SEAHURST PARK BEACH RESTORATION PROJECT

Seahurst Project Update - March 17 presentation to City Council

Embed Size (px)

DESCRIPTION

This presentation was shared with the Burien City Council on March 17, 2014. It is an update regarding progress on the Seawall Removal and Beach Restoration Project at Seahurst Park. For more information about the project, visit www.burienwa.gov/SeahurstProject

Citation preview

Page 1: Seahurst Project Update - March 17 presentation to City Council

SEAHURST PARKBEACH RESTORATION

PROJECT

Page 2: Seahurst Project Update - March 17 presentation to City Council

Groundbreaking: September 16, 2013

Page 3: Seahurst Project Update - March 17 presentation to City Council
Page 4: Seahurst Project Update - March 17 presentation to City Council

Construction Phase Contractors

• USACE: Project Partner and Construction Management

• CKY Inc. : Prime Contractor (San Pedro, CA)

• SCI Infrastructure: Grading/Earthwork (SeaTac, WA)

• Cadman Inc.: Materials/Gravel/Sand (Redmond, WA)

• Northwest Lining and Geotextiles: (Kent, WA)

• Pacific Pile and Marine: Barge Services (Seattle, WA)

• Dutton Electrico Co.: (Lynwood, WA)

• Cal Portland: Concrete (Seattle, WA)

• Cherry Valley Logging: Wood materials (Duvall, WA)

• Play Creations: Playground (Burien, WA)

Page 5: Seahurst Project Update - March 17 presentation to City Council

Park Closed: October 28, 2013

Page 6: Seahurst Project Update - March 17 presentation to City Council

Project Footprint

Page 7: Seahurst Project Update - March 17 presentation to City Council

Recap of Project Scope

Page 8: Seahurst Project Update - March 17 presentation to City Council
Page 9: Seahurst Project Update - March 17 presentation to City Council
Page 10: Seahurst Project Update - March 17 presentation to City Council
Page 11: Seahurst Project Update - March 17 presentation to City Council
Page 12: Seahurst Project Update - March 17 presentation to City Council
Page 13: Seahurst Project Update - March 17 presentation to City Council
Page 14: Seahurst Project Update - March 17 presentation to City Council
Page 15: Seahurst Project Update - March 17 presentation to City Council
Page 16: Seahurst Project Update - March 17 presentation to City Council
Page 17: Seahurst Project Update - March 17 presentation to City Council
Page 18: Seahurst Project Update - March 17 presentation to City Council
Page 19: Seahurst Project Update - March 17 presentation to City Council
Page 20: Seahurst Project Update - March 17 presentation to City Council
Page 21: Seahurst Project Update - March 17 presentation to City Council
Page 22: Seahurst Project Update - March 17 presentation to City Council
Page 23: Seahurst Project Update - March 17 presentation to City Council
Page 24: Seahurst Project Update - March 17 presentation to City Council

Project Challenges withImpacts on Schedule and

Costs

• Underground cultural resource conditions

• Unknown utility conditions/ locations in specific areas

• New concrete work related to future recreational costs

Page 25: Seahurst Project Update - March 17 presentation to City Council

New Concrete Work

Page 26: Seahurst Project Update - March 17 presentation to City Council

UpdatedProject Schedule and Cost

• Original estimated date: May 17, 2014• Revised completion date: July 11, 2014

• Original estimated cost: $7.7M• Revised construction cost: $8.15M (+5.9%)

Page 27: Seahurst Project Update - March 17 presentation to City Council

Source of Funds

State PSAR and $400,000ESRP Grants

Burien General Fund $50,000(add’l concrete work)

Page 28: Seahurst Project Update - March 17 presentation to City Council

Project Funding Partners

• Army Corps of Engineers

• Washington Department of Fish and Wildlife (ESRP)

• Environmental Protection Agency (EPA)

• Salmon Recovery Funding Board (PSAR)

• King Conservation District

• Green-Duwamish Watershed Forum (WRIA-9)

• City of Burien