Transcript
Page 1: Maynard Jackson High School - Atlanta Public Schools · • Lower Level topping slabs to resume. • Main Level ceiling installation and painting to continue. • Lower Level ceiling

- 1 -

Maynard Jackson High School Weekly Photo Report

This Week’s Activities – Classroom Building

October 21 – October 27

• Upper level and Main level Science room sink installation is ongoing.

• Kitchen equipment installation has begun.

• Upper Level Corridor VCT installation is ongoing.

• Main Level corridor painting is ongoing.

• Main Level Science Room casework installation is ongoing.

• Theater ceiling painting is complete and lighting is ongoing.

• Lower Level ceiling and wall framing is ongoing.

• Stair 5 wall installation is ongoing.

• Theater entry curtain wall installation is ongoing.

• Roof grading is complete.

Upper Level Corridor

Upper Level Ceiling Tile

Date: October 25, 2013

Client: Atlanta Public Schools

Project Name: Maynard Jackson High School Renovation

Project #: #12-034

Prepared By: Coralys Rodriguez

Distribution: APS Project Team, TWCC Project Team, Perkins & Will, Spurlock & Associates,

Uzun & Case

Comments: October 21st

to October 27th

, 2013 Photo Report

Page 2: Maynard Jackson High School - Atlanta Public Schools · • Lower Level topping slabs to resume. • Main Level ceiling installation and painting to continue. • Lower Level ceiling

- 2 -

Maynard Jackson High School Weekly Photo Report

Main Level Corridors

Theater Curtain Wall

Kitchen

Theater Entry

Page 3: Maynard Jackson High School - Atlanta Public Schools · • Lower Level topping slabs to resume. • Main Level ceiling installation and painting to continue. • Lower Level ceiling

- 3 -

Maynard Jackson High School Weekly Photo Report

Stair 5

Roof

This Week’s Activities – Gymnasium

October 21 – October 27

• Main Level C wall framing and drywall installation is ongoing.

• Stair 9 installation is ongoing.

• Joist erection has begun.

• CMU wall installation has begun.

Gym Addition Steel Gym Exterior Walls

Page 4: Maynard Jackson High School - Atlanta Public Schools · • Lower Level topping slabs to resume. • Main Level ceiling installation and painting to continue. • Lower Level ceiling

- 4 -

Maynard Jackson High School Weekly Photo Report

This Week’s Activities - Sitework

October 21 – October 27

• Glenwood Ave tree planting is complete.

• Service drive tree planting has begun.

• East campus paving is ongoing.

• East campus sidewalks are ongoing.

• Softball field bleacher slabs and flumes are being placed.

East Campus and Softball Field Glenwood Ave Streetscape

Next Week’s Activities

October 28 – November 3

• Joist erection at Gym to continue.

• Roof railings to be complete.

• Upper Level VCT installation to continue.

• Main Level VCT installation to resume.

• Lower Level topping slabs to resume.

• Main Level ceiling installation and painting to continue.

• Lower Level ceiling framing to continue.

• Upper Level Science rooms sink installation to be complete.

Schedule Status • Classroom Building TCO December 1, 2013

• FF&E Deliveries to Start December 2, 2013

• Relocation on Weekends to Start December 7, 2013

• Full Time Relocation to Start December 20, 2013

• Band/Orchestra Corridor TCO December 31, 2013

• Classroom Building Classes Begin January 7, 2014

• Gym CO March 7, 2014

� Project is on schedule to date


Recommended