Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
QUEENSTOWN BUSINESS CASE KEY PROBLEMS
Queenstown Transport
Business Cases
Queenstown TC DBC
Frankton to Queenstown (NZUP) SSBC
Passenger Transport IBC
Que
enst
own
Inte
grat
ed T
rans
port P
BC
Other Business Cases
Masterplans
Town centre PBCParking IBC
Arterials IBC
Grant Rd to Kawerau Fall
Bridge IBC
Ferry IBCMRT IBC
Queenstown town centre
Frankton Queenstown
AirportQueenstown event centre
Lake Wakatipu Public Water Ferry
Services DBC
Active Travel Network SSBC
Peop
le
0
50,000
100,000
150,000
200,000
2018 20482028
GROWTH FORECAST
Resident population
Peak day visitors
Avg day visitors
CAR DEPENDENCY
CarTour coach
Bus9%
7%83%
Active modes1%
If these problems are not resolved, it is
estimated that there will be between a
$670M to $1.2 billion loss to the
Queenstown economy, over a 40 year period,
through visitors travelling elsewhere
“
“
SH6A FLOW PROFILESV
ehic
les
per
day
0
17500
19500
21500
23500
Jan JulApr DecOct
25500
27500
29500
31500
20192015 2017 Road capacity
Feb Mar May Jun Aug Sep Nov
TRAFFIC GROWTH COMPARISON
0%
10%
20%
30%
40%
2012 20182015
50%
60%
70%
Wellington SH1Queenstown SH6 Christchurch SH1
2013 2014 2016 2017 2019
Tauranga SH2 Auckland SH1
The Queenstown area is one of New Zealand’s fastest growing regions, driven by growth in population, the tourism industry and supporting activities. This growth is placing increasing pressure on infrastructure and, in particular, the transport system.
This Queenstown Business Case provides a detailed assessment of the previous work undertaken and direction set by the Queenstown integrated Transport PBC and the QTC Masterplan PBC. Both of these PBC recommended programmes, that were economically robust, sought to address the following key identified issues:
• Efficiency.
• Amenity,
• Safety,
• Resilience.
While Covid-19 has affected current growth rates, these are expected to recover by the medium term and do not compromise the findings of this business case.
The agreed investment objectives of the business case are to:
1. Provide more efficient and reliable access for people and goods that:
• Sustainably manages growth
• Reduces reliance on private vehicle travel
• Enables enhanced land use
2. Is adaptable to change and disruption
3. Enhances the livability and quality of the natural and built environment
4. Enhances safety with a goal of vision zero.
A wide range of interventions and programmes have been considered in the development of this business case. The overarching philosophy when developing the preferred programme was to shift the current reliance on the private vehicle, providing users with choice, and to have a programme that is adaptive and scalable such that a response is agile to respond to uncertainties in the future.
A key outcome of the assessment process was that additional road capacity for State Highway 6A (SH6A) between Frankton and Queenstown would be unfeasible due to cost and geotechnical challenges. Furthermore, a step change is required to achieve the 40% alternative mode share needed during the PM peak on SH6A by 2028 to meet the investment objectives.
The recommended programme has therefore identified a mixture of infrastructure, public transport and travel behaviour change improvements for implementation.
Why invest?
• Peak day residential population is forecast to grow fromapproximately 120,000 in 2018 to 200,000 in 2048.
• SH6A practical capacity was exceeded on 140 daysin 2019 resulting in high levels of delay and congestion.
• Private car trips make up 83% of trips on SH6A which isnot sustainable impacts resident and visitor growth opportunities, efficiency, amenity, safety and network resilience.
• An estimated $ 670 million to $1.2 billion loss to theQueenstown economy will occur, over a 40 year periodthrough reduced visitor arrivals and/or activity.
Spatial Plan
Spatial Plan
Attachment A
91
QUEENSTOWN BUSINESS CASE PROGRAMME DEVELOPMENT
The development of the recommended programme involved an iterative optioneering process alongside stakeholders representing local Iwi, businesses, and community groups, as follows:
• More than 300 options were put forward (240 ideas for Queenstown Town Centre and 140 ideas for Frankton to Queenstown).
• Options that did not meet at least one of the project’s Investment Objectives were omitted. The remaining interventions were then categorised into 9 ‘strawman’ shortlist packages, ranging from car-focused to public-transport focused.
• The original scope was extended to include Frankton and Ladies Mile to provide a comprehensive assessment of the Wakatipu Basin transport system
• Integration with the Queenstown Spatial Plan, through regular communication with the spatial plan team.
• The best performing components of each package would then be reassembled into an optimised preferred programme.
SUMMARY OF FUNDING SOURCES (10 YEAR PROGRAMME)
NZUP
$107m
ORC$269m
CIP$119m
QLDC$151m
Waka Kotahi
$26m
The Benefit-Cost Ratio for the committed programme phases
of the overall project is 2.3
“ “Do nothing
Do Minimum + RTI
QTC masterplan preferred
Private vehicle friendly
Optimise existing
Public transport friendly
Get about with ease
Urban hub
Cars not needed
117
127
248
161
211
276
300
Relative Score
266
304
9
8
5
7
6
3
2
Ranking
4
1
Note: not in ranked order
Mor
e ca
r ba
sed
More PT
based
SHORTLIST MULTI-CRITERIA ANALYSIS
IO1 IO2 IO3 IO4
NZ Upgrade Programme and CIP funding was also secured in 2020 which has reduced the overall funding requirements of this business case.
Implementation of the recommende programme will enable the full value of these investments to be realized. The integrated programmed has therefore been shown in three parts:
1. Committed Activities,
2. Supporting Activities: Where funding is sought (2021-2027 NLTP Periods), and
3. Other Activities: Where programme endorsement is sought (2027+)
4. Other Activities: For noting only as potential future activities which will be subject to further evaluation.
Longlist300+ elements
Full Priority$300M
Offline Priority$5M
ShortlistingDeveloped 9 packages
Emerging Programme
Preferred Programme
Infr
astr
uctu
re
PT
Ser
vice
Trav
el B
ehav
iour
Cha
nge
RecommendedProgramme
NZUP+ CIP
*
1
Do
Not
hing
2
Do
Min
imum
with
RTI
3
QTC
Mas
terp
lan
Pre
ferr
ed
4
Priv
ate
Vehi
cle
Frie
ndly
5
Opt
imis
e Ex
istin
g
6
Pub
lic T
rans
port
Frie
ndly
7
Get
Abo
ut w
ith E
ase
8
Urb
an H
ub
9
Peop
le o
ver C
ars
*Approved 2019
Scope extended to include: Frankton +Ladies Mile
Mode Share Requirements Confirmed40% by 2028 l 60% by 2048
RECOMMENDED OPTION - 10 YEAR PROGRAMME
$114M
PT Services and Infrastructure
$162M $374M 2.3NZUP Enabled PT ServicesStanley + Shotover StreetsQueenstown Bus Hub
Programme60-year NPV
Cost BenefitBCR
Full ProgrammeNZUP Enabled PT ServicesStanley + Shotover StreetsQueenstown Bus HubTown Centre Upgrades - Stage 2Queenstown Arterial - Stage 2Queenstown Arterial - Stage 3
LIFETIME PROGRAMME - 50 YEAR
$295M $445M 1.5
$187M 1.6Offline public transport (inc. Frankton Bus Hub)
EXPENDITURE PROFILE (10 YEAR PROGRAMME)
$0
$20m
$40m
$60m
20252022 2028
$80m
Waka Kotahi NZUP CIP
2021 2023 2024 2026 2027 2029
QLDC ORC
$100m
$120m
$140m
$160m
Includes Crown and QLDC funding for Arterials – Stage 1 and Town Centre Street Upgrade – Stage 1
92
QUEENSTOWN BUSINESS CASE PREFERRED PROGRAMME
2018 2021 2024 2027 2030+
Arterial developments Area improvementsPublic transport
PT ServicesSH6A
Improvements
Travel Demand Management
package
Travel Demand Management
package
Travel Demand Management
package
Ladies Mile Improvements
Town Centre Upgrade – Stage 1
Town Centre Upgrade – Stage2
Travel Demand Management
package
Offline PT Service ImprovementsPT Services
Behavioural Change
Programme Endorsement Sought Funding Sought
Funding Sought
Stanley Street and Shotover Street Improvements
Funding Sought
Funding Sought
Funding Sought
Stanley StreetBus Hub
Funding Sought
NZUP
GR2KFB Improvements
NZUP
CIP
NZUP
Programme Endorsement Sought
On Road PT Service Improvements
Programme Endorsement Sought
Programme Endorsement Sought
Programme Endorsement Sought
Arterials – Stage 1 Arterials – Stage 2 Arterials – Stage 3
Funding SoughtCIPProgramme
Endorsement Sought
Outcomes
Preferred Programme• Town Centre – Arterial Stage 1 and streetscape upgrades.
• SH6A Corridor Improvements – Targeted PT priority and intersection improvements.
• SH6 Ladies Mile Corridor Improvements - Targeted PT priority and intersection improvements.
• SH6 Improvements - Targeted PT priority, intersection improvements, town centre upgrades and an upgrade to the existing Frankton bus hub.
• Other infrastructure – Stanley Street PT Hub, Arterials Stage 2 and Stage 3, increased active mode amenity.
• Public Transport Services – Enhanced PT fleet, Ferry services and PT hubs.
• Travel Behavioural Change – Travel demand management and parking management.
In summary, the proposed interventions will deliver the following key benefits and fufill the projects investment objectives:
• Corridor capacity increases in excess of 100% on the most constrained parts of the network will allow the Queenstown area to continue the grow and flourish as a tourist destination of international standing and a high quality place to live. This is estimated to unlock between $670M and $1.2 billion of economic growth.
• The delivery of a BRT based transport system, coupled with travel demand management measures, will improve travel times across the network by over 20%, along with significant reliability improvements.
• The suite of improvements in the town centre will increase the quality of the built environment stimulating development.
• Safety and access improvements across the network.
0
1000
2000
3000
3500
2021-2025 2031-20352026-2030
SH6A MOVEMENT CAPACITY
Car capacity(at capacity now)
Bus spare capacity
Forecast PT demand
Forecast people movement
Peop
le
500
1500
2500
2036-2040
MODEL SH6A TRAVEL TIMES 11AM-12PM
2018 2028 2048
2
4
6
8
0
Tra
vel T
ime
(min
)
Maximum
Average
Minimum
10
12
14
16
2028 Do-Min 2028 Preferredprogramme
Increase PT capacity incrementally*
*Interventions scheduled to achieve value for money and address capacity constraints
• Infrastructure to support PT services
• Town centre traffic reduction
• Town centre urban realm improvements
Outcomes
• Improved PT capacity
• Town centre hub
• Further town centre improvements
• BRT services
• Step change in PT capacity
• Further town centre traffic reduction
• Offline PT providing additional capacity
93
QUEENSTOWN BUSINESS CASE ADDITIONAL INFORMATION AND NEXT STEPS
Delivery approach:As part of the NZUP and CIP funding, an alliance approach has been agreed between the investment partners for delivery of these critical infrastructure projects.
Key risks:Risk allocation is dependent on the procurement approach and delivery model. For the projects that are delivered through the traditional approach it is expected that most risks would remain with QLDC or Waka Kotahi, but for the alliance it is expected that many of the risks would be transferred to the alliance.
A key philosophy is that the risks will be allocated to the organisation that is best placed to manage them. This requires that the individual projects develop their own risk registers for their next stage (under the traditional approach). These would be managed together under an alliance.
The key risks outlined in the commercial case for the recommended programme are:
1. That even with the infrastructure and service improvements in place the minimum mode shift target is not achieved to maintain a functioning transport as behavioural change to travel by non-car -modes has not occurred. Mitigation includes recommending a wider transport package with travel demand management and behavioural change initiatives developed and implemented.
2. That we are not be able to rely on the compulsory acquisition provisions of the Public Works Act to acquire all the land needed in time for planned construction start date, noting that here is a significant number of portions of privately owned land that is required for the package. This could cause delay to the programme. Mitigation includes the early development of the project property strategy and the early identification of the required properties for discussions to begin with property owners. Consideration of staging of construction also may help to minimise the delay from property acquisition.
3. There is a risk that the costs increase as more detailed assessment and investigation is complete. Mitigation of this risk includes the business case work going into a high level of detail to reduce this risk. Also, the parallel estimate currently being undertaken will provide a greater level of certainty with the project cost.
Next steps:1. The Queenstown Business Case programme is endorsed by the by Way to Go partners
2. A data improvement plan and final benefit realisation plan is delivered and signed off by the Way to Go Board
3. A parking implementation plan is delivered by Queenstown Lakes District Council, that is consistent with the Parking Strategy and able to support the ambitious mode share targets.
4. That a Travel Demand Management SSBC is progressed with urgency
5. That the Public Transport Services DBC is progressed with urgency.
Artists impression94
5aa. Queenstown Transport Business Case Poster