Page 1: Seahurst Project Update - March 17 presentation to City Council

SEAHURST PARKBEACH RESTORATION

PROJECT

Page 2: Seahurst Project Update - March 17 presentation to City Council

Groundbreaking: September 16, 2013

Page 3: Seahurst Project Update - March 17 presentation to City Council
Page 4: Seahurst Project Update - March 17 presentation to City Council

Construction Phase Contractors

• USACE: Project Partner and Construction Management

• CKY Inc. : Prime Contractor (San Pedro, CA)

• SCI Infrastructure: Grading/Earthwork (SeaTac, WA)

• Cadman Inc.: Materials/Gravel/Sand (Redmond, WA)

• Northwest Lining and Geotextiles: (Kent, WA)

• Pacific Pile and Marine: Barge Services (Seattle, WA)

• Dutton Electrico Co.: (Lynwood, WA)

• Cal Portland: Concrete (Seattle, WA)

• Cherry Valley Logging: Wood materials (Duvall, WA)

• Play Creations: Playground (Burien, WA)

Page 5: Seahurst Project Update - March 17 presentation to City Council

Park Closed: October 28, 2013

Page 6: Seahurst Project Update - March 17 presentation to City Council

Project Footprint

Page 7: Seahurst Project Update - March 17 presentation to City Council

Recap of Project Scope

Page 8: Seahurst Project Update - March 17 presentation to City Council
Page 9: Seahurst Project Update - March 17 presentation to City Council
Page 10: Seahurst Project Update - March 17 presentation to City Council
Page 11: Seahurst Project Update - March 17 presentation to City Council
Page 12: Seahurst Project Update - March 17 presentation to City Council
Page 13: Seahurst Project Update - March 17 presentation to City Council
Page 14: Seahurst Project Update - March 17 presentation to City Council
Page 15: Seahurst Project Update - March 17 presentation to City Council
Page 16: Seahurst Project Update - March 17 presentation to City Council
Page 17: Seahurst Project Update - March 17 presentation to City Council
Page 18: Seahurst Project Update - March 17 presentation to City Council
Page 19: Seahurst Project Update - March 17 presentation to City Council
Page 20: Seahurst Project Update - March 17 presentation to City Council
Page 21: Seahurst Project Update - March 17 presentation to City Council
Page 22: Seahurst Project Update - March 17 presentation to City Council
Page 23: Seahurst Project Update - March 17 presentation to City Council
Page 24: Seahurst Project Update - March 17 presentation to City Council

Project Challenges withImpacts on Schedule and

Costs

• Underground cultural resource conditions

• Unknown utility conditions/ locations in specific areas

• New concrete work related to future recreational costs

Page 25: Seahurst Project Update - March 17 presentation to City Council

New Concrete Work

Page 26: Seahurst Project Update - March 17 presentation to City Council

UpdatedProject Schedule and Cost

• Original estimated date: May 17, 2014• Revised completion date: July 11, 2014

• Original estimated cost: $7.7M• Revised construction cost: $8.15M (+5.9%)

Page 27: Seahurst Project Update - March 17 presentation to City Council

Source of Funds

State PSAR and $400,000ESRP Grants

Burien General Fund $50,000(add’l concrete work)

Page 28: Seahurst Project Update - March 17 presentation to City Council

Project Funding Partners

• Army Corps of Engineers

• Washington Department of Fish and Wildlife (ESRP)

• Environmental Protection Agency (EPA)

• Salmon Recovery Funding Board (PSAR)

• King Conservation District

• Green-Duwamish Watershed Forum (WRIA-9)

• City of Burien