Upload
trinhthu
View
218
Download
0
Embed Size (px)
Citation preview
YEW TREE VILLAGE PLANNING APPEAL AGAINST REFUSAL PROOF OF EVIDENCE BY RICHARD PETTITT
Client
S.O.G.O.S.
Brownheath House
Brown Heath Lane, Newland
Droitwich, Worcestershire
WR9 7JF
Infrastructure Planning and Design Limited
YEW TREE VILLAGE PLANNING APPEAL AGAINST REFUSAL PROOF OF EVIDENCE BY RICHARD PETTITT
Project Information
Infrastructure Planning and Design Ltd. The Coach House Blakenhall Park Barton under Needwood Burton upon Trent Staffordshire DE13 8AJ
Tel: 01283 716869
Mob: 07971 989194
Email: [email protected]
Job No. IPD-13-286
Report No. 01
Prepared By RNP
Checked By SEF/DS
Approved By RNP
Status FINAL
Issue No. 01
Date January 2014
Infrastructure Planning and Design Limited
Proof of Evidence by Richard Pettitt
1 Introduction ............................................................................................................................ 1 Qualifications and Experience ........................................................................................ 1 Scope of Evidence ............................................................................................................... 1
2 Background Conditions ....................................................................................................... 3 Site Location and Environs .............................................................................................. 3 Description of Newland Road ......................................................................................... 8
3 Traffic and Transportation .............................................................................................. 10 Appellant Transport Assessment ................................................................................ 10 Traffic Impacts on Local Highway Network ........................................................... 12 Impacts on Users of the Local Highway Network ................................................ 13
4 Highway Network Mitigation Proposals ..................................................................... 15 Highway Access Proposals ............................................................................................ 15 Critique of Proposed Pulley Lane Mitigation Measures ...................................... 16 Width of Site Access and Pulley Lane Mitigation .................................................. 19 Effective ‘Lane Full’ Capacity (Saturation Flow) ................................................... 21 Effect on Pulley Lane ....................................................................................................... 22 Junction Visibility Splays ............................................................................................... 23 Proposed Mitigation Measures ..................................................................................... 25 Layout of the improved bell-mouth junction with Primsland Way ................ 26 Topography Constraints ................................................................................................. 27
5 Site Drainage ........................................................................................................................ 31 Existing Site Drainage Issues ...................................................................................... 31 Appellants Surface Water Drainage Strategy ........................................................ 31 Critique of Surface Water Drainage Strategy ........................................................ 32 Northern Area Adjacent to Newland Road .............................................................. 34 Western Area Adjacent to Isaacs Way ..................................................................... 37 Critique of Foul Water Drainage Strategy ............................................................... 39
6 Brine Runs and Ground Conditions .............................................................................. 41 Ground Conditions as Evidenced in the Appellants Documents ..................... 41 Potential Effects on Drainage Infrastructure ......................................................... 44 Potential Effects on Highway Retaining Structures ............................................ 45
Contents Page
Infrastructure Planning and Design Limited
Proof of Evidence by Richard Pettitt
Table 3.1 13 Figure 5.1 33
Appendices Appendix A Resident’s Photographs of Horses on Pulley Lane
Appendix B Resident’s Notes & Photographs of Newland Road
Appendix C IPaD Drawings & Sections on Newland Road
Appendix D IPaD Summary of Trip Distribution Figures
Appendix E Resident’s Notes & Photographs of Footpath Through Pulley Woods
Appendix F Extract from Worcestershire County Council Design Guide
Appendix G Example Narrow Country Lane Verge Damage
Appendix H Pulley Lane Visibility Splays – Annotated Drawing
Appendix I Resident’s Photographs of Flooding on Isaacs Way
Appendix J HR Wallingford Greenfield Runoff Calculation Output
Appendix K Severn Trent Water Document
Appendix L Annotated Drawing Showing Brine Run Zones
Tables & Figures Page
Proof of Evidence by Richard Pettitt 1
1 Introduction
Qualifications and Experience
1.1 My name is Richard Pettitt, and I am presently a Director and Principal of
Infrastructure Planning and Design Limited; a company I founded in January
2010.
1.2 I hold a BSc Degree in Civil Engineering; I am a Chartered Engineer (CEng)
plus a Chartered Water and Environmental Manager (CWEM). I am a Fellow of
both the Institution of Civil Engineers and Chartered Institution of Highways
and Transportation. In addition, I am a member of the Chartered Institution of
Water and Environmental Management.
1.3 I have worked in the industry as a Civil Engineer on roads and drainage
projects for over forty years, specialising for the past 25 years in development
planning, with particular reference to transport, highways and development
infrastructure for all forms of development.
1.4 I have been a Chartered Engineer for over 30 years and a Fellow of ICE and
CIHT over 20 years.
Scope of Evidence
1.5 My Proof of Evidence is presented in association with evidence from my
colleague Stephen Stoney of Wardell Armstrong, who is dealing with planning
and other matters.
1.6 My Evidence considers the traffic and transportation impacts/effects plus
highway mitigation proposals and site drainage of both the Barberry and
Persimmon developments proposed at Yew Tree Hill, and which are the
subject of Appeals Against Refusal of Planning Permission by Wychavon
District Council.
1.7 I act for a residents group known as S.O.G.O.S. (Save Our Green Open
Spaces), as a Non-Rule 6 Party, and therefore I have not provided full copies
of documents I make reference to.
Proof of Evidence by Richard Pettitt 2
1.8 As I will set out in my group, I have concerns relating to traffic and highways
matters in the absence cases, and have attempted to discuss these concerns
with Worcestershire County Council (WCC) the highway authority. At the time
of writing and submitting this Proof, despite considerable efforts by myself,
SOGOS and WDC (Wychavon District Council), WCC has declined to discuss
these issues. My Proof has therefore been written without the benefit of a
response from WCC on the issues I feel they should have picked up at the
consultation stage on the original application.
1.9 My Proof of Evidence will critique the planning application proposals in matters
set out in paragraph 1.5 above. In particular I will deal with the Appellant
documents including:
! Transport Assessments (TA)
! Highways Mitigation Proposals
! Water Management Strategy
! Persimmon Phase 1 Appraisal (Desk Study)
Proof of Evidence by Richard Pettitt 3
2 Background Conditions
Site Location and Environs
2.1 The site is located on the southern side of Droitwich Spa; bounded on its
southern edge by Pulley Lane and Newland Lane; and existing residential
developments to the east, north and west.
2.2 The site is in an area of Droitwich Spa known as Yew Tree Hill, and from the
centre of the proposed development to Droitwich Town Centre is
approximately 2km straight-line distance.
2.3 The travel distance by car from the junction of Pulley Lane and Newland Lane
the town centre is 3.9km. The walking distance between the same points is
approximately 3km.
2.4 The existing highway network in the vicinity of the proposed development
comprises:
2.4.1. Newland Road passes through the site in a north/south direction,
splitting the development area approximately ⅔ to the east and ⅓ to
the west. Newland Road has been closed to vehicular traffic, between
Primsland Way and a point some 350m to the south, for over 20 years
(closure in May 1993). More details will be given on Newland Road
later in this Section, and the Appellant’s proposals for it in Section 4 of
my Proof.
2.4.2. From the junction of Newland Road and Newland Common Road, Pulley
Lane routes in a westward direction to its junction with the A38/Copcut
Lane, and Newland Lane routes eastwards to its junction with Tagwell
Road. Newland Common Road routes southwards, becoming Hulls
Lane, then Smite Lane and Offerton Lane, before connecting to the
A4538 just to the north of the M5 Junction 6.
2.4.3. Members of my client team (SOGOS), who have lived in the area for
some considerable time, advise me, that Pulley Lane is the main
vehicular route from the southern edge of Droitwich to the Strategic
Proof of Evidence by Richard Pettitt 4
Highway Network. Newland Lane via Tagwell Road is occasionally used
to travel to local services, as the A38 is presently a significantly
congested corridor, and with the current priority junction, is difficult to
exit onto the A38, particularly towards the north. I have verified this
through site visits assessing journey times for various routes using
appropriate software.
2.4.4. Pulley Lane is relatively narrow, being between 4.8m and 5.5m in
width (also noted as such in the Appellant’s evidence), with no
footways or street lighting. It has a poor alignment with blind bends,
generally narrow grass verges and substantial hedgerows. Whilst cars
and light vans can pass with care, anything larger (HGVs and larger
farm vehicles) can require one of the vehicles to "mount" the grass
verge if sufficient verge exists, or wait in a field access to safely pass
each other.
2.4.5. Newland Road through the site and Newland Common Road routing to
the south is a primary SUSTRANS cycle route No. 45, and is a lane of
similar dimensions and characteristics to Pulley Lane.
2.4.6. It should be noted that the closed section of Newland Road, from
Primsland Way for some 330m towards the south, is of the order of
2.4m to 2.7m wide (surfaced width), and hence despite its name of
“Road” it is little more than a generous footpath.
2.4.7. As well as being frequently used cycle routes, Newland Common Lane,
Pulley Lane and Newland Road are also used by the two nearby equine
riding/stables businesses. This results in regular cyclist and horse-
riding activity along these lanes. Examples of the uses of Pulley Lane
by horse riders and pedestrians are shown in three photographs
provided by a local resident (taken on 21st December 2013) and which
are attached in Appendix A.
2.4.8. Indeed, even with the present traffic levels there have been incidents
in recent years that typify the danger. On 29 December 2007, a short
Proof of Evidence by Richard Pettitt 5
distance along Newland Common Road from its junction with Pulley
Lane, a horse was killed and a man walking with the horse and another
person was seriously injured when a motor vehicle struck the horse.
The BBC report on the incident is quoted below:
Crash injures man and kills horse
A man has been seriously injured and a horse was killed after
being hit by a car in Worcestershire.
West Midlands Ambulance Service said it received a number of calls
after the incident in Newland Common Road, Droitwich, about 1045
GMT on Saturday.
It is understood that a 4x4 vehicle hit the man who was walking
behind the horse with another pedestrian.
The man, believed to be in his 30s, suffered serious head, shoulder
and leg injuries. He was flown to hospital.
A woman riding the horse which died and a 15-year-old girl riding
another horse in the group were uninjured.
A West Midlands Ambulance Service spokesman said the driver of the
car was checked at the scene by ambulance staff but did not require
hospital treatment.
The spokesman added: "A vet that was called to the scene confirmed
the horse had died in the accident."
2.4.9. The two riding/livery stables establishments close to the proposed
development are:
! Equestrian Communications and Training, Oakley Farm, Pulley
Lane
! Newland House Farm Livery, Newland Common Road
Proof of Evidence by Richard Pettitt 6
2.4.10. The incident reported in 2.4.8 above occurred near the entrance to
Newland House Farm Livery.
2.4.11. With a major increase in traffic (I will make detailed comments in
Section 3 of this Proof regarding the traffic increase on Pulley Lane),
the danger to equestrian activity on these roads would escalate
exponentially. This could significantly affect the ability of these
businesses to carry on using the local roads, as it may well be decided
that the risks associated would be too great. My colleague Stephen
Stoney will be taking this point further by considering the social and
commercial impacts.
2.4.12. Cyclists would also be at significant risk using these presently quiet
country lanes, should the developments proceed as presently
proposed. In the original proposals, now no longer proposed, the
upgrade Pulley Lane was to be improved substantially for cyclists and
horses as follows:
! Widened to 6.5 m
! Improving forward visibility at some of the bends
! Realignment at some of the bends to a larger radius
! Provision of cycle lanes (on carriageway with appropriate road
markings) on both sides for some of the route between Newland
Road and the A38
2.4.13. In paragraph 5.2.8 of the May 2011 TA, it is stated “The aim of these
works is to provide a more amenable environment for all road users
and facilitate a future reduction of the posted speed limit on Pulley
Lane to 40mph”. The TA further states in paragraph 5.2.9 that the
Highway Authority has agreed in principle to the proposed strategy.
2.4.14. At paragraph 2.2 of the July 2012 Addendum TA, it is stated that “The
overall off-site mitigation package as set out below is identical to that
already agreed with the Highway Authority and Highways Agency for
the previous larger proposals”. However the Addendum TA goes on to
Proof of Evidence by Richard Pettitt 7
outline a very different approach for the mitigation package on Pulley
Lane.
2.4.15. The amended proposals that are subject of these two co-joined
Appeals, following the two Appellants separating their development
proposals into two entities, are significantly different in respect of
Pulley Lane. There is NOT now a proposal to widen Pulley Lane to
6.5m and/or provide cycle lanes at either side (see drawings in the
addendum TA Nos. 10154-68 to 10154-74 inclusive). This issue will be
dealt with in more detail in Section 4 of my Proof.
2.4.16. This change of stance has probably been brought about by the
assertion in the Addendum TA July 2012 in paragraph 4.3, that “as set
out in the original TA there is no forecast pedestrian or cycle demand
from the site on this section of the road” I am unable to find any such
reference in the original TA, and in any event it is in direct
contradiction with the May 2011 TA where at paragraph 4.4.8 and the
related drawing, it is stated that Pulley Lane is classified as a ‘local
cycle route’, which links SUSTRANS Route 45 with the A38 and other
routes to the West.
2.4.17. Indeed, much of Section 4.4.1 to 4.4.9 of the Appellant’s original TA
indicates that there would be substantial opportunities for cyclists to
access other routes via Pulley Lane, some of which would naturally be
via the ‘local cycle route’ along Pulley Lane. I will give further evidence
on this issue in Section 4 where I deal with the proposed mitigation
measures.
2.4.18. The original TA suggests that the proposed amendment to Pulley Lane
(referred to in paragraph 2.4.13 above) encourages slower speeds and
thus justifies the proposal for a Traffic Regulation Order (TRO) to
reduce the limit from the current 60mph to 40mph. However, with the
abandonment of the mitigation proposals described as justifying the
speed reduction, it could be questioned whether the proposed TRO
would be successful?
Proof of Evidence by Richard Pettitt 8
Description of Newland Road
2.5 The form of Newland Road, especially along the section presently closed to
vehicular traffic, is extremely constrained. Indeed, as stated earlier, with a
width of surfaced pavement between 2.4m and 2.7m, it is little more than a
footpath. One of the local residents, and a member of SOGOS, has provided a
useful photographic and descriptive note on the nature of Newland Road
particularly the part that is proposed to be reopened as a route for for public
transport and emergency services vehicles as well as the pedestrians and
cyclists it already accommodates. This factual note is attached to my Proof as
Appendix B.
2.6 It is clear from the photographs, and which can be verified by the Inspector at
a site visit, that the embankment to the both the east and west sides of
Newland Road are heavily vegetated and it seems clear from the steep slopes
that the extensive root structures are binding the soil to keep it stable at such
a steep angle of repose.
2.7 Paragraph 8 of the note at Appendix B identifies that the land to the east,
opposite No 27 Yew Tree Hill, is several metres higher than Newland Road. At
this point the Appellant proposes that Newland Road would be realigned such
that the eastern kerb-line would be 12m to the east of the existing western
boundary of Newland Road.
2.8 Photographs F and G in particular show the steep embankments with
extensive vegetation on either side of Newland Road. The proposed widening
would completely remove one side of the existing lane, which comprises a
steep and high embankment.
2.9 A small section of Ordnance Survey digital mapping and LIDAR level data (2m
grid and 100mm level accuracy) has been obtained and augmented by a
professional topographical survey to ensure accuracy on the key sections, and
I attach a contoured plans of the proposals at the northern end of Newland
Road at Appendix C. These plans shows the extreme level changes that occur
along the section of Newland Road in question, which corroborates the content
of the note in Appendix B.
Proof of Evidence by Richard Pettitt 9
2.10 I will consider the feasibility and effects of the proposals for Newland Road in
Section 4 of my Proof.
Proof of Evidence by Richard Pettitt 10
3 Traffic and Transportation
Appellant Transport Assessment
3.1 My company, IPaD Limited, has undertaken a review of the information
presented within the Transport Assessment dated 6th May 2011 as provided
by David Tucker Associates (DTA) in support of proposals for a new residential
development located off Pulley Lane to the south of Droitwich, Worcestershire.
3.2 The results of our analysis indicate that:
3.2.1. We consider the Person Trip rates derived by DTA from TRICS are
reasonably robust.
3.2.2. We accept the use of the National Travel Survey (NTS) to derive a
breakdown of person trips by journey purpose.
3.2.3. Whilst we question the use of the NTS as a means to accurately
derive baseline mode share estimates for trips of different purposes,
the resulting baseline estimates of vehicle traffic generation generated
by DTA for the development appear robust.
3.2.4. There are errors apparent within the TA with regards to the routing
assumptions suggested within the main narrative of the document, as
it appears that they do not accord with the trip distribution routing
diagram shown in Appendix K (of the DTA TA). We would agree with
the distribution depicted on the routing diagram.
3.2.5. A routing assumption has been used by DTA whereby a large
proportion of development traffic that wishes to route towards
destinations to the north of Droitwich (i.e. Bromsgrove and M5
Northbound) does so by routing eastbound along Pulley Lane from the
site entrance rather than by routing towards the A38. This contravenes
the assumptions presented within the accompanying trip distribution
diagram presented within Appendix K (of the DTA TA). This shows that
all trips except those to Droitwich East would route via Pulley Lane to
the west via the A38 junction.
Proof of Evidence by Richard Pettitt 11
3.2.6. No specific evidence is presented to confirm the accuracy of the above
distribution assumption other than to state that shortest journey time
path analysis was calculated between journey O-D (Origin –
Destination) pairs within ArcView. If this is the case, it does not appear
that the analysis takes account of the betterment in journey time that
would be achieved from delivery of the new signalised road junction at
the A38/Pulley Lane junction that would reduce delay time for vehicles
wishing to access out onto the A38 from Pulley Lane to around 35
seconds according to DTA’s own assessments.
3.2.7. There are inaccuracies within the distribution table contained within
Table 23 of the TA, with particular issues in attempting to define how
the traffic would distribute along Pulley Lane. It is unclear how
westbound flows along Pulley Lane have been calculated within the
table, as the flows do not appear to tie in with the flows presented in
the table for other junctions that would be accessed via Pulley Lane
west.
3.2.8. A knock-on effect of the additional traffic that I consider would route
via Pulley Lane (West), is that the LINSIG analysis of the performance
of the proposed signalization of Pulley Lane/A38/Copcut Lane junction,
would no longer be correct. It would be important that the analysis be
re-run with corrected figures for all scenarios, as the junction may well
be overcapacity in many of them.
3.2.9. The TA has looked at several scenarios, using DTA baseline trips,
development with Travel Plan based trips, and trip rates according to
Halcrow (acting for the HA). It is not clear how errors in the
distribution analysis may have affected the results and justification for
the operation of the proposed signals. I therefore suggest to the
Inspector that as stated above, the analysis work done for the signals
should be revisited based upon the corrected trips on Pulley Lane
(West).
Proof of Evidence by Richard Pettitt 12
Traffic Impacts on Local Highway Network
3.3 My colleagues at IPaD and I have undertaken our own routing analysis using
widely available route analysis software to define the most appropriate
distribution of traffic to/from the site and it would appear that predicted flows
along Pulley Lane West within the DTA have been heavily underestimated.
DTA calculate that two-way flows along Pulley Lane West (Towards A38) would
be in the region of 287 (AM Peak) and IPaD calculate two-way flows along this
route using the corrected distribution as being 378 (AM Peak), which is 32%
higher.
3.4 An analysis of the pm peak traffic flows on Pulley Lane, again using DTA’s own
Travel Plan based trip rates but the corrected distribution, would be 346 two-
way trips rather than 246 in the TA which is 41% higher.
3.5 In order to explain this as clearly as possible, I refer to the tables and
diagrams contained in Appendix D which shows the following (N.B. all trip
numbers are based upon the DTA travel plan rates):
! The first table takes the correct distribution, as derived from the
trip assignment diagram in Appendix K of the May 2011 TA
document, and shows the number of development trips on each
route.
! The two central trip assignment diagrams show how the above
trips would distribute around the network for both AM and PM
traffic peak periods.
! The final table and diagram relate the corrected trip assignments
and how they would distribute to the three possible routes to and
from the development for vehicular traffic.
3.6 It is from this final table that I draw the corrected development AM and PM
vehicular trips on Pulley Lane of:
! 378 two-way AM peak
! 346 two-way PM peak
Proof of Evidence by Richard Pettitt 13
3.7 Even if we were to take the lower DTA calculated two-way figures for Pulley
Lane West the increases in traffic volume along this link as a result of the new
development would result in a 642% increase in flows along this route during
the AM peak period as compared to existing levels.
3.8 Using the IPaD calculated routing assumptions (which broadly accord with the
distribution assumptions shown on DTA’s diagram in Appendix K) the increase
in AM Peak traffic volumes along Pulley Lane West as compared to existing
levels is more likely to be 873%, which is 36% higher than DTA’s figures.
3.9 Table 3.1 below shows the existing, predicted development and predicted total
vehicular flows, together with percentage differences:
DTA TA RNP Proof
Two-Way Flows am pm am pm
Existing Flows 44 39 44 39
Development Flows 287 246 378 346
Totals 331 287 422 385
Increase 652% 631% 859% 887%
Average Increase 642% 873%
Percentage Addition 36% additional
Table 3.1
3.10 In summary, whilst I have some reservations on the methodology, the trip
rate and mode-share data appears to be reasonable estimates. However,
there are errors in the TA when it calculates the distribution of the
development traffic, such that I consider there would be considerably more
traffic likely to use Pulley Lane than DTA suggests. There would also be
correspondingly less predicted trips on Tagwell Road and Newland Common
Road
Impacts on Users of the Local Highway Network
3.11 I am focusing on the impacts for users of Pulley Lane (West) as this would be
the most affected corridor by some considerable margin.
3.12 The predicted 873% (average AM/PM) increase in traffic movements would
clearly have a major effect on the existing residents, businesses and users of
Proof of Evidence by Richard Pettitt 14
Pulley Lane. To put this change into perspective, the average number of two-
way vehicle movements on Pulley Lane (West) in the morning peak hour
would be:
! Existing 44 one every 1 min 22 sec
! With Dev. 422 over 7 trips per min / 1 every 8.5 sec
3.13 With the frequency of vehicle movements rising from one every 1min 22sec to
one every 8.5sec, it is easy to see how the occurrences of vehicles passing
would rise considerably. This would equate to the general public perceiving
traffic in peak hours as almost being a continuous stream of vehicles
compared to current conditions.
3.14 For businesses currently using Pulley Lane, especially those with larger
vehicles such as farming/equine related businesses; the effect is likely to be
severe. Although guidance would suggest that a road width of 5.5m would be
sufficient for cars and lorries passing, or even two lorries passing very closely
(Manual for Streets Issue 1 page 79), this is based upon a properly designed
street with kerbs, lighting and off-road pedestrian facilities.
3.15 Pulley Lane would not be a road of this nature, and the substantial increase in
traffic would have a major effect, and I will deal with this issue further next
section of my Proof.
3.16 The width required for two HGVs to pass is in practice more than 5.5 m. The
standard web of an HGV (Worcestershire county council design guide) is 2.55
m excluding mirrors. Mirrors can protrude by 200 mm from the vehicle. If it is
assumed that two lorries are passing, the exact width of the two is 2.55m +
0.2m + 0.2m + 2.55m = 5.50m. Thus I would argue that a carriageway width
of 5.5 m for two HGVs passing is a theoretical and not a practical proposition.
Proof of Evidence by Richard Pettitt 15
4 Highway Network Mitigation Proposals
Highway Access Proposals
4.1 The original proposal, when both Appellants were promoting Yew Tree Village
jointly, was for the whole development to access/egress vehicular traffic on to
Pulley Lane and Newland Lane from the internal loop road. When the
development proposals were amended shortly before submission of planning
applications, the same two points of access are still proposed but the internal
layouts are no longer formally connected, for vehicular traffic at the boundary
between Barberry and Persimmon.
4.2 The main change in traffic movements to and from the site that this creates, is
that for the larger Barberry development (500 residential units plus 200 care
units and a local centre) would only be able to use the Pulley Lane access.
4.3 The Persimmon site would wholly access the public highway network from
Newland Lane, at a point some 285m east of the Pulley Lane/Newland
Common Road/Newland Lane crossroads junction. Whilst there is a note on
the Appellant’s masterplan drawings (drawing reference P.0742_09A) to the
effect that there may potentially be a link between the two sites, this is not
guaranteed.
4.4 In the event, whether or not the two parts of the site are connected for
vehicular traffic would not significantly alter my conclusions related to this
point.
4.5 In my opinion the ‘desire line’ for traffic travelling to and from the proposed
development would largely utilise Pulley Lane (West) and the junction with the
A38 that is proposed to be signalised as part of the mitigation works. This is
explained in more detail in section 3.2 of this Proof. The original mitigation
proposals recognised that the majority of traffic movements to and from the
site would take this route, and proposed an upgrade package on Pulley Lane
as shown in the drawings in Appendix E of the original TA (drawing reference
10154-58 to 10154-60 inclusive):
Proof of Evidence by Richard Pettitt 16
4.6 In the revised proposals related to the Appeals A & B, which are the subject of
this Inquiry, the proposals for Pulley Lane changed substantially. The lane is
no longer to be widened to 6.5m; rather it is to be regularised to its current
maximum of 5.5m, and would not feature the earlier proposed cycle
provisions. The improvements at some of the bends remain, yet the worst
section (situated between 150 and 250 metres from the A38 junction) has no
improvement proposed other than warning signs and features.
4.7 Dropping the proposal to widen Pulley Lane from 6.5m to 5.5m is an
unexpected change considering that there would be quite a small difference in
the distribution of traffic as resulting from the ‘split’ between the two elements
of the development. Even more surprising is the shift away from cyclist
provision. These amended proposals in the application being appealed are
justified by the assertion in paragraph 4.3 of the Addendum TA July 2012, that
“as set out in the original Transport Assessment there is no forecast
pedestrian or cycle demand from the site on this section of the road” In my
opinion the latter is not a valid assertion considering that the Appellant's own
evidence states that Pulley Lane is a main cycle route link as I have set out in
paragraph 2.3.12 of my Proof. Nor can I find such a reference to there being
no forecast demand in the Appellant’s original TA as suggested.
Critique of Proposed Pulley Lane Mitigation Measures
4.8 The proposed mitigation works on Pulley Lane have been reviewed and I make
the following observations and conclusions:
Dropping Proposed Cycle/Pedestrian Facilities
4.9 The proposed width of Pulley Lane is 5.5m in the Appeal applications for the
majority of the section between the proposed site and its junction with the
A38. This is shown on a series of drawings in the July 2012 Addendum TA
Appendix A. The Appellants consultant states (Para 4.3 Addendum TA - “A
number of different options for improvements to the route have been
discussed with the County Council. It has now been agreed that the
development will procure the widening of the road to a minimum of 5.5m.”).
Proof of Evidence by Richard Pettitt 17
4.10 The consultant goes on to justify the loss of cycle provision (Para 4.4
Addendum TA - “As set out in the original Transport Assessment there is no
forecast pedestrian or cycle demand from the site on this section of the road.
The site also provides for the ability to significantly improve the Sustrans route
which passes through the site and facilitate alternative routes for existing
cyclists wishing to travel east–west.”) and justifies the reduced mitigation
package. Having undertaken a word search on "cycle" and/or "demand", I
cannot find any reference as such.
4.11 Indeed, in Appendix J of the original TA, the predicted cycle movements from
the development would be 40 in the AM and 43 in the PM peak. It does not
appear that any assessment of the distribution of the cycle trips has been
undertaken, so the number wishing to route by Pulley Lane and Newland Lane
is presently unknown, but is unlikely to result in no demand at all as
suggested in the TA.
4.12 There does not appear to be any justification for the change other than the
assertion that cycle and pedestrian routes other than Pulley Lane exist. In
Appendix A of the addendum TA on a drawing titled ‘Yew Tree Village -
Transport Strategy’, a route is shown for cyclists travelling to the West (via
Sandles Road, Showell Road and Addyes Way). Whilst I acknowledge that this
route might be regarded as a reasonable environment for cyclists, there are
significant problems. It is not a convenient route as it winds through
residential streets and it would require all cyclists using it to negotiate the
very busy A38 five-arm roundabout; and large roundabouts are notoriously
difficult and unsafe junctions for cyclists.
4.13 I therefore do not consider that such a route being available would dissuade
cyclists from using Pulley Road (West).
4.14 In respect of pedestrians, a route is shown on the same drawing, where an
existing footpath runs through Pulley Woods between Pulley Lane and the
existing residential estate immediately to the north, and is annotated "existing
off-road footway".
Proof of Evidence by Richard Pettitt 18
4.15 This facility is accessed from a point in the south-west corner of the proposed
development, opposite the driveway to Oakley Farm and Equestrian Centre. It
appears to have one intermediate access point via a gate located to the east
of the ‘chicane’/double bend on Pulley Lane, and terminates on the A38 at a
series of small steps in a narrow gap in the hedge, located some 135m north
of the Pulley Lane junction.
4.16 A photographic record of this route is attached in Appendix E.
4.17 As previously stated, the initial proposals to make Pulley Lane west of the
development access more cycle and pedestrian friendly by widening to 6.5m
and providing cycle lanes, has been dropped. The Appellants appear to have
assumed that the existing footpath through Pulley Woods is sufficient for any
east/west pedestrian movement and that they can replace Pulley Lane as a
‘local cycle route’ with the alternative route through the adjacent housing
estate.
4.18 It is my opinion that neither of these routes is particularly attractive as
alternatives to Pulley Lane, unless of course Pulley Lane becomes too
dangerous for cyclists and pedestrians to use.
4.19 For pedestrians, particularly lone walkers, the existing footpath would be an
unattractive proposition with no escape routes and limited security overview
from residential properties. I have been advised by one of the residents that “I
would certainly not walk alone there after dark and could easily have had my
iPad stolen if a mugger had been in wait along the path today. I would not
encourage any loan female to walk along there at any time of the year let
alone after dark”. I therefore question whether it would be appropriate to
consider this to be a sensible alternative for residents of the new
development, or indeed existing pedestrians on Pulley Lane. It is also worthy
of note that the footpath is extremely waterlogged and boggy in section which
cannot really be used without waterproof boots.
4.20 I therefore question whether the appellant's proposals for Pulley Lane are
valid, when they appear to be based upon assertions regarding the use of
Proof of Evidence by Richard Pettitt 19
alternative cyclist and pedestrian facilities. It is my opinion that cyclists and
pedestrians would still use Pulley Lane (West) despite its poor standard, even
with the proposed (limited) improvements.
Width of Site Access and Pulley Lane Mitigation
4.21 I question the Appellant's position that 5.5m width is sufficient for the two site
accesses and proposed mitigation measures on Pulley Lane.
4.22 The position of the Appellants as evidenced by the various planning
submission documents is that the site highway access and proposed mitigation
works on Pulley Lane are adequate and appropriate to serve the level of
development proposed.
Compliance With Design Standards
4.23 for the internal road network within the proposed development, the
appropriate design parameters and standards we set out in the relevant
design guides. It is less clear what design standards should be used in relation
to proposed off-site highway mitigation works, but in my experience it would
be the DfT Design Manual for Roads and Bridges (DMRB). DMRB is primarily
for trunk roads and motorways, but many local highway authorities also use it
for county highway networks, in association with their own development
design guidance.
4.24 Both the WCC Design Guide (WCC-DG) and MfS design standards are written
primarily to provide guidance on internal layouts within new developments,
and in my opinion should not be applied to justify isolated specifications such
as the width of existing country lanes between a new development and the
strategic road network (SRN). In both these documents, safe and appropriate
carriageway geometry is predicated on there being footways and useable
verges such that drivers have a clearly delineated carriageway to drive within,
pedestrians are not walking within the carriageway, and that appropriate
forward visibility etc. is always available.
Proof of Evidence by Richard Pettitt 20
4.25 The A38 to the west of the site was originally a Trunk Road but is no longer
part of the SRN. However, it would be controlled in design terms by DMRB,
which has a minimum single carriageway road design width of 7.3m.
4.26 The last (in hierarchical terms) road in both appeal sites where the Barberry
and Persimmon sites access onto Pulley Lane and Newland Lane respectively,
serve significantly more than the WCC-DG limit of 200 dwellings for a cul-de-
sac. Thus the only appropriate carriageway format for the main entry/exit
roads in accordance with the design guide is a "Local Distributor" as set out in
section 2.10 of that document.
4.27 The appropriate format and design for such road is shown in Appendix F where
I give an extract from the WCC-DG. It is abundantly clear therefore, that
neither the main access roads to the developments nor the supposed
mitigation measures on Pulley Lane, are in fact in accordance with the WCC-
DG.
4.28 It is clear that the two Appeal sites (serving 500 dwellings + 200 care home
units for Barberry, and 265 dwellings for Persimmon) should both have
primary access roads that conform to the Design Guide Local Distributor
standard. A Local Distributor should be 7.3m plus a minimum of 2m width
verges and footways both sides on both developments.
4.29 For Pulley Lane, which carries more than just development traffic including
farming and other HGV traffic, the mitigation should be to a level at least of a
Local Distributor.
4.30 Whilst I have knowledge that WCC appears to have reviewed the planning
application proposals, and that given a "no objection" response, I believe that
they are wrong to have done so. In my opinion, it is abundantly clear that the
development would require a WCC highway category of Local Distributor for
the main access it to appeal sites, and adequate mitigation on Pulley Lane
would be no less than the Local Distributor standard as well.
Proof of Evidence by Richard Pettitt 21
4.31 It is therefore my opinion that the main access roads within the two
developments and treatment of Pulley Lane is not in accordance with the
WCC-DG and is therefore inadequate for the development proposals.
4.32 Therefore I consider the Appellant’s reasoning to be flawed on the following basis:
4.32.1. Pulley Lane is not an internal residential estate road with the traffic
mix that such a road would have to accommodate.
4.32.2. It is a rural lane used by a wide range of large vehicles including a
variety of farming implements and HGVs. One notable example is the
daily visit of a large milk tanker to a farm along this route. Thus I
reiterate that in my opinion that it could be argued that this route
should be designed as a ‘Local Distributor’ or the equivalent.
4.32.3. Residential roads are expected to only have the occasional refuse
vehicles or delivery vans, and not 16.5m articulated HGVs and all
manner of farming equipment.
4.33 It is clear in the case of Pulley Lane that it is not a new road that has been designed correctly in accordance with the above criteria.
Effective ‘Lane Full’ Capacity (Saturation Flow)
4.34 Mr. Tucker also seeks to justify the 5.5m road width on Pulley Lane in relation
to ‘link capacity’ of the road by reference to the statement in paragraph 6.5.1
of his original TA where he says " Whilst this is a significant increase over the
current flows on the link, the absolute volume of traffic remains modest and
well within the capacity of a 5.5m link". I have assumed this is based upon the
DMRB Chapter 13 theoretical calculation for link capacity of a 5.5m wide single
carriageway road where it states it has a maximum capacity of 920 vehicles
per hour in each direction.
4.35 As I have set out in Section 4.23 to 4.29 inclusive of my Proof, I do not
consider this is relevant to Pulley Lane which is not a standard design and
format road as set out in the guidance and does not, even with the mitigation
proposed, conform to the normal standards assumed in DMRB upon which the
link capacities are based. The normal minimum width, bendiness, forward
Proof of Evidence by Richard Pettitt 22
sight distance etc., are all well below the minimum standards DMRB considers
in deriving the figure of 920.
Effect on Pulley Lane
4.36 An important aspect that should also be taken into account is the fact that
without kerbs, and with HGVs and farm equipment using the road, increasing
the traffic volume by over 850% will have a major effect that I will
demonstrate by way of an example.
4.37 The example is use is a similar Lane that is one of four links by which a village
of approximately 2000 dwellings in total connects to a local ‘A’ classification
road. It is similar to Pulley Lane as it represents the shortest, most direct
route, albeit not the most substantial road, southbound to a main ‘A’ road. At
present the volume of traffic on this lane is of the order of 200 vehicles per
hour in the normal traffic peak periods. This lane also varies between around
4.5m and 5.5m in width, has no street lighting, no kerbs and limited width
grass verges; very similar to Pulley Lane in many respects.
4.38 Despite the theory that cars and light goods vehicles can pass ‘easily’ on such
a road, the photographic records contained in Appendix G show what in actual
fact happens.
4.39 Drivers seek to ensure they do not clash with oncoming vehicles by driving as
close as they feel comfortable to the grass verge, creating progressive rutting
as the verges are worn back and progressively destroying the verge.
4.40 The verges and sides of the road disintegrate with deep potholes forming that
encroach into the road construction. It is bad enough in dry and daylight
conditions where drivers can see the potholes in time to stop between them
whilst other vehicles pass. The problem becomes acute in the hours of
darkness and/or where puddles obscure potholes.
4.41 Drivers who regularly travel along this lane are extremely wary of the
condition of the road edges and potholes and in places the ‘effective’ road
width drops to about 3.5-4.0m, becoming a single carriageway with for all
practical purposes.
Proof of Evidence by Richard Pettitt 23
4.42 This makes the effective capacity of the road substantially less than the
theoretical ‘lane full’ capacity of 920 vehicles per hour in each direction.
4.43 I personally travel the lane I have used in the example, on average twice per
day, and I regularly observe the fact that drivers slow considerably when
passing oncoming vehicles, and many (like myself) try to come to a standstill
to avoid being hit, or at least not be the one at fault if I am hit. It is an
extremely uncomfortable situation to drive along because of the high risk of
clashes with other vehicles.
4.44 I suggest to the Inspector that this or worse would be the fate of Pulley Lane if
the developments as proposed were to be permitted.
Junction Visibility Splays
4.45 I have attached an annotated copy of the Appellant’s drawing No. 10154-74 in
Appendix H. This drawing shows the section of Pulley Lane where it is to be
realigned into the development site, becoming the main exit/entrance for the
development, and the continuation of Pulley Lane to the east is a minor arm
off the realigned road.
4.46 The original drawing states that the visibility splays are 2.4 ‘x’ dimension and
90m ‘y’ dimension. However, the splays drawn for the minor arm into the
residential site only have a 60m ‘y’ dimension. The ‘x’ dimension of 2.4m for
this junction is satisfactory.
4.47 As noted in Section 2.4.13 of my Proof, the Appellant had planned to seek
approval for a speed reduction TRO, bringing the speed limit down to 40mph.
It is also noted that without the original mitigation package on Pulley Lane,
the speed limit reduction TRO may not be possible.
4.48 I will progress my arguments on the basis that the TRO is successful on Pulley
Lane. However it should be noted that if this is not the case, then the design
criteria would be considerably more onerous.
Proof of Evidence by Richard Pettitt 24
4.49 In any event, the appropriate visibility splays for junctions on a 40mph road
where the minor arm is a continuation of the 40mph road and not a small cul
de sac would be 4.5m ‘x’ dimension and 120m ‘y’ dimension.
4.50 It can be seen therefore, that the visibility splay provided where the junction
would be formed at the continuation of Pulley Lane eastwards beyond the
Appeal site entrance, is not specified correctly. The splay criteria should be
4.5m ‘x’ dimension and 120m ‘y’ dimension, as I have annotated on the
drawing.
4.51 The most critical aspect of the Appellants proposed highway mitigation
measures relates to the treatment of Pulley Lane from the site entrance to the
A38 junction in the west.
4.52 I have shown in the section relating to the transport assessment work by DTA,
that DTA has underestimated the volume of development traffic that would
use Pulley Lane by over one third. The Appellant has put forward some
highway improvements proposals for Pulley Lane, but as I will show, the
proposals are inadequate for the predicted traffic levels within the TA, and
hence would be even less acceptable when taken in context with the larger
volume of traffic I have highlighted (using the Appellant’s own TA distribution
diagram).
4.53 The Appellants propose to upgrade Pulley Lane by:
! Regularising the current 4.8 m - 5.5 m wide Lane to a consistent
5.5 m
! Improving (increasing) the radius of some of the bends on the
section in question
! Cutting back hedgerows to give improved forward visibility at
Bends
4.54 As stated in paragraph 4.49 above, the forward visibility requirement for a 40
mph road is 120 m. On drawings 10154–70 to 73 inclusive, whilst there as
been some attempt to provide improved forward visibility, only 60 m appears
Proof of Evidence by Richard Pettitt 25
to be shown. On the ‘chicane’ section at the western end, the worst existing
section, no attempt has been made to provide greater visibility.
4.55 Where the appellants have shown mitigation measures at bends and land is
shown being acquired, it would seem sensible that sufficient land would be
acquired to provide adequate and safe forward visibility for mitigation works.
Proposed Mitigation Measures
Impacts on Newland Road by the proposed widening/relocation for public
transport and emergency service vehicles.
4.56 The Appellant proposes to ‘reopen’ Newland Road at its junction with
Primsland Way, as a route for public transport and emergency service
vehicles, as well as the existing cyclist (SUSTRANS Route 45) and pedestrian
use.
4.57 The route is proposed to be a 5m wide carriageway plus 2m wide footway,
making 7m width in total, except for a short narrower section of some 50m
length immediately south of Primsland Way.
4.58 The current proposals do not give details of how the creation of the 7 m wide
route would be achieved in a physical sense. As the note at Appendix B states,
the level change on the east side of Newland Road in places is several metres
higher and rising across the adjacent fields.
4.59 The Appellant has only given a relatively simple 2D sketch of the proposal
(drawing No. 10154-64), and it is not possible to properly assess the
feasibility of the proposal from this information or consider likely effects of
carrying out such works on the existing corridor and residents of properties
adjacent to it.
4.60 In order to make such an assessment and using the O.S. mapping, LIDAR
sourced level information and augmented by topographical survey, the
proposed modifications shown on the Appellant's drawing No. 10154–64 have
been ‘recreated’ by Infrastructure Planning and Design Ltd., to check the
feasibility.
Proof of Evidence by Richard Pettitt 26
Layout of the improved bell-mouth junction with Primsland Way
4.61 Firstly it is important to note that the private boundaries on the West side
(properties on Yew Tree Hill) are not the fences that have been erected by the
private property owners; rather the centreline of the hedge and trees on the
western side of new link road.
4.62 The geometry of this proposed junction amendment has been checked for
suitability for buses and emergency service vehicles, and I have the following
observations:
4.63 The radii proposed, or the maximum that could be achieved without
encroachment into third-party land, would not allow an all-movements
junction for vehicles it is supposed to cater for. I attach in Appendix C an
additional drawing (IPD-13-286-103) that shows the AutoTrack data for a bus
and fire engine manoeuvring at this junction.
4.64 The currently proposed bus route modification This for a bus to approach
along Primsland Way, then right turn into Newland Road and then exit by a
left turn out of Newland Road back onto Primsland way. This is not possible
under the proposed layout as the buses could not turn in or out of Newland
Road (see insets C & D on drawing No. IPD-13-286-103). Such a lack of
flexibility could cause significant problems in the future if bus routes need to
change and public transport operators can no longer route as described by the
Appellants. Furthermore, if the bus operating companies wish to modify the
route to approach from the east, a left-in/right-out from the east could not be
accommodated either.
4.65 This lack of flexibility prejudices the viability of bus services penetrating the
site in the future, which in turn, if service changes occur that prevent buses
turning into the amended section of Newland Road, would seriously reduce the
suggested sustainability of the development. This issue would also affect
access for emergency service vehicles.
4.66 If emergency services vehicles found their normal route via Pulley Lane
impassable, they would almost certainly access the site via the alternative
Proof of Evidence by Richard Pettitt 27
route from Primsland Way and in the case of the appellant's proposal, a fire
engine would have difficulty utilising the new junction (see insets A & B on
drawing No. IPD-13-286-103). In my opinion it would be unsafe and
impractical to create a situation where a fire engine could only enter the site if
it approached from a specific direction towards the junction.
4.67 It does not appear to be possible to create radii that would allow buses and
emergency service vehicles to enter Newland Roads south of Primsland Way,
from Primsland Way itself, without taking land from private gardens adjacent
to the access point.
4.68 This alone calls into question the viability of the proposed bus route, but the
deliverability is further affected by the topography of the route.
Topography Constraints
4.69 The topography constraints on Newland Road (the northern section to be
reopened for buses and emergency service vehicles) have been considered,
and I have the following observations:
4.70 My assumption is that the levels on Newland Road would remain broadly as
existing, as the current longitudinal gradient cannot be significantly increased.
The legal property boundary of the Yew Tree Hill development is the centreline
of the row of trees/hedgerow on the western side of Newland Road, and not
what the appellants may have assumed, i.e. the fences that had been erected
by the property owners to prevent the embankment eroding into their
gardens.
4.71 Hence, to implement the northern section of the proposed modification of
Newland Road (a 2m footway + 3m carriageway for one-way operation of
buses and emergency service vehicles) setting out would be as follows:
! Boundary on West side is the centreline of trees/hedgerow
! Allow 500mm between boundary and footway edge
! 2m wide footway
Proof of Evidence by Richard Pettitt 28
! Kerb and carriageway construction (if allowable within 2.5m of
the centreline of the row of substantial trees)
! 3m wide carriageway with kerb on eastern side
! 1m verge between curved face and retaining structure
4.72 It should be noted that it is not normally allowable to construct a kerb-line and
full depth road construction as close as 2.5m to substantial trees, as it can
seriously damage the root structure. This point should be verified with the
appropriate landscape specialist
4.73 On the section of Newland Road where it passes between the rear boundaries
of four dwellings on Primsland Fields and private boundaries to properties on
Yew Tree Hill, the width of the route between private boundaries is extremely
narrow, with challenging level differences.
4.74 I have produced three cross-sections along this part of the route plus a further
cross-section about 220m south of Primsland Way. A drawing is attached in
Appendix C (No. IPD-13-286-100) showing my interpretation of layout of the
proposed bus, emergency service vehicles, cyclists and pedestrians route, and
cross sections (No. IPD-13-286-101) with the various constraints highlighted
including:
4.74.1. Section A-A shows how an improvement embankment would
undermine the rear gardens of Primsland Fields unless a retaining
structure is used. It can be seen that the retaining structure would be
directly underneath the private boundary, and the excavation behind
the structure to enable its construction prior to backfilling would
encroach substantially into the private garden.
4.74.1. Section B-B is at the pinch point (narrowest section) and shows how
the private garden boundary is situated directly above the edge of
the 1m verge alongside the road, and the retaining structure would
be situated well inside the garden, whilst the excavation behind the
structure would take up the entire garden.
Proof of Evidence by Richard Pettitt 29
4.74.1. Section C-C This section is similar to Section A-A, where the
retaining structure would fall directly beneath the private boundary,
and the excavation behind the structure to enable its construction
prior to backfilling would encroach substantially into the private
garden.
4.74.1. Section D-D shows the situation behind No.49 Yew Tree Hill. Even
with the new alignment of Newland Road at the highest level
achievable based upon an appropriate vertical alignment; it creates
the need for a very large earth embankment or (high) retaining
structure on the east side. To give an impression of relative heights,
it should be noted that the top of a retaining structure would be
approximately level with the roof of No.49 Yew Tree Hill Such a
structure might need to be considerably higher than the existing Krib-
Lok retaining wall situated at the end of Rebekah Gardens cul-de-sac.
4.74.1. Note: I have assumed the use of Gabion or Krib-Lok retaining
structures for the purposes of preparing these indicative sections.
4.75 Even if it were possible to raise the level of the new alignment of Newland
Road it would not remove the need for retaining structures, it merely splits the
total height across two structures, as there would then be a requirement for
retaining structures at both sides. To put this into perspective, the top of the
embankment/wall would be at the same level as the roof of No.49 Yew Tree
Hill.
4.76 It is my opinion that even if the proposed bus-lane could be constructed with
its western kerb-line within 2.5m of the trees/hedgerow, the route cannot be
delivered due to their being insufficient width available between private
property boundaries. This situation would become even more important if a
greater stand-off is required to protect the tree roots.
4.77 My conclusion on this aspect of the appellant's proposal is that it is clear the
amendments to Newland Road have not been considered adequately, and
insufficient detail in the design has been undertaken to demonstrate the
Proof of Evidence by Richard Pettitt 30
feasibility of what is being proposed and that it is not feasible and cannot be
delivered.
4.78 Others will deal with the landscape and visual impacts of the works that would
be necessary on Newland Road.
4.79 Hence if the public transport link cannot be delivered due to the route being
unfeasible, the requirements for access to bus services for the site (300m walk
distance between all dwellings and an available bus stop) cannot be achieved.
It must therefore be concluded that if the bus and emergency services route is not deliverable, the development proposals are not deliverable because:
! For a cul-de-sac development of more than 200 residential units,
a secondary access is required for emergency services
! To achieve required level of transport sustainability, access to
public transport is required where the greatest distance to a bus
stop should be no more than 400m
4.80 Neither of these requirements would be met if the upgrade of Newland Road
cannot be achieved.
Proof of Evidence by Richard Pettitt 31
5 Site Drainage Existing Site Drainage Issues
5.1 The site comprises largely impermeable clay soils, and has surface gradients between
1 in 5 and 1 in 30 (reference page 2 of Atkins Water Management Strategy, May
2011).
5.2 The steep gradients and relatively impermeable ground conditions result in
considerable surface water flooding, even at relatively low intensity storm events as
evidenced by the regularity of the resident’s reported occurrences. One such example
where I have photographic records and accounts of residents is where floodwater
passes through the narrow gap (presently a public footpath) adjacent to No. 16 Isaacs
Way. See the photograph below which was taken after a flooding event in
2009, showing material washed off the hill behind Isaacs Way, through the
gap between Nos. 14 & 16.
5.3 Photographs and information from the occupier of No. 16 Isaacs Way are given in
Appendix I.
Appellants Surface Water Drainage Strategy
5.4 The Appellant proposes to deal with surface water run-off from the development site
by means of:
! Attenuation ponds
! Underground storage
! Ditches and Swales
Proof of Evidence by Richard Pettitt 32
5.5 Collecting surface water from housing, hard-standing areas and roads, and
attenuating the flows using the above forms of storage is normal industry practice and
provided the correct parameters and calculations are employed, would adequately
deal with surface water falling on the built environment.
5.6 In addition to collecting drainage in the traditional manner of piped networks from
houses, hard-standings and roads, the Appellant has to deal with surface water runoff
from other areas such as green-space, plus flows entering the site from upstream
catchments. In this respect the Appellant proposes a network of ditches and swales
along boundaries.
5.7 One of the key issues in calculating the quantum of flow that such a design has to deal
with, is the assessment of what is known as ‘greenfield’ or ‘equivalent agricultural’
run-off. The general rule of thumb is to adopt 5 l/s per hectare, and there are a
number of calculation methodologies available to undertake a more detailed
assessment. Atkins has used an ADAS (Agriculture Development and Advisory
Service) methodology, and has arrived at a greenfield run-off figure of 474.1 l/s for
the major 41.89ha part of the development site (Reference a note on Atkins drawing
No. 5090327/DRA/DS/001 RevA). This figure is crucial to the design of surface water
attenuation on the site, as it represents the allowable discharge rate at the outfall,
which in turn fixes the quantum of the retained a volume. It should be noted that the
figure Atkins is using is over double the normal ‘rule of thumb’ 5 l/s per ha, at 11.32
l/s per ha.
Critique of Surface Water Drainage Strategy
5.8 The ADAS method of calculation that the Appellant has used is primarily for field
drainage pipe size analysis. Any analysis that is for the sizing of pipes to deal with
surface water run-off is going to have an allowance for what I will term ‘factor of
safety’ to ensure the resultant pipe sizes are not found wanting thus it could lead to
an over-estimate. Therefore it is more appropriate to use a calculation methodology
that is specifically to identify ‘greenfield run-off quantities/rates’. In my opinion a
more appropriate tool is the HR Wallingford calculator for estimating greenfield run-
off, which for this site would give a value of 367l/s for the 41.89ha site area for which
the Atkins figure is 474l/s. Thus it is my contention that the Appellant’s assumptions
for allowable maximum flow rate to the off-site outfall may be significantly
overestimated. The level of overestimation would be 29% compared to the outflow
calculated by the HR Wallingford method described above.
Proof of Evidence by Richard Pettitt 33
5.9 I have attached a copy of the HR Wallingford calculation output in Appendix J.
5.10 I do not have access to the design work undertaken by the Appellant's consultants to
be able to check their figures for proposed storage volumes. I would therefore
respectfully suggest to the Inspector that the Appellants be required to revisit their
proposals on the basis of a significant potential overestimation of the allowable ‘pass-
through’ flow into receiving watercourses. This would be to satisfy all stakeholders
that sufficient storage volume is being proposed.
5.11 The primary storage proposed by the Appellant is an open pond in the south-west
corner of the Barberry site, which has a total storage capacity of 9125 m³ (as stated
on Atkins drawing No. 5090327/DRA/DS/001 RevA)
5.12 The physical topography of the site in this location would probably preclude any
significant expansion of this storage pond to cater for the much larger run-off volume
I predict. The additional work to justify the volume of storage including the primary
storage pond in the southwest corner should include a 3-D preliminary design showing
how the pond could be constructed into the steep hillside. Importantly, it should show
how the impounded pond’s structure would protect Pulley Lane (West) should it
overtop. Also, very importantly, how the structure of the pond banks would not be
compromised should over-topping occur in an exceptional rainfall event (i.e. more
than a 100 year +30% climate change edition). I stress this latter point, as there is
the potential for this pond to have to be over 10,000 m³ capacity, which is a level at
which Government is currently considering amending the Reservoirs Act to include. It
should be noted that if the storage capacity rises above 10,000 m³, and the pond is
impounded, it may well be categorised as a reservoir and fall under the Reservoirs Act
legislation (the trigger volume is currently being considered by Government) that is
extremely onerous. The topography of the site would indicate that the storage pond is
at a level above that of the downstream land, and should Ministers choose to lower
the present threshold to 10,000 m3, the Appellant would have a considerably greater
liability to maintain the facility.
5.13 I will also comment later in my Proof on the ground conditions at the location
of this pond, as they might affect the viability of its construction
5.14 The points I wish to highlight here are;
Proof of Evidence by Richard Pettitt 34
! The Appellant appears to have overestimated the greenfield run-
off for the site which in turn;
! Overestimates the flow rate out of the site’s attenuation facilities,
which in turn;
! Underestimates the storage requirements on site for a design
storm event; and
! The site topography would make it difficult or impossible to
practicably enlarge the ponds/storage sufficiently to deal with the
additional volume.
5.15 I would respectfully suggest to the Inspector that a much more detailed
analysis of the surface water run-off regime is required, together with a more
detailed preliminary design to satisfy the Inspector and regulatory authorities
that a solution is indeed achievable, before any planning permission should be
granted.
5.16 In addition to the concerns detailed above regarding the overarching surface
water discharge calculations and the physical proposals to deal with it, I have
further observations on the Appellants proposals to deal with surface water
from areas that are not provided with positive drainage.
5.17 Whilst the Appellant recognises that there are existing surface water flooding
problems on the development site, which results in surface water flooding in
the surrounding areas, the proposals to deal with this are somewhat limited.
5.18 The Appellant proposals would appear to be restricted to provision of ditches
and swales to collect run-off from steep sloping areas of the site. I will take
two of these areas as examples to demonstrate my view that the proposals
are extremely limited and suggest that proof that the proposals would perform
the identified function should be unequivocally provided or the Appellant
should not be granted planning permission.
Northern Area Adjacent to Newland Road
Proof of Evidence by Richard Pettitt 35
5.19 This is a steeply sloping area, made all the more onerous to drain by the
proposals to create a wide cutting to accommodate the amendments to
Newland Road for the bus/emergency service vehicle route.
5.20 On drawing number 5090327/DRA/DS/01 RevA, the Appellant proposes the
following:
! “New ditch/swale interceptor to capture flow and infiltrate to
ground”
! "Adventure playground to be a permeable area. However some
drainage ditches/swales to be added at the edge of the site to
reduce surface flows off steep ground during heavy rainfall"
! "Catchment falling to this area covers 6.64 ha. However it is
assumed that the Appellant only needs to manage the run-off
from the adventure playground and paths. It is expected that
STW will not allow the existing greenfield drainage to be captured
and drained the sewer. So the existing method of draining this
area must be maintained.”
5.21 I would take issue with the Appellant’s proposals quoted in the bullets above
as follows:
5.22 Bullet 1 - the existing run-off in these areas is demonstrably substantial, and
there does not appear to be a fully developed strategy for dealing with it.
5.23 The comment about the captured flow infiltrating to ground seems to be at
odds with other comments in the Appellant's evidence where it is stated that
the clay soils to not allow for infiltration solutions. Yew Tree Village, Water
Management Strategy, May 2011, Conclusions – “based on the evidence from
the trial pits excavated and the soakaway test results proving a negligible soil
infiltration rate, we consider that infiltration drainage will not be a practical
option for the development site.” Therefore, if infiltration solutions are not
appropriate and negligible flow would soak into the ground the ditches and
swales would have to be very large indeed to accommodate the run-off as
Proof of Evidence by Richard Pettitt 36
straightforward storage. Also, if the water would not soak away, and these
features have no formal outfall, where does the water go?
5.24 For example if 50mm of rain falls on the stated catchment area of this part of
the site, and little or nothing can infiltrate into the ground, then of the order of
3000 m³ of water would fall on the catchment and allowing a conservative
‘loss’ of 50% to being held in surface depressions, interstices in the surface,
evaporation etc., there would still be a volume of about 1500 m³ to capture.
5.25 For a ditch of 1m depth and 1:2 side slopes, the bank-full volume would be
3m³ per linear metre of ditch. Thus there would be a need for about 500 lin m
of ditch of this scale. The drawing has indicated three sections of ditch/swale
in the northernmost section, amounting to about 180 lin m, which do indeed
follow contours. However the line along the top of the cutting of the proposed
realigned Newland Road has a longitudinal gradient of about 1:20 over about
half of the line shown, and would thus have minimal long-term storage
capacity. I therefore suggest that the Appellant's proposal to capture surface
run-off in this steeply sloping area to be somewhat lacking, and in my opinion
would not perform the function suggested.
5.26 Bullet 2 - this states that permeable surfacing would be used. However, I
would again query how effective permeable surfaces would be if the subgrade
beneath has negligible permeability. There would be some storage in the sub-
base provided beneath the play area, but if water is prevented from escape
into the substrata, then it would result in semi-permanent (in winter months
particularly) waterlogged construction layers and increase the potential for
frost damage, not to mention icy conditions in winter, making the play areas
unsafe in low temperatures.
5.27 Bullet 3 - this appears to suggest that although the ‘white land’ area (shown
on the drainage strategy drawing) outside of the Appellants control is
technically within the catchment, the Appellant has assumed that it would not
have to deal with any run-off. This is technically true if the ‘white’ land outside
of the development red line has its own drainage arrangements where there is
no outflow, as the riparian owner of the property has a legal duty to prevent
Proof of Evidence by Richard Pettitt 37
floodwater discharging onto a neighbour's land. However, under the 1991
Land Drainage Act, the riparian owner of land through which an established
drainage path exists has a legal duty to ‘pass on flow without obstruction,
pollution or diversion affecting the rights of others’.
5.28 Also, it is not appropriate to take the stance "I don't have to consider that land
is it belongs to someone else", as the established historic drainage may be via
the Appellants land. If this is the case it may still be the Appellant's
responsibility to maintain drainage outfall mechanisms. The legal duty on the
1991 Act is to ‘accept flood flows through your land, even if caused by
inadequate capacity downstream, as there is no common law duty to improve
a watercourse’.
5.29 In conclusion, the area at the north of site has a number of serious omissions
in the Appellant's proposals with respect to how surface water run-off would
be dealt with. It is my contention that with the evidence before the Inspector,
there are serious questions as to whether the surface water run-off can be
properly managed. At the very least, the Appellant should provide sufficient
detail to satisfy all parties that the issue can be resolved properly and
practically.
Western Area Adjacent to Isaacs Way
5.30 This is an area where there are many recorded flooding events, and the
Appellants consultants are clearly aware of this, as they have proposed
mitigation measures as detailed below:
! Development restricted in this area (circa 700 m²).
! Attenuation required to prevent surface water run-off from this
corner of the site flowing along alleyway.
! To be specified at the detailed design stage be this great storage,
swale, or permeable car parking area.
! Drainage formally shown crossing field to reduce debts of
excavation.
Proof of Evidence by Richard Pettitt 38
! However, this area is now designated as an orchard, so the
drainage has been diverted around this area.
! This will result in increased depth to excavation
5.31 As set out in paragraphs 5.2 and 5.3 of my Proof, there is a substantial
problem of surface water run-off from the existing fields in this area.
Photographs of the floodwater flowing past No.16 Isaacs Way are shown in
Appendix I. The resident of No.16 Isaacs Way has also provided a video of the
flood flow, as still photographs do not give an adequate impression of the
speed of flow and volume passing. I hope to have the facility to show this
video at the Appeal Inquiry, or possibly provide an electronic copy as a movie
file with my Proof of Evidence. There may also be the opportunity for the
Inspector to view the video on his site visit
5.32 As this is a major problem for residents in Isaacs Way, I consider that the
proposals with respect to preventing surface water flooding of existing
properties has not been sufficiently detailed.
5.33 There are no calculations that justify the surface water collection/disposal
arrangements would be sufficient as presented in planning application
supporting documents. Essentially this is a similar problem as the previous
section, where the use of ditches and swales has been proposed with the
expectation that there would be soakage into the ground. This does not accord
with the Appellant’s own assertion that the ground is essentially impermeable.
In this instance, underground storage is also proposed, but the Appellant says
it is a matter for detailed design.
5.34 In conclusion on surface water matters, the Appellant's case is flawed in that
their own documents state that there is “negligible permeability” in the ground
beneath the site, yet much of the drainage strategy for run-off from the land
is based on swales and ditches with no apparent outfalls, and statements that
they will "capture flow and infiltrate to ground".
5.35 The swale and ditch features shown in some areas are on steeply sloping
ground and would result in minimal storage.
Proof of Evidence by Richard Pettitt 39
5.36 Where there are significant existing flooding problems, no detailed design
proposals have been given to deal with the problem, which naturally leaves
adjacent residents worried that problems will get worse if the development
were to go ahead.
Critique of Foul Water Drainage Strategy
5.37 The Appellant has undertaken the usual investigations with Severn Trent
Water to obtain appropriate outfall points for the foul water disposal from the
development. Seven Trent has confirmed that foul flows can be
accommodated at three locations (give references) at
! Isaacs Way 2.5 l/s
! Sandals Road 14.0 l/s
! Primsland Way 5.0 l/s
5.38 A particular aspect of concern
to the residents of Isaacs
Way, is how the Appellant
proposes to make a
connection through the
narrow gap (footpath)
between Nos.14 and 16. The
width of the footway between
the two property boundaries is
1.3m. The normal
requirement of a water utility
company is for a five or 5m
easement over a public sewer
of this scale.
Figure
5.1
Proof of Evidence by Richard Pettitt 40
5.39 This requirement for space above a sewer is set out in the Severn Trent Water
document "The Consequence of a Water or Sewerage Undertakers Assets
Passing Through Land", a copy of which is attached in Appendix K
5.40 As there is only 1.3 m between the private boundaries and 4.17 m between
physical buildings, it is difficult to see how the Appellant can provide a public
sewer through the available space. It is my understanding from the owner of
No. 16, that there has been no contact in respect of negotiations for additional
land for an easement or construction working space.
5.41 I would question whether the space available between the two properties is
sufficient to physically lay a publicly adoptable sewer with appropriate working
space and subsequent easement. It is suggested that the Appellant has not
completed sufficient investigation to prove this outfall is feasible.
5.42 If the foul water connection cannot be implemented as stated, then at very
least the Appellant should have shown alternative arrangements that are
demonstrably feasible could be achieved, with confirmation of such from the
Water Company being provided as evidence. It is conceivable that without the
ability to drain through this route, there may not be sufficient capacity in the
alternative outfall points to deal with the resultant additional flows.
Proof of Evidence by Richard Pettitt 41
6 Brine Runs and Ground Conditions
6.1 This section relates to existing ground conditions as they would affect
proposed development infrastructure.
6.2 I do not give evidence on specific geotechnical matters, but use evidence from
the Appellant's supporting documents and draw conclusions related to the
proposed drainage and highway infrastructure works, from my 40yrs plus of
experience as a Civil Engineer, where I must interpret such geotechnical
reports to facilitate infrastructure design.
Ground Conditions as Evidenced in the Appellants Documents
6.3 A report produced by GRM Ltd was submitted as part of the planning
application by Persimmon and is entitled Phase 1 Appraisal (Desk Study). The
report has been written in support of Persimmon’s development ‘Red Line’
site. There does not appear to have been a similar report produced for the
Barberry development site. The GRM Phase 1 report also contains a report on
the Brine Run geology by Johnson Poole and Bloomer (JPB) in its Appendix H,
to which I shall refer.
6.4 There are a number of important statements in this report, as well as
locational information on the zones of influence of the soluble rock geology,
sometimes known as ‘Brine Runs’. There is a considerable amount of
information publicly available on the history of the Droitwich Spa Brine Runs,
but in summary the naturally occurring sodium chloride in the rock is dissolved
by strong groundwater flow, creating a brine solution. As the sodium chloride
is removed, cavitation is caused, that in turn leads to collapses in the rock and
surface subsidence.
Extracts from the Phase 1 Report:
Main Report, Appendix G: gives a map of the overall site showing
areas 1 and 2 (which equates to the Brine Run Zones C & B respectively)
plus a brown shaded area on the plan showing what is known as Brine
Run Zone A. To aid the Inspector I have prepared an overlay of these
Proof of Evidence by Richard Pettitt 42
Zones on the overall Yew Tree Village master-plan, which is attached in
Appendix L.
Main Report, Section 5: describes how the Persimmon site is situated
in Zones B and C (or areas 2 & 1 respectively in GRM terminology) and it
quotes:
“Area 2 (Moderate Risk Area) is currently characterised as a brine
subsidence risk Zone B by JPB. With a risk that Zone A (in practice un-
developable) encroaches in the far north-western corner.”
6.5 A key phrase in the above quote is that in practice Zone A land is un-
developable.
JPB Report in Appendix H, paragraph 4.4.4, Zone A, Active Brine Run:
“Maximum annual subsistence in the axis is currently recorded at up to
12.5 mm and the maximum discernible annual tilt, across the axis, is up
to approximately 1 in 3,520. Locally, such rates of subsidence and tilt
may be exceeded, although general rates are lower with tilts of between
1 in 5,000 to 1 in 20,000. The above values are based on those recorded
over the last four years. Analysis of trends over the same stations for
periods of 6, 10, 14 and 19 years show these rates to be relatively
consistent. There is an expectation of an overall relatively stabilised
amount of future ground subsidence at a relatively constant rate, but
such subsidence appears likely to continue for the foreseeable future, and
no absolute assurance can be given that more significant subsidence will
not re-occur in the future."
JPB Report in Appendix H, paragraph 4.4.5, Zone B, Active Brine Run:
“Zone B represents areas known or anticipated from precise levelling
surveys and/or surface features to be experiencing minor ground
movements at worst, with little or no differential factor. This Zone
includes areas which may previously have been included in Zone A but
for which long-term precise levelling has demonstrated sufficient
Proof of Evidence by Richard Pettitt 43
retardation of subsidence to justify re-zoning, i.e. Droitwich Town Centre
and part of Yew Tree Hill. There is a possibility, however, that Zone B
may at some time be encroached upon by the widening of Zone A.
Similarly, whilst unlikely, it is possible that Zone B could widen and
encompass more of the study area.”
JPB Report in Appendix H, paragraphs 5.6 & 5.7 dealing with Zone A,
Active Brine Run:
“5.6 Within Zone A, significant total and differential subsidence is
occurring, and the annual subsidence could be of the order of
approximately 17 mm with a tilt of 1 in 3,429 per annum. If projected
over a 60-year period (anticipated development life), they could in the
worst case, reach an accumulation of up to 1 m of total settlement and a
tilt of 1 in 57 respectively. Locally, this might be exceeded and ground
fissuring may develop, but generally this would be the maximum to be
anticipated. All proposed building development and associated
underground services within Zone A should be designed and constructed
to withstand such potential ground movements."
"5.7 In practice this requirement is likely to prohibit normal building
development but substantial foundation precautions may be appropriate
for specialist buildings within Zone A. Conventional building development
should only proceed after long-term precise levelling has proven effective
consistency to the equivalent criteria of Zone B. Specialist advice should
be sought for all proposed development within Zone A. The design should
be based upon specific levelling data and structural advice sought to
enable design to make allowances further."
6.6 The important aspect of the above report is that JPB, who has been monitoring
Brine Run activity in Droitwich Spa for many years and has found the
subsidence activity to be constant and consistent for a period of 19 years up
to production of the report, states that there could be approximately 1 m of
subsidence and 1 in 57 differential settlement over the next 60 years. Also in
Proof of Evidence by Richard Pettitt 44
paragraph 5.7 JPB states that in Zone A, the predicted settlement and tilt "is
likely to prohibit normal building development".
6.7 From the above extracts in the Appellant's own supporting technical reports, it
seems odd that the development is being promoted in its current form. With
large parts of the Barberry site being within Zone A, and specifically from an
infrastructure engineering point of view, placing drainage pipework, large
balancing ponds requiring extensive earthworks, and retaining structures for
highways in this area, would seem extremely unwise.
Potential Effects on Drainage Infrastructure
6.8 Drainage pipe runs (both foul and surface) are particularly susceptible to
settlement (subsidence) problems. Even relatively small amounts of
differential settlement will cause pipe fractures in normal materials of clay and
concrete. This would disrupt the ability of pipes to carry the intended flow and
could/would give rise to foul sewage entering the very active groundwater
regime. Also, if large volumes of water from fractured pipes were to enter the
active Brine Run geology, it could exacerbate the Brine Run problems. This is
evidenced by references such as paragraph 5.F (main report Phase 1
Assessment, page 10) where it states that the discharge of water into the
ground could give rise to "the risk of dissolution". That is to increase the rate
of sodium chloride dissolving that would increase the rate of cavitation and
thus subsidence.
6.9 Both sites (Barberry and Persimmon) rely upon key elements of drainage and
highway infrastructure, which would lay within or on the transitory boundaries
between Zones A and B.
6.10 The foul and surface water drainage from the Persimmon site appears to rely
upon a discharge route from the north-west corner of the site through the
Barberry development (reference the Travis Baker Flood Risk Assessment for
Persimmon Homes).
6.11 Barberry's own development lays predominantly in Zone A and hence a
considerable proportion of the drainage infrastructure would lay within, and
Proof of Evidence by Richard Pettitt 45
perhaps more importantly straddle the boundary of, Zone A. Pipe runs
crossing the boundary would be likely to experience the greatest differential
settlement.
6.12 One very major concern I would have as an experienced Civil Engineer, is the
construction of a very large surface water balancing facility (south-west corner
of the site) clearly situated on the boundary between Zones A and B, where
differential settlement of up to 1 m is suggested possible by the JPB report in
Appendix H of the GRM Phase 1 Assessment.
6.13 It is conceivable that the impounded pond, which is at a higher level than the
land south of Pulley Lane, might fail due to differential settlement and
inundate the land the south. I have (in paragraphs 5.10 & 5.12) drawn
attention to the scale of the balancing pond perhaps having to increase, and
the potential for it to fall under the Reservoirs Act. The uncertain geology may
then become a deal-breaker.
Potential Effects on Highway Retaining Structures
6.14 Another key feature of infrastructure that is necessary to enable the full
development of both Appellants sites is the creation of a bus/emergency
services/cycle/pedestrian route into the site along Newlands Road from
Primsland Way to the north.
6.15 As I have shown in Section 4 of my Proof, the creation of such a route (even if
possible due to land availability) would require a combination of substantial
retaining structures and large earth embankments. Some of this work would
fall within or on the boundary of Zone A. I would have serious concerns about
the structural stability of these proposed features.
6.16 I would also note that the existing Primsland development area (Yew Tree Hill
and Rebekah Gardens) also sits within or on the boundary of Zone A. I would
not necessarily accept because of this it must be acceptable to develop Yew
Tree Village. It is important to note that these developments were approved
and implemented before much of the current information on ground conditions
was available. If it had been known, or at least similar levels of investigatory
Proof of Evidence by Richard Pettitt 46
evidence had been available, it is possible that these developments may not
have been granted permission.
6.17 It is also possible that over the past few years, the most aggressive ground
movements have been limited to the eastern boundary between Zones A & B.
It is along that boundary where the property known as “Montrosa’ (originally
situated off Newland Road near ‘Casa Colina’) had to be demolished due to
subsidence damage. It is possible that Yew Tree Hill and Rebekah Gardens
might suffer subsidence problems in years to come.
6.18 In conclusion, I submit to the Inspector that the evidence on ground
conditions gives rise to considerable concerns, and the clear geotechnical
advice in evidence from the Appellant's own professional teams is that Zone A
is to all intents and purposes "un-developable", and therefore should not be
granted permission.
Proof of Evidence by Richard Pettitt 47
Appendix A Resident’s Photographs of Horses on Pulley Lane
Proof of Evidence by Richard Pettitt 48
Appendix B Resident’s Notes & Photographs of Newland Road
Proof of Evidence by Richard Pettitt 49
Appendix C IPaD Drawings & Sections on Newland Road
Proof of Evidence by Richard Pettitt 50
Appendix D IPaD Summary of Trip Distribution Figures
Proof of Evidence by Richard Pettitt 51
Appendix E Resident’s Notes & Photographs of Footpath Through Pulley Woods
Proof of Evidence by Richard Pettitt 52
Appendix F Extract from Worcestershire County Council Design Guide
Proof of Evidence by Richard Pettitt 53
Appendix G Example Narrow Country Lane Verge Damage
Proof of Evidence by Richard Pettitt 54
Appendix H Pulley Lane Visibility Splays – Annotated Drawing
Proof of Evidence by Richard Pettitt 55
Appendix I Resident’s Photographs of Flooding on Isaacs Way
Proof of Evidence by Richard Pettitt 56
Appendix J HR Wallingford Greenfield Runoff Calculation Output
Proof of Evidence by Richard Pettitt 57
Appendix K Severn Trent Water Document
Proof of Evidence by Richard Pettitt 58
Appendix L Annotated Drawing Showing Brine Run Zones