HiRadMat safety preparation

Follow-up meeting24/06/2011

Page 2: HiRadMat  safety preparation

Processes

• See Marion’s talk

Page 3: HiRadMat  safety preparation

Alarms• Instruction meeting for CCC operators on Monday June 20th• https://edms.cern.ch/document/1149524/1• List of alarms consolidated • Lot of them not yet operational• Operational procedure in being written

Page 4: HiRadMat  safety preparation

Beam commissioning low intensity

• Operational procedure approved• https://edms.cern.ch/document/1149525/2• Dry run outcome• https://edms.cern.ch/document/1149523/1• Additional DSO tests on Tuesday• First shot hit the dump !

Page 5: HiRadMat  safety preparation

First protons through TT60-TT66

Page 6: HiRadMat  safety preparation

DSO tests

Page 7: HiRadMat  safety preparation

B.846 works during next TS

• Met L. Colly• 2 x 2 lifting points• Load specification by FB• Will be installed during next TS

Page 8: HiRadMat  safety preparation

Evacuation hardware

• Met GS-ASE• Cable extension during next TS• Evacuation buttons and sirens will be installed

during the August TS.

Page 9: HiRadMat  safety preparation

Safety file descriptive part

• Still in work.


Recommended