Alcoa – Valhalla/McKenzie Program Feb. 19, 2013
Highlights and Project Team • $20,000,000 program, on time and under budget with great
teamwork and coordination • Project included a District wide effort: Tech Shop, CM
Wiremen, System Operations, Engineering, Project Management, Legal, Safety, Environmental, Drafting
• Alcoa (Funding) • Fluor (Alcoa’s project management firm) • BPA (Partner during Valhalla transition) • SAIC Engineering (formerly RW Beck, Alcoa’s consultant) • NAES Power Contractors (Alcoa’s contractor) • Various sub-contractors (Alcoa’s contractor)
2
Real District Wide Team Work!
3
• Alcoa and the District began work on a facilities study in 2007 to provide reliable service to three pot lines, able to sustain a worst case outage, through 2028.
• To ensure reliable electric service for Alcoa, the District purchased the low side of BPA’s Valhalla Substation. All reimbursed by Alcoa including internal costs plus admin. fee.
• Major retrofit of two very old substations
Why did we build it?
4
Program negotiations began: 2006 Major Construction start: Late 2010 Planned completion: April 2013
Budget
5
Timeline Initial: $20,000,000 Spent to date: $19,817,000 Projected: $20,000,000 Est. at completion: $20,000,000
Project is on time and under budget
What we accomplished • Tied together two substations and Alcoa for the District’s
ability to provide power to Alcoa • Program duration was six years. Design, procurement, and
construction took 3 years beginning in 2010. • Successfully tied two energized yards together under N-1
condition with no project work-related power loss to plant • Alcoa/Fluor identified this program as their operationally
highest risk program. District crews sustained one safety incident in 32,800 hrs worked to-date.
• During construction Alcoa determined it would start a third pot line. This was about a year ahead of schedule, causing significant challenges.
6
Original configuration (District assets in purple, McKenzie Substation)
7
New configuration (District’s assets in purple)
8
Engineering Highlights/Challenges
9
• Outside engineering • Plant contingencies • N-1 planning throughout construction –
wireman & tech on call 24/7 • Switching & clearances • No significant unscheduled outages
Wiremen Highlights/Challenges
10
• Great interface/coordination with construction contractors
• Switching & clearances: Some 289 switching/clearances were performed (very complex), with flawless coordination
• Safety throughout project execution • Very tight working conditions • Plan execution & attention to details
Technician Highlights/Challenges
• New SCADA system • New Remote Telemetry Unit • New metering (4 ea.) & relay package • Capacitor bank • Testing & commissioning: District technicians
completed all technical tie-in and programming integral to systems operation
11
How was it successfully completed?
12
• Long-range planning - project began in 2006 (initial discussion)
• Vision for long-term power sale contracts
• Project team daily and weekly progress meetings
• Deliberate attention to N-1 condition planning and power outage coordination. If a pot line was de-energized it could freeze up in a matter of hours and would need to be rebuilt.
Project Status • Project is substantially complete and Alcoa is being serviced
through project improvements • 230kV yard & transformer modifications completed • New 115kV power transformer & bus connections completed • McKenzie & Valhalla 13.8kV yard modifications completed • New capacitor bank and relocations completed • Remote Telemetry Unit & revenue meter completion • Cable tray expansions completed • Remaining work:
– Continue Valhalla protection panel installations and testing through April 2013