Trenchless Crossing Evaluation on the Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer

An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Page 2: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Introduction

• Purpose− Provide engineers and owners with one example of a trenchless crossing evaluation.

• Outline−

•− Trenchless Considerations− Trenchless Methods

HDD, microtunneling, pipe jacking, auger-boring, pipe ramming.

−Martha Lake Sewer Project Overview−Martha Lake Trenchless Evaluation− Conclusion of Evaluation− Next Steps

Page 3: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Trenchless Considerations

• Ground Conditions− Soil Type−Groundwater− Rock / Boulders−−Mixed Face Conditions−Wood−Man-made Debris (concrete, steel, VW Bugs, etc.)

• Crossing Length• Pipe / Casing Diameter• Alignment (Horizontal and Vertical) • Depth (cover over excavation)

Page 4: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Trenchless Methods

• Horizontal Directional Drilling (HDD)• Microtunneling• Pipe Jacking• Auger Boring• Auger Boring• Pipe Ramming

Page 5: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Horizontal Directional Drilling (HDD)• Pilot hole• Reaming pass(es)• Spoils removed by recirculation of drilling mud•• Pipe insertion

Page 6: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Horizontal Directional Drilling (HDD)• Strengths− Performs well in groundwater− Drilling mud mix can be alteredfor ground conditions

− Very long crossings−−− Curved alignments

• Weaknesses− Elevated risk of frac-out or settlement− Smaller diameters (< 36”)− Difficult to control line and grade− Requires a 2% minimum slope for gravity applications

− Large area for pullback layout

Page 7: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Microtunneling

• Jacking shaft• Spoil Removal via slurry lines• Slurry pressure provides •excavation face support• Hydraulic jacks advance pipe string and MTBM

Page 8: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Microtunneling• Strengths− Performs well above or below groundwater− Slurry pressure can be varied based on support needed at excavation face

− Longer Drive Lengths−Good line and grade control−Good line and grade control

• Weaknesses− Has difficulties excavatingobstructions larger than 1/3 the diameter

−Most do not allow face access to remove obstructions− Rescue pit required if stopped by an obstruction− Can be deflected by mixed-face conditions

Page 9: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Pipe Jacking

• Jacking Shaft• Open face allows manned access• Spoil Removal via mechanical or manned methods• Hydraulic jacks provide advance pipe string and • Hydraulic jacks provide advance pipe string and pipe jacking machine

Page 10: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Pipe Jacking• Strengths− Face access allows removal of obstructions− Longer Drive Lengths−Good line and Grade Control

• Weaknesses− Difficult to control groundwater− Difficult to control flowing soils− Can be deflected by mixed-face conditions

Page 11: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Auger-boring• Jacking Shaft• Spoil Removal via auger flight though jacking pipe• Hydraulic jacks advance pipe string and auger flight

Page 12: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Auger-boring• Strengths−Good in cohesive soils−Minor line and grade control

• Weaknesses− Difficult to control groundwater−Max. drive length of around 300’

Page 13: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Pipe Ramming

• Excavated pit• Pneumatic tool advances pipe• Minimal Spoil Removal• Face support provided by soil plug• Face support provided by soil plug

Page 14: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Pipe Ramming• Strengths−Minimal risk of ground settlement

− Excavation continuously supported

−− Performs well above orbelow groundwater

• Weaknesses− Difficult to control line and grade

− Short drive lengths (< 300’)

Page 15: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Martha LakeProject Overview• Alderwood Water & Wastewater District • Lynnwood, WA

Site

Page 16: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Martha Lake Project Overview

• I-5 and 164th St. SW• 3,400 LF of 12” to 15” gravity sewer• Residential Septic• Residential Septic• Commercial Pump Stations• 1700 LF of 24”water main added• Currently at 60%

Page 17: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Martha Lake Trenchless Crossing• Ground Conditions− Soil

§ Dense Glacial Till overridden by fill−Groundwater

§§ Perched groundwater on top of Till§ Pockets within Till

− Rock / Boulders§ Boulders: 1.5’ to 7’

−Mixed Face Conditions – None Known−Wood – None Known−Man-made Debris – None Known

Page 18: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Martha Lake Trenchless Crossing

TILL

Page 19: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

• Drive Length− 535’

• Pipe Diameter(s)− 54” - 60” Casing

Martha Lake Trenchless Crossing

− 54” - 60” Casing− 12” Ductile Iron Sewer− 24” Ductile Iron Water− Six 4” Conduits

• Alignment− Vertical profile lies completely within Glacial Till

• Depth− 14’ minimum, 25’ maximum

Page 20: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Martha Lake Trenchless Evaluation

Trenchless Trenchless Trenchless Trenchless MethodsMethodsMethodsMethods

Soil Types

(Glacial Till)

Ground Water

(Gravel Pockets)

Rock / Boulders

Settlem

ent Risk

Drive Length

(535')

Line and Grade

Control

TOTA

LTOTA

LTOTA

LTOTA

L

(Glacial Till)

Ground Water

(Gravel Pockets)

Rock / Boulders

Settlem

ent Risk

Drive Length

Line and Grade

HDD 6 8 5 6 9 4 38

Microtunnel 7 8 6 8 8 8 45

Pipe Jack 8 5 8 6 8 8 43

Auger-bore 5 4 5 6 1 4 25

Pipe Ramming 4 8 2 8 1 3 26

Page 21: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Conclusion

• Microtunneling or Pipe Jacking− Two options increases number of eligible contractors− Contractor can chose machine he believes will work best for ground conditions

− Three jacking pipe options give more flexibility− Three jacking pipe options give more flexibility§ HOBAS§ Reinforced Concrete§ Steel (PermaLok)

• GO BIG!!! = 60” Casing

Page 22: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

WSDOT

PUD

Page 23: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

WSDOT

Boulders!!

Boulders!!

Page 24: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Next Steps

• Specifications− Specify MTBM best suited for ground conditions− Specify options for rescue shaft to free MTBM− Require mitigation plan for encountering groundwater with a pipe jacking machinewith a pipe jacking machine

− Require obstruction removal plan for pipe jacking• GBR−Must apply to both pipe jacking and microtunneling operations

Page 25: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Trenchless Tips

• Use in combination with other methods• Pay a premium for short crossings• Talk with machine manufacturers and local contractors!contractors!

Page 26: Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer PNCWA... · 2016. 7. 14. · Introduction •Purpose −Provide engineers and owners with one example of a trenchless

Questions?