Upload
hemang-kothari
View
1.360
Download
1
Tags:
Embed Size (px)
Citation preview
04/11/2023 Computer Engineering Department - MEFGI 1
Module 3 – Process Scheduling
Hemang KothariAssistant Professor
Computer Engineering Department MEFGI, Rajkot.
Email: [email protected]: http://www.slideshare.net/hemangkothari
04/11/2023 Computer Engineering Department - MEFGI 2
04/11/2023 Computer Engineering Department - MEFGI 3
Objective
• Max CPU utilization• Max throughput• Min turnaround time • Min waiting time • Min response time
04/11/2023 Computer Engineering Department - MEFGI 4
Process Scheduling Goals• CPU utilization – keep the CPU as busy as possible• Throughput – # of processes that complete their execution per
time unit• Turnaround time – amount of time to execute a particular process• Waiting time – amount of time a process has been waiting in the
ready queue• Response time – amount of time it takes from when a request was
submitted until the first response is produced, not output (for time-sharing environment)
04/11/2023 Computer Engineering Department - MEFGI 5
Background Work• Maximum CPU utilization obtained with Multiprogramming• CPU–I/O Burst Cycle.
04/11/2023 Computer Engineering Department - MEFGI 6
CPU Schedular• Selects from among the processes in memory that are ready to
execute, and allocates the CPU to one of them.• CPU scheduling decisions may take place when a process:
1. Switches from running to waiting state.2. Switches from running to ready state.3. Switches from waiting to ready.4. Terminates.
• Scheduling under 1 and 4 is nonpreemptive.• All other scheduling is preemptive.
04/11/2023 Computer Engineering Department - MEFGI 7
First-Come, First-Served (FCFS) Scheduling
Process Burst TimeP1 24
P2 3
P3 3
• Suppose that the processes arrive in the order: P1 , P2 , P3
The Gantt Chart for the schedule is:
• Waiting time for P1 = 0; P2 = 24; P3 = 27• Average waiting time: (0 + 24 + 27)/3 = 17• Average turn around time: (24 + 27 + 30) / 3 = 81/3 = 27
P1 P2 P3
24 27 300
04/11/2023 Computer Engineering Department - MEFGI 8
First-Come, First-Served (FCFS) SchedulingSuppose that the processes arrive in the order
P2 , P3 , P1 .• The Gantt chart for the schedule is:
• Waiting time for P1 = 6; P2 = 0; P3 = 3• Average waiting time: (6 + 0 + 3)/3 = 3• Much better than previous case.• Convoy effect short process behind long process
P1P3P2
63 300
04/11/2023 Computer Engineering Department - MEFGI 9
Review - FIFO• Suppose the following jobs arrive for processing at the times
indicated, each job will run the listed amount of time.
• Give Gantt charts illustrating the execution of these jobs using FCFS scheduling algorithms. Compute the average turn around time and average waiting time.
Remember that turnaround time is finishing time minus arrival time, so you have to subtract the arrival times to compute the turnaround times.
04/11/2023 Computer Engineering Department - MEFGI 10
Shortest Job First (SJF)• Associate with each process the length of its next CPU burst. Use
these lengths to schedule the process with the shortest time.• Two schemes:
– nonpreemptive – once CPU given to the process it cannot be preempted until completes its CPU burst.
– preemptive – if a new process arrives with CPU burst length less than remaining time of current executing process, preempt. This scheme is know as the Shortest-Remaining-Time-First (SRTF).
• SJF is optimal – gives minimum average waiting time for a given set of processes.
04/11/2023 Computer Engineering Department - MEFGI 11
Example of Non Preemptive SJFProcess Arrival Time Burst TimeP1 0.0 7
P2 2.0 4
P3 4.0 1
P4 5.0 4• SJF (non-preemptive)
• Average waiting time = (0 + 6 + 3 + 7)/4 ≈ 4
P1 P3 P2
73 160
P4
8 12
04/11/2023 Computer Engineering Department - MEFGI 12
Review - Non Preemptive SJF • Suppose the following jobs arrive for processing at the times
indicated, each job will run the listed amount of time.
• Give Gantt charts illustrating the execution of these jobs using SJF scheduling algorithms. Compute the average turn around time and average waiting time.
04/11/2023 Computer Engineering Department - MEFGI 13
Example of Preemptive SJFProcess Arrival Time Burst TimeP1 0.0 7
P2 2.0 4
P3 4.0 1
P4 5.0 4• SJF (preemptive)
• Average waiting time = (9 + 1 + 0 +2)/4 = 3
P1 P3P2
42 110
P4
5 7
P2 P1
16
04/11/2023 Computer Engineering Department - MEFGI 14
Review - Preemptive SJF • Suppose the following jobs arrive for processing at the times
indicated, each job will run the listed amount of time.
• Give Gantt charts illustrating the execution of these jobs using SJF scheduling algorithms. Compute the average turn around time and average waiting time.
04/11/2023 Computer Engineering Department - MEFGI 15
Priority Scheduling • A priority number (integer) is associated with each process• The CPU is allocated to the process with the highest priority (smallest
integer highest priority).– Preemptive– nonpreemptive
• SJF is a priority scheduling where priority is the predicted next CPU burst time.
• Problem Starvation – low priority processes may never execute.• Solution Aging – as time progresses increase the priority of the
process.
16
Priority Scheduling: Example
Process Duration Priority Arrival Time
P1 6 4 0
P2 8 1 0
P3 7 3 0
P4 3 2 0
0 8 P4 (3) P1 (6)11 P3 (7) 18
P2 waiting time: 0P4 waiting time: 8P3 waiting time: 11P1 waiting time: 18
The average waiting time (AWT): (0+8+11+18)/4 = 9.25(worse than SJF)
P2 (8)24
04/11/2023 Computer Engineering Department - MEFGI 17
Round Robin • Each process gets a small unit of CPU time (time quantum), usually
10-100 milliseconds. After this time has elapsed, the process is preempted and added to the end of the ready queue.
• If there are n processes in the ready queue and the time quantum is q, then each process gets 1/n of the CPU time in chunks of at most q time units at once. No process waits more than (n-1)q time units.
• Performance– q large FIFO– q small q must be large with respect to context switch, otherwise overhead
is too high.
04/11/2023 Computer Engineering Department - MEFGI 18
Round Robin with Quantum = 20Process Burst TimeP1 53
P2 17
P3 68
P4 24• The Gantt chart is:
• Typically, higher average turnaround than SJF, but better response.
P1 P2 P3 P4 P1 P3 P4 P1 P3 P3
0 20 37 57 77 97 117 121 134 154 162
Example of RR with Time Quantum = 20
• Waiting Time:– P1: (68-20)+(112-88) = 72– P2: (20-0) = 20– P3: (28-0)+(88-48)+(125-108) = 85– P4: (48-0)+(108-68) = 88
• Completion Time:– P1: 125– P2: 28– P3: 153– P4: 112
• Average Waiting Time: (72+20+85+88)/4 = 66.25• Average Completion Time: (125+28+153+112)/4 = 104.5
A process can finish before the time quantum expires, and release the CPU.
Lec 3 Operating Systems 19
04/11/2023 Computer Engineering Department - MEFGI 20
Review • Five batch jobs A through E , arrive at a computer center at almost the same
time. They have estimated running times of 10, 6, 2, 4, and 8 minutes. Their (externally determined) priorities are 3, 5, 2, 1, and 4, respectively, with 5 being the highest priority. For each of the following scheduling algorithms, determine the mean process turnaround time. Ignore process switching overhead.(a) Round robin.(b) Priority scheduling.(c) First-come, first-served (run in order 10, 6, 2, 4, 8).(d) Shortest job first.
• For (a), assume that the system is multiprogrammed, and that each job gets its fair share of the CPU. For (b) through (d) assume that only one job at a time runs, until it finishes. All jobs are completely CPU bound.
04/11/2023 Computer Engineering Department - MEFGI 21
Solution • For round robin, during the first 10 minutes each job gets 1/5 of the CPU. At the
end of 10 minutes, C finishes. During the next 8 minutes, each job gets 1/4 of the CPU, after which time D finishes. Then each of the three remaining jobs gets 1/3 of the CPU for 6 minutes, until B finishes, and so on. The finishing times for the five jobs are 10, 18, 24, 28, and 30, for an average of 22 minutes.
• For priority scheduling, B is run first. After 6 minutes it is finished. The other jobs finish at 14, 24, 26, and 30, for an average of 18.8 minutes.
• If the jobs run in the order A through E, they finish at 10, 16, 18, 22, and 30, for an average of 19.2 minutes.
• Finally, shortest job first yields finishing times of 2, 6, 12, 20, and 30, for an average of 14 minutes.
04/11/2023 Computer Engineering Department - MEFGI 22
Review Job Time Arrival Priority
1 8 0 32 4 0 23 6 0 14 1 0 4
• All jobs arrive at time 0(but in the order 1, 2, 3&4).Draw charts and calculate the average time to complete (turn-around time) using the following scheduling algorithms: FCFS, SJF, Priority scheduling and round Robin (t=2)
04/11/2023 Computer Engineering Department - MEFGI 23
Out of Subject Context - Technical
• Chaos Theory “ Chaos: When the present determines the future, but the
approximate present does not approximately determine the future “
• Watch “ Butterfly Effect “ Movie - Thriller