View
1.015
Download
0
Embed Size (px)
DESCRIPTION
Citation preview
Output-Based Aid for Water in Africa:
Uganda Small Towns Water Project
Eng Chris Azuba
Ministry of Water & Environment, Uganda
African International Water Congress
Kampala, March 15 -18, 2010
Outline
Context – small towns water reform
OBA in Uganda’s water sector
Small towns and RGC project - design,
implementation, achievements and
challenges
Concluding remarks
Small towns water sector reform
Prior to 1997,Central Government ran all formal water supply systems with most resources anchored at the centre, but with regional/ town offices working on the ground.
This was not sustainable: decision making was far from the users.
Example: Revenue from water sales had to be remitted to the Centre as “government revenue”, and requests for operational funds would follow a long laborious process which could take as long as 3 months.
After the reforms…
Performance ContractAssets Delegation
Customer Contract
Management Contract
Water Authority(Assets Management)
Users/Clients
MW&E
Private Operator(Management of Technical, Financial and Commercial Operations)
5 Member WSS Board•Town clerk•Chair Social Services Committee•Rep of domestic consumers•Rep of institutional consumers•Rep of Other Consumers
New framework for
the small towns
water sector
OBA interventions in Uganda
Objective: Pilot OBA sub-projects in 6 small towns (extensions) and 4 RGCs (greenfield). Project expected to benefit almost 45,000 people
Outputs: 1) Household yard-taps or public kiosks and 2) continued service for 1 year (small towns) or 6 months (RGCs). Total number of connections: 2000
Private operators have been engaged in Design-Build-Operate (“DBO”) contracts of 5 years in brownfield, 7-10 years in greenfield.
Private Sector leveraging: 10-30% of capital costs depending on small town/RGC.
Available subsidy is $2,6m for first 10 towns; subsidy per town ranges between 80 to 90% (whereas normally with donor funding, 100%).
.
MoWE
Small TownRGC
Performance Contract
Local Water Authority
Water users
DWDImplementing Agency
Private Operator
Service
provision
PrivateSector
Funds Disbursement
Agent
GPOBA
Contracts
Funds
Control
Grant
Agreement
FiduciaryAgent
Implementation
Agreement
Funds
Administration
Agreement
DBO
Agreement
Memorandum of Understanding (MoU)
Monitoring and Verification
Function
Institutional framework
Targeting
Geographic: concentrated rural areas in Uganda for those
currently without access. Self-selection: public kiosks
Innovation and efficiency
A competitive bidding process resulted in an average
efficiency gain of 20% in 10 towns.
Sustainability
Subsidies are one-off investments and tariffs cover O&M costs
plus a margin for investment. Tariffs levels are embedded in
the contracts. These contracts are of longer duration that what
has been seen so far in the Ugandan water sector
Progress to date…
In the 6 towns, progress is as follows:
Town Target Completed Remarks
Kachumbala 156 150 Verified
Kalisizo 150 150 To be verified
Luweero 250 180 To be verified
Rukungiri 200 113 Awaiting additional
applicants
Wakiso 300 300 Verified
Wobulenzi 200 68 To be verified
Construction in the 4 RGCs is at an advanced stage and
is expected to be completed by the end of March 2010.
Achievements and challenges
Tariffs embedded in contract = big step in Uganda.
Acceptance of “tariff localization”.
Bidding process demonstrated enthusiasm from POs.
Real challenge in getting bidders to understand the new format of bidding documents. Some lots were re-bid.
Some towns = no subsidy required for making connections.
Outputs being delivered – some more slowly than others –construction and verification process approaching completion.
Access to finance, in particular to “pre-finance” investments until OBA subsidy disbursed is a challenge.
JVs with construction companies helped.
Phasing in of outputs in the greenfield cases were required (but still 40% paid on working connections and water delivered).
POs relied more on own cash, working capital (e.g. supplier credit) than bank loans.
Conclusions and way forward
Uganda-tailored approaches. Working largely with existing contractual framework.
Challenges related to technical assistance capacity and access to finance remain.
Now scaling-up: increased collaboration with all stakeholders, donor harmonization and adopting (and adapting) government approaches as far as practicable.
MoWE has agreed in principle to adopt OBA approaches within the new WSDFs, being negotiated for next fiscal year, regardless of source of funding.