X.Dong, USTC/LBNL 1Feb. 20th, 04, STAR Collaboration Meeting
TOF Software Progress
Xin Dong, for TOF Group
TOF detectors in Run IVOnline softwareOffline software -- Data base & Geometry -- Makers
- match - calibration - simulation and embedding - MuDstSummary & Outlook
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 2
TOF detectors in Run IV
TPC
pVPDeast
pVPDwest
Au
TOFx
East-TPC
TOFp TOFr
x
y
Au
Some changes this year:
pVPDs moved ~4” further from Z=0 TOFp moved one slot clockwise when facing west from the east side --- read out channels no change (41) TOFr did not move, but the tray size and module positions in the tray changed --- First 20 modules (out of 32) in the tray have read-out electronics ( 72+48 channels totally)
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 3
Online Software
‣ Online software extended to 3 CAMAC crates in order to accommodate the read-out of 48 additional TOFr channels. ‣ new TOF raw data format (41+72+48 channels) required similar changes to the offline DAQ reader. ‣ Clearly we still have issues with the TCD-Bira communications which show up in TOF DAQ. --- mostly due to a hardware problem, not a software problem
-- TOFr HV is now only one channel. Software was updated accordingly and so was its interface with SlowControls. -- TOFp HV. No changes, only updated the Cell Mapping for its SlowControl interface -- TOFr Gas. No changes. -- SlowControls interfaces. Reviewed the Red/Yellow alarm settings and made them available as a document
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 4
TOF Offline Software Framework
STAR/TOF DAQ
TOF Data
TOF Cell/Slat
TOF Hit
TOF Match Maker
TOF Calibration MakerTO
F C
olle
ctio
n
StE
ven
tGSTAR geant hits
TOF DAQ Reader, TOFMaker TOF Simulation Maker
MuDst TOF
TOF MuFill Maker+ MuDst Maker
TOF Mixer Maker
TOF MCCell/MCSlat
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 5
TOF Geometry
Data Base
Find the tracked cell/slat from a HelixCoordinates transferringInitialization from GEANT
TOF configurations --- ready --- pVPD configuration --- pVPD Strobe events configuration --- tof detectors configuration --- tof Tray configuration --- tof Module configurationDAQ mapping --- ready --- tof DAQ mapping
TOF geometry & dbase
Many new introduced structures
Calibration parameters --- ongoing --- tof T0 (timing offset) --- tof Correction (overall) --- tof Correction (each channel)Simulation parameters --- ready --- MRPC simulation parametersTOFp Geometry --- need to be updated this year
GEANT definition change due to the geometry & position change this year
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 6
TOF Collection in StEvent
TOF Data:Raw ADC, TDC in each DAQ channel 42 + 6 + 72 (120)
TOF Cell/Slat:Cells/Slats with track matchedCell/Slat Id, ADC, TDC, associated tracks, projected position
TOF Hit:After calibrationPhysical tof, β, pathlength, etc.
MCCell/MCSlat: Additional MC information
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 7
Ongoing Makers I
TOF Match Maker:
Fired channels from DAQ
Projected cells from global tracksMatched within one pad distance
Get rid of multi-hit cells
Order cells for cross talks
Save those have primary tracks into TOF Cell Collection
TOFp Match Maker already in library,TOFr Match Maker ready to be committed
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 8
Ongoing Makers II
TOF Calibration Maker:
Calibration parameters from dbase
TOF Cell in StEvent
pVPD calibration – start time
TOF Data in StEvent
Time-of-flight correction
Write TOF Hit in StEvent
Waiting for dbase structure ready to do corresponding change for checking in
Fast offline data for calibration
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 9
Ongoing Makers III
TOF Simulation Maker:
Ready to be committed in
Simulation parameters in dbase
Geant hits
Cell response simulation
Write raw ADC & TDC in TOF Data
TOF embedding Makers:TPC embedding
TOF Data from DAQ TOF Data from simulation
Tof Mixer Maker
Tof association MakerNeed corresponding change for dbase configuration read-in
?
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 10
Ongoing Makers IV
TOF in MuDst: ---- MuTof introduced in MuDst
TOF Hit
TOF CellMuTofFill Maker – write MuTof
Corresponding changed MuDSTMaker
Write into MuDst
Ready to be reviewed and committed
Makers summary:Almost all are ready!Need to be committed ASAP before production
pVPD Fill Maker?
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 11
Summary
Online DAQ corresponding change for additional TOFr channels, little changes for other online software
Many new introduced structures in dbase --- calibration structure on the way --- request corresponding changes for the Makers or Utilities
Geometry changes in GEANT due to the position change of detectors this year
Most of the offline Makers are ready to be committed for the coming production
Feb. 20th, 04, STAR Collaboration Meeting X.Dong, USTC/LBNL 12
Outlook
Preliminary timing resolution ~120psPreliminary calibrations for Run IV
Great thanks to the Software Group & … helpers!
With the development of software,important physics will come out soon!
Overall slewing correction