Thursday Nov. 3, 2011Toronto, OnJanice Bray
Parry Sound DSSAB
First inspection done in 2003
Inspection 2008 – Fire Department • In violation of the Fire Code – no fire separation in the attic
area• Possible fire separation issues with the crawl space as well
Relocated one tenant as soon as we had a suitable unit available to bring us into compliance
Second Inspection – August 2008Engineers confirmed :• The continued deterioration • That the building did not meet fire codes of 2008 or1975
when built or 1985 when it was reconfiguredAnd provided a• Estimate of the cost to come into compliance
SHRRP funding • Possibility of a regeneration project
Third Inspection – July 9, 2009• Cost analysis of the different options• Minimum repairs needed• Additional improvements in addition to minimal repairs• Demolish and rebuild
Board Approval to demolish and rebuild July 16, 2009
Started the process for Ministerial Consent• Fall of 2009 had an ESA I completed • Compiled all the documents necessary
Complete package sent to Ministry in February 2010
Ministerial consent granted February 2011
Board approval of process March 2010
Signed contract with SHSC for technical assistance in developing our Design/Build RFP, all site visits and the evaluation of the proposals• 3 proposal submitted
Demolition started the middle of June 2011 with a rebuild completion date of December 15, 2011
Open house for Board members in December