Guru Nanak Dev Thermal Power Plant is a coal- based plant. The requirement of coal for four units based on specific fuel consumption of 0.60 kg / kWh. The conveying and crushing system will have the same capacity as that of the unloading system. The coal comes in as large pieces. This coal is fed to primary crushers, which reduce the size of coal pieces from 400mm to 150mm. Then the coal is sent to secondary crusher through forward conveyors where it is crushed from 150mm to 200mm as required at the mills. Then the coal is sent to boilers with the help of primary fans. The coal is burnt in the boiler. Boiler includes the pipes carrying water through them; heat produced from the combustion of coal is used to convert water in pipes into steam. This steam generated is used to run the turbine. When turbine rotates, the shaft of generator, which is mechanically coupled to the shaft of turbine, gets rotated so, three phase electric supply is produced. The basic requirements are:- Page | 1 INTRODUCTION

Bathinda thermal power plant mid semester report

Embed Size (px)

Citation preview

Page 1: Bathinda thermal power plant mid semester report

Guru Nanak Dev Thermal Power Plant is a coal-based plant. The requirement of

coal for four units based on specific fuel consumption of 0.60 kg / kWh. The conveying

and crushing system will have the same capacity as that of the unloading system. The

coal comes in as large pieces. This coal is fed to primary crushers, which reduce the size

of coal pieces from 400mm to 150mm. Then the coal is sent to secondary crusher through

forward conveyors where it is crushed from 150mm to 200mm as required at the mills.

Then the coal is sent to boilers with the help of primary fans. The coal is burnt in the

boiler. Boiler includes the pipes carrying water through them; heat produced from the

combustion of coal is used to convert water in pipes into steam. This steam generated is

used to run the turbine. When turbine rotates, the shaft of generator, which is

mechanically coupled to the shaft of turbine, gets rotated so, three phase electric supply is

produced.

The basic requirements are:-

♣ Fuel (coal)

♣ Boiler

♣ Steam turbine

♣ Generator

♣ Ash handling system

♣ Unit auxiliaries

Page | 1

INTRODUCTION

Page 2: Bathinda thermal power plant mid semester report

Due to high rate of increasing population day by day, widening gap between power

demand and its availability was one the basic reason for envisaging the G.N.D.T.P. for

the state of Punjab. The other factors favoring the installation of the thermal power

station were low initial cost and comparatively less gestation period as compared to

hydro electric generating stations. The foundation stone of G.N.D.T.P. at bathinda was

laid on 19th November 1969, the auspicious occasion of 500th birth anniversary of great

Guru Nanak Dev Ji.

The historic town of bathinda was selected for this first and prestigious thermal

project of the state due to its good railway connections for fast transportations of coal,

availability of canal water and proximity to load center.

The total installed capacity of the power station 440MW with four units of

110MW each. The first unit of the plant was commissioned in September, 1974.

Subsequently second, third and fourth units started generation in September 1975, March

1978, and January 1979 respectively. The power available from this plant gives spin to

the wheels of industry and agricultural pumping sets.

Page | 2

BRIEF HISTORY OF PLANT

Page 3: Bathinda thermal power plant mid semester report

The selection of site for Thermal Power Plant is more difficult compared to Hydro

Power Plant, as it involves number of factors to be considered for its economic

justification. The following consideration should be examined in detail before selection

of the site for the Plant. The location for plant should be made with full consideration not

only of the trends in the development and location but also the availability and location of

the cheapest source of primary energy:-

Availability of fuel

Ash disposal facilities

Space requirement

Nature of land

Availability of labour

Transport facilities

Public society problems

Development of Backward Area

Page | 3

SITE SELECTION

Page 4: Bathinda thermal power plant mid semester report

Guru Nanak Dev Thermal Plant, Bathinda, in addition to indirect contribution in various

facts of state economy, is also responsible for:-

Narrowing the gap between power demand and power availability of the state.

Providing employment potentials to thousands of workers.

Covering the backward surrounding area into fully developed Industrial

Township.

Providing additional relief to agricultural pumping sets to meet the irrigation

needs for enhancing the agriculture production.

Reliability and improvement in continuity of supply and system voltage.

Achieving cent percent rural electrification of the state.

Page | 4

CONTRIBUTION OF THE PLANT

Page 5: Bathinda thermal power plant mid semester report

PROJECT AREA:-

Power plant 238 acres

Ash disposal 845

Lake 180

Residential colony 285

Marshalling yard 256

Total area 1804

TOTAL COST: - Rs. 115 crores

STATION CAPACITY: - four units of 110MW.each

BOILER:-

Manufacturers B.H.E.L.

Maximum continuous rating (M.C.R.) 375 T/hr.

Superheater outlet pressure 139 kg/cm²

Reheater outlet pressure 33.8 kg/cm²

Final superheater/reheater temperature 540C

Feed water temperature 240C

Efficiency 86%

Coal consumption per day per unit 1400 tones (Approximate)

Page | 5

PLANT SALIENT FEATURESTHE PLANT

Page 6: Bathinda thermal power plant mid semester report

STEAM TURBINE:-

Manufacturers B.H.E.L.

Rated output 110 MW.

Rated speed 3000 r.p.m.

Number of cylinders three

Rated pressure 130 kg/cm²

Rated temperature 535C

Condenser vacuum 0.9 kg/cm²

GENERATOR:-

Manufacturers B.H.E.L.

Rated output

(Unit- 1 & 2) 125000KVA

(Unit -3 & 4) 137000KVA

Generator voltage 11000 volts

Rated phase current

(unit –1 & 2) 6560 Amps.

(unit –3 & 4) 7220 Amps.

Generator cooling hydrogen

BOILER FEED PUMPS:-

Number per unit two of 100% duty each

Type centrifugal

Rated discharge 445 T/hr.

Discharge head 1960 MWC.

Page | 6

Page 7: Bathinda thermal power plant mid semester report

Speed 4500 r.p.m.

CIRCULATING WATER PUMPS:-

Numbers for two units five of 50% duty each

Type mixed flow

Rated discharge 8600 T/hr.

Discharge head 24 MWC.

COOLING TOWERS:-

Numbers four

Water cooled 18000 T/hr.

Cooling range 10C

Height 120/12 metres

COAL PULVERISING MILLS:-

Numbers three per unit

Type drum-ball

Rated output 27 T/hr.

Coal bunkers 16 per unit

RATING OF 6.6 KV AUXILLIARY MOTORS:-

Coal mill 630 KW

Vapour fan 320 KW

Page | 7

Page 8: Bathinda thermal power plant mid semester report

C.W. Fan 800/746 KW

Coal crusher 520 KW

Primary air fan 320 KW

Forced draught fan 320 KW

Boiler feed pump 3500 KW

Induced draught fan 900/1000 KW

Condensate pump 175 KW

Page | 8

Page 9: Bathinda thermal power plant mid semester report

Coal received from collieries in the rail wagon is mechanically unloaded by

Wagon Tippler and carried by belt Conveyor System Boiler Raw Coal Bunkers after

crushing in the coal crusher. The crushed coal when not required for Raw Coal Bunker is

carried to the coal storage area through belt conveyor. The raw coal feeder regulates the

quantity of coal from coal bunker to the coal mill, where the coal is pulverized to a fine

powder. The pulverized coal is then sucked by the vapour fan and finally stored in

pulverized coal bunkers. The pulverized coal is then pushed to boiler furnace with the

help of hot air steam supplied by primary air fan. The coal being in pulverized state gets

burnt immediately in the boiler furnace, which is comprised of water tube wall all around

through which water circulates. The water gets converted into steam by heat released by

the combustion of fuel in the furnace. The air required for the combustion if coal is

supplied by forced draught fan. This air is however heated by the outgoing flue gases in

the air heaters before entering the furnace.

The products of combustion in the furnace are the flue gases and the ash. About

20% of the ash falls in the bottom ash hopper of the boiler and is periodically removed

mechanically. The remaining ash carried by the flue gases, is separated in the

electrostatic precipitators and further disposed off in the ash damping area. The cleaner

flue gases are let off to atmosphere through the chimney by induced draught fan.

The chemically treated water running through the water walls of boiler furnace

gets evaporated at high temperature into steam by absorption of furnace heat. The steam

is further heated in the super heater. The dry steam at high temperature is then led to the

turbine comprising of three cylinders. The thermal energy of this steam is utilized in

turbine for rotating its shaft at high speed. The steam discharged from high pressure

(H.P.) turbine is returned to boiler reheater for heating it once again before passing it into

the medium pressure (M.P.) turbine. The steam is then let to the coupled to turbine shaft

is the rotor of the generator, which produces electricity. The power from the generator is

pumped into power grid system through the generator transformer by stepping up the

voltage.

Page | 9

WORKING OF THERMAL PLANT

Page 10: Bathinda thermal power plant mid semester report

Page | 10

Page 11: Bathinda thermal power plant mid semester report

The steam after doing the useful work in turbine is condensed to water in the

condenser for recycling in the boiler. The water is pumped to deaerator from the

condenser by the condensate extraction pumps after being heated in the low pressure

heater (L.P.H) from the deaerator, a hot water storage tank. The boiler feed pump

discharge feed water to boiler at the economizer by the hot flue gases leaving the boiler,

before entering the boiler drum to which the water walls and super heater of boiler are

connected.

The condenser is having a large number of brass tubes through which the cold

water is circulated continuously for condensing the steam passing out sides the surface of

the brass tubes, which has discharged down by circulating it through the cooling tower

shell. The natural draught of cold air is created in the cooling tower, cools the water fall

in the sump and is then recirculated by circulating water pumps to the condenser.

Page | 11

Page 12: Bathinda thermal power plant mid semester report

BOILER FEED PUMP:-

As the heart is to human body, so is the boiler feed pump to the steam power plant. It is

used for recycling feed water into the boiler at a high pressure for reconversion into

steam. Two nos. 100% duty, barrel design, horizontal, centrifugal multistage feed pumps

with hydraulic coupling are provided for each unit. This is the largest auxiliary of the

power plant driven by 3500 KW electric motor.

The capacity of each boiler at GURU NANAK DEV THERMAL PLANT is

375 tones/hr. The pump which supplies feed water to the boiler is named as boiler feed

pump. This is the largest auxiliary in the unit with 100% capacity which takes suction of

feed water from feed water tank and supplies to the boiler drum after preheating the same

in HP-1, HP-2 and economizer. The delivery capacity of each boiler feed pump is 445

tones/hr. to meet better requirements corresponding to the various loads, to control steam

temperature, boiler make up water etc. The detailed particulars checking of protections

and inter locks, starting permission etc. are as below:-

Particulars of BFP and its main motor:-

BOILER FEED PUMP : - The 110 MW turboset is provided with two boiler feed

pumps, each of 100% of total quantity. It is of barrel design and is of horizontal

arrangement, driven by an electric motor through a hydraulic coupling.

Type 200 KHI

No. of stages 6

Delivery capacity 445 t/hr.

Feed water temperature 158C

Speed 4500 rpm

Pressure at suction 8.30 kg/cm²

Stuffing box mechanical seal

Lubrication of pump by oil under pressure

And motor bearing supplied by hydraulic coupling

Consumption of cooling water 230 L/min.

Page | 12

GENERAL DESCRIPTION

Page 13: Bathinda thermal power plant mid semester report

WATER TREATMENT PLANT:-

The water before it can be used in the boiler has to be chemically treated, since untreated

water results in scale formation in the boiler tubes especially at high pressure and

temperatures. The water is demineralised by Ion Exchange Process. The water treatment

plant has production capacity of 1800 Tonnes per day for meeting the make-up water

requirement of the power station.

COAL MILL:-

Coal Mill pulverizes the raw coal into a fine powder before it is burnt in the boiler

furnace. The pulverizing of coal is achieved with the impact of falling steel balls,

weighing 52.5 tonnes, contained in the mill drum rotating at a slow speed of 17.5 r.p.m.

The raw coal is dried, before pulverizing, with inert hot flue gases tapped from the boiler.

Three coal mills each with a pulverizing capacity of 27 T/hr. are provided for one unit.

INDUCED DRAUGHT FAN:-

Two nos. axial flow Induced Draught Fans are provided for each unit to exhaust ash

laden flue gases from boiler furnace through dust extraction equipment and to chimney.

The fan is driven by an electric motor through a flexible coupling and is equipped with

remote controlled regulating vanes to balance draught conditions in the furnace. The fan

is designed to handle hot flue gases with a small percentage of abrasive particles in

suspension.

CONTROL ROOM:-

The control room is the operational nerve center of the power plant. The performance of

all the equipments of the plant is constantly monitored here with the help of sophisticated

instrumentation and controllers. Any adverse deviation in the parameters of various

systems is immediately indicated by visual and audio warning and suitable corrective

action is taken, accordingly. The control room is air conditioned to maintain the desired

temperature for proper functioning of the instruments.

Page | 13

Page 14: Bathinda thermal power plant mid semester report

WAGON TIPPLER:-

The coal received from the collieries, in more than 100 rail wagons a day, is unloaded

mechanically by two nos. wagon tipplers out of which one serves as a standby. Each

loaded wagon is emptied by tippling it in the underground coal hopper from where the

coal is carried by conveyor to the crusher house. Arrangements have been provided for

weighing each rail wagon before and after tippling. Each tippler is capable of unloading

6-8 rail wagons of 55 tonnes capacity in an hour.

CRUSHER HOUSE:-

Coal unloaded by the wagon tippler is carried to crusher house through conveyors for

crushing. Two nos. hammer type coal crushers are provided, which can crush coal to a

size of 10 mm. The crushed coal is then supplied to Boiler Raw Coal Bunkers. The

surplus coal is carried to coal storage area by series of conveyors. Crushing of coal is an

essential requirement for its optimum pulverizing and safe storage.

COOLING TOWERS:-

Cooling Towers of the power plant are the land mark of the Bathinda City even for a far

distance of 8-10 kilometers. One cooling tower is provided for each unit for cooling

18000 tones of water per hour by 10C. cooling towers are massive Ferro-concrete

structure having hyperbolic profile creating natural draught of air responsible for

achieving the cooling effect. Cooling tower is as high as 40 storey building.

Page | 14

Page 15: Bathinda thermal power plant mid semester report

BOILER:-

It is a single drum, balanced draught, natural circulation, reheat type, vertical combustion

chamber consists of seamless steel tubes on all its sides through which water circulates

and is converted into steam with the combustion of fuel. The temperature inside the

furnace where the fuel is burnt is of the order of 1500C. The entire boiler structure is of

42meter height.

BOILER CHIMNEY:-

The flue from the boiler, after removal of ash in the precipitators, are let off to

atmosphere through boiler chimney, a tall ferro-concrete structure standing as high as the

historic Qutab Minar. Four chimneys, one for each unit, are installed. The chimney is

lined with fire bricks for protection of ferro-concrete against hot flue gases. A protective

coating of acid resistant paint is applied outside on its top 10 meters.

CIRCULATING WATER PUMP:-

Two nos. of circulating water pumps provided for each unit, circulate water at the rate of

17200 T/hr. in a closed cycle comprising of Turbine Condenser and Cooling Tower. An

additional Circulating Water Pump provided serves by for two units. The water

requirement for bearing cooling of all the plant auxiliaries is also catered by these pumps.

Page | 15

Page 16: Bathinda thermal power plant mid semester report

Since G.N.D.T.P. units are primarily coal fired units so each boiler is

provided with closed milling circuits to pulverize the raw coal which is

received from coal conveying system after coal crushes before it is fired in

the furnace. The necessity of pulverizing the coal is to be ensuring its

maximum possible combustion in the furnace. The coal data for units are: -

COAL DATA UNITS 1 & 2 UNITS 3 & 4

Type of Coal

Net Calorific Value

Moisture

Ash Content

Volatile Matter Incombustible

Inlet of Coal

Bituminous

4300 Kcal/kg

10 %

30 %

24 %

10 mm

Bituminous

4727 Kcal/Kg

7.5 %

32 %

27 %

20 mm

Raw coal of maximum size 10 mm – 20 mm is pulverized in the milling

circuit and the output from the mill is fine coal.

Page | 16

COAL MILLING PLANT

Page 17: Bathinda thermal power plant mid semester report

COAL MILL:-

These are mainly of two types:-

i) Ball Mills

ii) Bowl Mills

Ball Mills: - In Ball Mills there are steel balls which are revolving in horizontal

cylindrical drum. These balls are free from any shaft and balls are touching with each

other and with internal body of drum. These types of mills are at Bathinda Thermal Plant.

On the other hand, bowl mills part of the mill contain drive system i.e. it contains 6.6 kV

electric motor and gear system which translates the revolution about horizontal axis to

revolve about vertical axis. The revolving vertical axis contains a bowl about the driving

system. This bowl is fixed with driving and revolving with shaft. There are also three

rollers which are suspended at some inclination, so that there is a gap of few mm between

roller surface. These rollers are free to rotate about the axis.

Page | 17

Page 18: Bathinda thermal power plant mid semester report

Bowl Mills: - The coal is grinded and then fed into the mill at the center or near of

revolving bowl. It passes between the grinding ring in revolving bowl and rolls as

centrifugal force causes the material to travel towards the out perimeter of bowl. The

springs, which load the rolls, impart the necessary force for grinding. The partially

pulverized coal continue going up and down and over the edge of bowl.

WAGON TIPPLER:

The tippler is designed to work on the following cycle of operation:-

Tipping 90 seconds

Pause 5-12 seconds

Return 90 secondS

Weighing 30 seconds

Total 215-222 seconds

Allowing 85 seconds for wagon changing it will be seen that 12 eight-wheel wagons or

24 four-wheel wagons per hours can be tipped. However since the coal carrying capacity

is 500 tones per hour load of 12 wagons comes to 8 to 9 per hour.

CRUSHER HOUSE:-

Page | 18

Page 19: Bathinda thermal power plant mid semester report

The crusher house accommodates the discharge ends of the conveyor 4A, 4B receiving

ends of conveyor 5A, 5B and conveyor 7A and 7B, two crushers, vibrating feeders and

necessary chute work. There are two crushers each driven by 700H.P. electric motor, 3

phase, 50 cycles and 6.6 kV supply. The maximum size of the crushed coal is 10mm. The

capacity of each crusher is 500 tones/hr. one crusher works at a time and the other is

standby. From the crusher the coal can be fed either to the conveyors 5A, 5B or 7A, 7B

by adjusting the flap provided for this purpose. There is built in arrangement of bypassing

the crusher by which the coal can be fed directly to the conveyors bypassing crusher.

CONVEYOR BELT AND CRUSHER HOUSE

Page | 19

Page 20: Bathinda thermal power plant mid semester report

It is main part of STEAM GENRATOR’ it is an assembly of a large no. of vertical riser

tubes embedded in refractory walls. There are two boilers one for each unit. The type of

the boiler is NATURAL CIRCULATION RADIENT SINGLE REHEAT boiler. The four

refectory walls make a closed box called FURANCE.The walls are given special names.

These are;

1. RIGHT WALL consisting 130 TUBES.

2. LEFT WALL consisting 130 TUBES.

Page | 20

BOILER SECTION

Page 21: Bathinda thermal power plant mid semester report

3. FRONT WALL consisting 181 TUBES.

4. REAR WALL consisting 181 TUBES.

On the right and left wall, the WIND BOXES are installed. Thus there are Four Furnace

Coroners.

FRONT WALL

(181)

REAR WALL(181)

The water tubes cool the walls by absorbing the heat and transferring it to the

water running in them. The tubes are embedded in refectory walls very close (the Gap

between two tubes is 10 mm). The inner diameter of the tubes is 63.5mm.

JUSTIFICATION OF THE BOILER TYPE;

The type of boiler is WATER TUBE, NATURAL CIRCULATION, RADIENT SINGLE

REHEAT boiler. The meaning of each word has been explained below;

WATER TUBE; It mean the water runs in the tubes and the fire is outside the tubes.

NATURAL CIRCULATION; The CIRCULATION word mean how the water is raised

in the walls. We know that the water upwards we have to supply some external power

e.g., some pump system’ But here a law dose this work naturally. The saturated water

collected at the bottom known as RING HEADER. The water rises from it in riser pipes

naturally. There is a TWO PHASE MIXTURE of WATER and STEAM in risers. There

is a DIFFERENCE BETWEEN the DENSITIES of the MIXTURE and SATURATED

WATER in Ring Header. Also there is a STATIC HEAD. Due to the result of both

factors there is NATURAL CIRCULATION operates in boiler.

RADIENT TYPE: As the name implies, the heat is transferred from combustion gas to

the water by RADIATION. The heat is then CODUCTED to water tubes and through the

thickness of tubes. There is CONVECTED to the TWO PHASED MIXTURE.

Page | 21

Page 22: Bathinda thermal power plant mid semester report

SINGLE REHEAT; It implies that the system is reheated only once . When the steam

goes to H Turbine its temperature decreases from 540 deg to 343 deg. It is then send to

reheater to increase the temp to again 540 deg.

1. It should be absolutely reliable and capable of raising maximum amount of steam

for minimum fuel consumption, attention, initial cost and maintenance charges.

2. It should be light in weight and should occupy small space.

3. It should be capable of quick starting and meeting rapidly large variation of load

demands.

4. The water surface and tube should be so arranged so as to avoid priming.

5. The tubes should not accumulate soot or water deposits.

6. The refractory system should be as little as possible, but sufficient to secure easy

ignition and smokeless combustion of fuel on reduced load.

Manufacturers B.H.E.L

Maximum continuous rating 375 T/ hr

Superheater outlet Pressure 139 Kg/cm2

Final Superheater Temp. 5400C

Feed Water Temp. 2400C

Efficiency 86%

Coal Consumption Per day 1400 tones (approx.)

Page | 22

Page 23: Bathinda thermal power plant mid semester report

Spending my six months of training in Guru Nanak Dev Thermal Plant, Bathinda, I

concluded that this is a very excellent industry of its own type. They have achieved

milestones in the field of power generation. They guide well to every person in the

industry i.e. trainees or any worker. I had an opportunity to work in various sections

namely switch gear, Boiler section, Turbine section, De-mineralized water plant, E.S.P,

EM-2 CELL etc. while attending various equipments and machines. I had got an

endeverous knowledge about the handling of coal, various processes involved like

unloading, belting, crushing and firing of coal. The other machines related to my field

that I got familiar with boiler, turbine, compressors, condenser etc. I found that there

existed a big gap between the working in an institute workshop and that in the industry.

Above all the knowledge about the production of electricity from steam helped me a lot

to discover and sort out my problems in my mind related to the steam turbine, their

manufacture, their capacity, their angle of blades and their manufacturing. The training

that I had undergone in this industry will definitely help me to apply theoretical

knowledge to the practical situation with confidence.

Page | 23

CONCLUTION

Page 24: Bathinda thermal power plant mid semester report

1. A Textbook of electrical technology (A.C & D.C Machines) – B.L.THERAJA, A.K.THERAJA

2. A course in electrical power: - J.B.GUPTA

3. A course in electrical & electronic measurement and instrumentation: - A.K.SAWHNEY

4. A course in electrical power: - M.L.SONI, P.V.GUPTA

5. A textbook of power plant engineering: - Er. R.K.RAJPUT

6. www.wikipedia.com

7. www.sensorland.com

8. Manual of GURU NANAK DEV THERMAL PLANT, BATHINDA