Quality In The Construction of Turnouts Trackwork Services Alliance Charles Vuong & David Nguyen 22 - 23/05/14

Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Embed Size (px)

DESCRIPTION

Charles Vuong & David Nguyen delivered the presentation at 2014 RISSB National Rail Turnouts Workshop. The RISSB National Rail Turnouts Workshop gives all those involved an in-depth forum for discussion and the sharing of expertise. A key element of this workshop is participation and knowledge sharing from audience as well as the workshop leaders. It is a chance for you to bring your experience and to take away new approaches for best practice. For more information about the event, please visit: http://www.informa.com.au/railturnoutsworkshop14

Citation preview

Page 1: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In The Construction of

Turnouts

Trackwork Services Alliance

Charles Vuong & David Nguyen

22 - 23/05/14

Page 2: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In the Construction Of Turnouts

Agenda

1. TSA – Who we are? What do we do?

2. How is quality ultimately achieved in construction through:

• Design

• Procurement/Manufacturing

• Prebuild

• Construction

3. Case study – Lithgow

4. Conclusion

Page 3: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

TSA – Who We Are?

Page 4: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

TSA – What we do?

Objectives:

1. Service delivery of turnout renewals

2. Rail industry objectives

Page 5: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Construction Methods

How Quality Is Achieved in Construction

Work Methodology

Increased efficiency

Quality Assurance

Culture and

Behaviours

Page 6: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

How Quality Is Achieved in Construction

Quality of the end product will be influenced by:

Page 7: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Fix it here

Page 8: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

How Quality Is Achieved in Construction

Design:

• Design for constructability

• Design for manufacturability

How?

• Constructor input / feedback at design stage

• Greater accessibility between constructors and

designers

• Collaborative design

Page 9: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

How Quality Is Achieved

Manufacturing:

• Suitability of ordered components to site

• Manufacturing tolerances and design requirements are

met

• Compliance to design

How?

Site inspections before procurement

Manufacturing quality inspections

Page 10: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

How Quality Is Achieved

Manufacturing:

• Procurement of materials to suit site requirements

Turnout to be

renewed

End of stockrail

(Aluminothermic weld)

Existing joint (flash butt)

600mm from end of stockrail

Plain line track not

to be renewed

Glued Insulated Joint

Cost:• Closure

• Weld

• Time

Impact on Quality

(additional weld in

track)

Page 11: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

How Quality Is Achieved

Cost:• Truck Costs: $1400

• Modification of plates: $5750

• Safe Working: $1000

• Site Supervisor: $1300

• Labour: $1500

Total Cost = ~$11,000

Manufacturing:

• Ensuring No Manufacturing Defects through Inspections

Page 12: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

How Quality Is Achieved

Prebuild

Page 13: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Case Study: Lithgow 77A/B, 78A/B, 79 &

81A/B Turnout Renewal

Page 14: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In DesignCase Study: Lithgow 77A/B, 78A/B, 79 & 81A/B

Page 15: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In Design

Page 16: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In Manufacturing

Manufacturing inspection conducted:

1. Victoria

2. New South Wales

3. Queensland

Case Study: Lithgow 77A/B, 78A/B, 79 & 81A/B

Page 17: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In Manufacturing

Customised Inspection Checksheet:

• Actual measurements recorded

• Acceptance only once manufacturing

tolerances and design requirements met

• Rectification list provided to manufacturer’s

post inspection

Page 18: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In PrebuildPrebuild on level surface

• Entire shift prior to prebuild used to level surface

Page 19: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In Prebuild

Self performing team

Page 20: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In PrebuildPrebuild 16th – 24th January, 6 weeks & prebuild inspections: prior to welding

Page 21: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In Construction

Lithgow 77A/B, 78A/B, 79 & 81A/B Points Renewal

Page 22: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In Construction

Track Scope of Works

• Renewal of 7 point ends

• Full depth recondition

• Installation with PEM LEM’s

• Welding

• Resurfacing

Page 23: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In Construction

Signalling Scope of Works

• Replace existing points motors

• Replace existing ESML with EOL

• Circuit modifications

• Relocation of signals

Page 24: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In Construction

OHW Scope of Works

• Major OHW adjustments to

suit new track arrangement

• Installation 22off OHW

footings

• Erection 11off new OHW

structures

• Removal 6off redundant

OHW structures

Page 25: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In Construction

• Safe & reliable product at end of possession

• No late possession handback

Page 26: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In ConstructionQuality During Construction:

• Prior testing of material

• Allowing for contingency

• Customised ITP’s

• Live Survey

• NCR tracking

• PEM LEM

Page 27: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In Construction

Page 28: Charles Vuong & David Nguyen - Trackwork Services Alliance - Case study session: Quality in the construction and installation of turnouts

Quality In the Construction Of Turnouts

Outcomes

– Reduction in number of defects

– Reduced the risk of late possession handback

– Reduction in the cost of rework

– Increased scope deliverables