Readiness Scorecard – Market Readiness Series
Brandon McElfreshNodal Readiness and Transition
January 28, 2010
Agenda
• Nodal Metrics Objective• Nodal Scorecard Overview• Active Market Participant Metrics• Metrics Roadmap for Market Participants
• Real-Time Market
• CRR
• Outage Scheduler
• DAM/RUC
• Network Model
• Useful Documents
http://nodal.ercot.com 2
Nodal Metrics Objective
http://nodal.ercot.com 3
Objective• The objective of the Nodal Metrics is to provide a concise and transparent view of
ERCOT’s and its Market Participant’s progress towards launching the Nodal Market.
History• In the previous Nodal EDS effort, any changes to the Nodal Metrics were approved
by TPTF and TAC.
Governance• In the current Market Trials effort, NATF reviews the metrics monthly to advise on
design and scheduling decisions submitted by ERCOT. TAC also reviews the metric scores monthly.
Population• There are 61 ERCOT metrics and 19 MP metrics to be completed.
http://nodal.ercot.com 4
Nodal Scorecard
Functionality• Rollup by MP
type.
• Weighting for Overall Scores
• QSERs – Gen Ratio Share
• TSPs – Ownership Share
• REs – Registered MW Capacity Ratio Share
• QSEs, CRRAHs, and LSEs – even weighting within the MP type
AcronymsQSERs – QSEs with ResourcesQSEs – QSEs without ResourcesTSPs – Transmission Service ProvidersREs – Resource EntitiesCRRAHs – CRR Account HoldersLSEs – Load Serving Entities
As of 1/26/2010
http://scorecard.ercot.com
Nodal Scorecard Continued
http://nodal.ercot.com 5
Confidentiality• QSERs, QSEs, CRRAHs,
and LSEs have a private view to see their individual metrics
Escalation• At least 5 days advanced
notice from ERCOT for “AMBER” or “RED” scores
Updates• “GREENs” updated ASAP• “AMBERs” & “RED” updated
based on Metric Update Calendar
Example
Example
Access• E-mail [email protected] for login credentials
http://nodal.ercot.com 6
Active Mark Participant Metrics
Metric NameCurrent Score
(as of 1/25/2010)
Applies to Weight Green % Red % Yellow % Not Scored % Primary
Criteria Notes
MP3 Market Submissions Connectivity Qualification
Green QSERs
Generation Ratio Share 76% 0% 0% 24%
Successful submission of RT and DAM transactions (289 total entities included sub-QSEs)
19 out of 45 QSERS Qualified. 5 partially qualified. First “AMBER” & “RED” scores will be released 2/11/2010.
Green QSEsEven weighting 54% 0% 0% 58%
60 out of 112 QSEs qualified. First “AMBER” & “RED” scores will be released 2/11/2010.
MP6 QSER and TSP Compliance with the Nodal Protocols Section 3.10.7.5 Telemetry Criteria
Green QSERs
Generation Ratio Share 71% 0% 0% 29%
100% expected State Estimator telemetry submitted.
39 out of 45 QSERs completed. For the 6 QSEs in review, most issues have been resolved, leaving an estimated 6 SE points to be resolved out of 3659 required points (99.99%)
First scores - 2/10/2010 TSPs
Ownership Share
MP11 Resource Registration Green REs
Registered MW Capacity Ratio Share 98% 2% 0% 0%
RARF validated, Decision Making Authority form submitted, and GENMAP validated
MP15-B CRR Connectivity Qualification Green CRRAHsEven weighting 35% 0% 0% 65%
Successful submission of CRR transactions
29 out of 82 CRRAHs qualified. First “AMBER” & “RED” scores will be released 2/11/2010.
http://nodal.ercot.com 7
Metrics Roadmap
MP15A
MP16
MP20
MP3
MP6
MP11 MP14C
E9
E1
N2.1
EMO9
CRR3 CRR5
EMO6MO4 MO5
CO1
CO2
CO3
CO4
CO5
CO6 CO7
CO8 CO9
C10
E7
E11
E12
EMO2
EMO3
EMO8
MO3
C1-C10
EMO13
MO7
CRR4
E5
IMM1
R0
R2
R3
MP15B
MP3
N1
E3
E10
PURPLE
ORANGE
Timing and Design Confirmed
Timing subject to change, design in progress
R1
Metrics Roadmap – Real-Time Market
http://nodal.ercot.com 8
MP15AReal-Time Market
Participation(QSER)
MP3Market
SubmissionsConnectivityQualification
(QSER, QSE)
MP6 Telemetry
Compliance(QSER, TSP)
N2Telemetry/ICCP
Failover(ERCOT)
EMO1Network Security
Analysis& Transmission
ConstraintManagement
(ERCOT)
EMO9Nodal and ZonalSecurity Analysis
Results(ERCOT)
EMO6QSE Response
To Dispatch (ERCOT, QSER)
MO4SCED ExecutionQuality (ERCOT)
MO5Generate 6
Months of LMPs(ERCOT)
EMO2Voltage Support
(ERCOT)
EMO8Conduct EEA
Test (ERCOT)
N1Telemetry Alarms
(ERCOT)
EMO7Load Forecast
Accuracy(ERCOT)
PURPLE
ORANGE
Timing and Design Confirmed
Timing subject to change, design in progress
MP6 – QSERs and TSPs Telemetry Compliance with Nodal Protocols 3.10.7.5• QSERs SCED Scores Active – 2/11/2010• TSP Scores Active – 2/11/2010
MP15-A – QSERs Real-Time Market Participation• Scores based on daily submissions of Energy Offer Curves and Output Schedules• Active – 2/11/2010
EMO6 – QSERs respond to dispatch• Scores based on participation in LFC testing in MT Phase 5• Active – May 2010
Metrics Roadmap – CRR Market
http://nodal.ercot.com 9
CRR3Operation ofMonthlyCRRAuction andAllocation(ERCOT)
CRR5Operation ofAnnual CRR
Allocation andAuction
(ERCOT)
MP15-B CRR
ConnectivityQualification
(CRRAH)
MP15-B – CRRAH Connectivity Qualification• Scores based on submission of selected CRR transactions. For example,
• Logged-in and accessed the CRR application• Downloaded one of the pre-auction market information• Uploaded a bid/offer portfolio (in either XML or CSV)
• Active
PURPLE
ORANGE
Timing and Design Confirmed
Timing subject to change, design in progress
Metrics Roadmap – Outage Scheduler
http://nodal.ercot.com 10
MP20Outage
SchedulerConnectivityQualification(QSER, TSP)
EMO3Outage
EvaluationFunctionality
(ERCOT)
MP20 – QSERs and TSPs Outage Scheduler Connectivity Qualification• Scores based on submission of selected OS transactions. For example,
• Planned outage on a single piece of equipment• Maintenance Level 1 outage on a group of Resources
• Active – 2/10/2010
PURPLE
ORANGE
Timing and Design Confirmed
Timing subject to change, design in progress
Metrics Roadmap – DAM/RUC
http://nodal.ercot.com 11
MP16Day-Ahead
MarketParticipation
(QSER, QSE)
MO3Verify
SupplementalAS
Market(ERCOT)
MP3Market
SubmissionsConnectivityQualification
(QSER, QSE)
MP3 – QSERs and QSEs Market Submissions Connectivity Qualification• Scores based on submission of selected DAM transactions. For example,
• Three Part Offers• Ancillary Service Offers• Energy-only Offers and Bids
• Active. First “AMBER” or “RED scores on 2/11/2010
MP16 – QSERs and QSEs Day-Ahead Market Participation • Scores based on participation in Day-Ahead Market Runs.• Active – April 2010
PURPLE
ORANGE
Timing and Design Confirmed
Timing subject to change, design in progress
Metrics Roadmap – Settlements/COMS
http://nodal.ercot.com 12
CO1Settle Market for
7 Days(ERCOT)
CO2Verify Dispute
Process(ERCOT)
CO3Verify DAMStatements(ERCOT)
CO4Zonal/NodalCoordinatedSettlements
(ERCOT)
CO5Verify RTMStatements(ERCOT)
CO6Verify RTM
Invoices(ERCOT)
CO7Verify DAM
Invoices(ERCOT)
CO8Verify CRR
AuctionInvoices(ERCOT)
CO9Verify Financial
Transfer(ERCOT)
C10Verify CreditCalculations
(ERCOT)
Settlements/COMS Metrics• No specific MP Metrics for Settlements currently• ERCOT will submit regular status reports and evidence of completion to NATF for each metric
PURPLE
ORANGE
Timing and Design Confirmed
Timing subject to change, design in progress
Metrics Roadmap – Nodal Reports
http://nodal.ercot.com 13
E3Validate EDW
Telemetry/StateEstimator
Access andAccuracy
(ERCOT, QSER,QSE, TSP)
E7Validate EDW
IMM and PUCTAccess andAccuracy
(ERCOT, IMM)
E10Validate EDWCommercial
Systems Accessand Accuracy
(ERCOT, QSER,QSE, TSP)
PURPLE
ORANGE
Timing and Design Confirmed
Timing subject to change, design in progress
Reporting/EDW Metrics• ERCOT, MPs, and IMM will be required to verify access to and accuracy of Market Monitoring, Settlement, Operations , and Compliance EDW and MIS reports.
E11Validate EDWCompliance
Access(ERCOT)
Metrics Roadmap – Cutover/Go-Live Sequence
http://nodal.ercot.com 14
PURPLE
ORANGE
Timing and Design Confirmed
Timing subject to change, design in progress
R1Nodal
ReadinessDeclaration(ERCOT)
R0Market
ParticipantOperationsReadiness
(ERCOT, MPs)
E5Nodal SAS70
Readiness(ERCOT)
C1-C10Fallback andContingency
Plans(ERCOT)
R2Develop NodalMarket Launch
Plan(ERCOT)
R3Complete 168
Hour Test(ERCOT)
CRR4Implement TCR
To CRR Transition Plan
(ERCOT)
Readiness Metrics• R0 – ERCOT asserts readiness of Market Participants for Nodal Go-Live.• R1 – ERCOT, TAC, NATF, and the ERCOT Board of Directors assert readiness for Nodal Go-Live• IMM1 – Market Monitor and PUCT asserts readiness of Market Monitoring systems
IMM1Market Monitor
SystemsCapability
(IMM)
Metrics Roadmap – Other Readiness Metrics
http://nodal.ercot.com 15
MP11 – REs Resource Registration• Scores based on submission of necessary Resource Registration data
• RARF• Decision Making Authority Form• GENMAP – Mapping of Resource Nodes to EPS Meters• Active (first DMA scores – 1/27/2010)
MP14-C – TSPs Network Model Validation• Scores based on TSPs validating their portion of the network model • Criteria and schedule to be discussed at 2/2/2010 NATF meeting
PURPLE
ORANGE
Timing and Design Confirmed
Timing subject to change, design in progress
MP11Resource
Registration(RE)
E1ERCOT
Staff Completes
Training(ERCOT)
E9DevelopNodal
Procedures(ERCOT)
MP14CTSP
NetworkModel
Validation(TSP
E12MIS
ComplianceTest
(ERCOT)
EMO13OperationsPersonnel
AndFacilities
Readiness(ERCOT)
MO7Market
OperationsPersonnel
And Facilities
Readiness(ERCOT)
Useful Documents
Artifacts• Nodal Scorecard (http://scorecard.ercot.com)• Index of Nodal Metrics
(http://nodal.ercot.com/readiness/scorecard/metrics/index.html)• Others Artifacts on the Nodal Readiness Center• (http://nodal.ercot.com/readiness/scorecard/index.html)
• Active Metric Inventory• Completed Metric Inventory• Removed Metric Inventory• Metrics Update Calendar• Metrics Roadmap - Metrics overlaid on the Market Trials
Roadmap (will be published after Feb 2nd NATF meeting)
http://nodal.ercot.com 16
Next Steps
http://nodal.ercot.com 17
February 2nd NATF Meeting• Review Active Metric Scores• Discuss criteria for MP6 SCED Telemetry and MP15-A Real-Time Market Daily Participation • Discuss possible breakout of Sub-QSEs on the Nodal Scorecard• Metrics Roadmap
Next MP Metric Update• February 11th, 2010• First “AMBER” or “RED” scores for MP3 Market Submissions• Activate MP15-A, MP20 Outage Scheduler Connectivity Qualification