36
Steelhead Haven Landslide Steelhead Haven Landslide Fine Sediment Reduction Fine Sediment Reduction Project Project Tracy Drury, PE Anchor Environmental L.L.C. Pat Stevenson Stillaguamish Tribe of Indians

Steelhead Haven

  • Upload
    swcnabi

  • View
    856

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Steelhead Haven

Steelhead Haven Landslide Steelhead Haven Landslide Fine Sediment Reduction Fine Sediment Reduction

Project Project

Tracy Drury, PEAnchor Environmental L.L.C.

Pat StevensonStillaguamish Tribe of Indians

Page 2: Steelhead Haven

Stillaguamish Tribe’s InterestsStillaguamish Tribe’s Interests

Chinook Populations at 8% of historic levels

Fine sediments inputs was determined to be a major contributing factor

Success would improve habitat conditions for more than 30 miles downstream

Page 3: Steelhead Haven

Steelhead Haven Landslide 2004Steelhead Haven Landslide 2004

Page 4: Steelhead Haven

Historical PerspectiveHistorical Perspective

19651965 20002000

Page 5: Steelhead Haven

Then came 1967…Then came 1967…

Page 6: Steelhead Haven

Project PlanningProject Planning

Prioritized in the Chinook recovery plans, 1990, 2000, 2005

Began community involvement / public outreach, 1995

Evaluated in the Corps Ecosystem Restoration Plan, 2000

Conceptual Designs Developed, 2001

Funding for design and construction: Salmon Recovery Funding Board (500K) and Centennial Clean Water (500K), 2005

Page 7: Steelhead Haven

Project DesignProject Design

Design conducted, 2005-06Design conducted, 2005-06

ObjectivesObjectives Maximize sediment storageMaximize sediment storage Promote long-term stabilization of the slidePromote long-term stabilization of the slide Improve in-stream habitat conditionsImprove in-stream habitat conditions

ConstraintsConstraints No increase in flood impact to the local communityNo increase in flood impact to the local community

Page 8: Steelhead Haven

Preliminary Design ConceptPreliminary Design Concept

Page 9: Steelhead Haven

Slide Failure: January 2006Slide Failure: January 2006

Page 10: Steelhead Haven

BackwaterBackwater at low flowat low flow

Page 11: Steelhead Haven

Management ConcernsManagement Concerns

Page 12: Steelhead Haven

Management ActionsManagement Actions

Page 13: Steelhead Haven

Opening a channelOpening a channel

Page 14: Steelhead Haven

Channel BeginningsChannel Beginnings

Page 15: Steelhead Haven

January 29January 29thth 2006 2006

Flow through the treesFlow through the trees

Where the river wants to goWhere the river wants to go

Channel we clearedChannel we cleared

Page 16: Steelhead Haven

Former Former ChannelChannelBankBank

Pre-slidePre-slideHead scarpHead scarpLocation Location

730730FeetFeet

Post Slide Post Slide ChannelChannel

Page 17: Steelhead Haven

Redesign ConditionsRedesign Conditions

Page 18: Steelhead Haven

Creek Draining the SlideCreek Draining the Slide

Page 19: Steelhead Haven

Creek Mixing with RiverCreek Mixing with River

Page 20: Steelhead Haven

Project DesignProject Design

Design conducted, 2005-06

Objectives Maximize sediment storage Promote long-term stabilization of the slide Improve in-stream habitat conditions

Constraints No increase in flood impact to the local community

Page 21: Steelhead Haven

River 2D Hydraulic Model Output - DepthRiver 2D Hydraulic Model Output - Depth

Page 22: Steelhead Haven

River 2D Hydraulic Model Output - VelocityRiver 2D Hydraulic Model Output - Velocity

Page 23: Steelhead Haven

Expected Channel MigrationExpected Channel Migration

Expected Head cutExpected Head cut

Expected ChangeExpected ChangeLog Cribwall PlacementLog Cribwall Placement

Page 24: Steelhead Haven

Temporary Bridge Temporary Bridge

Page 25: Steelhead Haven

Isolating the River From the Construction Isolating the River From the Construction

Page 26: Steelhead Haven

Log Cribwall 1300 feet long, 25 feet high Log Cribwall 1300 feet long, 25 feet high

Page 27: Steelhead Haven

Ballast Blocks Approximately Every 50 Feet Ballast Blocks Approximately Every 50 Feet

Page 28: Steelhead Haven

Backfilled With Woody Debris Backfilled With Woody Debris

Page 29: Steelhead Haven

What the River Will See What the River Will See

Page 30: Steelhead Haven

Approximately 20 Acre-feet of StorageApproximately 20 Acre-feet of Storage

Page 31: Steelhead Haven

As-BuiltAs-BuiltConditionsConditions

Page 32: Steelhead Haven

First Flood EventFirst Flood Event

Page 33: Steelhead Haven

Channel Migrated Toward the StructureChannel Migrated Toward the Structure

Page 34: Steelhead Haven

Migration Progressing Downstream Migration Progressing Downstream

Page 35: Steelhead Haven

Take Home MessagesTake Home Messages

Landslide failure forced redesign to be more highly engineered placement

Constructability was a major decision making factor

The structure was designed to deform and settle as the river undercuts it’s face

Thorough analysis and communications prior to the failure facilitated permit acquisition after the failure

Page 36: Steelhead Haven

Steelhead Haven Landslide Steelhead Haven Landslide Fine Sediment Reduction Fine Sediment Reduction

Project Project

Tracy Drury, PEAnchor Environmental L.L.C.

Pat StevensonStillaguamish Tribe of Indians