7/29/2019 CSG - Method Statement
1/4
1
Method statement for cement stabilized gravel (C S G) will be as below:
1) Excavate area to required level.
2) Screen material at spoil area.
3) Mix material.
- Load screened material into pugmill hopper- Load cement into Pugmill silo- Load water into pugmill.
The conveyor belt on the pugmill shall be calibrated by timing the belt andweighting the amount of material on the belt in the given time.
The gate on the cement hopper shall be set and the flow calculated byweighing the amount of cement on the belt in a given time
The gate of the cement hopper shall be adjusted to be coordinated withthe flow of material to 60kg +/- 10kg cement per meter cube of material.
The water flow rate shall be adjusted to allow the addition of water to OMC+/- 5%
4) Transport
The material shall be transported from the pugmill to the placing area byADT/Tipper Trucks at the placing area.
5) Placing and compaction
The material shall tipped and spread by loader and or grader. Once thematerial has been spread it shall be compacted by 10T vibrating roller andpedestrian roller.
6) Cure With Water From Water Tanker( within 2 hrs from placement)
Notes
The slopes shall be overbuilt to allow for compaction on the edges. The slope shall be trimmed to correct line and level by excavator
Proposed placing rate is 200m3 per day.
7/29/2019 CSG - Method Statement
2/4
2
Cement to be PPC 32.5N
Plant and method statement shall be finalized after completion oftrial section
Cure with bitumen once reaching final level
7) Plant List
Water Tanker Supply Water To Pugmill
Generator 250KVA Power Pugmill
Pugmill Mix Material
Komatsu 420 Loader (Or Similar) Load Pugmill
Vibrating Screen Screen Material
2no ADT/Tipper Transport Csg
Komatsu 420 Loader ( Or Similar) Spread Material
Grader Spread Material
BW 212 Vibration Roller Or Similar Compaction
1Tonne Pedestrian Roller Or Similar Compaction
Excavator Trim Slopes
7/29/2019 CSG - Method Statement
3/4
3
ALTERNATIVE METHOD STATEMENT
1) Screen materials at spoil bank
2) Transport material to placing area
3) Spread material with loader/grader to required thickness with added
water and condition to OMC +/- 5 %
4) Layer to be over built to allow for compaction on edges.
5) Layout cement at the required spacing and empty the bags.
6) Mix with re-claimer
7) Compact with vibrating rollers to required compaction.
8) Cure with water
Notes
Cement to be PPC 32.5
Trim slopes to correct line and level.
Rate 300m3/Day
PLANT
Komatsu 420 Loader Load Screen
Vibrating Screen Screen Material
Re Claimer Mix Material
Grader Spread Material
Excavator Trim Slopes
2 X ADT/ Tipper Transport Material Spoil Bank To
Placing Area
7/29/2019 CSG - Method Statement
4/4
4
BW 212 Roller Compaction
Pedestrian Roller Compaction
Flat Truck Cement From Store To Site
Water Tanker Add Water To Material/Curing