4
QUEENSTOWN BUSINESS CASE KEY PROBLEMS Queenstown Transport Business Cases Queenstown TC DBC Frankton to Queenstown (NZUP) SSBC Passenger Transport IBC Q u e e n s t o w n I n t e g r a t e d Tr a n s p o r t P B C O t h e r B u s in e s s C a s e s M a s t e r p l a n s Town centre PBC Parking IBC Arterials IBC Grant Rd to Kawerau Fall Bridge IBC Ferry IBC MRT IBC Queenstown town centre Frankton Queenstown Airport Queenstown event centre Lake Wakatipu Public Water Ferry Services DBC Active Travel Network SSBC People 0 50,000 100,000 150,000 200,000 2018 2048 2028 GROWTH FORECAST Resident population Peak day visitors Avg day visitors CAR DEPENDENCY Car Tour coach Bus 9 % 7 % 83 % Active modes 1 % If these problems are not resolved, it is estimated that there will be between a $670M to $1.2 billion loss to the Queenstown economy, over a 40 year period, through visitors travelling elsewhere SH6A FLOW PROFILES Vehicles per day 0 17500 19500 21500 23500 Jan Jul Apr Dec Oct 25500 27500 29500 31500 2019 2015 2017 Road capacity Feb Mar May Jun Aug Sep Nov TRAFFIC GROWTH COMPARISON 0% 10% 20% 30% 40% 2012 2018 2015 50% 60% 70% Wellington SH1 Queenstown SH6 Christchurch SH1 2013 2014 2016 2017 2019 Tauranga SH2 Auckland SH1 The Queenstown area is one of New Zealand’s fastest growing regions, driven by growth in population, the tourism industry and supporting activities. This growth is placing increasing pressure on infrastructure and, in particular, the transport system. This Queenstown Business Case provides a detailed assessment of the previous work undertaken and direction set by the Queenstown integrated Transport PBC and the QTC Masterplan PBC. Both of these PBC recommended programmes, that were economically robust, sought to address the following key identified issues: Efficiency. Amenity, Safety, Resilience. While Covid-19 has affected current growth rates, these are expected to recover by the medium term and do not compromise the findings of this business case. The agreed investment objectives of the business case are to: 1. Provide more efficient and reliable access for people and goods that: Sustainably manages growth Reduces reliance on private vehicle travel Enables enhanced land use 2. Is adaptable to change and disruption 3. Enhances the livability and quality of the natural and built environment 4. Enhances safety with a goal of vision zero. A wide range of interventions and programmes have been considered in the development of this business case. The overarching philosophy when developing the preferred programme was to shift the current reliance on the private vehicle, providing users with choice, and to have a programme that is adaptive and scalable such that a response is agile to respond to uncertainties in the future. A key outcome of the assessment process was that additional road capacity for State Highway 6A (SH6A) between Frankton and Queenstown would be unfeasible due to cost and geotechnical challenges. Furthermore, a step change is required to achieve the 40% alternative mode share needed during the PM peak on SH6A by 2028 to meet the investment objectives. The recommended programme has therefore identified a mixture of infrastructure, public transport and travel behaviour change improvements for implementation. Why invest? Peak day residential population is forecast to grow from approximately 120,000 in 2018 to 200,000 in 2048. SH6A practical capacity was exceeded on 140 days in 2019 resulting in high levels of delay and congestion. Private car trips make up 83% of trips on SH6A which is not sustainable impacts resident and visitor growth opportunities, efficiency, amenity, safety and network resilience. An estimated $ 670 million to $1.2 billion loss to the Queenstown economy will occur, over a 40 year period through reduced visitor arrivals and/or activity. S p a t i a l P l a n S p a t i a l P l a n Attachment A 91

Zu v QUEENSTOWN BUSINESS CASE KEY PROBLEMS...business case. The agreed investment objectives of the business case are to: 1. Provide more efficient and reliable access for people and

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • QUEENSTOWN BUSINESS CASE KEY PROBLEMS

    Queenstown Transport

    Business Cases

    Queenstown TC DBC

    Frankton to Queenstown (NZUP) SSBC

    Passenger Transport IBC

    Que

    enst

    own

    Inte

    grat

    ed T

    rans

    port P

    BC

    Other Business Cases

    Masterplans

    Town centre PBCParking IBC

    Arterials IBC

    Grant Rd to Kawerau Fall

    Bridge IBC

    Ferry IBCMRT IBC

    Queenstown town centre

    Frankton Queenstown

    AirportQueenstown event centre

    Lake Wakatipu Public Water Ferry

    Services DBC

    Active Travel Network SSBC

    Peop

    le

    0

    50,000

    100,000

    150,000

    200,000

    2018 20482028

    GROWTH FORECAST

    Resident population

    Peak day visitors

    Avg day visitors

    CAR DEPENDENCY

    CarTour coach

    Bus9%

    7%83%

    Active modes1%

    If these problems are not resolved, it is

    estimated that there will be between a

    $670M to $1.2 billion loss to the

    Queenstown economy, over a 40 year period,

    through visitors travelling elsewhere

    SH6A FLOW PROFILESV

    ehic

    les

    per

    day

    0

    17500

    19500

    21500

    23500

    Jan JulApr DecOct

    25500

    27500

    29500

    31500

    20192015 2017 Road capacity

    Feb Mar May Jun Aug Sep Nov

    TRAFFIC GROWTH COMPARISON

    0%

    10%

    20%

    30%

    40%

    2012 20182015

    50%

    60%

    70%

    Wellington SH1Queenstown SH6 Christchurch SH1

    2013 2014 2016 2017 2019

    Tauranga SH2 Auckland SH1

    The Queenstown area is one of New Zealand’s fastest growing regions, driven by growth in population, the tourism industry and supporting activities. This growth is placing increasing pressure on infrastructure and, in particular, the transport system.

    This Queenstown Business Case provides a detailed assessment of the previous work undertaken and direction set by the Queenstown integrated Transport PBC and the QTC Masterplan PBC. Both of these PBC recommended programmes, that were economically robust, sought to address the following key identified issues:

    • Efficiency.

    • Amenity,

    • Safety,

    • Resilience.

    While Covid-19 has affected current growth rates, these are expected to recover by the medium term and do not compromise the findings of this business case.

    The agreed investment objectives of the business case are to:

    1. Provide more efficient and reliable access for people and goods that:

    • Sustainably manages growth

    • Reduces reliance on private vehicle travel

    • Enables enhanced land use

    2. Is adaptable to change and disruption

    3. Enhances the livability and quality of the natural and built environment

    4. Enhances safety with a goal of vision zero.

    A wide range of interventions and programmes have been considered in the development of this business case. The overarching philosophy when developing the preferred programme was to shift the current reliance on the private vehicle, providing users with choice, and to have a programme that is adaptive and scalable such that a response is agile to respond to uncertainties in the future.

    A key outcome of the assessment process was that additional road capacity for State Highway 6A (SH6A) between Frankton and Queenstown would be unfeasible due to cost and geotechnical challenges. Furthermore, a step change is required to achieve the 40% alternative mode share needed during the PM peak on SH6A by 2028 to meet the investment objectives.

    The recommended programme has therefore identified a mixture of infrastructure, public transport and travel behaviour change improvements for implementation.

    Why invest?

    • Peak day residential population is forecast to grow fromapproximately 120,000 in 2018 to 200,000 in 2048.

    • SH6A practical capacity was exceeded on 140 daysin 2019 resulting in high levels of delay and congestion.

    • Private car trips make up 83% of trips on SH6A which isnot sustainable impacts resident and visitor growth opportunities, efficiency, amenity, safety and network resilience.

    • An estimated $ 670 million to $1.2 billion loss to theQueenstown economy will occur, over a 40 year periodthrough reduced visitor arrivals and/or activity.

    Spatial Plan

    Spatial Plan

    Attachment A

    91

  • QUEENSTOWN BUSINESS CASE PROGRAMME DEVELOPMENT

    The development of the recommended programme involved an iterative optioneering process alongside stakeholders representing local Iwi, businesses, and community groups, as follows:

    • More than 300 options were put forward (240 ideas for Queenstown Town Centre and 140 ideas for Frankton to Queenstown).

    • Options that did not meet at least one of the project’s Investment Objectives were omitted. The remaining interventions were then categorised into 9 ‘strawman’ shortlist packages, ranging from car-focused to public-transport focused.

    • The original scope was extended to include Frankton and Ladies Mile to provide a comprehensive assessment of the Wakatipu Basin transport system

    • Integration with the Queenstown Spatial Plan, through regular communication with the spatial plan team.

    • The best performing components of each package would then be reassembled into an optimised preferred programme.

    SUMMARY OF FUNDING SOURCES (10 YEAR PROGRAMME)

    NZUP

    $107m

    ORC$269m

    CIP$119m

    QLDC$151m

    Waka Kotahi

    $26m

    The Benefit-Cost Ratio for the committed programme phases

    of the overall project is 2.3

    “ “Do nothing

    Do Minimum + RTI

    QTC masterplan preferred

    Private vehicle friendly

    Optimise existing

    Public transport friendly

    Get about with ease

    Urban hub

    Cars not needed

    117

    127

    248

    161

    211

    276

    300

    Relative Score

    266

    304

    9

    8

    5

    7

    6

    3

    2

    Ranking

    4

    1

    Note: not in ranked order

    Mor

    e ca

    r ba

    sed

    More PT

    based

    SHORTLIST MULTI-CRITERIA ANALYSIS

    IO1 IO2 IO3 IO4

    NZ Upgrade Programme and CIP funding was also secured in 2020 which has reduced the overall funding requirements of this business case.

    Implementation of the recommende programme will enable the full value of these investments to be realized. The integrated programmed has therefore been shown in three parts:

    1. Committed Activities,

    2. Supporting Activities: Where funding is sought (2021-2027 NLTP Periods), and

    3. Other Activities: Where programme endorsement is sought (2027+)

    4. Other Activities: For noting only as potential future activities which will be subject to further evaluation.

    Longlist300+ elements

    Full Priority$300M

    Offline Priority$5M

    ShortlistingDeveloped 9 packages

    Emerging Programme

    Preferred Programme

    Infr

    astr

    uctu

    re

    PT

    Ser

    vice

    Trav

    el B

    ehav

    iour

    Cha

    nge

    RecommendedProgramme

    NZUP+ CIP

    *

    1

    Do

    Not

    hing

    2

    Do

    Min

    imum

    with

    RTI

    3

    QTC

    Mas

    terp

    lan

    Pre

    ferr

    ed

    4

    Priv

    ate

    Vehi

    cle

    Frie

    ndly

    5

    Opt

    imis

    e Ex

    istin

    g

    6

    Pub

    lic T

    rans

    port

    Frie

    ndly

    7

    Get

    Abo

    ut w

    ith E

    ase

    8

    Urb

    an H

    ub

    9

    Peop

    le o

    ver C

    ars

    *Approved 2019

    Scope extended to include: Frankton +Ladies Mile

    Mode Share Requirements Confirmed40% by 2028 l 60% by 2048

    RECOMMENDED OPTION - 10 YEAR PROGRAMME

    $114M

    PT Services and Infrastructure

    $162M $374M 2.3NZUP Enabled PT ServicesStanley + Shotover StreetsQueenstown Bus Hub

    Programme60-year NPV

    Cost BenefitBCR

    Full ProgrammeNZUP Enabled PT ServicesStanley + Shotover StreetsQueenstown Bus HubTown Centre Upgrades - Stage 2Queenstown Arterial - Stage 2Queenstown Arterial - Stage 3

    LIFETIME PROGRAMME - 50 YEAR

    $295M $445M 1.5

    $187M 1.6Offline public transport (inc. Frankton Bus Hub)

    EXPENDITURE PROFILE (10 YEAR PROGRAMME)

    $0

    $20m

    $40m

    $60m

    20252022 2028

    $80m

    Waka Kotahi NZUP CIP

    2021 2023 2024 2026 2027 2029

    QLDC ORC

    $100m

    $120m

    $140m

    $160m

    Includes Crown and QLDC funding for Arterials – Stage 1 and Town Centre Street Upgrade – Stage 1

    92

  • QUEENSTOWN BUSINESS CASE PREFERRED PROGRAMME

    2018 2021 2024 2027 2030+

    Arterial developments Area improvementsPublic transport

    PT ServicesSH6A

    Improvements

    Travel Demand Management

    package

    Travel Demand Management

    package

    Travel Demand Management

    package

    Ladies Mile Improvements

    Town Centre Upgrade – Stage 1

    Town Centre Upgrade – Stage2

    Travel Demand Management

    package

    Offline PT Service ImprovementsPT Services

    Behavioural Change

    Programme Endorsement Sought Funding Sought

    Funding Sought

    Stanley Street and Shotover Street Improvements

    Funding Sought

    Funding Sought

    Funding Sought

    Stanley StreetBus Hub

    Funding Sought

    NZUP

    GR2KFB Improvements

    NZUP

    CIP

    NZUP

    Programme Endorsement Sought

    On Road PT Service Improvements

    Programme Endorsement Sought

    Programme Endorsement Sought

    Programme Endorsement Sought

    Arterials – Stage 1 Arterials – Stage 2 Arterials – Stage 3

    Funding SoughtCIPProgramme

    Endorsement Sought

    Outcomes

    Preferred Programme• Town Centre – Arterial Stage 1 and streetscape upgrades.

    • SH6A Corridor Improvements – Targeted PT priority and intersection improvements.

    • SH6 Ladies Mile Corridor Improvements - Targeted PT priority and intersection improvements.

    • SH6 Improvements - Targeted PT priority, intersection improvements, town centre upgrades and an upgrade to the existing Frankton bus hub.

    • Other infrastructure – Stanley Street PT Hub, Arterials Stage 2 and Stage 3, increased active mode amenity.

    • Public Transport Services – Enhanced PT fleet, Ferry services and PT hubs.

    • Travel Behavioural Change – Travel demand management and parking management.

    In summary, the proposed interventions will deliver the following key benefits and fufill the projects investment objectives:

    • Corridor capacity increases in excess of 100% on the most constrained parts of the network will allow the Queenstown area to continue the grow and flourish as a tourist destination of international standing and a high quality place to live. This is estimated to unlock between $670M and $1.2 billion of economic growth.

    • The delivery of a BRT based transport system, coupled with travel demand management measures, will improve travel times across the network by over 20%, along with significant reliability improvements.

    • The suite of improvements in the town centre will increase the quality of the built environment stimulating development.

    • Safety and access improvements across the network.

    0

    1000

    2000

    3000

    3500

    2021-2025 2031-20352026-2030

    SH6A MOVEMENT CAPACITY

    Car capacity(at capacity now)

    Bus spare capacity

    Forecast PT demand

    Forecast people movement

    Peop

    le

    500

    1500

    2500

    2036-2040

    MODEL SH6A TRAVEL TIMES 11AM-12PM

    2018 2028 2048

    2

    4

    6

    8

    0

    Tra

    vel T

    ime

    (min

    )

    Maximum

    Average

    Minimum

    10

    12

    14

    16

    2028 Do-Min 2028 Preferredprogramme

    Increase PT capacity incrementally*

    *Interventions scheduled to achieve value for money and address capacity constraints

    • Infrastructure to support PT services

    • Town centre traffic reduction

    • Town centre urban realm improvements

    Outcomes

    • Improved PT capacity

    • Town centre hub

    • Further town centre improvements

    • BRT services

    • Step change in PT capacity

    • Further town centre traffic reduction

    • Offline PT providing additional capacity

    93

  • QUEENSTOWN BUSINESS CASE ADDITIONAL INFORMATION AND NEXT STEPS

    Delivery approach:As part of the NZUP and CIP funding, an alliance approach has been agreed between the investment partners for delivery of these critical infrastructure projects.

    Key risks:Risk allocation is dependent on the procurement approach and delivery model. For the projects that are delivered through the traditional approach it is expected that most risks would remain with QLDC or Waka Kotahi, but for the alliance it is expected that many of the risks would be transferred to the alliance.

    A key philosophy is that the risks will be allocated to the organisation that is best placed to manage them. This requires that the individual projects develop their own risk registers for their next stage (under the traditional approach). These would be managed together under an alliance.

    The key risks outlined in the commercial case for the recommended programme are:

    1. That even with the infrastructure and service improvements in place the minimum mode shift target is not achieved to maintain a functioning transport as behavioural change to travel by non-car -modes has not occurred.  Mitigation includes recommending a wider transport package with travel demand management and behavioural change initiatives developed and implemented.

    2. That we are not be able to rely on the compulsory acquisition provisions of the Public Works Act to acquire all the land needed in time for planned construction start date, noting that here is a significant number of portions of privately owned land that is required for the package. This could cause delay to the programme.   Mitigation includes the early development of the project property strategy and the early identification of the required properties for discussions to begin with property owners. Consideration of staging of construction also may help to minimise the delay from property acquisition.

    3. There is a risk that the costs increase as more detailed assessment and investigation is complete.  Mitigation of this risk includes the business case work going into a high level of detail to reduce this risk.  Also, the parallel estimate currently being undertaken will provide a greater level of certainty with the project cost.

    Next steps:1. The Queenstown Business Case programme is endorsed by the by Way to Go partners

    2. A data improvement plan and final benefit realisation plan is delivered and signed off by the Way to Go Board

    3. A parking implementation plan is delivered by Queenstown Lakes District Council, that is consistent with the Parking Strategy and able to support the ambitious mode share targets.

    4. That a Travel Demand Management SSBC is progressed with urgency

    5. That the Public Transport Services DBC is progressed with urgency.

    Artists impression94

    5aa. Queenstown Transport Business Case Poster