Transcript
Page 1: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

Oracle|PrimaveraProgram Management

Information System (PMIS)

Solutions for Transportation Programs   November, 2011

Page 2: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Thank you for joining today’s technical webinar• Mute – all call in phones are automatically muted in order to 

preserve the quality of the audio for all attendees.• Questions – due to the high volume of participants, you can 

email questions to [email protected]. We will try to address your questions during or at the end of the presentation. 

• Follow up – all registrants will receive an Excel file listing all questions and responses along with a link to the recorded webinar.

11/30/2011 2

Page 3: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

• Oracle Primavera Software• Oracle Certified Training• Oracle Certified Implementation Support• Project support services – administrators, schedulers

• Managed Hosting Services• Primavera Portfolios, P6, P6 Pro, Contract Management, Risk • Acumen Fuse, Prism, Ecosys, MS Project, MS Dynamics…• Subscription based Oracle|Primavera utilities

Twenty‐five + years experience with Primavera

11/30/2011 3

Page 4: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

11/30/2011 4

Today's presenters

• Don McNatty, PSP – Co‐founder of DRMcNatty. Provides Principal Consultant overview and system architect support to all projects. 

• Brian Criss, PSP – Directory of Professional Services, DRMcNatty, Metro Project Manager (DRM) and Lead Consultant.

Page 5: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Agenda• Characteristics of Large Transportation Programs• Management Challenges• Project Controls as the Foundation• Program Management Information System (PMIS)• PMIS Overview ‐ LA Metro Case Study• The Road Ahead• Lessons Learned• Questions

11/30/2011 5

Page 6: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Characteristics of Large Transportation Programs

• Outdated technologies in existing controls systems• Good, but silo’d information• Data not shared or easily available for sharing• Redundant and disconnected data entry without continuous audit trails

• Heavy reliance on spreadsheets• Cost information cumbersome and not aligned• Summary reports and Management “dashboards” are compiled manually from multiple sources of information

11/30/2011 6

Page 7: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

• Management Challenges because of Measure R–Need for increased oversight and accountability–Potential aggressive / accelerated schedule–Maxes out internal Metro resources– Increased expectations for project delivery–Delivery strategy 4‐5 projects at a time–Current structure 1‐2 projects at a time–Paradigm shift required

11/30/2011 7

Page 8: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

ExistingProject ControlsArchitecture

• Good use of existing tools

• Most processes manual• Outdated technologies• Reliance on

spreadsheets• Processes differed

across major projects• Labor intensive to

produce reports• “Islands” of excellence

11/30/2011 8 8

Page 9: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

OracleDB

Project Management Information System ‐ PMIS

Key Concepts• Centralized

Oracle database• Single source of

information• Automated

financials• Timely reports• Real-time data

available via web

11/30/2011 9

Page 10: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

What does an Oracle|Primavera PMIS do?

• Gathers timely and accurate data• Combines data based on business rules • Puts it into the proper context

– (Which turns data into “Information”)

• To be combined with PM team knowledge• To produce higher quality work output• To impact strategies, directions, and decisions…

11/30/2011 10

Page 11: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Data Information Knowledge Work

3

Ea

5

0$3.75 Ea500 required

$3.75 Ea x 500 + 5% waste = $1,968.75Freight: $200.00

Install: 5 Sq @ $100.00 Sq = $500.00Total: 2,668.75

Silo’d andunconnected

data

Put into proper context and

format

combined with the team’s knowledge,

experience and goals

Produces higher quality management information

and decisions with less effort by the project

managers

AND…

What does a PMIS do?

11/30/2011 11

Page 12: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

… It’s more AUDITABLE!

• A uniform data structure + standard practices• Role based responsibilities & training• Easier quality assurance with centralized DB• Allows summary data to be tracked back to originating transactions

• With web interface, “transparency” can be as easy as a click of the mouse

11/30/2011 12

Page 13: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Recommended HOSTED Deployment Model• Uses “best of breed” software• Reduce risk and cost through hosted deployment 

• With custom configuration  and integration utilities

• Leverages existing investment • Complies with existing standards• Multiple levels of security• Specific tools shown here are flexible based on results of piloting on Metro projects

• System address all roles and types of project participants

• System supports “geographically dispersed team licensing” of software to reduce direct and ongoing Metro software cost.

11/30/2011 1311/30/2011 13

Lowered risk for dependable availability, at a predictable cost

Page 14: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Benefits of Hosting

11/30/2011 14

• Quick deployment that scales (in cost and capacity) as the program grows.

• Metro traded the risk (dependable deployment) for a lower and predictable cost.

• By hosting directly with an Oracle Certified provider, no dependency on any single CM or Contractor.

• Eliminated issues related to access for external participants.

• Maintained by an Oracle|Primavera Certified team.• Subscription based utility (CMI) allows access by 

contractors while keeping internal data secure.

Page 15: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

PMIS Overview – LA Metro Case Study• PMIS = Project Management Information System

– Primavera P6 / P6 Web• Schedule tracking at the detailed and summary level• Dashboard reporting and collaboration via P6 Web

– Primavera Contract Management• Document Control• Cost and Change Control

– Ecosys EPC• Resource Tracking• Cost Tracking for Small Capital Projects

11/30/2011 15

Page 16: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Access to PMISPowered by:

11/30/2011 16

Page 17: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Deployment of P6 Client

• Early objective was the understanding that preserving the integrity of global data was essential to a successful P6 deployment.– Maintaining order and cleanliness of P6 data.

• Deployment of sandbox environment for testing of functionality and initial import of contractor schedule files.

• Revisions to contractor schedule specifications

– Security profiles and access

11/30/2011 17

Page 18: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Deployment of P6 Client• P6 Client Users have been

provided access to 2 separate databases

• PMDB = Production Environment for Project information.

• PMDB_Sandbox = Sample Environment for Metro Project Controls staff to import files and test functionality without compromising the P6 Database.

11/30/2011 18

Page 19: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Schedule Development Strategy1. Level 1 Schedule – Summary Level

Project information which is intended to be public facing and provide high level project status.

2. Level 2 Schedule – Provide more detailed level of schedule for management of overall project flow. This level of schedule provides sufficient detail for MTA internal control of the project.

3. Level 3 Schedule – Contractor level schedule which is typically submitted to MTA for review and acceptance. Contractor schedules are linked to key items in the Level 2 Control Schedule for bottom up integrated scheduling.

11/30/2011 19

Page 20: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Level 2 Control schedule provides detail to allow MTA Project Controls staff to track all phases of the project at sufficient levels of detail to achieve Critical Path Scheduling.

11/30/2011 20

Page 21: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

MTA Summary Schedules are intended to provide high level project information. Schedules are developed using Milestone activities along with Level Of Effort activities linked to the MTA Control Schedule. When individual projects are used to track and drive Control and Summary level schedules, integrated bottom up schedules become a reality.

11/30/2011 21

Page 22: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

P6 Web• P6 Web provides High Level project information in a dashboard display.

• Provides MTA with a collaborative portlet for the inclusion of information such as Notebook topics and Issues.

• Allows for Links to Costs in Contract Management for complete project information in one single place.

• Allows for the development of project Portfolios for unique and customized views of Project Information.

11/30/2011 22

Page 23: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Sample Major Rail Project DashboardBelow is a sample of the overall Dashboard for Major Rail Projects and allows you to display up to 12 portlets. Customized Portfolio views can be created and added to any dashboard for display of project information. Issues created for projects within the portfolio are immediately accessible via the main Portfolio Dashboard.

11/30/2011 23

Page 24: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Sample Project Workspace

11/30/2011 24

The project Workspace provides users with a dashboard view of information for a single project. In the example below, the project is linked to its associated project in Contract Management which allows for visibility into the Cost Worksheet as well as Control Center Portlets.

Page 25: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Single Page Summary ReportA single page summary report has been created for each of the Major Rail projects and dynamically display data from P6 and Contract Management related to convey high level project information in a single view.

11/30/2011 25

Page 26: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Reports are easily accessed via a custom portlet in the P6 Web Dashboard and users can select the specific project link and launch the report directly from within P6 Web.

11/30/2011 26

Single Page Summary Report

Page 27: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Summary Report ContentSummary Report fields for Project Description and Current Status are receiving information from Notebook Topics within P6. This information has the capability to be updated within the P6 Client Application or P6 Web.

11/30/2011 27

Page 28: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Single Page Summary ReportReport information for Gantt Chart and Project Milestones are updated from schedule information contained within the P6 Summary Schedule. Activity codes are used to identify the proper information and the report consolidates the information for display.

11/30/2011 28

Page 29: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Issues• The P6 Issues module provides for the capacity to track project issues as well as risks associated with a project.

• The P6 Issue module can be customized for Metro requirements through the use of Issue Codes.

• Standardized Issue Forms allow for consistency in entry of project information.

11/30/2011 29

Page 30: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Sample Custom Issue FormCustomized Issue forms provides MTA a consistent method of entering information Issues related to a project. Fields can be customized and new fields added as needed. In the sample below, Issue Codes are pre-populated in the form.

11/30/2011 30

Page 31: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Primavera Contract Management• Document Control

– Track submittals, RFI’s– Used in conjunction 

with Contract Management Interface (CMI)

• Change Control• Cost Control

– Integrated with Metro’s Financial Information System (FIS)

11/30/2011 31

Page 32: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Sample Contract Management Cost WorksheetContract Management Cost Worksheet data is used to display project information based on assigned cost code. Information displayed in the cost worksheet can be customized via the Layout options available in CM. In the example below, Cost Worksheet data is displayed by MTA Task Number.

11/30/2011 32

Contract Management will also support cost reporting by FTA Codes

Page 33: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

CM13 Drill Down CapabilitiesSelect a Cost Code on the CM13 Cost Worksheet lets MTA cost engineers drill down to the detailed commitment documents within a specified Cost Code.

Drill Down capabilities allow you to access transaction level details including documents and details.

Contract/PO Line Items are also associated with P6 Activities.

11/30/2011 33

Page 34: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Custom Applications ‐ CMI• Contract Management Interface is a custom web based 

application (developed by DRMcNatty) which allows contractors working with Metro to submit documents electronically directly into the Metro CM13 database.

• Reduces the amount of data handling needed to be performed by Metro staff and insures data confidentiality.

• Metro document controls staff are alerted that a new document has been submitted via an update on their control center or email.

• Contractors are not forced to use Contract Management, only to submit their documents through the interface.

11/30/2011 34

Page 35: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Contract Management Interface

11/30/2011 35

MTA Contractors can submit directly into the MTA System for Review

Page 36: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

CMI Custom ReportsCustomized reports are available for Contractors to check on and verify the status of documents submitted to Metro.

11/30/2011 36

Page 37: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Integration with Metro FIS

11/30/2011 37

Page 38: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

FIS Integration with CM13Actual Costs are imported into CM13 via a custom integration utility which identifies key information and updates existing or creates new records where required in CM13. Custom Field definition in CM13 is used to more accurately align FIS Cost Data with CM13 Cost information on projects.

11/30/2011 38

Page 39: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Ecosys EPC• Used in conjunction with P6 for tracking of MTA staffing plans along with actual hours assigned to projects– Integrated with timekeeping data for actual hours charged to projects

• Tracking of Small Capital Projects which may be monitored outside of P6 and CM13

11/30/2011 39

Page 40: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Ecosys EPCSmall Capital Projects which would typically be managed only in FIS or in spreadsheets are now tracked with Ecosys EPC. Spreadsheet data populated Ecosys and custom identifiers were developed to allow Metro project controls staff to track additional information such as Sponsor and CP Number.

11/30/2011 40

Page 41: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Ecosys EPCResource Budget and Actual information are uploaded for tracking in Ecosys EPC

Display graphical resource information in P6 Web

11/30/2011 41

Page 42: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

“The Road Ahead”• Upgrade to P6 8.x

– Increased functionality, specifically Risk Register and BI Publisher– Increased functionality, preview changes, web administration– Increased compatibility with Mobile devices

• Upgrade to Contract Management 14 BIPE– Tool of the future – no more Infomaker – Support for workflows – Available Web Services Licenses for better integration & lower cost– Increased speed, appearance aligned with P6

• Expand implementation beyond major rail projects– MTA Highway Programs– Workflow support with other departments

11/30/2011 42

Page 43: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

11/30/2011 43

Lessons Learned• Have we spent the appropriate amount of time “Marketing change” to 

individuals within the organization?  Can we achieve a level of excitement for learning and participation by our team members?

• Understand and Leverage existing tools and processes if you can – it helps reduce the impact of “change”.

• Must have executive support and direction from the top down.• “Be quick…but don’t hurry”.  Speed of implementation should be 

secondary to understanding and participation from Team!• Technology is the easy part…this can be deployed quickly.  What is 

important is the understanding of stakeholders and that their process and training is gradual, structured, and measured.

• Establish a centralized Implementation Team which meets and communicates regularly.  Strive to achieve a consensus so that implementation decisions are understood by all.

Page 44: Oracle|Primavera Program Management Information System …€¦ · • Oracle Primavera Software • Oracle Certified Training • Oracle Certified Implementation Support • Project

W W W . D R M C N A T T Y . C O M

Questions?Don McNatty

Principal Consultant

Brian CrissProject Manager/Lead Consultant

T. (877) 367‐7990E. [email protected]. www.drmcnatty.comW. www.mlmpsinc.com

11/30/2011 44


Recommended