trafic management plans,

photography. (online).

Link:https://www.alphenaandenrijn.nl/Bestuur/Actuele_berichten/Koningin_Julianabrug

(accessed 14 October 2015)

Authority, H.S.A., 2006. Guidelines on Risk Assessments and Method statements. (Online).

Link:

http://www.hsa.ie/eng/Topics/Managing_Health_and_Safety/Safety_Statement_and_Risk_As

sessment/

(Accessed 12 October 2015).

Authority, H.S.A., 2014. Risk Assessments. (Online), Link:

http://www.hsa.ie/eng/Small_Business/Risk_Assessment_Made_Easy/

(Accessed 10 October 2015)

Authority, H.S.A., 2014. Hazard and Risk (online). Link:

http://www.hsa.ie/eng/Topics/Hazards/

(Accessed 10 October 2015)

Page 30: Health and safety management 2

C123 Alphen ann den rijn crane salvage 30

001 - Abrasive Wheels 030 - Employee Duties

002 - Accident Prevention 031 - Environment

003 - Arrow Props 032 - Excavations

004 - Advice to Supervisors 033 - Eyes Protection 1

005 - Alcohol and Drugs

006 - Asbestos Cement Sheets 035 - Fire Precautions + Extinguishers

007 - Backfill to Structures 036 - Flammable Liquids

008 - Banking Vehicles 037 - Forklift Operators 1

009 - Breakers 038 - Forklift Operators 2

010 - Buried Services 039 - Gas Cylinders Gen

011 - Cherry Picker 040 - Gas Services

012 - Concrete Breakers 041 - Hand Arm Vibration (Havs)

013 - Concrete Burns 042 - Hand Protection

014 - Concrete Pour 043 - Hand Tools

015 - Concrete Pumps 044 - Harnesses and Lanyards

016 - Concrete Set Up 045 - HAV Toolbox Talk

017 - Confined Spaces 046 - HD Elec Breaker

018 - Control Of Waste 047 - Head Protection

019 - CoSHH Symbols 048 - Hearing Protection

020 - CoSHH 049 - Holes and Openings

021 - Demolition 050 - Hooks + Eyebolts

022 - Dermatitis 051 - House Keeping

023 - Dumper Drivers 052 - Illegal Substances Drugs

024 - Dust and Fumes 053 - Ladders

025 - Electric Services 054 - Look After Your Back

026 - Electric Tools 055 - Manual Hand

027 - Electricity A to Z 056 - Manual Handling

028 - Electricity General 057 - Mats - Mobile Access Tower Scaffolds

029 - Employee Advice 058 - MEWPS - Cherry Pickers

Page 31: Health and safety management 2

C123 Alphen ann den rijn crane salvage 31

059 - MEWPS - Scissor Lifts 088 - Stanley Knives

060 - Mobile Crane Reminders 089 – Steel fixers

061 - Near Miss 090 - Step Ladders

062 - New Starts 091 - Tetanus

063 - Noise - for Site Staff 092 - Tirfors

064 - Noise 093 - Traffic Management

065 - Openings and Edges 094 - Underground Services

066 - Overhead Cables 095 - Unsafe Conds

067 - Painting + CoSHH 096 - Vertical Concrete Traffic Barriers

068 - Permit to Work 097 - Water Services

069 - Piling 098 - Weils Disease

070 - Portable Electric Tools 099 - Welding Precautions

071 - Portable Hand Held Power Saws 100 - Windy Conditions

072 - PPE Q&A 101 - Winter Conditions

073 - Pressure Washers 102 - Work At Heights

074 - Psittacosis 103 - Work Near Mobile Plant

075 - Responsibilities 104 - Work Near to Water

076 - Road Formation 105 - Working Attitudes

077 - Roofwork 106 - Working Close to A Crane

078 - Safe Stacking 107 - Working Clothes

079 - Scaffolding 1 108 - Working Cold Weather

080 - Scaffolding 2 109 - Working Habits

081 - Shackles 110 - Working Hot Weather

082 - Shafts 111 - Working With Compressed Air Tools

083 - Skin Protection 112 - Needlestick Injuries

084 - Slinger - Signallers

085 - Slings

086 - Slips Trips Falls

087 - Solvents