Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 20071
LTU Installation CoordinationKathleen Ratcliffe
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 20072
Agenda
LTU Installation CoordinationObjectives
Overall Schedule
Documentation and Release
Issues and Concerns
Close Out / Action Items
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 20073
Responsibilities
Mike Saleski / Safety Systems
Chan / Linac Project Management
Ratcliffe / Installation Manager
Tim Montagne / LTU Area Design and Integration
Phil Cutino / LTU Water
Bob Law and Jesse Saldivar/ LCLS CF
Ponciano Rodriguez / Cable Installation
Bob Fuller / Controls Checkout
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 20074
Installation Objectives
Install, Check out, and Control all components and systems for LTU
Beamline components represented by Emma’s current MAD Deck
All other that is necessary for safe and reliable commissioning
Water, Vacuum, AC Power, Air, Purge Gas, RF Systems
Safety SystemsRadiation Shielding, BCS, MPS, and PPS
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 20075
Overall Schedule
P3 consistent with Installation ScheduleStart Date 1/3/2008
End Date 8/18/2008
Schedule Considerations:Hardware availability
Davis Bacon / Cable Pulling / Stand Installation
General Laboratory Resources
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 20076
Special Conditions
Co occupancy with contractors
Aggressive installation schedule
No allowance for schedule drift
Temporary lighting
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 20077
LCLS LTU Installation Schedule
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 20079
Documentation Status
LTU StatusDesign and Integration Engineering – Tim Montagne and Venkat SrinivasanThree designers currently assigned to this areaDesign of components and supports is 85% completePDR’s and FDR’s of all diagnostics are completePDR’s and FDR’s of structural engineering are completeFirst samples of drift chambers are in testEverson Tesla magnets are in magnetic measurement testingSupport stands released to fabrication
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 200710
LTU Section 71
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 200711
LTU Section 71
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 200712
Documentation Status
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 200713
Documentation Status
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 200714
Product Assurance & Safety
Following safety documents are required prior to installation or operation
Safety Overview ApprovalWork authorization approval from LCLSPenetration permitsEarthquake approvalsBuilding inspection approvalsElectric safety approvalsRP approvalsNon-ionizing approvals
Kathleen Ratcliffe
LTU Installation Coordination [email protected]
October 30, 200715
Issues and Concerns
InstallationInstallation is dependent upon co-occupancy in December and that conflicts with facility final construction
Might need to install vacuum hardware when core drilling is taking place
Temporary lighting and power