Upload
group-delta
View
521
Download
1
Embed Size (px)
DESCRIPTION
Case study of the design, construction and axial load testing of 48" diameter cast-in-steel-shell (CISS) Piles for supports of a freeway interchange in Southern California. Group Delta conducted a geotechnical investigation of the site and based on the subsurface conditions found at the location provided geotechnical input parameters in the design of the CISS piles. The pipe piles were 100 feet long and 4 feet (48 inches) in diameter. A full-scale load test was conducted to verify that the piles would have more than adequate capacity to support the interchange. For more information please visit http://www.groupdelta.com
Citation preview
CASE STUDY: Design, Construction, and Axial Load
Testing of 48” Diameter Cast-in-Steel-Shell Piles for
Support of a Highway Bridge
GDCU OCTOBER
18, 2013
Project DescriptionImprovements were proposed for the SR-22 / I-405 interchange to improve capacity, including a new 6-span High Occupancy Vehicle (HOV) direct connector bridge and replacement of the existing SB I-405 to EB SR-22 connector bridge.
Geotechnical Investigation
Group Delta’s scope included subsurface investigation and recommendations for bridge foundation support.
Data Review:Poorly consolidated alluvial soilsShallow groundwaterExisting structures on piles
New bridges would be supported on pile foundations Key issues include pile design, approach fill
settlement, and liquefaction potential
Geotechnical Investigation
Subsurface Investigation (minimum one boring per support):4 Mud Rotary Borings 51.5 feet to 137 feet bgs 5 Cone Penetration Tests (CPTs) 105.5 feet to 150.3 feet bgs.
Geotechnical Investigation(Mud Rotary Borings)
Geotechnical Investigation (CPT)
Geotechnical Investigation (CPT)
Geotechnical Investigation (CPT)
Geotechnical Investigation
Laboratory Testing:
Subsurface Conditions
Subsurface Conditions
100 ft x 48” CISS PilesBents 3 & 4
75 ft x 48”CISS PilesBents 2 & 5
14” PS Conc Piles at Abuts
DEVELOP DESIGN PROFILE: DIVIDE INTO LAYERS OF COHESIONLESS SOILS (SPT “N”) and COHESIVE SOILS (“Su”)
LOCATE DESIGN WATER TABLE
Groundwater
BENT FOUNDATION DESIGN(Type Selection)
DEEP FOUNDATIONSHALLOW FOUNDATION
P
VM
T =
qmax
qmin
Soil/Rock Bearing Resistance
Passive Soil/Rock Resistance
Sliding FrictionResistance
Shallow Competent Soil/Rock
and/or
Light Loads
P
VM
Heavy Loads, Uplift Loads,
and/or
Weak or Compressibleor Scourable
Soil
DeeperCompeten
t Soil/Rock
Passive Resistance
compression
tension
Lateral PileResistance
End Bearing
Skin Friction
48” CISS PILES SELECTED FOR BENTS
FOUNDATION DESIGN (Loads)Load and Resistance Factor Design (LRFD)
( * Qi ) < * Rn
“The sum of the factored loads must be less than the sum of the factored resistances.”
Limit States•Service: (settlement, slope stability, lateral capacity, etc.)
• All load factors and resistance factors = 1.0•Strength:
• Load factors > 1.0, Resistance Factors < 1.0•Extreme Event:
• All load factors and resistance factors = 1.0
FOUNDATION DESIGN(Design for Axial Capacity =
Determination of Pile Tip Elevation)
Estimation of Nominal (Ultimate) Axial ResistanceBasic Definition of Nominal Resistance-Skin Friction and End Bearing:
Qu
Qe
qe
Layer 1
Layer 2
Layer 3
Layer 4
fs4
fs3
fs2
fs1
B
D
d1
d2
d3
d4
QS
Qu = Qs + Qe
Qu = (Asi*fsi) + qe*Ae
where
Qu = nominal resistance in compression
Qs = ultimate side friction (all layers)
Qe = ultimate end bearing at tip
fsi = average ultimate unit skin friction in layer i
Asi = side area in contact with soil in layer i
= Pi * di
Pi * = pile perimeter within layer i
qe = unit ultimate end bearing at tip
Ae = pile end area
FOUNDATION DESIGN(Skin Friction and End Bearing)
American Petroleum Institute Recommended Practice 2A , July 1, 1993
(API RP 2A)
FOUNDATION DESIGN(Skin Friction and End Bearing)
American Petroleum Institute Recommended Practice 2A , July 1, 1993
(API RP 2A)
PLUGGING OF PIPE PILES:•Plugs if Qsi > Qep end bearing on full area and friction on outside only•Unplugged if Qsi < Qep end bearing on annulus only, friction inside and outside
QseQsi
Qep
Qea
FOUNDATION DESIGN(Skin Friction and End Bearing)
American Petroleum Institute Recommended Practice 2A , July 1, 1993
(API RP 2A)
FOUNDATION DESIGN (Skin Friction and End Bearing)American Petroleum Institute (API RP 2A)
FOUNDATION DESIGN(Design and Specified Tip Elevation)
2 Design Piles: L = 75 feet for 1150 kip nominal resistanceL = 100 feet for 1800 kip nominal resistance
FOUNDATION DESIGN(Pile Layout)
FOUNDATION DESIGN(Pile Layout and Load Test Pile Locations)
100’ TestPile
Reaction Piles
FOUNDATION CONSTRUCTION(Pile Driving)
Caltrans policy requires axial load test for all driven piles larger than 3 feet in diameter
First Piles Driven are Load Test Piles (to be used as production piles)
• 100 ft piles:• 1 test pile and 4 reaction piles• 1800 kip nominal resistance required
• 75 ft piles:• 1 test pile and 4 reaction piles• 1150 kip nominal resistance required
• Delmag D62 Diesel Hammer• Pile Driving Analyzer (PDA) Measurement
FOUNDATION CONSTRUCTION(Pile Driving)
100 ft long48” diameter pipe pilesWith ¾” wall thicknessPP 48 x 0.75
FOUNDATION CONSTRUCTION(Pile Driving)
Piles “Stabbed”With Vibratory HammerPrior to Driving
Large Crane required special FAA clearance
FOUNDATION CONSTRUCTION(Pile Driving)
Helmet
Delmag D62-22
Leads
Hammer
Delmag D62-22 Single Acting Diesel HammerRated Energy = 162 ft-k / blowRam Weight = 13.66 kipsMax. Stroke = 11.82 ft
FOUNDATION CONSTRUCTION(Pile Driving)
FOUNDATION CONSTRUCTION(Pile Driving)
FOUNDATION CONSTRUCTION(Pile Driving)
FOUNDATION CONSTRUCTION(Pile Driving)
FOUNDATION CONSTRUCTION(Dynamic Testing Pile Driving Analyzer [PDA])
FOUNDATION CONSTRUCTION(Pile Driving)
Blowcounts versus depth on initial drive
FOUNDATION CONSTRUCTION(PDA Acceptance Curves Considering Setup)
FOUNDATION CONSTRUCTION(PDA Time-Setup Relationship)
PILE LOAD TEST(PLT)
4000 kip Capacity Load Test Frame
FULL-SCALE PILE LOAD TEST(PLT)
FULL-SCALE PILE LOAD TEST(PLT)
Calibrated Hydraulic Jacks
FULL-SCALE PILE LOAD TEST(PLT)
Jobsite Artwork
FULL-SCALE PILE LOAD TEST(PLT)
Test in Progress
FULL-SCALE PILE LOAD TEST(PLT)
Deflection Measurements
PLT RESULTS
LOAD (KIPS)
PLT RESULTS
LOAD (KIPS)
PDA & PLT RESULTSUMMARY
Pile No.
Pile Length
RequiredCapacity
PDA ResultEnd of Initial Drive (EOID)
PDARESTRIKE
Load Test
CapacityPDA
SetupFactor
BlowCount Stroke
Est.EOID
Capacity
BOR BlowCount
EOR BlowCount
9 75’ 1150kips
39 9.4’ 885kips
210 90 1700kips
1.92 @ 23 days
10 100’ 1800kips
53 10.3’ 1300 kips
630 230 2600kips
2.0@ 34 days
Based on the results of the load test, Group Delta recommended reducing the pile length of 100 ft piles to 85 feet and 75 ft piles to 68 feet.
Due to a problem in recent revisions to the Caltrans Standard Specifications, the savings could not be realized and piles were driven to the design tip elevations.. Acceptance criteria (blowcount vs. stroke) were developed and used to confirm the capacity of the remaining production piles.
POURING THE FOOTING
POURING THE FOOTING
POURING THE FOOTING
POURING THE FOOTING
THE END