52
Placing and Finishing Concrete By Prof. Adel El Kordi & Dr. Meheddene Machaka Structural Engineering Department Faculty of Engineering Beirut Arab University CVLE 321

6 placing and finishing concrete

  • Upload
    khawwam

  • View
    533

  • Download
    1

Embed Size (px)

Citation preview

Placing and Finishing Concrete

ByProf. Adel El Kordi

&Dr. Meheddene Machaka

Structural EngineeringDepartment

Faculty of EngineeringBeirut Arab University

CVLE 321

Basic Requirements for Placing Concrete (1)

Preserve concrete quality Water-cement ratio Slump Air-content Homogeneity

Avoid separation ofaggregate and mortar

2

Basic Requirements for Placing Concrete (2)

Avoid excessive horizontalmovement

Consolidate adequately Maintain sufficient placement

capacity Choose the right equipment for

the concrete

3

Preparation Before Placing Includes: Moistening the subgrade

4

Preparation Before Placing Includes: Compacting the subgrade

5

Depositing Concrete DO NOT —

(a) disturb saturated subgrades sobearing capacity is maintained

(b) deposit on frozen subgrade

Deposit continuously and as near aspossible to its final position

Rate of placement should be suchthat previously placed concrete hasnot set when the next layer is placedupon it

6

Depositing Concrete

Discharging into previouslyplaced concrete

Effective use ofwheelbarrows

7

Incorrect Placement with Conveyor Belt

Baffle

Mortar Rock Mortar

MortarRock

Shallowhopper

8

Placement with Conveyor Belt

Belt Scraper

NoSeparation

Provide at least 0.6 m(24 in.) headroom fordownpipe, elephanttrunk or equivalent

9

Depositing Concrete

Pavement Slab

Concrete deposited infront of slip form paverby dump trucks

Concrete spreadevenly across thesubgrade by the paverbefore consolidationand finishing

10

Curb/Curb and Gutter

Depositing Concrete

Concrete depositedinto hopper of slipform curb and guttermachine which thenextrudes the concreteinto the desiredshape

11

Depositing Concrete

Deposit in horizontal layers ofuniform thickness Reinforced — 150 mm to 500 mm Mass — 375 mm to 500 mm

Consolidate each layer beforenext is placed

Timely placement & consolidationprevents flow lines and cold joints

Walls

12

Horizontal Construction Joint

13

Horizontal Construction Joints

14

Underwater Placement Methods

Tremie Pump Bottom dump buckets Grouted preplaced

aggregate (specialized) Toggle bags Bagwork Diving bell

15

Placing Concrete Under Water

Water velocity 3 m (10 ft) / min. Water temperature 5°C

(if below — test for strength gain) w/c 0.45 Cementing materials content

390 kg/m3 (600 lb/yd3) Slump range 150 to 225 mm (6 to

10 in.)

Basic Recommendations

16

Placing ConcreteUnderwater

Used: Tremie

Advantages: Can be used tofunnel concrete down throughthe water into the structure.

Watch for: Discharge endalways has to be buried in freshconcrete to ensure sealbetween water and concretemass.

17

ConsolidatingConcrete

Internal Vibration

External Vibration

18

Internal Vibration

d

1½ R

Vibrator

Radius of Action19

Systematic Vibration of Each New Lift

CORRECTVertical penetration a few inches intoprevious lift (which should not yet berigid) of systematic regular intervalswill give adequate consolidation

INCORRECTHaphazard random penetration of thevibrator at all angles and spacingswithout sufficient depth will not assureintimate combination of the two layers

20

Placing Concrete in a Sloping LiftCORRECTStart placing at bottom of slope sothat compaction is increased byweight of newly added concrete.Vibration consolidates the concrete.

INCORRECTWhen placing is begun at top of slopethe upper concrete tends to pullapart especially when vibrated belowas this starts flow and removes fromconcrete above. 21

External Vibration

Form vibrators Vibrating tables Surface vibrators

Vibratory screeds Plate vibrators Vibratory roller screeds Vibratory hand floats or

trowels

22

Consolidating Concrete

Inadequate consolidationcan result in: Honeycomb Excessive amount of entrapped

air voids (bugholes) Sand streaks Cold joints Placement lines Settlement cracking

23

Nuclear Gauges to Determine Subbase Compaction

24

Screeding (Strikeoff)The process of cutting off excessconcrete to bring the top surface of aslab to proper grade

25

VibratoryScreeds

26

Flooring

27

Flooring

28

Edging

Required along all edge forms,isolation and construction jointsin floors and exterior slabs

Cut concrete away from formsto a depth of 25 mm with apointed mason or margin trowel

Edging may be required aftereach subsequent finishingoperation for interior slabs

Edging densifies and compacts concretenext to forms where floating is less effective

29

Highway Straightedges

30

Floating (Power or Hand)

To embed aggregateparticles just beneath thesurface

To remove slightimperfections, humps, andvoids

To compact the mortar atthe surface in preparationfor additional finishingoperations.

31

Toweling Creates smooth, hard,

dense surface Exterior concrete should

not be toweled because: it can lead to a loss of

entrained air caused byoverworking the surface

toweled surfaces can beslippery when wet.

32

Curing and Protection

Cure for 7 days33

Placing on Hardened ConcretePreparing Hardened Concrete

34

Bonding New to Previously Hardened Concrete

Cement-sandgrout

Latex Epoxy

35

1- Isolation Joints

36

2- Contraction Joints

37

Spacing of Contraction Joints in MetersSlab

thickness,mm

Maximum-sizeaggregate

less than 19 mm

Maximum-sizeaggregate

19 mm and larger100 2.4 3.0125 3.0 3.75150 3.75 4.5175 4.25 5.25200 5.0 6.0225 5.5 6.75250 6.0 7.5

Metric38

Making Contraction Joints

Dry-cut sawing concrete

Grooving toolon bull-float

39

3- ConstructionJoints

40

Typical Joint Layout

41

Finishing Operations

Consolidation Strike-off Edging Darbying or Bull Floating

Lapse of Time Edging Grooving (if desired) Floating (power or hand) Troweling (power or hand)

Lapse of Time Second Troweling (power or hand) Final Troweling (hand) Curing

Single Course Floors

42

Finishing Operations - Exterior Slabs

Consolidation Strike-off Depress aggregate with metal/wood strip

at joint location if hand tooled Darbying or Bull floating

Lapse of time Edging Jointing (optional if hand tooled) Floating

Lapse of time Texturing (brooming/swirl float finish) Curing

Sidewalks, Driveways etc.

43

Patching

44

Curing Patches

45

Cleaning Concrete Surfaces

Cleaning methods:

Water

Chemical

Mechanical

46

Special Surface Finishes

Pattern and Textures

Exposed Aggregate Concrete

Colored Finishes

Stains, Paints and Clear

Coatings

47

Placing andFinishing Concrete

48

Videos 1/4

Placing and Consolidating Vibration

49

Videos 2/4

Finishing I Finishing II

50

Videos 3/4

Contraction Joints Jointing

51

Videos 4/4

Improper Finishing

52