Transcript
Page 1: Queens Quay Revitalization Progress Update - May 2014

• Transit infrastructure and most of the utilities and municipal services

beneath Queens Quay require major upgrades and/or expansion now

– The TTC tracks have reached the end of their service life

– Toronto Hydro is replacing aging electrical infrastructure

– Bell will building new infrastructure and run new fibre optic cable

– The aging sanitary line will be rebuilt and relocated

– Storm sewer and water main upgrades

• These projects would have happened in the near future with or without the

revitalization of Queens Quay

• We are coordinating these upgrades with our work to avoid the need for

more disruptive construction in the near future

Queens Quay Progress Update Neighbourhood Meeting – May 2014

Page 2: Queens Quay Revitalization Progress Update - May 2014

We’re transforming Queens Quay from austere and uninviting…

BEFORE

Page 3: Queens Quay Revitalization Progress Update - May 2014

…into a truly great and vibrant waterfront street

AFTER

Page 4: Queens Quay Revitalization Progress Update - May 2014

BEFORE

From a place to move through…

Page 5: Queens Quay Revitalization Progress Update - May 2014

AFTER

…into a great place to be

Page 6: Queens Quay Revitalization Progress Update - May 2014

What We’re Building

Page 7: Queens Quay Revitalization Progress Update - May 2014

5. Roadway

2. South Side Promenade

6. Martin Goodman Trail

3. North Side Sidewalk

4. TTC Streetcar Corridor

What We’re Building: Our Construction Sequence

1. Below Grade Infrastructure

Page 8: Queens Quay Revitalization Progress Update - May 2014

1. Below Grade Infrastructure Construction Update

Underground utilities and municipal

infrastructure work is 97% complete

Revitalization includes new or upgraded:

• Gas mains

• Hydro electrical infrastructure

• Bell and telecomm infrastructure

• Sanitary sewers

• Storm sewer

• Catch basins and manholes

Most of the underground work will be

complete mid-June with a few remaining

Hydro activities in the fall

Page 9: Queens Quay Revitalization Progress Update - May 2014

1. Below Grade Infrastructure Construction Update

Underground utilities and municipal

infrastructure work is 97% complete

Revitalization includes new or upgraded:

• Gas mains

• Hydro electrical infrastructure

• Bell and telecomm infrastructure

• Sanitary sewers

• Storm sewer

• Catch basins and manholes

Most of the underground work will be

complete mid-June with a few remaining

Hydro activities in the fall

Page 10: Queens Quay Revitalization Progress Update - May 2014

2. Southside Promenade

Page 11: Queens Quay Revitalization Progress Update - May 2014

2. Southside Promenade Construction Update

• Southside promenade is 20% complete

• Work complete:

Harbourfront Sailing

Pawsway Plaza

Queens Quay Terminal

York Slip

Simcoe WaveDeck

• Work underway:

Ontario Square

(complete late June)

Peter Slip to Rees WaveDeck

(complete late August)

• Upcoming work:

Bay Street to York Street

• Promenade will be complete for

June 2015

Page 12: Queens Quay Revitalization Progress Update - May 2014

A Look at Southside Promenade Construction Across Queens Quay

Page 13: Queens Quay Revitalization Progress Update - May 2014

3. North Side Sidewalks

Page 14: Queens Quay Revitalization Progress Update - May 2014

3. Northside Sidewalk Construction Update

• Northside sidewalks are 40% complete

• Work complete at

8 York Street (Starbucks)

Rees Parking Lot (West Side)

• Work underway:

York ramp (complete June)

208/218 Queens Quay

(complete June)

Lower Simcoe to Rees Parkette

(complete July)

460/470/480 King’s Landing

• Northside sidewalks will be complete

end of 2014

Page 15: Queens Quay Revitalization Progress Update - May 2014

3. Northside Sidewalk Construction Update

• First delivery of trees

occurred in May

• Planting underway in

areas where granite is

complete:

Rees Parking Lot

York Ramp

York to Simcoe

• Southside trees will be

planted next spring

Page 16: Queens Quay Revitalization Progress Update - May 2014

A Look at Northside Sidewalk Construction Across Queens Quay

Page 17: Queens Quay Revitalization Progress Update - May 2014

4. TTC Streetcar Corridor

Page 18: Queens Quay Revitalization Progress Update - May 2014

4. TTC Streetcar Corridor Construction Update

• Spadina Loop rebuild is 65% complete and

streetcar corridor is 20% complete

• Work complete :

West of Lower Simcoe to Robertson

Crescent

Lower Spadina to Queens Quay +

inner loop

• Work underway:

Portal to York Street

West of York to Queens Quay Terminal

West of Rees to parking lot

Lower Simcoe intersection

Lower Spadina intersection

• Upcoming work:

• Poles, platforms, and commissioning

• TTC Streetcars scheduled to resume service

on August 31, 2014

Page 19: Queens Quay Revitalization Progress Update - May 2014

A Look at TTC Streetcar Corridor Construction Across Queens Quay

Page 20: Queens Quay Revitalization Progress Update - May 2014

5. New Roadway

Page 21: Queens Quay Revitalization Progress Update - May 2014

5. New Road Construction Update

• Road construction is now getting

underway

• Curbs must be installed first to

define the road

York to Simcoe curbs

complete

• Road work will follow TTC

installation

York to Simcoe

Simcoe to Rees

• Process for building the road

Install curb

Excavate/grading

Asphalt pour

Page 22: Queens Quay Revitalization Progress Update - May 2014

6. Martin Goodman Trail

Page 23: Queens Quay Revitalization Progress Update - May 2014

6. Martin Goodman Trail Construction Update

• Martin Goodman Trail construction will begin in select areas

this summer

• This construction will occur between the completed TTC streetcar

corridor and the southside promenade

• First construction areas

York to Simcoe

Simcoe to Rees

• Process for building the Martin Goodman Trail

Demo/road removal of asphalt and base concrete

Excavate for silva cells

Install silva cells

Asphalt pavement and granite buffer (and promenade finishes)

Light poles

Page 24: Queens Quay Revitalization Progress Update - May 2014

More Information

Construction Website:

www.waterfrontoronto.ca

Email:

[email protected]

Weekly email construction notices

Sign up at [email protected]

On-the-ground construction support

(24/7 for urgent issues):

Construction Liaison Officer

Robert Pasut at 416-505-3073


Recommended