Page 1: Dane County CNG Efforts

Dane County CNG Efforts

John Welch, PESolid Waste Manager

Dane County

April 25, 2013

Page 2: Dane County CNG Efforts

Dane County’s CNG History

• Experience with landfill gas and digesters• Pipeline quality gas project• Continued to evaluate options• Pilot bioCNG project• Funding from SEO and WCTP

– CNG station, bioCNG station, and vehicles

Page 3: Dane County CNG Efforts

What’s Driving Fleet Conversions• Fuel Savings• Proven Technology – engines• Emissions regulations

– Capital Cost– O&M Costs– Payload

• Available Fuel Stations (Chicken & Egg)• Contract Requirements• Image / Marketing

Page 4: Dane County CNG Efforts

Environmental Benefits

Fuel Carbon Intensity (gCO2e/MJ)

Gasoline 95.86

CNG from Pipeline 68.00

CNG from Digester 13.45

CNG from Landfill 11.26

http://www.arb.ca.gov/fuels/lcfs/121409lcfs_lutables.pdf

Page 5: Dane County CNG Efforts

Vehicles• 24 vehicles in fleet

– All Dual-fuel– F150s, F250s, F350s,

Ford Fusion, Transit Connect– 7 Departments

• Will add 15-20 in 2013– Some dedicated CNG– Plow Trucks, van, pickups, passenger car

• Conversion cost– $10,000 - $12,000 each

Page 6: Dane County CNG Efforts

Vehicle Conversion Options

• Dedicated, bi-fuel, or dual fuel– Available options & intended use– Range– Typical route (return to shop?)

• Direct from manufacturer or OEM conversion– Available models– Warranty / service– Cost

Page 7: Dane County CNG Efforts

Vehicle ROI

• Variables– Initial Conversion Cost

• Dedicated or Dual-fuel– Miles driven per year– MPG– Fuel Savings

~$2.00/gal

Page 8: Dane County CNG Efforts

Vehicle ROI Examples

Vehicle Conversion Cost

MPG Miles/yr GGE/yr Payback Savings After

PaybackCar $9,000 25 25,000 1,000 4.5 yrs $7,000

Pickup $10,000 15 30,000 2,000 2.5 yrs $16,670

Garbage Truck $50,000 3 24,000 8,000 3.125 yrs $62,000

Delivery Van $30,000 6 25,000 4,200 3.6 yrs $37,000

Note: Does not include any grant funds or maintenance costs

Page 9: Dane County CNG Efforts

Infrastructure ROI

• Components of CNG cost– Supply Gas– Electricity– O&M– Capital Ammortization (grants)– Taxes and Tax Credits– Other incentives

Page 10: Dane County CNG Efforts

Dane County’s CNG Station

– Natural gas only– 2 hoses– Fast-fill– 100 GGE storage– 30 GGE/hr from compressor– Funding

• ~$280,000 grant from SEO and WCTP• ~$42,000 from County funds

Page 11: Dane County CNG Efforts
Page 12: Dane County CNG Efforts

Fueling Station ROI ResultsStephe Yborra Values

CNG w/ Grant

CNG w/o Grant

Natural Gas $0.81-$0.89 $0.709 $0.709

Electricity $0.04-$0.30 $0.376 $0.376

Capital $0.35-$0.65 $0.129 $0.987

WI Taxes $0.247 $0.247 $0.247

Federal Taxes $0.183 $0.183 $0.183

Tax Credits -$0.50 -$0.50 -$0.50

O&M $0.30-$0.65 $0.60 $0.60

Total $1.24-$2.24 $1.561 $2.419*Based on 1600-2000 GGE/month

Page 13: Dane County CNG Efforts

What if we increase CNG Usage?CNG w/o Grant2000 GGE/month

CNG w/o Grant5000 GGE/month

Natural Gas $0.709 $0.70

Electricity $0.376 $0.22

Capital $0.756 $0.30

WI Taxes $0.247 $0.247

Federal Taxes $0.183 $0.183

Tax Credits -$0.50 -$0.50

O&M $0.60 $0.60

Total $2.188 $1.567

Page 14: Dane County CNG Efforts

Dane County’s BioCNG Station

• Pilot System– Biogas from landfill

• 5 GGE/hr– 1 hose– Fast-fill – 40 GGE storage– Funding

• All Dane County

• New System– Biogas from landfill

• 10 GGE/hr– Pipeline gas backup– 2 fast-fill hoses– 4 slow-fill hoses– 200 GGE storage– Funding

• $150,000 from SEO

Page 15: Dane County CNG Efforts

Old System New System

Page 16: Dane County CNG Efforts

BioCNG Differences

• Extra Capitol• Extra O&M Costs• Cheaper Gas?

– Other revenue potential for gas?• RINs

Page 17: Dane County CNG Efforts

CNG vs BioCNG ROI ResultsCNG w/o Grant BioCNG w/o Grant

Natural Gas / Biogas $0.709 -

Electricity $0.376 $1.04

Capital $0.987 $1.974

WI Taxes $0.247 $0.247

Federal Taxes $0.183 $0.183

Tax Credits -$0.50 -$0.50

RINs - -$0.75

O&M $0.60 $0.91

Total $2.419 $2.921

*2000 GGE/month. Breaks even at ~4000-5000 GGE/month

Page 18: Dane County CNG Efforts

Hurdles• Vehicle Procurement

– EPA Certifications– Limited options– Delays

• Fueling Stations• Training

– Infrastructure & vehicle maintenance• Learning Curve

– Permitting, codes, regulatory agencies, taxes, maintenance, etc

Page 19: Dane County CNG Efforts

Other Considerations

• Vehicle maintenance– Local options?– Tools and training

• Building Modifications– Code compliance

• Training– Technicians, drivers,

Department heads, etc

Page 20: Dane County CNG Efforts

Vehicle Performance

• Dyno testing• Driver experience• Reliable• Maintenance/Service

Page 21: Dane County CNG Efforts

Future of CNG in Dane County

• Dane County - 10 yr Strategic Plan

– Convert most/entire fleet to CNG

– Looking for partners – fueling stations

– Looking for bioCNG opportunities

Page 22: Dane County CNG Efforts

Questions?

John Welch

Solid Waste Manager

608-267-8815

[email protected]