SEAHURST PARKBEACH RESTORATION
PROJECT
Groundbreaking: September 16, 2013
Construction Phase Contractors
• USACE: Project Partner and Construction Management
• CKY Inc. : Prime Contractor (San Pedro, CA)
• SCI Infrastructure: Grading/Earthwork (SeaTac, WA)
• Cadman Inc.: Materials/Gravel/Sand (Redmond, WA)
• Northwest Lining and Geotextiles: (Kent, WA)
• Pacific Pile and Marine: Barge Services (Seattle, WA)
• Dutton Electrico Co.: (Lynwood, WA)
• Cal Portland: Concrete (Seattle, WA)
• Cherry Valley Logging: Wood materials (Duvall, WA)
• Play Creations: Playground (Burien, WA)
Park Closed: October 28, 2013
Project Footprint
Recap of Project Scope
Project Challenges withImpacts on Schedule and
Costs
• Underground cultural resource conditions
• Unknown utility conditions/ locations in specific areas
• New concrete work related to future recreational costs
New Concrete Work
UpdatedProject Schedule and Cost
• Original estimated date: May 17, 2014• Revised completion date: July 11, 2014
• Original estimated cost: $7.7M• Revised construction cost: $8.15M (+5.9%)
Source of Funds
State PSAR and $400,000ESRP Grants
Burien General Fund $50,000(add’l concrete work)
Project Funding Partners
• Army Corps of Engineers
• Washington Department of Fish and Wildlife (ESRP)
• Environmental Protection Agency (EPA)
• Salmon Recovery Funding Board (PSAR)
• King Conservation District
• Green-Duwamish Watershed Forum (WRIA-9)
• City of Burien