Bethel Park High SchoolBethel Park, PA
Weekly Progress Slide ShowWeekly Progress Slide ShowMarch 26, 2010
Massaro
Waterproofing and Insulation Continue
Massaro
Grade Beams are Being Poured and Excavated
Massaro
Area D Progressingg g
Massaro
Forms Are Being Placed and Stripped In Several Areas
Massaro
Chemical Lab Acid Neutralizing Tank
Massaro
Area D Footing Foundation g
Massaro
Underground MEP Items Continue
Massaro
Steel Being Tiedg
Massaro
Area H Wall Stripped
Massaro
Safety Break Lunch 2!y
With An Appearance FromThe School District
Massaro
Scheduled Work For Next Few Weeks:
• Building foundations and wall formingBuilding foundations and wall forming.• Several Walls and Grade Beams Poured.
C ti t k il il t bili ti it• Continue stock pile, soil stabilization items and back fill operations.
• Waterproofing in areas C, F, and H.• Area D Concrete Work.• Underground building MEP items.• Steel Fabrication continues at Sippel Fab
Massaro• Steel Fabrication continues at Sippel Fab.
Thank You The End
By Jeremy Beitery Je e y e teIntern, Massaro CMS, LLC