Marriott Residence Inn at Johns Hopkins Medical Campus
Baltimore, MD
Project Schedule Narrative
Project Activities:
Site Improvements & Underground Utilities:
• Permanent Power from BGE complete
• Exterior Material Hoist demobilization
• Installation of Punch Windows and Ari Barrier at Material Hoist Location
Back of House/Lobby:
• Overhead Rough – In in progress
• Permanent back of house lighting installation underway
• Level 2 east Lobby Curtain Wall framing complete
• MEP Piping insulation in progress
• Painting of Lower Level Mechanical and Electrical Rooms
• Fire Pump and Controller assembly in progress
Retail:
• Overhead Rough–In in progress
• Precast Punch-List has begun
• Level 2 Storefront Framing in progress
• Level 2 hanging drywall
• Precast cap installation currently in progress
Tower:
• Overhead Rough-In in progress
• In-Wall Rough-In in progress
• 3 Bank Elevator construction in progress - Construction Elevator Cab in operation
• Elevator 4 and 5 construction in progress
• Exterior Metal Panel installation in progress along North fin
• Interior Dry Install has begun 6
• Tape and Finish of dry wall in progress through Level
• Guestroom Millwork on lower levels delivered and installation in progress
Upcoming Activities:
Site Improvement & Underground Utilities:
• Installation of topping slab at Porte Cochere
• Installation and relocation of Street Lights
• Site Pavers and Hardscape scheduled for late March
• Asphalt along Madison
Exterior
• EIFS installation
Tower:
• Installation of Level 16 Roof Terrace
• Waterproofing of bathroom spaces
• Permanent Heat and Gas
• Exterior Ornamental Handrail on Balcony
• Installation of Nanawall
Interior:
• Guestroom Tile and Flooring installation
• Guestroom Carpet installation
• Installation of Mincey Marble shower basins