Fiscal Year 2011/12 Project Report
Project Name Power Capacity(kW) Remarks
Hewa Khola 4455 kW completed
Lower Piluwa 990 kW completed
Gamgad small hydropower
project
400 kW completed
Dhalkebar-Muzaffarpur doublecircuit transmission line
400 kV Cross-border interconnectionbetween Nepal and India.
Necessary ground works are now
in place for taking off the
implementation. Expected to be
in operation by 2014
Rasuwagadhi
HydroelectricProject
111MW
Middle Bhotekoshi Hydroelectric
Project
102MW
Upper Sanjen Hydroelectric
Project
14.8 MW
Sanjen Hydroelectric Project 42.5 MW
Upper Modi Hydropower Project 47 MW NEA and K-Water(S.Korea) with
20% NEA share ownership
Upper Trishuli Hydropower
Project
60 MW
Hetaunda-Bharatpur
Transmission Line
220 kV
Bhotekoshi Hydropower Project 9 MW
Kulekhani-3 Hydroelectric
Project
14 MW Completion date September
13,2014
Chameliya Hydrolectric Project 30 MW tunnel breakthrough on 12th
May, 2012
Overall progress of civil works is
75%
Upper Trishuli 3A 60 MW Construction of major works of
the Project is to commence only
after the issuance of Work Order
by the Consultant.
The Khimti Dhalkebar Double
Circuit Transmission line Project
220 kV 95 % work completed
the completion of the project is
hampered due to obstructions
created by local residents
regarding the right of way issue
Hetauda- Bharatpur Bardghat
transmission line
220 kV Work is underway
Syangja substation 132 kV Almost complete and expected
to be commissioned soon
7/29/2019 Fiscal Year 2012 Project
2/2
Fiscal Year 2011/12 Project Report
Dumre-Damauli-Marsyangdi
132kV transmission line
132 kV Substantial Progress
Singati-Lamosangu 132kV
transmission line
132 kV Substantial Progress
Kabeli 132 kV transmission line 132 kV Substantial Progress
Chapali 132 kV substation 132 kV Substantial ProgressPathlaiya 132 kV substation 132 kV Substantial Progress
Matatirtha 132 kV substation
extension
132 kV Substantial Progress
Second circuit stringing of
Butwal Kohalpur-
Mahendranagar 132 kV
transmission line
132 kV Substantial Progress
Second circuit stringing of
Hetauda Kulekhani-II -
Siuchatar 132 kV transmission
line
132 kV Substantial Progress
Hetauda Dhalkebar Duhabi
400 kV transmission line project
400 kV Cross border power exchange
with India
Upper Tamakoshi Hydro Power
Company Limited (UTKHPL)
456 MW NEA with 41% stake
A Project Of National Pride
Construction Works ongoing at
full swing
Tanahu Hydropower Project 140 MW The detailed engineering study
of the project is in the final stage
of completion. Construction
could begin by mid 2013
Upper Trishuli 3BHydroelectric Project
37 MW Under development