Chalmers Energy Conference
Wave Power – Status and Challenges
COPYRIGHT@PÖYRY 2011-09-16
Wave Power – Status and Challenges 2
CHALLANGES
STATUS
Intro
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 3
•Renewable energy source •High energy density • Substantial potential • Expected to have low environmental and visual impact •Relatively predictable and stable •…
INTRO – WHY WAVE POWER?
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 4
INTRO – WHY WAVE POWER?
Theoretical Resource
Practical Resource
Europe 2000+ TWh US 2100 TWh UK 700 TWh 50TWh Norway 600 TWh Ireland 500 TWh Denmark 30 TWh Sweden 10-15 TWh
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 5
INTRO – WAVE ENERGY ENGINEERING
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 6
Commercial wave farms Demonstration Project Pilot Test
•Full scale offshore tests •Test births •Grid connected
•10MW wave energy demo plant •Sub sea grid
Initial R&D
•Concept and theory •Tank test •Scale tests
STATUS – DEVELOPMENT CYCLE
•+100MW wave energy plant •Reduced subsidies
COPYRIGHT@PÖYRY
STATUS – DEVELOPMENT CYCLE
2011-09-16 Pöyry SwedPower – Marine Energy Team 7
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 8
Commercial wave farms Demonstration Project Pilot Test
•EMEC •MAREN •Lysekil Test Site •WAVE HUB •OCEAN Plug
•Shetland 10MW •Sotenäs 10MW
Initial R&D
•+100 concept word wide
STATUS – DEVELOPMENT CYCLE
•Pentland Firth
COPYRIGHT@PÖYRY
STATUS – SHETLAND 10MW DEMONSTRATION PLANT
2011-09-16 Pöyry SwedPower – Marine Energy Team 9
Pelamis P1A •Fullscale •Offshore •Gridconnected
Pelamis P1A •Re-launch •Orkney Islands (EMEC)
Pelamis P1 •3x750MW •Aguadora, Spain
Pelamis P2 •EOn •EMEC
Pelamis P2 •Scottish Power •EMEC
Pelamis P2e •Construction
Pelamis P2e •Launch •EMEC
10MW Plant •Launch 4+5 machines •Shetland
Commercial wave farms
2004 2007 2008 2010 2011 2012 2013 2014 2015 2016 2020
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 10
WILL THIS WORK?
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 11
WILL THIS WORK? CHALLANGES
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 12
CHALLANGES
Technical Economical
Political
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 13
CHALLANGES – TECHNICAL
Sunday 20 September 2009 a problem during the deployment phase led to its demonstration wave generator overturning as it was being taken out to sea to begin its year-long offshore trial.
Hit by a severe storm January 8th 2004 the main mooring connection broke and the platform drifted towards the shore where it stranded close to the beach.
Mc Cabe Wave Pump, Destroyed during sea trials during unexpected storm early 2000.
SURVIVABILITY
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 14
CHALLANGES – TECHNICAL
ABSORPTION
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 15
CHALLANGES – TECHNICAL
•Survivability •Absorption •O&M •Life length •Sub sea grid
•… •…
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 16
CHALLANGES – ECONOMICAL
FUNDING
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 17
CHALLANGES – ECONOMICAL
Investment calculation
CAPEX
O&M
Production
IRR NPV
kr/kWh ? BUSINESS CASE
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 18
CHALLANGES – ECONOMICAL
•Funding •Business case
•Many unknowns •Small margins
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 19
CHALLANGES
STATUS
Intro
WHAT DO WE NEED NOW?
SUCCESS! STAMINA!
COPYRIGHT@PÖYRY 2011-09-16
Wave Power – Status and Challenges 20
COPYRIGHT@PÖYRY 2011-09-16
Pöyry SwedPower – Marine Energy Team 21
CONTACT: NAME: OSKAR D FÄNGSTRÖM TITLE: MANAGER WAVE ENERGY MAIL: [email protected] PHONE: +46-703-863470