Transcript
Page 1: Hindawi Publishing Corporation - Research Article EPQ Model ...downloads.hindawi.com/journals/isrn/2013/485172.pdfEPQ Model for Trended Demand with Rework and Random Preventive Machine

Hindawi Publishing CorporationISRN Operations ResearchVolume 2013, Article ID 485172, 8 pageshttp://dx.doi.org/10.1155/2013/485172

Research ArticleEPQ Model for Trended Demand with Rework andRandom Preventive Machine Time

Nita H. Shah,1 Dushyantkumar G. Patel,2 and Digeshkumar B. Shah3

1 Department of Mathematics, Gujarat University, Ahmedabad, Gujarat 380009, India2Department of Mathematics, Government Polytechnic for Girls, Ahmedabad, Gujarat 380015, India3 Department of Mathematics, L.D. College of Engineering, Ahmedabad, Gujarat 380015, India

Correspondence should be addressed to Nita H. Shah; [email protected]

Received 20 April 2013; Accepted 9 June 2013

Academic Editors: I. Ahmad, P. Ekel, and Y. Yu

Copyright Β© 2013 Nita H. Shah et al. This is an open access article distributed under the Creative Commons Attribution License,which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

Economic production quantity (EPQ) inventory model for trended demand has been analyzed with rework facility and stochasticpreventive machine time. Due to the complexity of the model, search method is proposed to determine the best optimal solution.A numerical example and sensitivity analysis are carried out to validate the proposed model. From the sensitivity analysis, it isobserved that the rate of change of demand has significant impact on the optimal inventory cost. The model is very sensitive to theproduction and demand rate.

1. Introduction

An item that does not satisfy quality standards but can beattained after reprocess is termed as a recoverable item andthe process is known as rework. It is observed that in anindustrial sector, the rework reduced production cost andmaintained quality standard of the item. Schrady [1] debatedrework process. Khouja [2] formulated an economic lot-sizeand shipment policy by incorporating a fraction of defectiveitems and direct rework. Koh et al. [3] andDobos and Richter[4] discussed two production policies with options to ordernew products externally or recover old products. Chiu et al.[5] analyzed an imperfect rework process for EPQ modelwith repairable and scrapped items. Jamal et al. [6] advocatedthe policy for rework of defective items in the same cyclewhich was extended by Cardenas-Barron [7]. Widyadanaand Wee [8] gave an analysis of these problems using analgebraic approach. Chiu [9] and Chiu et al. [10] discussedEPQ model by allowing shortages and considering servicelevel constraint. Yoo et al. [11] discussed an EPQ modelwith imperfect production quality, imperfect inspection, andrework.

Meller and Kim [12], Sheu and Chen [13] and Tsou andChen [14] studied Variants of EPQ model with preventive

maintenance. Abboud et al. [15] analyzed an economicorder quantity model by considering machine unavailabilityowing to preventive maintenance and shortage. Chung et al.[16] extended the previous model to compute an economicproduction quantity for deteriorating inventory model withstochastic machine unavailable time and shortage. Wee andWidyadana [17] revisited the previous model incorporatingrework.

In this paper, we analyze an economic production quan-tity (EPQ) model with rework and random preventive main-tenance time together when demand is increasing function oftime. The consideration of random preventive maintenancetime, rework, and trended demand in the model increasesits applicability in the electronic and automobile industries.In this production system, produced items are inspectedimmediately. Defective items are stocked and reworked at theend of the production uptime. We will call these items asrecoverable items. Out of these recoverable items, the fractionof the items will be labeled as β€œnew” and rest will be scrapped.Preventivemaintenance is performed at the end of the reworkprocess, and the maintenance time is assumed to be random.When demand is increasing, shortages may occur which willbe treated as lost sales in this study. It is observed that the rateof change of demand has significant impact on the optimal

Page 2: Hindawi Publishing Corporation - Research Article EPQ Model ...downloads.hindawi.com/journals/isrn/2013/485172.pdfEPQ Model for Trended Demand with Rework and Random Preventive Machine

2 ISRN Operations Research

Table 1: Sensitivity analysis of 𝑇1π‘Žand total cost when preventive maintenance time is uniformly and exponentially distributed.

Parameter Percentage change Uniform distribution Exponential distribution πœ† = 20𝑇1π‘Ž

𝑇𝐢𝑇 𝑇1π‘Ž

𝑇𝐢𝑇

𝐴

βˆ’40% 0.1118836 2217.023407 0.165363168 3105.82179βˆ’20% 0.1127598 2396.444313 0.168010377 3225.8832310 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.1145095 2751.208003 0.173362159 3460.59955840% 0.1153831 2926.585673 0.176064945 3575.33395

𝑃

βˆ’40% 0.119 0.224 0.873011973 3769.650118βˆ’20% 0.116 0.220356527 0.280588937 3224.8966390 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.0784111 2671.944386 0.123903512 3421.12104640% 0.0598742 2748.060997 0.09758743 3473.297234

𝑃1

βˆ’40% 0.1252239 2840.779326 0.179184671 3667.154126βˆ’20% 0.117738 2670.650277 0.17374104 3462.4401060 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.1110459 2512.591082 0.168712009 3266.96521840% 0.1093473 2469.539689 0.167344624 3212.637461

a

βˆ’40% 0.0468611 2285.690117 0.081365729 2483.982152βˆ’20% 0.0736194 2419.311543 0.118822843 2928.2745450 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.1801641 2784.239588 0.248801609 3743.38927940% 0.313401 3147.605249 0.385620567 4166.830717

b

βˆ’40% 0.1133496 2572.975288 0.170020919 3336.335153βˆ’20% 0.113492 2573.73768 0.170347969 3340.2333530 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.1137789 2575.262185 0.171008033 3348.02255340% 0.1139235 2576.024314 0.1713411 3351.913594

π‘₯

βˆ’40% 0.1075459 2440.729188 0.165578265 3180.040146βˆ’20% 0.1105098 2506.778232 0.168074836 3261.5205650 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.1169347 2644.037111 0.173391457 3427.95442440% 0.1204229 2715.549502 0.176225505 3513.094599

π‘₯1

βˆ’40% 0.1131507 2451.633648 0.170247776 3220.242525βˆ’20% 0.1133924 2513.000758 0.170462207 3282.1199790 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.1138787 2636.131758 0.17089215 3406.27046440% 0.1141232 2697.89656 0.171107662 3468.544359

β„Ž

βˆ’40% 0.1163864 2035.802579 0.196138784 2497.162768βˆ’20% 0.114993 2306.766649 0.18157314 2935.5540590 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.1123112 2839.068303 0.162020977 3729.59749240% 0.11102 3100.535386 0.15486872 4096.262909

β„Ž1

βˆ’40% 0.113733 2555.165605 0.171388527 3315.223296βˆ’20% 0.113684 2564.8349 0.171031253 3329.6917750 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.1135862 2584.160837 0.170325715 3358.5356740% 0.1135373 2593.817484 0.169977356 3372.911591

Page 3: Hindawi Publishing Corporation - Research Article EPQ Model ...downloads.hindawi.com/journals/isrn/2013/485172.pdfEPQ Model for Trended Demand with Rework and Random Preventive Machine

ISRN Operations Research 3

Table 1: Continued.

Parameter Percentage change Uniform distribution Exponential distribution πœ† = 20𝑇1π‘Ž

𝑇𝐢𝑇 𝑇1π‘Ž

𝑇𝐢𝑇

𝑆

βˆ’40% 0.1119752 2570.475444 0.15263831 3147.25954βˆ’20% 0.1129966 2572.958931 0.162618107 3255.7438080 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.1140719 2575.549497 0.1774544 3418.94091440% 0.1143897 2576.310317 0.183312722 3483.929611

𝑆𝑐

βˆ’40% 0.113643 2453.561123 0.170776446 3223.952673βˆ’20% 0.113639 2514.030563 0.170726744 3284.0412150 0.1136351 2574.499976 0.170676999 3344.12915

20% 0.1136311 2634.969362 0.17062721 3404.21646740% 0.1136271 2695.438718 0.170577378 3464.303169

Time

T1a T2aT4rT3r

T1 T2

T3

T

Inventory level

Im

Figure 1: Inventory status of serviceable items with lost sales.

inventory cost. It is suggested that when demand is trended,preventivemaintenance time should be controlled by recruit-ing well-qualified technicians. The uniform distribution andexponential distribution for preventive maintenance time areexplored.The paper is organized as follows: Section 2 is aboutthe mathematical development of the proposed problem. InSection 3, example and sensitivity are given. Conclusions arehighlighted in Section 4.

2. Mathematical Model

Assumptions. (1) The inventory system under considerationdeals with single item. (2) Standard quality items must begreater than the demand. (3) The production and reworkrates are constant. (4) The demand rate, 𝑅(𝑑) = π‘Ž(1 + 𝑏𝑑), isincreasing function of time, where π‘Ž > 0 is scale demand and0 < 𝑏 < 1 denotes the rate of change of demand. (5) Setup costfor rework process is zero or negligible. (6) Recoverable itemsare spawned during the production uptime, and scrappeditems are produced during the rework uptime.

The status of the serviceable inventory is depicted inFigure 1. Production occurs during [0, 𝑇

1π‘Ž]. In phase π‘₯

defective items per unit time are to be reworked. The reworkprocess starts at the end of the predetermined productionuptime. The rework time ends at 𝑇

3π‘Ÿtime period. The

different production processes of the material and defectiveitems result in different product rates. During the rework,some rejected and scrapped items will occur. LIFO policyis assumed for the production system. So, serviceable itemsduring the rework uptime are utilized before the fresh itemsfrom the production in uptime. The new production run isstarted when the inventory level reaches zero at the end of𝑇2π‘Žtime period. It may happen that the production may not

start at 𝑇2π‘Žtime period because unavailability of the machine

is randomly distributed with a probability density function𝑓(𝑑). The nonavailability of machine may result in shortageduring 𝑇

3time period. The production will resume after the

𝑇3time period.From the above description, the inventory level in a

production uptime period is governed by the differentialequation

𝑑𝐼1π‘Ž(𝑑1π‘Ž)

𝑑𝑑1π‘Ž

= 𝑃 βˆ’ 𝑅 (𝑑1π‘Ž) βˆ’ π‘₯, 0 ≀ 𝑑

1π‘Žβ‰€ 𝑇1π‘Ž. (1)

The inventory level in a rework uptime is

𝑑𝐼3π‘Ÿ(𝑑3π‘Ÿ)

𝑑𝑑3π‘Ÿ

= 𝑃1βˆ’ 𝑅 (𝑑

3π‘Ÿ) βˆ’ π‘₯1, 0 ≀ 𝑑

3π‘Ÿβ‰€ 𝑇3π‘Ÿ. (2)

The inventory level in a production downtime is

𝑑𝐼2π‘Ž(𝑑2π‘Ž)

𝑑𝑑2π‘Ž

= βˆ’π‘… (𝑑1π‘Ž) , 0 ≀ 𝑑

2π‘Žβ‰€ 𝑇2π‘Ž. (3)

The inventory level in a rework downtime is

𝑑𝐼4π‘Ÿ(𝑑4π‘Ÿ)

𝑑𝑑4π‘Ÿ

= βˆ’π‘… (𝑑4π‘Ÿ) , 0 ≀ 𝑑

4π‘Ÿβ‰€ 𝑇4π‘Ÿ. (4)

Page 4: Hindawi Publishing Corporation - Research Article EPQ Model ...downloads.hindawi.com/journals/isrn/2013/485172.pdfEPQ Model for Trended Demand with Rework and Random Preventive Machine

4 ISRN Operations Research

Under the assumption of LIFO production system, theinventory level of good items depletes at a constant rateduring rework uptime and downtime. The inventory level isgoverned by

𝑑𝐼3π‘Ž(𝑑3π‘Ž)

𝑑𝑑3π‘Ž

= 0, 0 ≀ 𝑑3π‘Žβ‰€ 𝑇3π‘Ÿ+ 𝑇4π‘Ÿ. (5)

Using 𝐼1π‘Ž(0) = 0, the solution of (1) is

𝐼1π‘Ž(𝑑1π‘Ž) = (𝑃 βˆ’ π‘Ž βˆ’ π‘₯) 𝑑

1π‘Žβˆ’π‘Žπ‘

2𝑑2

1π‘Ž, 0 ≀ 𝑑

1π‘Žβ‰€ 𝑇1π‘Ž

(6)

which is the inventory level during [0, 𝑇1π‘Ž]. Hence, the total

inventory in a production uptime is

𝑇𝐼1π‘Ž= ∫

𝑇1π‘Ž

0

𝐼1π‘Ž(𝑑1π‘Ž) 𝑑𝑑1π‘Ž

= (𝑃 βˆ’ π‘Ž βˆ’ π‘₯)𝑇2

1π‘Ž

2βˆ’π‘Žπ‘

6𝑇3

1π‘Ž.

(7)

Using 𝐼3π‘Ÿ(0) = 0, 𝐼

4π‘Ÿ(0) = 0, the total inventory of serviceable

items for the rework uptime and rework downtime is

𝑇𝐼3π‘Ÿ= (𝑃1βˆ’ π‘Ž βˆ’ π‘₯

1)𝑇2

3π‘Ÿ

2βˆ’π‘Žπ‘

6𝑇3

3π‘Ÿ,

𝑇𝐼4π‘Ÿ= π‘Ž[

𝑇2

4π‘Ÿ

2+𝑏

3𝑇3

4π‘Ÿ] ,

(8)

respectively.Using 𝐼

2π‘Ž(𝐼2π‘Ž) = 0, the total inventory level of a

production downtime is

𝑇𝐼2π‘Ž= π‘Ž[

𝑇2

2π‘Ž

2+𝑏

3𝑇3

2π‘Ž] . (9)

The maximum inventory is

πΌπ‘š= 𝐼1π‘Ž(𝑇1π‘Ž) = (𝑃 βˆ’ π‘Ž βˆ’ π‘₯) 𝑇

1π‘Žβˆ’π‘Žπ‘

2𝑇2

1π‘Ž(10)

and hence, the total inventory in a rework uptime is

𝑇𝐼3π‘Ž= πΌπ‘š(𝑇3π‘Ÿ+ 𝑇4π‘Ÿ) . (11)

Now, let us analyze the inventory level of recoverableitems (Figure 2).

The inventory level of recoverable items in a productionuptime is governed by the differential equation

π‘‘πΌπ‘Ÿ1(π‘‘π‘Ÿ1)

π‘‘π‘‘π‘Ÿ1

= π‘₯, 0 ≀ π‘‘π‘Ÿ1≀ 𝑇1π‘Ž. (12)

Since initially there are no recoverable items, that is, πΌπ‘Ÿ1(0) =

0, the solution of (12) is

πΌπ‘Ÿ1(π‘‘π‘Ÿ1) = π‘₯𝑑

π‘Ÿ1, 0 ≀ 𝑑

π‘Ÿ1≀ 𝑇1π‘Ž. (13)

x

Time

IMr

T1a T3r

Figure 2: Inventory status of recoverable items.

Hence, the total inventory of recoverable items in a produc-tion uptime is

π‘‡π‘‡πΌπ‘Ÿ1=π‘₯𝑑2

1π‘Ž

2

(14)

and the maximum recoverable inventory is

πΌπ‘€π‘Ÿ= πΌπ‘Ÿ1(𝑇1π‘Ž) = π‘₯𝑇

1π‘Ž. (15)

The inventory level of recoverable item in the rework uptimeis modeled as

π‘‘πΌπ‘Ÿ3(π‘‘π‘Ÿ3)

π‘‘π‘‘π‘Ÿ3

= βˆ’π‘ƒ1, 0 ≀ 𝑑

π‘Ÿ3≀ 𝑇3π‘Ÿ. (16)

Using πΌπ‘Ÿ3(𝑇3π‘Ÿ) = 0, the inventory level of recoverable item in

rework uptime is

πΌπ‘Ÿ3(π‘‘π‘Ÿ3) = 𝑃1(𝑇3π‘Ÿβˆ’ π‘‘π‘Ÿ3) , 0 ≀ 𝑑

π‘Ÿ3≀ 𝑇3π‘Ÿ. (17)

Hence, the total inventory of recoverable item in the reworkuptime is

π‘‡π‘‡πΌπ‘Ÿ3=𝑃1𝑇2

3π‘Ÿ

2. (18)

The number of recoverable inventories is

πΌπ‘€π‘Ÿ= πΌπ‘Ÿ3(0) = 𝑃

1𝑇3π‘Ÿ. (19)

Hence,

𝑇3π‘Ÿ=πΌπ‘€π‘Ÿ

𝑃1

. (20)

Substituting πΌπ‘€π‘Ÿ

from (15), we get

𝑇3π‘Ÿ=π‘₯𝑇1π‘Ž

𝑃1

. (21)

Hence, the total recoverable inventory is

𝐼𝑀= 𝑇𝑇𝐼

π‘Ÿ1+ 𝑇𝑇𝐼

π‘Ÿ3=π‘₯𝑇2

1π‘Ž

2(1 +

π‘₯

𝑃1

) . (22)

Page 5: Hindawi Publishing Corporation - Research Article EPQ Model ...downloads.hindawi.com/journals/isrn/2013/485172.pdfEPQ Model for Trended Demand with Rework and Random Preventive Machine

ISRN Operations Research 5

The inventory level at the beginning of the productiondowntime is equal to the inventory level at the end of theproduction uptime; that is,

𝐼1π‘Ž(𝑇1π‘Ž) = 𝐼2π‘Ž(0) . (23)

Therefore,

𝑇2π‘Žβ‰ˆ1

π‘Ž[(𝑃 βˆ’ π‘Ž βˆ’ π‘₯) 𝑇

1π‘Žβˆ’π‘Žπ‘

2𝑇2

1π‘Ž] . (24)

When 𝑑3π‘Ÿ= 𝑇3π‘Ÿand 𝑑4π‘Ÿ= 0, the inventory level for serviceable

item in rework process satisfies

(𝑃1βˆ’ π‘Ž βˆ’ π‘₯

1) 𝑇3π‘Ÿβˆ’π‘Žπ‘

2𝑇2

3π‘Ÿ= π‘Ž [𝑇

4π‘Ÿβˆ’π‘

2𝑇2

4π‘Ÿ] . (25)

Neglecting 𝑇24π‘Ÿ(because 0 < 𝑇

4π‘Ÿ< 1), we get

𝑇4π‘Ÿβ‰ˆ1

π‘Ž(𝑃1βˆ’ π‘Ž βˆ’ π‘₯

1)π‘₯

𝑃1

𝑇1π‘Ž. (26)

The total production inventory cost is the sum of theproduction set up cost, inventory cost of serviceable item,inventory cost of recoverable item, and scrap cost:

𝑇𝐢 = 𝐴 + β„Ž [𝑇𝐼1π‘Ž+ 𝑇𝐼3π‘Ÿ+ 𝑇𝐼2π‘Ž+ 𝑇𝐼4π‘Ÿ+ 𝑇𝐼3π‘Ž]

+ β„Ž1𝐼𝑀+ 𝑆𝐢π‘₯1𝑇3π‘Ÿ

(27)

and the total cycle time is𝑇 = 𝑇

1π‘Ž+ 𝑇3π‘Ÿ+ 𝑇2π‘Ž+ 𝑇4π‘Ÿ. (28)

Hence, the total cost per unit time without lost sales is givenby

𝑇𝐢𝑇NL =𝑇𝐢

𝑇. (29)

The optimal production uptime for the EPQ systemwithout lost sales can be obtained by setting

𝑑𝑇𝐢𝑇NL (𝑇1π‘Ž)

𝑑𝑇1π‘Ž

= 0. (30)

When unavailability time of a machine is longer than theproduction downtime duration, lost sales will occur. So thetotal inventory cost is

𝐸 (𝑇𝐢) = 𝐴 + β„Ž [𝑇𝐼1π‘Ž+ 𝑇𝐼3π‘Ÿ+ 𝑇𝐼2π‘Ž+ 𝑇𝐼4π‘Ÿ+ 𝑇𝐼3π‘Ž]

+ β„Ž1𝐼𝑀+ 𝑆𝐢π‘₯1𝑇3π‘Ÿ+ 𝑆𝐿

Γ— ∫

∞

𝑑=𝑇2π‘Ž+𝑇4π‘Ÿ

𝑅 (𝑑) (𝑑 βˆ’ (𝑇2π‘Ž+ 𝑇4π‘Ÿ)) 𝑓 (𝑑) 𝑑𝑑

(31)

and the total cycle time for lost sales is

𝐸 (𝑇) = 𝑇1π‘Ž+ 𝑇3π‘Ÿ+ 𝑇2π‘Ž+ 𝑇4π‘Ÿ

+ ∫

∞

𝑑=𝑇2π‘Ž+𝑇4π‘Ÿ

(𝑑 βˆ’ (𝑇2π‘Ž+ 𝑇4π‘Ÿ)) 𝑓 (𝑑) 𝑑𝑑.

(32)

Hence, the total cost per unit time for lost sales is

𝐸 (𝑇𝐢𝑇) =𝐸 (𝑇𝐢)

𝐸 (𝑇). (33)

We discuss lost sales scenario for two distributions, namelyuniform distribution and exponential distribution.

2.1. UniformDistribution. Define the probability distributionfunction 𝑓(𝑑), when the preventive maintenance time 𝑑 isdistributed uniformly as follows:

𝑓 (𝑑) =

{{

{{

{

1

𝜏, 0 ≀ 𝑑 ≀ 𝜏

0, otherwise.(34)

Substituting 𝑓(𝑑) in (33) gives the total cost per unit time foruniform distribution as

π‘‡πΆπ‘‡π‘ˆ

= (𝐴 + β„Ž [𝑇𝐼1π‘Ž+ 𝑇𝐼3π‘Ÿ+ 𝑇𝐼2π‘Ž+ 𝑇𝐼4π‘Ÿ+ 𝑇𝐼3π‘Ž] + β„Ž1𝐼𝑀

+ 𝑆𝐢π‘₯1𝑇3π‘Ÿ+ π‘†πΏβˆ«

𝜏

0

(π‘Ž (1 + 𝑏𝑑)

𝜏) (𝑑 βˆ’ (𝑇

2π‘Ž+ 𝑇4π‘Ÿ)) 𝑑𝑑)

Γ— (𝑇1π‘Ž+ 𝑇3π‘Ÿ+ 𝑇2π‘Ž+ 𝑇4π‘Ÿ+ (1

𝜏)

Γ—βˆ«

𝜏

𝑑=𝑇2π‘Ž+𝑇4π‘Ÿ

(𝑑 βˆ’ (𝑇2π‘Ž+ 𝑇4π‘Ÿ)) 𝑑𝑑)

βˆ’1

(35)

substituting all the time variables in (35) in terms of 𝑇1π‘Ž,

the objective function; 𝑇𝐢𝑇𝑒is a function of 𝑇

1π‘Žonly. The

optimum value of 𝑇1π‘Žcan be computed by setting

π‘‘π‘‡πΆπ‘‡π‘ˆ(𝑇1π‘Ž)

𝑑𝑇1π‘Ž

= 0. (36)

To derive the best solution from nonlost sales and lost salesscenarios, we propose the following steps [17].

Step 1. Calculate (30), (24), and (26) and set 𝑇sb = 𝑇2π‘Ž + 𝑇4π‘Ÿ.

Step 2. If 𝑇sb < 𝜏, then the obtained solution is not feasible,and go to Step 3; otherwise the solution is obtained.

Step 3. Set 𝑇sb = 𝜏. Find 𝑇1aub using (26) and (24). Calculate𝑇𝐢𝑇NL(𝑇1aub) using (29).

Step 4. Calculate (36), (24), and (26) and set 𝑇sb = 𝑇2π‘Ž + 𝑇4π‘Ÿ.

Step 5. If 𝑇sb β‰₯ 𝜏, then π‘‡βˆ—1π‘Ž = 𝑇1aub and the correspondingtotal cost is 𝑇𝐢𝑇NL(𝑇1aub); otherwise, calculate π‘‡πΆπ‘‡π‘ˆ(𝑇1π‘Ž).

Step 6. If 𝑇𝐢𝑇NL(𝑇1aub) ≀ π‘‡πΆπ‘‡π‘ˆ(𝑇1π‘Ž), then π‘‡βˆ—1π‘Ž = 𝑇1aub:otherwise π‘‡βˆ—

1π‘Ž= 𝑇1π‘Ž.

2.2. Exponential Distribution. Define the probability distri-bution function 𝑓(𝑑), when the preventive maintenance time𝑑 is distributed exponential with mean 1/πœ† as

𝑓 (𝑑) = πœ†π‘’βˆ’πœ†π‘‘, πœ† > 0. (37)

Page 6: Hindawi Publishing Corporation - Research Article EPQ Model ...downloads.hindawi.com/journals/isrn/2013/485172.pdfEPQ Model for Trended Demand with Rework and Random Preventive Machine

6 ISRN Operations Research

0.11 0.112 0.114 0.116 0.118 0.1220.12 0.124T1a

2580

2590

2600

2610

2620

2630

2640

2650

2660To

tal c

ost

Figure 3: Convexity of total cost.

0.09

0.095

0.1

0.105

0.11

0.115

0.12

0.125

0 20 40

Prod

uctio

n up

time f

or u

nifo

rm d

istrib

utio

n

Change in inventory parameter (%)βˆ’40 βˆ’20

A

P

P1

a

b

x

x1

h1

h

S

Sc

Figure 4: Sensitivity analysis of production uptime for uniformdistribution.

Here, the total cost per unit time for the lost sale 𝑆𝐿is

𝑇𝐢𝑇𝐸= (𝐴 + β„Ž [𝑇𝐼

1π‘Ž+ 𝑇𝐼3π‘Ÿ+ 𝑇𝐼2π‘Ž+ 𝑇𝐼4π‘Ÿ+ 𝑇𝐼3π‘Ž]

+ β„Ž1𝐼𝑀+ 𝑆𝐢π‘₯1𝑇3π‘Ÿ

+π‘†πΏβˆ«

∞

𝑑=𝑇2π‘Ž+𝑇4π‘Ÿ

𝑅 (𝑑) (𝑑 βˆ’ (𝑇2π‘Ž+ 𝑇4π‘Ÿ)) πœ†π‘’βˆ’πœ†π‘‘π‘‘π‘‘)

Γ— (𝑇1π‘Ž+ 𝑇3π‘Ÿ+ 𝑇2π‘Ž+ 𝑇4π‘Ÿ+ (1

πœ†) π‘’βˆ’πœ†(𝑇2π‘Ž+𝑇4π‘Ÿ))

βˆ’1

.

(38)

1800

2000

2200

2400

2600

2800

3000

3200

0 20 40Tota

l inv

ento

ry co

st fo

r uni

form

dist

ribut

ion

Change in inventory parameter (%)A

P

P1

a

b

x

x1

h

h1

S

βˆ’20βˆ’40

Figure 5: Sensitivity analysis of total cost for uniform distribution.

0.1

0.12

0.14

0.16

0.18

0.2

0.22

0.24

Change in inventory parameter (%)0 20 40βˆ’20βˆ’40

Prod

uctio

n up

time f

or ex

pone

ntia

ldi

strib

utio

n

A

P

P1

a

b

x

x1

h

h1

S

Figure 6: Sensitivity analysis of production uptime for exponentialdistribution.

Arguing as in (Section 2.1), we can obtain optimum totalcost. The high nonlinearity of the cost functions (29), (35),and (38) does not guarantee that the optimal solution isglobal. However, using parametric values, convexity of theobjective function is established.

3. Numerical Examples andSensitivity Analysis

Consider, following parametric values to study the workingof the proposed problem. Let𝐴 = $200 per production cycle,𝑃 = 10,000 units per unit time, π‘Ž = 5000 units per unittime, 𝑏 = 10%, π‘₯ = 500 units per unit time; π‘₯

1= 400

units per unit time, β„Ž = $5 per unit per unit time. β„Ž1=

Page 7: Hindawi Publishing Corporation - Research Article EPQ Model ...downloads.hindawi.com/journals/isrn/2013/485172.pdfEPQ Model for Trended Demand with Rework and Random Preventive Machine

ISRN Operations Research 7

3050

3100

3150

3200

3250

3300

3350

3400

3450

3500

Tota

l inv

ento

ry co

st fo

r exp

onen

tial d

istrib

utio

n

Change in inventory parameter (%)0 20 40βˆ’20βˆ’40

A

P

P1

a

b

x

x1

h

h1

S

Figure 7: Sensitivity analysis of total cost for exponential distribu-tion.

$3 per unit per unit time, 𝑆𝐿= $10 per unit, 𝑆

𝐢= $12

per unit, and the preventive maintenance time is uniformlydistributed over the interval [0, 0.1] [17]. Using the solutionprocedure outlined, the optimal production uptime is 𝑇

1π‘Ž=

41.5 days and the correspondingminimum total cost per unittime is 𝑇𝐢𝑇

π‘ˆ= $2575. This establishes that some lost sales

reduce the total cost per unit time. The convexity of π‘‡πΆπ‘‡π‘ˆis

established in Figure 3.The sensitivity analysis is carried out by changing each

of the parameters by βˆ’40%, βˆ’20%, +20%, and +40%. Theoptimal production uptime 𝑇

1π‘Žand the optimal total cost per

unit time for inventory parameters under consideration areshown in Table 1.

Figures 4 and 6 depict sensitivity analysis of productionuptime, 𝑇

1π‘Ž, with respect to all the inventory parameters

considered in the modeling when preventive maintenancetime follows uniform distribution/exponential distribution.It is observed that production uptime is slightly sensitive tochanges in 𝑃 and π‘Ž and moderately sensitive to changes in 𝑏and 𝜏, with little impact due to changes in the other inventoryparameters. 𝑇

1π‘Žhas negative impact with the increase in the

production rate, 𝑃, and positive impact when scale demand,π‘Ž, and rate of demand, 𝑏, increase.

The optimal total cost per unit time is slightly sensitiveto changes in π‘Ž, 𝑃, π‘₯, and 𝐿 and moderately sensitive tochanges in𝐴, 𝑏, 𝜏, 𝑆

𝐢, π‘₯1, and S

𝐿. No change is observed in the

optimal total cost per unit time for the remaining inventoryparameters. The optimal total cost per unit time is inverselyrelated to 𝑃 and 𝑃

1and directly related to other inventory

parameters (see Figures 5 and 7).

4. Conclusions

In this research, rework of imperfect quality and randompreventive maintenance time are incorporated in economic

production quantity model when demand increases withtime.The randompreventivemaintenance time is distributeduniformly and exponentially.Themodels are validated by theexample. The sensitivity analysis suggests that the optimaltotal cost per unit time is sensitive to changes in theproduction rate, the demand rate, and the product defectrate in both the uniform and the exponential distributedpreventive maintenance time. To combat increasing demand,the management should adopt the latest machinery whichdecreases defective production rate, reducing rework, andas a consequence, the machine’s production uptime can beutilized to its utmost. Further research can be carried out tostudy the effect of deterioration of units.

Notations

𝐼1π‘Ž: Serviceable inventory level in a production

uptime𝐼2π‘Ž: Serviceable inventory level in a production

downtime𝐼3π‘Ž: Serviceable inventory level in a rework

uptime𝐼3π‘Ÿ: Serviceable inventory level from rework

uptime𝐼4π‘Ÿ: Serviceable inventory level from rework

process in rework downtimeπΌπ‘Ÿ1: Recoverable inventory level in a production

uptimeπΌπ‘Ÿ3: Recoverable inventory level in a rework

uptime𝑇𝐼1π‘Ž: Total serviceable inventory in a production

uptime𝑇𝐼2π‘Ž: Total serviceable inventory in a production

downtime𝑇𝐼3π‘Ž: Total serviceable inventory in a rework

uptime𝑇𝐼3π‘Ÿ: Total serviceable inventory from a rework

uptime𝑇𝐼4π‘Ÿ: Total serviceable inventory from rework

process in a rework downtimeπ‘‡π‘‡πΌπ‘Ÿ1: Total recoverable inventory level in aproduction uptime

π‘‡π‘‡πΌπ‘Ÿ3: Total recoverable inventory level in a reworkuptime

𝑇1π‘Ž: Production uptime

𝑇2π‘Ž: Production downtime

𝑇3π‘Ÿ: Rework uptime

𝑇4π‘Ÿ: Rework downtime

𝑇sb: Total production downtime𝑇1aub: Production uptime when the total

production downtime is equal to the upperbound of uniform distribution parameter

πΌπ‘š: Inventory level of serviceable items at the

end of production uptimeπΌπ‘€π‘Ÿ

: Maximum inventory level of recoverableitems in a production uptime

𝐼𝑀: Total recoverable inventory

Page 8: Hindawi Publishing Corporation - Research Article EPQ Model ...downloads.hindawi.com/journals/isrn/2013/485172.pdfEPQ Model for Trended Demand with Rework and Random Preventive Machine

8 ISRN Operations Research

𝑃: Production rate𝑃1: Rework process rate

𝑅 = 𝑅(𝑑): Demand rate; π‘Ž(1+𝑏𝑑), π‘Ž > 0, 0 < 𝑏 < 1π‘₯: Product defect rateπ‘₯1: Product scrap rate

𝐴: Production setup costβ„Ž: Serviceable items holding costβ„Ž1: Recoverable items holding cost

𝑆𝐢: Scrap cost

𝑆𝐿: Lost sales cost

𝑇𝐢: Total inventory cost𝑇: Cycle time𝑇𝐢𝑇: Total inventory cost per unit time for

lost sales model𝑇𝐢𝑇NL: Total inventory cost per unit time for

without lost sales modelπ‘‡πΆπ‘‡π‘ˆ: Total inventory cost per unit time

for lost sales model with uniform dis-tribution preventive maintenance time

𝑇𝐢𝑇𝐸: Total inventory cost per unit time for

lost sales model with exponential dis-tribution preventive maintenance time.

References

[1] D. A. Schrady, β€œA deterministic inventory model for repairableitems,” Naval Research Logistics, vol. 14, no. 3, pp. 391–398, 1967.

[2] M.Khouja, β€œThe economic lot anddelivery scheduling problem:common cycle, rework, and variable production rate,” IIETransactions, vol. 32, no. 8, pp. 715–725, 2000.

[3] S.-G. Koh, H. Hwang, K.-I. Sohn, and C.-S. Ko, β€œAn optimal or-dering and recovery policy for reusable items,” Computers andIndustrial Engineering, vol. 43, no. 1-2, pp. 59–73, 2002.

[4] I. Dobos and K. Richter, β€œAn extended production/recyclingmodel with stationary demand and return rates,” InternationalJournal of Production Economics, vol. 90, no. 3, pp. 311–323,2004.

[5] S. W. Chiu, D.-C. Gong, and H.-M. Wee, β€œEffects of randomdefective rate and imperfect rework process on economicproduction quantity model,” Japan Journal of Industrial andApplied Mathematics, vol. 21, no. 3, pp. 375–389, 2004.

[6] A. M. M. Jamal, B. R. Sarker, and S. Mondal, β€œOptimal manu-facturing batch size with rework process at a single-stage pro-duction system,” Computers and Industrial Engineering, vol. 47,no. 1, pp. 77–89, 2004.

[7] L. E. Cardenas-Barron, β€œOn optimal batch sizing in a multi-stage production system with rework consideration,” EuropeanJournal of Operational Research, vol. 196, no. 3, pp. 1238–1244,2009.

[8] G. A. Widyadana and H. M. Wee, β€œRevisiting lot sizing for aninventory system with product recovery,” Computers andMath-ematics with Applications, vol. 59, no. 8, pp. 2933–2939, 2010.

[9] S.W. Chiu, β€œOptimal replenishment policy for imperfect qualityEMQ model with rework and backlogging,” Applied StochasticModels in Business and Industry, vol. 23, no. 2, pp. 165–178, 2007.

[10] S. W. Chiu, C.-K. Ting, and Y.-S. P. Chiu, β€œOptimal productionlot sizing with rework, scrap rate, and service level constraint,”Mathematical andComputerModelling, vol. 46, no. 3-4, pp. 535–549, 2007.

[11] S. H. Yoo,D. Kim, andM.-S. Park, β€œEconomic production quan-tity model with imperfect-quality items, two-way imperfectinspection and sales return,” International Journal of ProductionEconomics, vol. 121, no. 1, pp. 255–265, 2009.

[12] R. D. Meller and D. S. Kim, β€œThe impact of preventive main-tenance on system cost and buffer size,” European Journal ofOperational Research, vol. 95, no. 3, pp. 577–591, 1996.

[13] S.-H. Sheu and J.-A. Chen, β€œOptimal lot-sizing problem withimperfect maintenance and imperfect production,” Interna-tional Journal of Systems Science, vol. 35, no. 1, pp. 69–77, 2004.

[14] J.-C. Tsou and W.-J. Chen, β€œThe impact of preventive activitieson the economics of production systems:modeling and applica-tion,” Applied Mathematical Modelling, vol. 32, no. 6, pp. 1056–1065, 2008.

[15] N. E. Abboud, M. Y. Jaber, and N. A. Noueihed, β€œEconomic lotsizing with the consideration of randommachine unavailabilitytime,” Computers and Operations Research, vol. 27, no. 4, pp.335–351, 2000.

[16] C.-J. Chung, G. A. Widyadana, and H. M. Wee, β€œEconomicproduction quantity model for deteriorating inventory withrandom machine unavailability and shortage,” InternationalJournal of Production Research, vol. 49, no. 3, pp. 883–902, 2011.

[17] H.M.Wee and G. A.Widyadana, β€œEconomic production quan-tity models of deteriorating items with rework and stochasticpreventive maintenance time,” International Journal of Produc-tion Research, vol. 50, no. 11, pp. 2940–2952, 2012.

Page 9: Hindawi Publishing Corporation - Research Article EPQ Model ...downloads.hindawi.com/journals/isrn/2013/485172.pdfEPQ Model for Trended Demand with Rework and Random Preventive Machine

Submit your manuscripts athttp://www.hindawi.com

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttp://www.hindawi.com

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Journal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

CombinatoricsHindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

International Journal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

The Scientific World JournalHindawi Publishing Corporation http://www.hindawi.com Volume 2014

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttp://www.hindawi.com

Volume 2014 Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Stochastic AnalysisInternational Journal of


Recommended