Certified Seismic Installation Program (CSIP)
OSHPD Compliant
Rev. 070717
Name: Certified Seismic Installation Program (CSIP)
Status: Woodwork Institute’s (WI) Certified Seismic Installation Program is meant to be either a stand-alone quality control option that can be specified separately or in conjunction with our Certified Compliance or Monitored Compliance programs.
Benefits To: Design Professionals and Property Owners:
• SpecifieduseofWI’sseismiccaseworkpre-approvalsfromtheOfficeofStatewideHealth PlanningandDevelopment(OSHPD),withoutanyadditionalengineeringcostsand/or requirements.
• Assurancethatproperbackingwasinstalledinthewallsforcompliantcaseworkinstallation.
• AssurancethatcaseworkwasinstalledinaccordancewithWI’sseismiccaseworkpre-approvals withinOSHPD’scompliancerequirements.
• Certifiedacknowledgementthattheproject’sseismiccaseworkinstallationrequirements have been met.
Installers:
• Aconsistentcabinetinstallationmethodology
• Easeofspecificationcompliance
• DiscountedpricingthroughWIAffiliatestatus
Applicability: OSHPD WI OSHPD’s pre-approvals are adequate for casework installation within the State of California
at any height within the building where the SDS is not greater than 1.93 for base, peninsula, and mechanical chase cabinets, and 2.0 fir wall and tall storage cabinets, and includes:
• Concreteorconcretemasonryunit(CMU)wallconstruction
• Woodormetalstudwallconstructionwitheithercontinuous3x6or16GAinwallblocking respectivelyandoneortwolayersofsheetrock
• Caseworkconstructionofplywood,particleboard,MDForSolidPhenolicCore(SPC)in compliance with the minimum requirements of the Architectural Woodwork Standards (AWS),including:
• Basecabinets,upto36″tallx24″bodydepthx48″wide,includingpeninsulaandthose with mechanical chase
• Wallcabinetsupto48″tallx18″bodydepthx48″wide
• Tallstoragecabinetsupto96″tallx24″bodydepthx48″wide
• Peninsulabasecabinetsupto36″tallx36″bodydepthx48″wide
• Mechanicalchasebasecabinetsupto42″tallx36″bodydepthand48″wide
DSA Compliance – InaccordancewiththeCaliforniaDepartmentofGeneralServices(DGS), DivisionofStateArchitect(DSA),InterpretationofRegulationManual(IR),SectionA-5, titled“AcceptanceofProducts,Materials,andEvaluationReports”(rev10/05/12,2013 CBC)–WI’sOfficeofStatewideHealthPlanningandDevelopment(OSHPD),OSHPD Pre-approvalofAnchorages(OPA),OPA-2649-10meetstheeligibilitycriteriawhenusedin accordancewithIRA-4.13(GeologicHazardReportRequirements,rev12/19/13,2013CBC).
CopiesofDSA’sIRA-4.13andA-5maybefoundat: www.dgs.ca.gov/dsa/Resources/IRManual.aspx
Cost: See http://woodworkinstitute.com/services/cost-sheets/.
Specification Requirement: Should a design professional wish to take advantage of the Woodwork Institute’s Certified Seismic Installation Program (CSIP),projectspecificationsshallrequireconformancetothe North American Architectural Woodwork Standards(NAAWS)andcontainthefollowing wording:
• CertifiedSeismicInstallationProgram:
• Beforewallsareclosedup,provideawrittenWoodworkInstituteCertifiedSeismic InstallationProgramreportconfirmingthatbackingisprovidedinalllocationsrequired forcaseworkinstallationoridentifyingthoselocationswherebackingismissingor improperly located.
• OncompletionofinstallationprovideaWoodworkInstituteCertifiedSeismic InstallationProgramCertificate,identifyingtheworkcoveredandcertifyingthat installationmeetstherequirementsoftheWICSIPattachmentdetailsandschedules.
• AllfeeschargedbytheWoodworkInstitutefortheirCertifiedSeismicInstallation Programaretheresponsibilityofthemillworkinstallerandshallbeincludedintheirbid.
Casework Installer Requirements: The party responsible for installation of casework for any project requiring CSIP certification shall:
• ContacttheWoodworkInstituteandcoordinateCSIPcertificationwiththempriorto submittal of shop drawings.
• Ensurethatthecaseworkshopdrawings:
○ AreincompliancewiththeNAAWS’sminimumrequirementsasestablishedin Section1
○ Include,inaccordancewiththeminimumrequirementsWI’sOSHPDPre-approvals:
• Caseworkelevationsshowingthecenter-lineheightandhorizontallocationsofall required,continuous,internalwallblockingfurnishedbyothers,
• Acaseworkfastenerschedule,clearlyshowingthetype,size,locationand maximumspacing.
• Atwoodormetalstudwalls,priortoapplicationofwallsurfacing,CaseworkInstallershall examine,approveandacknowledgeblockingcompliancetoWI’sOSHPDPre-approval requirements,whileprovidingdocumentationofsuchthrough:
○ Aninspectionreportshowingrooms/wallsinspectedtypeofblocking(woodormetal), confirmationofcomplianceorstatementofnon-compliance,inspectorsname,dateand signaturewith:
• Photodocumentation(referencedbyroom/wall)ofatleast25%ofthewalls inspected,andinspectionreportshallidentifywhichwallsincludephoto documentation. • ContactWIandarrangeforfinalinspectionofthecaseworkinstallationbyaWIDirectorof ArchitecturalServices(DAS),and:
○ Ifinstallationisfoundcompliant,theDASwillauthorizeissuanceoftheCSIPCertificate.
Although it is not required, WI recommends, that those fabricators with the appropriate equipment pre-bore their cabinet backs with the proper number, spacing and location of the installationfastenerlocationsinaccordancewithWI’sOSHPDPre-approvalstoavoidfielderror.
WI Affiliate Requirements: In order to qualify for the WI Affiliate fee discount for CSIP certification, WI Affiliate shall hold a WI
SB-E Type License,whichwillbeofferedtoexistingWIAffiliatefirmswithoutaWI-TypeB-E LicenseandnewWIAffiliateapplicantsundernormalapplicationprotocols.
CSIPisnotapplicabletotheInstitute’sWIAffiliateSub-Subdiscount.
DISCLAIMER:TheWoodworkInstituteisanindependentinspectionservicethatdetermineswhetherworkconformstospecificstandardsorrequirements.TheInstitutedoesnotcertifyorguaranteethesafetyorperformanceofanymanufacturedproducts,components,orinstallationthereof,oranystandardorprocessrelatedthereto,regardlessofwhethertheycomplywiththeNorth American Architectural Woodwork Standards,theCertifiedSeismicInstallationProgramapprovedOSHPD(OPA-2649-10andOPM-0092-13)drawingsand/orcontractdocumentsundersaidStandard/Program.Additionally,theInstitutedoesnotguaranteeorcertifytheservices,fitnessforpurpose,advice,materialsorproductsprovidedbyanythirdparty,includingcontractors,architects,designersandengineers.
For more information call your WI Director of Architectural Services or our office at (916) 372-9943
Drawings: The current OPM approval does not include base and peninsula cabinets. However, WI’s CSIP has additional specifications with regard to base and peninsula cabinets.
For CSIP, use the approved OPM for wall and tall storage cabinets and the previously approved OPA requirements for base and peninsula cabinets. The applicable drawings and their sources are noted below and included in this document.
OPM—OPM0092-13
• DC01—OPM0092-13
• DC02—OPM2692-13
• SC01—OPM0092-13
• SC02—OPM2692-13
• SC03—OPM2692-13
• WC01—OPM2692-13
• WC02—OPM2692-13
• WC03—OPM2692-13
OPA—OPA2649-10
• BC01—OPA2649-10
• BC02—OPA2649-10
• PC01—OPA2649-10
• PC02—OPA2649-10
• ANC01—OPA2649-10
• ANC02—OPA2649-10
05/12/2015 OPM-0092-13: Reviewed for Code Compliance by Jeffrey Kikumoto Page 3 of 10
Jeffrey Y. Kikumoto
OPM-0092-13
05/12/2015
Currently Approved OPM
SAMPLE
05/12/2015 OPM-0092-13: Reviewed for Code Compliance by Jeffrey Kikumoto Page 4 of 10
Jeffrey Y. Kikumoto
OPM-0092-13
05/12/2015
Currently Approved OPM
SAMPLE
05/12/2015 OPM-0092-13: Reviewed for Code Compliance by Jeffrey Kikumoto Page 5 of 10
Jeffrey Y. Kikumoto
OPM-0092-13
05/12/2015
Currently Approved OPM
SAMPLE
05/12/2015 OPM-0092-13: Reviewed for Code Compliance by Jeffrey Kikumoto Page 6 of 10
Jeffrey Y. Kikumoto
OPM-0092-13
05/12/2015
Currently Approved OPM
SAMPLE
05/12/2015 OPM-0092-13: Reviewed for Code Compliance by Jeffrey Kikumoto Page 7 of 10
Jeffrey Y. Kikumoto
OPM-0092-13
05/12/2015
Currently Approved OPM
SAMPLE
05/12/2015 OPM-0092-13: Reviewed for Code Compliance by Jeffrey Kikumoto Page 8 of 10
Jeffrey Y. Kikumoto
OPM-0092-13
05/12/2015
Currently Approved OPM
SAMPLE
05/12/2015 OPM-0092-13: Reviewed for Code Compliance by Jeffrey Kikumoto Page 9 of 10
Jeffrey Y. Kikumoto
OPM-0092-13
05/12/2015
Currently Approved OPM
SAMPLE
05/12/2015 OPM-0092-13: Reviewed for Code Compliance by Jeffrey Kikumoto Page 10 of 10
Jeffrey Y. Kikumoto
OPM-0092-13
05/12/2015
Currently Approved OPM
SAMPLE
1 or 2 LAYER 5/8”
Note, these requirements are from the engineering of WI’s OPA-2649-10 dated 4/18/2013 and are part of WI’s CSIP requirement for Certifi cation eff ective 01/01/2015.
SAMPLE
1 or 2 LAYER 5/8”
Note, these requirements are from the engineering of WI’s OPA-2649-10 dated 4/18/2013 and are part of WI’s CSIP requirement for Certifi cation eff ective 01/01/2015.
SAMPLE
Note, these requirements are from the engineering of WI’s OPA-2649-10 dated 4/18/2013 and are part of WI’s CSIP requirement for Certifi cation eff ective 01/01/2015.
SAMPLE
Note, these requirements are from the engineering of WI’s OPA-2649-10 dated 4/18/2013 and are part of WI’s CSIP requirement for Certifi cation eff ective 01/01/2015.
SAMPLE
Note, these requirements are from the engineering of WI’s OPA-2649-10 dated 4/18/2013 and are part of WI’s CSIP requirement for Certifi cation eff ective 01/01/2015.
SAMPLE
Note, these requirements are from the engineering of WI’s OPA-2649-10 dated 4/18/2013 and are part of WI’s CSIP requirement for Certifi cation eff ective 01/01/2015.
SAMPLE
P.O. Box 980247 t West Sacramento, CA 95798-0247(916) 372-9943 t Fax: (916) 372-9950
E-mail: [email protected] t www.woodworkinstitute.com