Upload
nguyenlien
View
219
Download
0
Embed Size (px)
Citation preview
Wide Area Measurement Applications forImprovement of Power System Protection
Mutmainna Tania
Dissertation submitted to the faculty of the Virginia Polytechnic Institute and State
University in partial fulfilment of the requirements for the degree of
Doctor of Philosophy
in
Electrical Engineering
Arun G. Phadke (Co-Chair)
Jaime De La Reelopez (Co-Chair)
Virgilio A. Centeno
Richard W. Conners
Werner E. Kohler
December 7, 2012
Blacksburg, Virginia
Keywords: Back-up Distance Protection, Supervisory Control, Adaptive Loss-of-Field
Protection, Wide Area Measurement System, Generation Redistribution
c©Copyright 2012, Mutmainna Tania
Wide Area Measurement Applications for Improvementof Power System Protection
Mutmainna Tania
Abstract
The increasing demand for electricity over the last few decades has not been followed by
adequate growth in electric infrastructure. As a result, the reliability and safety of the electric
grids are facing tremendously growing pressure. Large blackouts in the recent past indicate
that sustaining system reliability and integrity turns out to be more and more difficult due
to reduced transmission capacity margins and increased stress on the system. Due to the
heavy loading conditions that occur when the system is under stress, the protection systems
are susceptible to mis-operation. It is under such severe situations that the network cannot
afford to lose its critical elements like the main generation units and transmission corridors.
In addition to the slow but steady variations in the network structure over a long term,
the grid also experiences drastic changes during the occurrence of a disturbance. One of
the main reasons why protection relays mis-operate is due to the inability of the relays to
adjust to the evolving network scenario. Such failures greatly compound the severity of
the disturbance, while diminishing network integrity leading to catastrophic system-wide
outages. With the advancement of Wide Area Measurement Systems (WAMS), it is now
possible to redesign network protection schemes to make them more adaptive and thus
improve the security of the system.
Often flagged for exacerbating the events leading to a blackout, the back-up distance
protection relay scheme for transmission line protection and the loss-of-field relay scheme for
generator unit protection can be greatly improved from an adaptability-oriented redesign.
Protection schemes in general would benefit from a power re-distribution technique that
helps predict generator outputs immediately after the occurrence of a contingency.
iii
Acknowledgements
I would like to express my sincere gratitude to my advisor, Dr. Jaime De La Ree, for his
patience and encouragement throughout my graduate career. He has been a great support for
me over the last several years and has provided vision and invaluable advice for completing
this dissertation, all while allowing me the freedom to pursue the work that interested me.
I am also heartily thankful to my research professor and mentor, Dr. Arun Phadke,
whose guidance from initial to final phase of my research work kept me inspired and enabled
me to develop a profound understanding of my field. It was a great privilege to receive
guidance from such a talented researcher, teacher and remarkable human being.
I would also like to extend thanks to Dr. Virgilio Centeno for his confidence in my
research ability to grant me research funding for pursuing a doctoral degree and for fostering
a continuous learning environment within our research group. I would like to thank the
rest of my committee members, Dr. Werner Kohler and Dr. Richard Conners, for their
encouragement, insightful comments, and relevant questions.
I wish to thank my parents, Khan Md. Abdur Rob and Shawkat Ara Begum, for their
love and blessings which served as one of my biggest driving forces. I owe everything to them
and would not be where I am without them. I also would like to extend my gratitude to
my sister, Zakia Farahna Shanta, my brother, Farzad Bari Auvi, and dearest friend, Santosh
Veda, for their love and constant support.
Finally, I would like to express my deepest appreciation to my beloved husband and best
friend, Kevin Jones, for his inspiration, friendship and love. I am indebted to him for his
patience, kindness and encouragement, which motivated me to finish my dissertation. I feel
extremely blessed to have such a wonderful partner who has helped make this journey such
an enjoyable one.
Contents
List of Figures viii
List of Tables xiii
1 Motivation 1
1.1 Power System Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.2 Wide Area Measurements . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.3 Organization of the Dissertation . . . . . . . . . . . . . . . . . . . . . . . . . 7
2 Technical Background 9
2.1 Power System Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
2.1.1 Steady State Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . 10
2.1.1.1 Bus-Admittance Matrix . . . . . . . . . . . . . . . . . . . . 10
2.1.1.2 Kron Network Reduction . . . . . . . . . . . . . . . . . . . 11
2.1.1.3 Sensitivity Factors . . . . . . . . . . . . . . . . . . . . . . . 13
2.1.1.4 Calculation of Susceptance Matrix Using DC Power Flow . . 14
2.1.1.5 Derivation of Generator Shift Factor . . . . . . . . . . . . . 20
2.1.1.6 Derivation of Line Outage Distribution Factor . . . . . . . . 21
2.1.2 Transient Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
iv
Contents v
2.2 Power System Simulation Tools . . . . . . . . . . . . . . . . . . . . . . . . . 25
2.3 Protection Schemes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
2.3.1 Distance & Impedance Protection . . . . . . . . . . . . . . . . . . . . 26
2.3.2 Loss-of-Field Protection . . . . . . . . . . . . . . . . . . . . . . . . . 29
2.3.3 Adaptive Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
3 Supervisory Control for Back-Up Zone Protection 33
3.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
3.2 Distance Relay Back-up Protection Criteria . . . . . . . . . . . . . . . . . . 34
3.3 Load-encroachment and Supervision of Back-up
Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
3.4 Study Model Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
3.4.1 WECC Full Loop Model . . . . . . . . . . . . . . . . . . . . . . . . . 37
3.4.2 California Model . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
3.5 Selection of Appropriate Location for Back-up
Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
3.5.1 Line Outage Distribution Factors . . . . . . . . . . . . . . . . . . . . 39
3.5.1.1 Technique for Determining Line Outage Distribution Factor 40
3.6 Implementation of LODF to California
(Heavy Summer) Model . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
3.6.1 Formation of LODF Matrix for CA System and
Identification of Critical Lines . . . . . . . . . . . . . . . . . . . . . . 41
3.6.2 Identification of Zone 3 Settings for Critical Lines after
Single Contingency . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
3.6.2.1 Relay Settings for Multi-Terminal Lines . . . . . . . . . . . 42
3.7 Multiple Contingency Studies . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Contents vi
3.7.1 Inertial Re-Dispatch of Generators . . . . . . . . . . . . . . . . . . . 44
3.7.2 Comparison between CA and Full-Loop Study System . . . . . . . . 46
3.8 Load-Encroachment Examples in CA System . . . . . . . . . . . . . . . . . . 46
3.9 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
4 Adaptive Loss-of-Field Protection 54
4.1 LOF Relaying Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
4.2 Loss-of-Field Relay Protection Criteria . . . . . . . . . . . . . . . . . . . . . 56
4.2.1 Steady State Instability as a Consequence of LOF Condition . . . . . 58
4.2.2 Steady State Stability Limit Circle . . . . . . . . . . . . . . . . . . . 61
4.3 Development Adaptive LOF Relay Scheme . . . . . . . . . . . . . . . . . . . 63
4.3.1 LOF Group Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
4.3.2 Adaptive LOF Relay Application in CA System . . . . . . . . . . . . 67
4.4 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
5 Impact of Generation Re-distribution Immediately after Generation Loss 72
5.1 Generation Re-distribution with Respect to Location . . . . . . . . . . . . . 74
5.2 Generator Location as a Function of Admittance from an Event Location . . 78
5.2.1 Network Reduction to Determine Admittance between
Generators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78
5.2.2 IEEE 39 Bus System Examples . . . . . . . . . . . . . . . . . . . . . 79
5.2.3 IEEE 118 Bus System Examples . . . . . . . . . . . . . . . . . . . . . 85
5.2.4 WECC System Examples . . . . . . . . . . . . . . . . . . . . . . . . 87
5.3 Linear Regression to Predict Power Injection
Changes at Generators after Contingency . . . . . . . . . . . . . . . . . . . . 88
5.3.1 IEEE 39 Bus System Examples . . . . . . . . . . . . . . . . . . . . . 89
Contents vii
5.3.2 Accuracy of Regression Model . . . . . . . . . . . . . . . . . . . . . . 101
5.3.3 IEEE 118 Bus System Examples . . . . . . . . . . . . . . . . . . . . . 103
5.4 Potential Application in Protection Studies . . . . . . . . . . . . . . . . . . . 114
5.5 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 117
6 Conclusion & Future Work 118
6.1 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118
6.2 Future Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
Bibliography 122
A Sample Study Systems 126
A.1 IEEE 39 Bus System Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
A.2 IEEE 118 Bus System Data . . . . . . . . . . . . . . . . . . . . . . . . . . . 131
A.2.1 IEEE 118 Bus System with 54 Generators . . . . . . . . . . . . . . . 131
A.2.2 IEEE 118 Bus System with 19 Generators . . . . . . . . . . . . . . . 132
List of Figures
1.1 Digital Relay Characteristics to Prevent Load Encroachment . . . . . . . . . 4
1.2 Loss-of-field Relay Characteristics . . . . . . . . . . . . . . . . . . . . . . . . 5
2.1 Two-port π-Model of a Transmission Line . . . . . . . . . . . . . . . . . . . 15
2.2 Distance Relay Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
2.3 Distance Relay Protection Zones . . . . . . . . . . . . . . . . . . . . . . . . . 27
2.4 Distance Relay Overlapping Zones . . . . . . . . . . . . . . . . . . . . . . . . 28
2.5 Mho Relay Element Characteristics . . . . . . . . . . . . . . . . . . . . . . . 29
2.6 Generator Capability Curve . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
2.7 Impedance Variance during LOF Conditions . . . . . . . . . . . . . . . . . . 31
3.1 Three Zone Distance (Mho Relay) Characteristics . . . . . . . . . . . . . . . 34
3.2 Effect of Load Encroachment on Zone-3 Characteristics . . . . . . . . . . . . 36
3.3 Supervision of Backup Protection . . . . . . . . . . . . . . . . . . . . . . . . 37
3.4 Principle of LODF . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
3.5 Effect of Infeeds on Zone Settings of Distance Relays . . . . . . . . . . . . . 42
3.6 Flow-Chart for Inertial Re-dispatch of Generators . . . . . . . . . . . . . . . 45
3.7 WECC Map, Relay at Captain Jack (500kV Bus) . . . . . . . . . . . . . . . 47
viii
List of Figures ix
3.8 R-X Characteristics of Relay at Captain Jack (500kv bus), Monitoring Line
from Captain Jack to Olinda . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
3.9 R-X Characteristics of Relay at Midway (500kV bus), Monitoring Line from
Midway to Vincent, ck 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
3.10 R-X Characteristics of Relay at Midway (500kV Bus), Monitoring Line from
Midway to Vincent, ck 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
3.11 R-X Characteristics of Relay at Midway (500kV Bus), Monitoring Line from
Midway to Vincent, ck 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
3.12 R-X Characteristics of Relay at Vincent (500kV Bus), Monitoring Line from
Midway to Vincent, ck 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
4.1 Phasor Diagram of Generator Voltage and Current during Reduced Excitation 56
4.2 Loss-of-Field as an Instability Condition . . . . . . . . . . . . . . . . . . . . 57
4.3 Simple System for Steady-State Stability Analysis . . . . . . . . . . . . . . . 58
4.4 Steady-State Stability Limit Circles . . . . . . . . . . . . . . . . . . . . . . . 59
4.5 Apparent Impedance Seen by an Impedance Relay . . . . . . . . . . . . . . . 60
4.6 Graphical Method for Steady State Stability Limit . . . . . . . . . . . . . . 62
4.7 LOF Relay at Diablo Machine Terminal . . . . . . . . . . . . . . . . . . . . 64
4.8 LOF Relay Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
4.9 Dibalo1- One Machine Infinite Bus . . . . . . . . . . . . . . . . . . . . . . . 66
4.10 LOF Relay Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
4.11 Network Diagram near Diablo . . . . . . . . . . . . . . . . . . . . . . . . . . 67
4.12 Apparent Impedances Seen by Traditional Relay after LOF Conditions . . . 68
4.13 Apparent Impedances Seen by Relay after LOF Conditions - Relay at Diablo1 69
4.14 Apparent Impedances Seen by Relay after LOF Conditions - Relay at Diablo1 69
4.15 Apparent Impedances Seen by Relay after LOF Conditions - Relay at Diablo1 70
List of Figures x
5.1 Abstract Power System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
5.2 Distribution of Generation in an Abstract Power System . . . . . . . . . . . 75
5.3 Loss of Generator G4 in an Abstract Power System . . . . . . . . . . . . . . 76
5.4 Re-distribution of Generation in an Abstract Power System, Just after the
Contingency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
5.5 One Line Diagram of IEEE 39 Bus System . . . . . . . . . . . . . . . . . . . 80
5.6 MW Outputs of Remaining Generators after Generator 3 at Bus 32 Outage . 81
5.7 Histogram of MW Outputs of Remaining Generator after Generator 3 at Bus
32 Outage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
5.8 MW Output at Remaining Generator after Generator 3 at Bus 32 Outage . . 83
5.9 MW Output at Remaining Generator after Generator 7 at Bus 36 Outage . . 84
5.10 Histogram of MW Outputs of Remaining Generator after Generator 7 at Bus
36 Outage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
5.11 MW Output at Remaining Generator after Generator 7 at Bus 36 Outage . . 85
5.12 MW Output at Remaining Generator after Generator at Bus 10 Outage . . . 86
5.13 MW Output at Remaining Generator after Generator at Bus 80 Outage . . . 86
5.14 MW Output at Remaining Generator after Generator at Bus 66 Outage . . . 87
5.15 Generators Dibalo 1 & 2 Outage in WECC System . . . . . . . . . . . . . . 88
5.16 Immediate Injection Changes at Generators Buses after Generator 1 Outage 90
5.17 Immediate Injection Changes at Generators Buses after Generator 3 Outage 91
5.18 Immediate Injection Changes at Generators Buses after Generator 10 Outage 92
5.19 Immediate Injection Changes at Generators Buses after Each Generators Outage 93
5.20 Immediate Injection Changes at Generators Buses after Each Generators Outage 93
5.21 Actual and Predicted Changes in Injections at Generator Buses after Gener-
ator 4 (543.5 MW) Outage . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
List of Figures xi
5.22 Actual and Predicted Changes in Injections at Generator Buses after Gener-
ator 5 (419.9 MW) Outage . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
5.23 Actual and Predicted Changes in Injections at Generator Buses after Gener-
ator 6 (561.7 MW) Outage . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
5.24 Actual and Predicted Changes in Injections at Generator Buses after Gener-
ator 7 (471.8 MW) Outage . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
5.25 Actual and Predicted Changes in Injections at Generator Buses after Gener-
ator 8 (451.8 MW) Outage . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
5.26 Actual and Predicted Changes in Injections at Generator Buses after Gener-
ator 9 (741.7 MW) Outage . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101
5.27 Immediate Injection Changes at Generator Buses after Generator 1 Outage . 105
5.28 Immediate Injection Changes at Generator Buses after generator 9 Outage . 105
5.29 Immediate Injection Changes at Generator Buses after Generator 11 Outage 106
5.30 Immediate Injection Changes at Generator Buses after Generator 16 Outage 106
5.31 Actual and Predicted Changes in Injections at Generator Buses after Gener-
ator 1 (450 MW) at Bus 10 Outage . . . . . . . . . . . . . . . . . . . . . . . 111
5.32 Actual and Predicted Changes in Injections at Generator Buses after Gener-
ator 7 (204 MW) at Bus 49 Outage . . . . . . . . . . . . . . . . . . . . . . . 111
5.33 Actual and Predicted Changes in Injections at Generator Buses after Gener-
ator 10 (160 MW) at Bus 61 Outage . . . . . . . . . . . . . . . . . . . . . . 112
5.34 Actual and Predicted Changes in Injections at Generator Buses after Gener-
ator 14 (477 MW) at Bus 80 Outage . . . . . . . . . . . . . . . . . . . . . . 112
5.35 Impedance Trajectory Seen by Relay at Line between Bus 90 and 91 . . . . . 115
5.36 Impedance Trajectory Seen by Relay at Line between Bus 68 and 65 . . . . . 116
5.37 Generators at SONGS 1 & 2 in WECC System . . . . . . . . . . . . . . . . 116
5.38 Impedance Trajectory Seen by Relay at Line between Hassayampa to North
Gila in WECC System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 117
List of Figures xii
A.1 One Line Diagram of IEEE 39 Bus System with 10 Generators . . . . . . . . 126
A.2 One Line Diagram of IEEE 118 Bus System with 54 Generators . . . . . . . . 131
A.3 One Line Diagram of IEEE 118 Bus System with 19 Generators . . . . . . . . 132
List of Tables
3.1 500 kV Links in CA System . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
3.2 Midway-Vincent Line Ratings . . . . . . . . . . . . . . . . . . . . . . . . . . 49
5.1 Slopes & y-Intercepts of Best Fitted Lines alongside Transient MW Changes 94
5.2 Coefficient of Determinations of Regression Models to Predict Power Injection
Changes for IEEE 39 Bus Study . . . . . . . . . . . . . . . . . . . . . . . . . 102
5.3 List of Contingency Cases Used for Prediction . . . . . . . . . . . . . . . . . 107
5.4 Coefficient of Determinations of Regression Models to Predict Power Injection
Changes for IEEE 118 Bus Study . . . . . . . . . . . . . . . . . . . . . . . . 113
A.1 IEEE 39 Bus System - Bus Data . . . . . . . . . . . . . . . . . . . . . . . . . 128
A.2 IEEE 39 Bus System - Branch Data . . . . . . . . . . . . . . . . . . . . . . . 130
A.3 IEEE 39 Bus System - Generator Data . . . . . . . . . . . . . . . . . . . . . 130
A.4 IEEE 118 Bus System - Original Bus Data . . . . . . . . . . . . . . . . . . . 137
A.5 IEEE 118 Bus System - Additional Bus Data . . . . . . . . . . . . . . . . . . 139
A.6 IEEE 118 Bus System - Branch Data . . . . . . . . . . . . . . . . . . . . . . 145
A.7 IEEE 118 Bus System - Additional Branch Data . . . . . . . . . . . . . . . . 146
A.8 IEEE 118 Bus System - Generator Data . . . . . . . . . . . . . . . . . . . . . 147
xiii
Chapter 1
Motivation
During northeast blackout of 2003, a series of line outages in northeastern Ohio caused heavy
loadings on parallel circuits that led to tripping and locking-out of the 345 kV Sammis-
Star line. As a result the high voltage paths into northern Ohio from southeast Ohio were
severely weakened. The Sammis-Star line tripped at Sammis Generating Station due to a
zone 3 impedance relay, the purpose of which is to serve as a back-up protection. A zone-3
relay can be defined as an impedance relay that is set to detect faults on the protected
transmission line and beyond. It operates through a timer to see faults beyond the next bus
up to and including the furthest remote element attached to the bus. It is used for equipment
protection beyond the line and it is also an alternative protection to equipment failure such
as breaker failure transfer trip. In the Sammis-Star trip, the zone-3 relay operated because
it was set to detect a remote fault on the 138-kV side of a Star substation transformer in
the event of a breaker failure. There were no system faults occurring at the time. The
relay tripped because excessive real and reactive power flow in the line caused the apparent
impedance to be within the impedance circle (trip zone) of the relay. Several 138-kV line
outages just prior to the tripping of Sammis-Star contributed to the over-load and ultimately
tripping of this line [1] [2].
This was the event that was mainly responsible for triggering a cascade of line outages
on the high voltage system, causing electrical fluctuations and generator trips such that
within seven minutes the blackout rippled from the Cleveland-Akron area through most of
the northeastern United States and Canada which left 10 million people in Ontario and 45
million people in eight U.S. states without electricity. This manifestation is an example
1
Chapter 1. Motivation 2
of improper or insufficient protection principles of the power system elements. A proper
supervision and adjustment to the back-up protection characteristics could have allowed
blocking of zone-3 impedance relay at that 345 kV line and as a result the cascade of line
trips might have been avoided.
Similar events were also responsible for initiating the recent Blackout in India in July,
2012. Pre-blackout the system was weakened by multiple scheduled outages of transmission
lines connecting the Western region (WR) with the Northern region (NR) boundary two
important part of the New Grid. As a result the 400 kV Bina-Gwalior-Agra (a single circuit)
was the only main AC inter-tie available between WR-NR boundaries prior to the distur-
bance. Many of the NR utilities drew excessive power from the grid, utilizing Unscheduled
Interchange (UI), a mechanism that is introduced in India to control frequency of the grid
more strictly, which severely contributed to high loading on 400 kV Bina-Gwalior-Agra link.
This tie line eventually tripped on zone-3 protection of distance relay. This happened due
to load encroachment (high loading of line resulting in high line current and low bus volt-
age). However, there was no fault observed in the system. Since the inter-regional tie was
already very weak, tripping of 400 kV Bina-Gwalior line caused the NR system to completely
separate from the WR which was the originator of the succeeding blackout [3].
These cases are just a few of many examples where mis-operation of protection schemes,
whether by design flaw, lack of maintenance, or simple mistakes, have played a part in
large events on the power grid. And because our society and others depends so heavily
on this critical energy infrastructure, large events on the power grid translate directly to
large events in our economies and our lives. This dissertation investigates several protection
schemes which aim to increase the reliability and security of the operation of the power grid
by providing a wide area perspective to relays that may the have the potential to mis-operate
due to certain system conditions. This includes a supervisory zone for back-up protection,
an adaptive loss-of-field relaying scheme, and a study of the potential effects of the transient
effects of the loss of a large generator on in appropriate operation of protection schemes.
These ideas are made possible by the advent of wide area measurement technology. As wide
area measurement technology proliferates, it can be applied to scenarios in power system
protection which would benefit from more information about a scenario before deciding to
block or trip. The next two sections in this chapter discuss the recent developments in power
system protection and wide area measurements to serve as an introductory discussion for
the topics covered in the later chapters of the dissertation.
Chapter 1. Motivation 3
1.1 Power System Protection
Distance or impedance relays are the main topics of this dissertation. The purpose of the
distance protection relays are to provide sufficient resistive reach, to ensure correct relay
operation when a fault is inside of the designed protective zone. Traditional relays with
dynamic Mho characteristics mostly satisfy these requirements. However stressed system
conditions, depressed voltages, and high line loading may cause the apparent impedance
to enter the relay characteristic and initiate incorrect tripping as described in the blackout
examples. Zone-3 distance elements provide remote backup if the primary zones fails to
operate, and act as alternate solution to remote breaker or other equipment failure as a result
this relay has over-reaching characteristics. These criteria also make the relay vulnerable
to load encroachment which relates to the influence of heavy load current on Mho relay
settings causing the impedance trajectory to move inside the trip zone especially if the load
is dynamically changing above the static rating of the transmission line. Several techniques
such as memory polarization, modified maximum torque angles (relay reach), alteration the
impedance relay characteristic from a circle to a lens are applied to increase load limits of
transmission lines or reduce susceptibility to loadability violations [4] [5].
Digital/ Numerical relays are able to incorporate logics that identify the appropriate
load limits and prevent three-phase distance units from mis-operating. These logics are
commonly referred as Load Encroachment Functions. An enhanced technique for distance
relay protection that improves load limits is a combination of a load blinder element with its
Mho characteristics to limit reach along the real axis (As in Figure 1.1(a)). Application of
the blinder separates the area of the impedance characteristic that may result in an operation
under excessive dynamic load conditions and the relay operation is blocked within this region
[6]. Another such option (in Figure 1.1(b)) can be the reduction of the protective area of
the zone-3 element and using the forward offset into the first quadrant to ensure appropriate
coverage of the outgoing lines at the remote end substation [4].
Chapter 1. Motivation 4
Figure 1.1: Digital Relay Characteristics to Prevent Load Encroachment
Loss-of-field (LOF) relay is another type of impedance relay (offset Mho relay specifically)
which is applied at the generator terminals to detect failure of the generator excitation
system. Such failure collapses the internal generator voltage and causes reactive power to
flow from the system into the generator beyond the generator rating. Literature review
demonstrates that LOF relays may pick up during stable power swings or trip if the relay is
not properly coordinated with excitation control and their limit settings. Some LOF relay
mis-operations occurred because the units were left on manual control and the excitation
output was set as frequency dependent (shaft driven exciters). V/Hz relays and overvoltage
relays also initiated inappropriate trips due to lack of coordination with excitation system
controls.
For conventional LOF protection, the impedance boundary criterion of steady state sta-
bility limit is widely used to identify loss-of-field conditions which is independent of system’s
operating point. Hence, a LOF relay can even fail to detect system instability as the sta-
bility limit may possibly shift due to system changes. During under- excitation condition,
generator operates on leading power factor as a result the generator operates as VAR sink, so
the relay must be coordinated with the excitation system minimum excitation limit (MEL)
settings to fully utilize the generator reactive power capability during disturbances.
Chapter 1. Motivation 5
Figure 1.2: Loss-of-field Relay Characteristics
To address continuing concern over LOF relay performance and verify the notion that
machine’s stability parameters have changed significantly since mid-nineties, a study was
initiated to review the application and the performance of the offset Mho LOF relay for a
variety of system conditions. This research specified an LOF protection consisted of two
independent Mho functions (as in Figure 1.2 ) and a built in timer which coordinates with
the larger of the two relay characteristics. One setting has a relay reach of 1.0 per unit
circular diameter and the other characteristic is set at a circle diameter equal to machine
synchronous reactance (xd) . The offset, in both cases, will be equal to one-half of the direct
axis transient reactance (x′d
2). The inner circle provides loss-of-excitation protection from
full load down to about 30% load. As a LOF condition in such loading range has the greatest
adverse effects on the generator and system, this zone is permitted to trip in high-speed.
The outer circle is able to detect a loss-of-excitation from full load down to no load. This
research shows that the larger setting of this relay was unable to differentiate between stable
and un-stable power swing, as a result this region may operate on stable swings. A time
delay of up to 3 seconds is suggested to prevent such undesired operations [7].
1.2 Wide Area Measurements
A wide area measurement systems (WAMS) can be defined as a monitoring device that takes
measurements in the power grid at a high granularity and in synchronized real time, across
Chapter 1. Motivation 6
traditional control boundaries and then utilize that information for safe operation, improved
learning and grid reliability through wide area situational awareness and advanced analysis.
This advanced measurement technology provides great informational tools and operational
infrastructure that facilitate the understanding and management of the increasingly complex
behavior exhibited by large power systems.
Measurements taken from different power systems cannot be fully integrated unless they
are captured at the same time. An important requirement of WAMS, therefore, is that the
measurements be synchronized. Measurements are precisely time synchronized against the
satellite based Global Positioning System (GPS), and are combined to form integrated and
high resolution views of power system operating conditions. The initial data source for this
system is the Phasor Measurement Unit (PMU), which provides high quality measurements
of bus angles and frequencies in addition to more conventional quantities. A high sampling
rate, typically, 30 or more samples per second, is particularly important for measuring system
dynamics and is another important requirement of WAMS technology [8].
In its present form, WAMS may be used as a stand-alone infrastructure that complements
the grid’s conventional supervisory control and data acquisition (SCADA) system. As a
complementary system, WAMS is specifically designed to enhance the operator’s real-time
view of the system in the form of situational awareness along with data sharing between
devices to ensure safe and reliable grid operation. Certain elements of WAMS existed in
basic forms in the Western Interconnection since the early 1990s. A significant contribution of
WAMS technologies was demonstrated during the failure of Western Electricity Coordinating
Council (WECC), the Western power system on August 10, 1996.
During this blackout, WECC system was divided into four asynchronous islands with
heavy loss of load. The results of this breakup, when compared to the dynamic information
being provided by WAMS led to several strategic actions such as remedial action schemes
(RAS) by the electric utilities. The data supported that electric grid operation in WECC
significantly relies on the existing system models and that these models were inadequate in
predicting system responses. One of the greatest benefits realized was that the data contained
precursors of the impending grid failure, which if had been properly analyzed, could have
allowed preventive actions which could have either eliminated or drastically reduced the
impact of the disturbance [9]. The cascading outage of 1996 was one of the biggest driving
forces for further WAMS development and improvement [8].
Chapter 1. Motivation 7
As the increasing demand for electricity over time was not followed by increases in trans-
mission capacity, a tremendous growing pressure bestowed upon the reliability and safety
of the electric grid. Recent large blackouts and outages, such as the August 2003 blackout
in the Northeast and 2011 Southwest Blackout indicated that maintaining the system reli-
ably had become more difficult because of reduced transmission margins and growing system
stress. The report by the U.S.-Canada Power System Outage Task Force on the August 2003
blackout recommended the development and adoption of technologies, such as WAMS, that
could improve system reliability by providing better wide area situational awareness [10].
The continuous data availability through PMUs, as well as their wide distribution through-
out the power system, was also proved beneficial to the post-event inquiry depicting accurate
representation of the events and state of the system at particular points in time throughout
September 2011 WECC (Southwest) disturbance [11].
1.3 Organization of the Dissertation
The dissertation contains six chapters which have been outlined in this section.
Chapter 1: Introduction - The first chapter introduces the dissertation by describing
the role of the mis-operation of protection schemes in large scale blackouts in the
last decade and the importance of adaptivity and wide area situational awareness in
power system protection. The chapter continues on to discuss relevant technologies
that enable many of the topics in this dissertation. The chapter concludes with the
motivation & objective for the work in this dissertation and a outline of the topics
covered in each chapter.
Chapter 2: Technical Background - This chapter outlines technical information related
to discussions and calculations contained in this dissertation. This includes a presenta-
tion of many types of steady-state analysis that are used in the large protection studies
presented in later chapters, transient analysis, a description of the software packages
used in the studies, and a discussion of adaptive power system protection.
Chapter 3: Supervision of Back Up Zones of Protection - CIEE (California Institute
for Energy and Environment) Electric Grid Research Program supported a research
study on the California study system to develop techniques for the supervision of back-
up zones of protection and the identification of locations which may benefit from the
Chapter 1. Motivation 8
implementation of such algorithms. This chapter discusses the work associated with
this study and presents the methodology and the results of the protection study [12].
Chapter 4: Adaptive Loss-of-Field Protection - Another study directly related to the
aforementioned project is one which aimed to develop an adaptive scheme for loss-of-
field relaying [13]. Loss-of-field protection is presented as an introduction to the idea
of an adaptive scheme for loss-of-field conditions.. The chapter continues on to explain
the details of this study and describes the results of the simulations testing the scheme
on the full California study system.
Chapter 5: Impact of Re-distribution of Generation on Protection - This chapter
presents the idea of an approximate linear relationship between the electrical distance
between generators in a power system & the transient change in MW just slightly after
the loss of a generator in the network. The idea is discussed abstractly followed by
numerical examples in the IEEE 39 bus system and the IEEE 118 bus system that verify
the ideas discussed. It is shown that for a small subset of contingencies calculated using
a dynamic simulation that the transient MW output of a generator can be predicted
for the remaining contingencies in a set. The coefficients of determination are used to
measure the effectiveness of the linear regression used in the aforementioned analysis.
A case is made for application to protection studies on large networks and an example
is shown from the IEEE 118 bus system and the WECC system.
Chapter 6 - Conclusion & Future Work - The final chapter summarizes the disserta-
tion and presents future work for the field related to the work described in this disser-
tation including implementation of the discusses protection schemes to various other
study models, utilizing the advanced EMS (Energy Management System)/ SCADA
system to compute more accurate protection settings on-line, addressing the issues
related to loss of WAMS data and their impacts on the proposed schemes and investi-
gation of the communication infrastructure for proper implementation of the research
of this dissertation.
Chapter 2
Technical Background
This chapter aims to explain some of the power system concepts, mathematical models &
tools and protection basics that is relevant to the research topics of this dissertation. This
discussion is provided as prelude to the detailed description in the later chapters.
2.1 Power System Analysis
The behaviors of large power systems are very complex phenomena due to the scale and
interdependency of the different parts of the system; events in geographically distant parts
of the network may interact strongly and in unexpected ways. The analysis of power systems
is concerned with understanding the behaviors of the integrated system with the purpose of
guiding operations and aiding in long term infrastructure planning. Generally, the system is
studied either under steady-state operating conditions or under dynamic conditions during
disturbances and the tools and algorithms used for both types of analysis can vary greatly
from one another in complexity, computational burden, and end use.
Chapters 3, 4 & 5 all present work on power system protection studies in which the
understanding and wielding of the power system analysis toolkit is required. This is not
only because of the type of information desired for the protection studies but also because of
the scale of the systems being studied. Realistic power systems are very large and handling
such large amount of data can be very different than working with many of the systems used
in power system research literatures. This section formally presents the analysis tools that
9
Chapter 2. Technical Background 10
were used in the studies described in the later chapters of the dissertation.
2.1.1 Steady State Analysis
Steady state analysis of power system concerns with small and slow disturbances in the
network, any transients from such disturbances are assumed to be subsided where the system
state is unchanging. Specifically, system load and transmission system losses are precisely
matched with power generation so that the system frequency remains constant. The foremost
concern during steady-state is economic operation of the system. However, reliability is also
important as the system must operate to avoid instability should disturbances or outages
occur. The primary tool for steady-state operation is the so-called load flow analysis, where
the node voltages and power flow through the system is determined using the steady state
power flow equations of the network. The time constant for the steady state operation is
in the order of several seconds to minutes. So all the differential equations involved in the
network model are assumed to be constant. Hence the power flow equations become algebraic
equations that can be solved using a non-linear iterative method such as Newton-Raphson.
This analysis is used for both operation and planning studies and throughout the system at
both the high transmission voltages and the lower distribution system voltages.
This section describes the types of steady-state analysis that have been used in the studies
contained in this dissertation. The bus-admittance matrix is presented as key metric in
steady state analysis as well as a prequel to the Kron network reduction which is used heavily
in Chapter 5 as a tool for removing zero-injection buses from the network. Additionally, the
derivation of generator shift factors and line outage distribution factors are presented as they
were used in heavily in Chapter 3.
2.1.1.1 Bus-Admittance Matrix
Bus-admittance matrix, [Y ], or [Ybus] is an n x n matrix which is fundamental to steady-
state network analysis. It relates current injections at a node to the node voltages in a
power system with n buses. It can be formed from the parameters of system components
such as such as transmission line series and shunt impedances, transformer impedances,
shunt capacitors and reactors etc. The [Y ] matrix is a key building block in formulating a
power flow study and can be written as following,
Chapter 2. Technical Background 11
[I] =
I1
I2
...
In
=
Y11 Y12 . . . Y1n
Y21 Y22 . . . Y2n
......
. . ....
Yn1 Yn2 . . . Ynn
V1
V2
...
Vn
= [Y ] ∗ [V ] (2.1)
The [I] vector contains the current injection phasors, where Ii is the current injection
into bus i and the [V ] vector is the voltage phasors of each node, where Vi represents the
voltage at bus i with respect to ground.
Each diagonal element of admittance matrix, Yii, is known as self admittance of ith
node in a power system and equals to the sum of the admittances connected to ith node,
including the shunt admittances. Each off-diagonal term Yij is known as mutual or transfer
admittance between ith & jth nodes and equals to the negative of all admittances connected
directly between these two nodes. Yij element is non-zero only when there exists a physical
connection between buses i and j. The admittance matrix can be formulated very quickly
from the network parameters through visual inspection. A real power system usually contains
with thousands of nodes, each node is rarely connected to more than two or three other nodes,
therefore most of the elements of the admittance matrix are zero and the [Y ] matrix is sparse.
2.1.1.2 Kron Network Reduction
In the steady-state analysis of an interconnected power system, the system is assumed to
be operating under balanced conditions and is represented by a single phase network. The
network contains all its nodes and branches with impedances specified in per unit on the
system MVA base. In the previous section, the formulation of the bus-admittance matrix
was presented as a key piece of information for many forms of steady-state power system
analysis. There are many situations where the matrix can be simplified by removing nodes
in the system which have zero-injection. This can be accomplished with a mathematical
algorithm called the Kron network reduction. Begin with the node voltage equations for the
power system.
[I] = [Y ][V ] (2.2)
Chapter 2. Technical Background 12
which can be also described as,[Ig
In
]=
[Ygg Ygn
Yng Ynn
]∗
[Vg
Vn
](2.3)
Where Ig and In represent the complex current injections at the generator and non-generator
buses. Also, Vg and Vn represent the complex voltages at the buses with injections and
voltages at zero injection buses, respectively.
In a power system, generator and load buses are considered the injection buses but the
current injection is always zero at buses where there are no external loads or generators
connected. Such nodes may be eliminated. Therefore, all of the loads in the system are
represented as impedances and included in the admittance matrix, as a result all of the
non-generator buses will have zero injection.[In
]= 0
Then, the network equation can be represented as,
[Ig
0
]=
[Ygg Ygn
Yng Ynn
]∗
[Vg
Vn
](2.4)
The matrix form of the network equations can then be separated into two separate equations:
[Ig] = [Ygg][Vg] + [Ygn][Vn] (2.5)
[0] = [Yng][Vg] + [Ynn][Vn] (2.6)
Solving for [Vn] in Equation 2.6 results in the following,
[Vn] = [Ynn]−1[Yng][Vg] (2.7)
Then, by substituting Equation 2.7 into Equation 2.5,
[Ig] = ([Ygg] + [Ygn][Ynn]−1[Yng])[Vn] (2.8)
Chapter 2. Technical Background 13
which again can be represented as the following.
[Ig] = [Yreduced][Vn] (2.9)
where,
[Yreduced] = [Ygg] + [Ygn][Ynn]−1[Yng] (2.10)
This [Yreduced] matrix is a m by m matrix for a system with m generators and each
off-diagonal elements of this matrix represents admittances between two generator buses i.e.
the Y1m element signifies the equivalent admittance between 1st and mth generator.
[Yreduced] =
Y11 Y12 . . . Y1m
Y21 Y22 . . . Y2m
......
. . ....
Ym1 Ym2 . . . Ymm
(2.11)
In Chapter 5, loads in the system will be replaced with impedances making all non-
generator buses zero-injection buses. The Kron network reduction will be used to remove all
of these buses from the bus admittance matrix to create a matrix which is a representation
of the admittance between any two generator buses in the network. The Kron network
reduction is a key steady state analysis tool for the work contained in Chapter 5.
2.1.1.3 Sensitivity Factors
Any practical power system contains very large number of elements. Contingency analysis
requires outages of all these elements one-by-one corresponding to any particular operating
condition. However, the operating point of the system changes quite frequently with change
in loading/generating conditions. For proper monitoring of system security, a large number
of outage cases need to be simulated repeatedly. Analysis of thousands of possible outage
cases with full AC power flow technique involves a significant amount of computation time.
Therefore, much faster techniques based on linear sensitivity factors are used to estimate
the post contingency values of different quantities of interest, instead of using full non-linear
AC power flow analysis. The basic purpose of the linear sensitivity factors is to quickly
approximate any possible violation of operating limits using the changes in line flows for
Chapter 2. Technical Background 14
any particular outage condition without the need of full AC power flow solution. The linear
approximations are derived using the relationships in the DC power flow.
Two such sensitivity factors for checking line flow violations are:
• Generation shift factors(GSF), and
• Line outage distribution factors (LODF)
The GSFs are defined as the relative change in the power flow on a particular line from bus
i to bus j due to a change in injection, ∆Pk, and corresponding withdrawal at the system
swing or slack bus.
The GSFs are linear estimates of the changes in flow with a change in power at one bus.
The total change in flow on each transmission line in the system may be calculated for the
change in injection at one or more buses using superposition. In a real power system, due to
governor actions, the loss of generation at the bus k will be compensated by other generators
throughout the system. A frequently used method is to assume that the loss of generation
is distributed among participating generators in proportion to their machine base, which is
a measure of their size.
LODFs represent the percentage of flow on a contingent line k that will flow on the
monitored elements such as line l, if the contingent facility is disconnected from the system.
After a line outage occurs in a system, the power flowing on that line is redistributed on
to the remaining lines in the system. LODFs determine the contribution of each remaining
lines in the system to reallocate the flow on the line that was taken out-of-service.
In Chapter 3, a study for CIEE is presented which aims to develop algorithms for the
supervision of back-up protection. These sensitivity factors are used to help to identify
locations which could potentially benefit from an implementation of such an algorithm.
2.1.1.4 Calculation of Susceptance Matrix Using DC Power Flow
The linear sensitivity factors are derived under the DC power flow conditions. To discuss
the basis for the DC power flow, the formulation of the Newton power flow equations is
discussed in the following section.
Consider a power system with N buses. Each bus i may be characterized by the net
Chapter 2. Technical Background 15
power injections; real power, Pneti and reactive power, Qneti , and the voltage phasor |Vi|∠θi.The bus admittance matrix is represented by the [Y] matrix. The bus admittance matrix of
diagonal elements Y=[Yij] may be calculated using Equation 2.12.
Y = G+ jB (2.12)
The bus conductance matrix is defined here as G=[Gij] , and the bus susceptance matrix is
defined as B=[Bij]. The diagonal elements Yii of the bus admittance matrix are the algebraic
sums of all of the complex admittances of the lines of the incident bus i. The off- diagonal
elements Yij of the bus admittance matrix are the negative sums of the complex admittances
between buses i and j. The Yij component of the matrix will be non-zero if and only if buses
i and j are connected by a transmission line or transformer. The system can be modelled
using the assumption that the transmission lines may be represented by the π-equivalent
model as shown in the following Figure 2.1.
Figure 2.1: Two-port π-Model of a Transmission Line
With this model, line charging admittances are yci, ycj and the off-diagonal bus admit-
tance matrix elements are determined given by,
Yij = −yij = −gij − jbij (2.13)
In Equation 2.13, the conductance is Gij= gij , and the susceptance is Bij = bij. As the
line impedance can be written as z = r + jx, the admittance term yij may also be written
as a function of the impedance, creating a relationship between the resistance, r, and the
Chapter 2. Technical Background 16
reactance, x.
yij =1
zij=
1
rij + jxij=
rijr2ij + jx2
ij
− j xijr2ij + jx2
ij
(2.14)
So,
Gij = −gij =−rij
r2ij + jx2
ij
(2.15)
Bij = bij =xij
r2ij + jx2
ij
(2.16)
To form the basic power flow equations, bus 1 in the N-bus system is chosen as the slack
bus in which both the voltage, V, and angle, θ, are known and constant. The power flow
equations have the form f(x) = 0 , where x is called the system state containing the bus
angles, θ, and bus voltages V of all of the buses excluding the system slack bus. The power
flow equations are solved by Equation 2.17-2.18 for the buses of the system not including the
system slack bus. For an injection at bus i, the measurements can be expressed as functions
of the state vector and elements of the bus-admittance matrix.
fpi = Pi = Gii|Vi|2 + |Vi|∑
k=busesconnected
toi
|Vk|[Gikcos(θi − θk)−Biksin(θi − θk)]− Pneti = 0 (2.17)
f qi = Qi = Bii|Vi|2 + |Vi|∑
k=busesconnected
toi
|Vk|[Giksin(θi − θk) +Bikcos(θi − θk)]−Qneti = 0 (2.18)
The Newton power flow scheme is an iterative method obtained by the Taylor series
expansion about the initial estimate and neglecting all the higher order terms. Jacobian
matrix provides the linearized relationship between small changes in voltage angle ∆θi and
voltage magnitude ∆|Vi| with the small changes in real and reactive power ∆Pi and ∆Qi.
Using the Newton power flow scheme, a Jacobian matrix can be defined as the gradient of
the power flow equations ∇xg. The structure of the Jacobian matrix appears as shown in
Equation 2.19.
Chapter 2. Technical Background 17
J(x) =∂f
∂x=
[∂fp
∂θ∂fp
∂|V |∂fq
∂θ∂fq
∂|V |
]=
[∂P∂θ
∂P∂|V |
∂Q∂θ
∂Q∂|V |
](2.19)
The equations used in the Newton power flow scheme are simplified to form the decoupled
power flow method by applying the following assumptions according to the terms in the
Jacobian matrix:
1. Power system transmission lines have a high X/R ratio. For such system real power
changes ∆Pi are less sensitive to changes in voltage magnitude and are most sensitive
to changes in phase angles ∆θi.
2. Similarly, reactive power changes ∆Qi are less sensitive to changes in phase angles and
are most sensitive to changes in voltage magnitude ∆Vi.
3. Bii is the sum of susceptances of all the elements incident to bus i. In a typical power
system, the self susceptance Bii � Qi and we may neglect Qi.
4. cos(θi - θk)=1, due to the usually small value of (θi - θk).
5. Also, Gik sin(θi - θk) � Bik
Using the assumptions listed above, the Jacobian equations and power flow equations
can be written as the following sets of equations, respectively.
∂Pi∂θk
= −|Vi||Vk|Bik (2.20)
∂Qi
∂|Vk||Vk|
= −|Vi||Vk|Bik (2.21)
∆Pi = (∂Pi∂θk
)∆θk (2.22)
∆Qi = (∂Qi
∂|Vk||Vk|
)∆|Vk||Vk|
(2.23)
By substituting Equation 2.20 and 2.21 in Equation 2.22-2.23 the following relationships
may be derived,
∆Pi = −|Vi||Vk|Bik∆θk (2.24)
Chapter 2. Technical Background 18
∆Qi = −|Vi||Vk|Bik∆|Vk||Vk|
(2.25)
Dividing the Equation 2.24- 2.25 by |Vi| and assuming |Vk| ∼= 1, further simplification can
be made to the power flow equations,
∆Pi|Vi|
= −Bik∆θk (2.26)
∆Qi
|Vi|= −Bik∆|Vk| (2.27)
Now, these matrix equations for the N-bus system can be represented, respectively.∆P1
|V1|∆P2
|V2|...
∆PN
|VN |
=
−B11 −B12 . . . −B1N
−B21 −B22 . . . −B2N
......
. . ....
−BN1 −BN2 . . . −BNN
∆θ1
∆θ2
...
∆θN
(2.28)
∆Q1
|V1|∆Q2
|V2|...
∆QN
|VN |
=
−B11 −B12 . . . −B1N
−B21 −B22 . . . −B2N
......
. . ....
−BN1 −BN2 . . . −BNN
∆|V1|∆|V2|
...
∆|VN |
(2.29)
To simplify the ∆P −∆θ relationship more assumptions can be made.
• First, all shunt reactances to ground are ignored.
• Second, all shunts to ground from auto-transformers are ignored.
• Lastly, the line resistance can be neglected due to the value of the line resistance
being much smaller than the line reactance, rik � xik, as mentioned earlier, which also
simplifies the Bik calculation.
So,
−Bik =−1
xik(2.30)
The ∆Q−∆|V | relationship is simplified by eliminating the effects from all phase shift
transformers. The simplifications to both relationships create two different B matrices. The
Chapter 2. Technical Background 19
B′ matrix is represented as the new simplified B matrix for the ∆P − ∆θ relationship by
ignoring the shunt susceptances. The off-diagonal elements B′ik are calculated using the
previous Equation 2.30 and the diagonal elements B′ii are also calculated using the sum of
susceptances of all the elements incident to bus i.
B′ik = −Bik =−1
xik(2.31)
B′ii =N∑k=1
1
xik(2.32)
The B′′ matrix is the new simplified B matrix for the ∆Q − ∆|V | relationship. The off-
diagonal elements B′′ik are calculated from Bik. The diagonal elements B′′ik can be calculated
using sum of negative susceptances of all the elements incident to bus i.
B′′ik = Bik =xik
r2ik + x2
ik
(2.33)
B′′ii =N∑k=1
−Bik (2.34)
The B′ik and B′′ik matrices are constant and only need to be calculated once, which is one
of the advantages of the decoupled power flow. The DC power flow is derived from the
decoupled power flow formulation by omitting the ∆Q − ∆|V | relationship and by setting
all |Vi|= 1.0 p.u. As a result, following the DC power flow equation is produced.
∆P = B′∆θ (2.35)
Equation 2.35 implies that the DC power flow only calculates the MW flows on transmission
lines and transformers without giving any information of MVAR flows or voltage magnitudes.
For the research, the information provided by the DC power flow is sufficient. From previous
equations, the power flowing on each line l connecting buses i and j can then be calculated
according to Equation 2.36.
fl = Pij =1
xij(θi − θj) (2.36)
The distribution factors use the standard matrices calculated in the DC power flow equations.
Given the linearity of the DC power flow model, the changes due to any set of system
conditions can be calculated. For this particular investigation, the generation, or power
Chapter 2. Technical Background 20
injection into the bus, is changed at all generator buses. Thus, a relationship between the
resulting change in the bus voltage angles and the change in the bus power injections ∆P
is desired.
Manipulating ∆P −∆θ relationship to calculate the change in bus voltage angles given
a known change in the bus power injections results in Equation 2.37.
∆θ = [X]∆P (2.37)
Then the relationship between the X matrix and the B′ matrix is defined in the next equation.
X = (B′)−1|incremented with a row and column of zeros at swing bus
[X] =
0 . . . 0... B′−1
0
(2.38)
The power on the swing bus is equal to the sum of injections of the remaining buses in the
system. Similarly, the net perturbations of the swing bus, in Equation 2.37 is the sum of the
changes on all other buses. Therefore, the [X] matrix in Equation 2.38 includes an entry of
zeros in the row and column of the system swing bus, considering bus 1 as swing bus.
2.1.1.5 Derivation of Generator Shift Factor
Sensitivity factors can be calculated for a change in power injection at bus k, which is
compensated by an opposite change in power at the swing bus. If the perturbation of
generator on bus k is set to +1.0 per unit power and the perturbation on other buses are
zero, then the power change is re-allocated to the swing/reference bus with -1 per unit power.
The generation shift from bus k to reference bus causes the flow on line l to change. The
ratio of the change in power flow on line l and generation change that occurs at bus k is
defined as the generator shift sensitivity factor(GSF).
The GSF for a line l connecting bus i to bus j with respect to a change in injection at
bus k can be represented by Equation 2.39.
al,k =dfldPk
=d
dPk(
1
xl(θi − θj)) =
1
xl(dθidPk− dθjdPk
) =1
xl(Xik −Xjk) (2.39)
Chapter 2. Technical Background 21
In the previous equation, xl represents the line reactance of line l connecting buses i and j,
and the values Xik and Xjk are the respective elements of the X matrix. The distribution
factors al,k are computed for each generator bus for the system. With M generator buses in
the system, the resulting change in the flow of real power on line l connecting buses i and j
is calculated as ∆Pij using the sensitivity factor from Equation 2.39.
∆Pij = ∆fl =∑k=1,M
al,kPk (2.40)
A generalized generator shift sensitivity factor (GGSF) can be derived when the change
in generation at bus k is compensated by the generation at bus s instead of reference bus.
In this case, the effect of re-allocating +1.0 per unit power from generator located at bus k
is observed as -1.0 per unit power change on a generator located at bus s. The generation
is shifted from bus k to bus s which results in a change of power flow on line l from bus i to
bus j.
GGSFs are calculated from the entries of the bus impedance matrix or [X] of the system
in the base case. The shifts are calculated between pairs of generators, in this case between
generators at bus c and at bus s, taking one pair at a time. In practice, when considering
contingencies, not all possible pairs of generators need be accounted for. Only those pairs of
generators are calculated which have the capability for such a shift [14].
gl,ks =(Xik −Xjk)− (Xis −Xjs)
xl= al,k − al,s (2.41)
GGSFs for line l for a generation shift from bus k to bus s is also the difference between
individual generation shift sensitivity factor for line l to a change in injection at bus k and
the same for shift in generation on bus s.
2.1.1.6 Derivation of Line Outage Distribution Factor
A line outage can be modelled by adding two opposite directional power injections each end
of the line to be dropped. So that the line can be left in the system but the effect of this
line is dropped which is modelled here by injections. Consider a line k from bus n to bus
m. Two injections ∆Pn and ∆Pm are added at each end of the line k where ∆Pn=Pnm and
∆pm=-Pnm. Pnm is equal to the power flowing over the line. Due to the added injections, the
Chapter 2. Technical Background 22
line will have no power through it which implies that the line is disconnected with respect
to the rest of the system [15],
As in Equation 2.37,
∆θ = [X]∆P (2.42)
where,
∆P =
...
∆Pn...
∆Pm...
(2.43)
so that,
∆θn = Xnn∆Pn +Xnm∆Pm (2.44)
∆θm = Xmn∆Pn +Xmm∆Pm (2.45)
According to the outage model criteria, the incremental injections ∆Pn and ∆Pm is equal
to the power flowing over the tripped line Pnm after the injections are added. θn and θm are
the bus voltage angles for bus n and m respectively, after the line outage.
Pnm = ∆Pn = −∆Pm (2.46)
where,
Pnm =1
xk(θn − θm) (2.47)
Then,
∆θn = (Xnn −Xnm)∆Pn (2.48)
∆θm = (Xmn −Xmm)∆Pn (2.49)
xk is the reactance of line k. Pnm is the flow on the line from bus n to bus m, before the line
outage. Similarly, θn and θn are the pre-outage bus voltage angles for bus n and m.
θn = θn + ∆θn (2.50)
θm = θm + ∆θm (2.51)
Chapter 2. Technical Background 23
Replacing θn and θm in Equation 2.47,
Pnm =1
xk(θn − θm) +
1
xk(∆θn −∆θm) (2.52)
Substitution of ∆θn and ∆θm in Equation 2.52 results in the following equation.
Pnm = Pnm +1
xk(Xnn +Xmm − 2Xnm)∆Pn (2.53)
As, Pnm = ∆Pn, the Equation 2.53 is simplified.
∆Pn =1
1− 1xk
(Xnn +Xmm − 2Xnm)Pnm (2.54)
If neither n or m is reference bus in the system, the change in phase angle at a different bus i
can be deduced using the next equation when the two injections ∆Pn and ∆Pm are imposed
at the two ends of line k.
∆θi = Xin∆Pn +Xim∆Pm = (Xin −Xim)∆Pn (2.55)
Again, the substitution of ∆Pn derives,
∆θi =(Xin −Xim)xk
xk − (Xnn +Xmm − 2Xnm)Pnm (2.56)
Assuming a line l from bus i to bus j, the LODF dl,k while monitoring line l can be defined
after an outage on line k using Equation 2.57.
dl,k =∆flPnm
(2.57)
where ∆fl represents the change is flow on line l and Pnm is the original flow on line k, before
it was disconnected.
Now, ∆fl = ∆Pij = 1xl
(∆θi −∆θj), where xl is the reactance of line l.
dl,k =1
xl(
∆θiPnm
− ∆θjPnm
) (2.58)
If neither i nor j is a reference bus, LODF for line l (between bus i and bus j), due to outage
Chapter 2. Technical Background 24
of line k (between bus n and bus m) is derived as,
dl,k =1
xl((Xin −Xim)xk − (Xjn −Xjm)xkxk − (Xnn +Xmm − 2Xnm)
) =xkxl∗ (Xin −Xjn −Xim +Xjm)
xk − (Xnn +Xmm − 2Xnm)(2.59)
2.1.2 Transient Analysis
In steady state, for a specified network configuration, a system supplies real power (P) and
reactive power (Q) at load nodes by adjusting generations. The system is in equilibrium if
the generation and demand in the system are balanced. As load or generation change or
network topology change, the equilibrium point changes. It cannot be determined whether
the transition was smooth or reasonably fast using steady-state analysis. It is possible that
the system loses stability if it is unable to reach the desired new equilibrium. In this case,
steady-state analysis most likely diverges. Dynamic analysis allows observation of how the
operating point of a system moves in the time domain. The path or trajectory of a system’s
operating point reaching a new equilibrium or steady-state may differ depending on its initial
condition, which can be identified with dynamic simulations.
In dynamic analysis, the power system components that are included are synchronous
generators along with their associated excitation systems, prime movers, and governor sys-
tems. Additionally, the interconnecting transmission network which include static loads,
induction and synchronous motor loads or dynamic loads. The controls for these devices
are complex and diverse such as voltage and frequency control, automatic voltage regulators
(AVRs), automatic excitation regulators (AERs). There are other special controls such as
power system stabilizers (PSS), HVDC and FACTS controllers in the system. All of these
control parameters are time varying where some are fast, some are slow. It is necessary
to ensure coordination between such parameters for stable system operation and enhanced
performance.
Dynamic analysis of power system deals with effect of large and sudden disturbances such
as the occurrence of faults, immediate outage of a line or sudden application or removal of
loads/ generations [16]. This study involves with electromechanical transients and neglects
the electromagnetic transients of the network. Hence, it considers only the fundamental
frequency components of voltage and current. The complexity of the component models is
reduced by neglecting differential equations that involve smaller time constant (less than
milliseconds) parameters. A typical time step used for power system dynamic simulation is
Chapter 2. Technical Background 25
10 ms [17].
In Chapters 3, 4 & 5, much steady-state analysis is performed for developing relay
settings and especially searching the network for regions of vulnerability that may be prone
to relay mis-operation or that would benefit from a fundamental change to their relaying
schemes. After the locations have been identified, algorithms developed and the settings
identified, dynamic power system simulations are used in all cases to verify the findings from
the steady-state analysis and to test the efficacy of the new relaying algorithms and settings.
2.2 Power System Simulation Tools
The purpose of this section is to describe the software tools used for the work in this dis-
sertation. Several software packages were used. Beyond the basic software tools such as
spreadsheet tools and text editors, the software packages used includes Matlab and a freely
distributed power system steady-state analysis tool called MATPower that runs inside of
Matlab. Additionally, GE’s PSLF software was used for both steady-state and dynamic
power system simulations in all of the studies described in this dissertation. Below is a more
detailed description of the capabilities of each of the software packages.
MATPower - MATPower is a set of Matlab scripts which were developed at Cornell that
are freely distributed for use by students, faculty, research institutions, and even in-
dustry. The scripts perform many different types of steady-state power system analysis
including power flow, constrained power flows including optimal power flow and secu-
rity constrained economic dispatch, and even energy market studies.
GE’s Positive Sequence Load Flow software (PSLF) - PSLF is an integrated, inter-
active program for simulating, analyzing and optimizing power system performances.
It contains the capability of modeling comprehensive, accurate, and flexible power
system, running load flow with relational database and graphics, fault analysis, dy-
namic simulation, large-scale short-circuit calculations of power system. To implement
the network model of a given power system in PSLF, the physical components like
transmission lines, generators, loads and control systems (excitation and governor) are
included using relational database [18].
Chapter 2. Technical Background 26
2.3 Protection Schemes
This section discusses several of the key protection schemes utilized in this dissertation
including distance & impedance protection schemes as well as loss-of-field relaying schemes
which can be implemented as a form of impedance protection. The section concludes with a
discussion of adaptive power system protection which describes the idea that a relay setting
or relaying scheme may benefit from the ability to adaptive to the current conditions of
the grid particularly with the information made available by wide area measurements and
situational awareness.
2.3.1 Distance & Impedance Protection
On high voltage transmission lines the preferred method of protection is usually through the
application of distance relays or impedance relays as they are often called. Distance relays
are faster, more selective as it uses information from both voltage and current, and easier
to coordinate as they are not affected as much by the changes in generation capacity and
system configuration. The actual point of tripping depends upon the comparison that is the
ratio of voltage to current; the relay is in fact measuring the impedance of the circuit being
protected including the load impedance. However if there is a fault on the line, such as
direct phase to phase fault, then the circuit impedance to the fault is that of the conductors
themselves which is relatively a small value. Indeed, this is the very reason that the current
increased to such a high magnitude.
The relay is set to operate when the measured impedance falls below a specific value. If
the impedance per mile of the line conductor is known, the impedance relay can be set to
trip for faults within any particular distance from the relay. For example, consider the line
in Figure 2.2. It is 150 mile long with a total impedance of 100 ohms. At the half way point,
the line impedance is 50 ohms, at 34
lengths, it is 75 ohms and so on. The relay is located at
substation where bus A is located and close to the breaker. But it can be adjusted to reach
out as far along the line as desired, typically it is set to protect up to 90% of the length of
the line i.e. an impedance of 90 ohms for this particular example. This is because relays
usually have 10% error margin. Such settings are selected to avoid over-reaching protection.
Chapter 2. Technical Background 27
Figure 2.2: Distance Relay Protection
The relay uses secondary values from CTs and PTs and measures secondary impedance.
The relay continuously compares voltage and current, if the primary impedance falls below
90 ohms, it trips its associated breaker. However if a fault occurs beyond the 90% of this
line, the impedance is higher than 90 ohm for such fault and the relay does not operate. So
the relay provides desired selectivity.
Figure 2.3: Distance Relay Protection Zones
An important feature of distance relay is the provision of zone protection, generally with
three zones. It allows the relay to provide back-up protection to its primary zones. Usually
a second element is installed to cover the rest of the line and reach out into the second zone
with impedance setting of 120% of the length of the line (Figure 2.3 ). A third element is
added to reach even further and provide back-up protection for first and second zones. In
Chapter 2. Technical Background 28
each case, a timer is included to delay operation of the second and third elements in order
to allow primary protection operate in those zones.
Generally, the first element of the relay protects the primary zone by opening the first
breaker, breaker A. The second element provides local back-up in case the first element fails
to operate, i.e. it will trip breaker A after a short time delay. The second element also
provides remote back-up in the case of a fault at B or out on line 2. This would only operate
and trip out breaker A, if the primary protection at bus B fails to operate. Similarly, zone 3
protection is provided as remote back-up for faults along the remainder of transmission line
2 and on into line 3.
Figure 2.4: Distance Relay Overlapping Zones
Also, for protection of line between bus A and B as in Figure 2.4, a set of distance
relays will be installed at bus B looking towards Bus A. The first zone elements overlap
and the fault occurring within this zone causes instantaneous operation of both relays and
opening of both breakers. But fault occurring at the last 10% of the line 1, breaker B trips
instantaneously, but it will wait for clearing of zone 2 element of relay at bus A.
A Mho relay is a common type of improved distance relay as it provides directional
protection. Figure 2.5 shows the operational equation and operating characteristic of a Mho
distance element. The characteristic is the locus of all apparent impedance values for which
the relay element is on the verge of operation. The operation zone is located inside the circle.
Chapter 2. Technical Background 29
Figure 2.5: Mho Relay Element Characteristics
The Mho characteristic is a circle passing through the origin of the impedance plane
where the relay element operates for impedances inside the circle. The characteristic is
oriented towards the first quadrant as in Figure 2.5, which is in the direction of forward
faults. For reverse faults, the apparent impedance lies in the third quadrant and represents
a restraint condition. The fact that the circle passes through the origin is an indication of
the inherent directionality of the Mho elements. However, close-in bolted faults result in a
very small voltage at the relay that may result in a loss of the voltage polarizing signal. This
needs to be taken into consideration when selecting the appropriate Mho element polarizing
quantity.
There are typically two settings in a Mho element: the characteristic diameter, ZM , and
the angle of this diameter with respect to the R axis, θM . The angle is equivalent to the
maximum torque angle of a directional element. The relay element presents its longest reach
and greatest sensitivity when the apparent impedance angle θ overlaps with θM . Normally,
θM is set close to the protected line impedance angle to ensure maximum relay sensitivity
for faults and minimum sensitivity for load conditions [19].
2.3.2 Loss-of-Field Protection
When a generator loses excitation capability, it appears to the system as an inductive load,
and the machine begins to absorb a large amount of VARs from the system. Hence, a loss-of-
field condition may be detected by observing for excessive reactive power flow. This condition
can, to some extent, be detected within the excitation system by monitoring field voltage or
Chapter 2. Technical Background 30
current. Small units can use even use power factor or reverse power relays. For generators
that are paralleled to a power system, the preferred method to identify loss-of-field at the
generator terminals using impedance type relays which observes apparent impedance.
Figure 2.6: Generator Capability Curve
The power diagram (P-Q plane) of Figure 2.6 shows a typical capability curve for a
generator which demonstrates various limits for over and under-excitation conditions. The
first quadrant of the diagram applies for lagging power factor operation which is typically
the normal operating state of a generator (generator supplies VARs). The trajectory starts
at point A and moves into the leading power factor zone (4th quadrant) and may readily
exceed the thermal capability of the unit reaching point B during loss-of-field condition. The
apparent impedance seen by a loss of relay also lies in 4th quadrant of the R-X diagram,
so the LOF relay characteristics set the protection boundary in this quadrant depending on
the steady-state stability margin.
Chapter 2. Technical Background 31
Figure 2.7: Impedance Variance during LOF Conditions
The LOF operates when impedance moves from a normal excitation condition to an
under-excitation state which is inside the trip zone and is typically marked by a Mho
impedance circle centered about the X axis, offset from the R axis. With complete loss
of excitation, the generator will eventually act like an induction generator with a positive
slip as the machine speed above synchronous speed, excessive currents can flow in the rotor,
resulting in overheating of elements. When a generating unit is initially supplying reactive
power and then draws reactive power due to los-of-excitation, the reactive swings can sig-
nificantly depress the voltage. In addition, the voltage will oscillate and adversely impact
sensitive loads. Such excessive reactive sink and voltage sag can cause system instability.
It can be observed from the basis of loss-of-field protection that the setting which dictates
when a relay would trip from a loss-of-field condition is calculated by metrics which change
based on the operating condition of the system. Most notably, the Thevenin impedance
will change dramatically for discrete changes in the system such as topology changes which
are close to the generator in question. Chapter 4 investigates a protection scheme which
enables the loss-of-field relay to adapt to prevailing system conditions such as topology
change yielding a more reliable and secure operation of the power system. The next section
introduces the idea that a relaying parameter may benefit from changing based on the current
system conditions.
Chapter 2. Technical Background 32
2.3.3 Adaptive Protection
Adaptive relaying is a concept of power system protection that allows for change and modifi-
cation to relay characteristics to adjust to existing network conditions. In general, protection
systems react to system faults or disturbances based on fixed, predetermined settings dic-
tated by previously observed system parameters. But it is difficult to anticipate all possible
power system scenarios or operating conditions (especially at the transmission level) as the
system is growing and changing so frequently. Even though a protective relay setting con-
siders many possible scenarios reflecting large sets of contingencies, one particular relaying
option may be the best protective solution. The adaptive relaying scheme provides multiple
protection options where individual settings may correspond to specific or a group of con-
tingency scenarios. Descriptions of such adaptive relaying are given in Chapter 3 & 4. An
approach to including a supervisory boundary for zone-3 back-up protection for transmission
lines and generator loss-of-excitation protection is also presented in this dissertation as an
adaptive protection technique to set alarm and indicate system stress so that preventive
actions can be taken to mitigate the emerging strain in the system. The adaptive protec-
tion requires input from various elements of the network to notify the relays about current
system state which is provided by WAMS with the help of phasor measurement units and
other devices (such as dual use line relays used for breaker statuses, or information about
outages) in current practice.
Chapter 3
Supervisory Control for Back-Up
Zone Protection
3.1 Introduction
A distance relay is a protective relay in which the response to the input quantities is primarily
a function of the electrical circuit distance between the relay location and the point of fault
[20]. As seen in Section 2.3.1, the protected zone-2 and -3 of this relay is used as back-up
for the primary protection. It is usually time delayed. In addition, the back-up zone usually
removes more of the system elements than required by the operation of the primary zone of
protection. This is especially true in the case of long transmission lines or zone-3 elements
that have to provide backup protection for lines outgoing from substations with significant
in-feed. This is quite dangerous during wide area disturbances and can result in cascading
failures as seen recently during India blackouts [21].
Due to similar major disturbances in the past during zone-3 relay operations, back-up
protection such as zone-3 was scrutinized and eventually was removed in many situations.
But back-up zone-3 protection is still required in certain scenarios. A solution may be to
monitor other relays in the vicinity to supervise zone-3 [22]. It means that if the protection
zone-3 of a distance relay sees impedance characteristics within its protection boundary but
an appropriate combination of zone-1 relays is not able to see a fault, this zone-3 should be
blocked. CIEE Electric Grid Research Program requested to perform a study on the full
33
Chapter 3. Supervisory Control for Back-Up Zone Protection 34
California study system in GE’s PSLF (Positive Sequence Load Flow Software) and develop
techniques for supervising the back-up zones [23] [12]. This chapter describes work related to
this project and aims to develop schemes for supervising back-up zones with remote phasor
measurements so that back-up protection is not allowed to operate when it is not appropriate.
An exhaustive testing of the developed protection schemes is performed through simulations
in the full California study system.
3.2 Distance Relay Back-up Protection Criteria
Distance relay identifies the impedance between the relay location and the fault from voltage
and current measurements at relay location. For a fault at the remote end of the line, the
voltage at the local relay equals the current multiplied by impedance of the line, i.e. IZ.
Therefore, the ratio of the voltage to the current measured at the relay is effectively the
impedance of the line, Z. As the ratio V/I is proportional to the line length between the
relay and the fault, the ratio V/I, therefore, determines the impedance to the fault. A
distance relay is designed to only operate for faults occurring between the relay location and
the selected reach point and remain unchanged for all faults outside its protection margin
or zone [24].
Figure 3.1: Three Zone Distance (Mho Relay) Characteristics
Chapter 3. Supervisory Control for Back-Up Zone Protection 35
Even though transmission lines are fully protected with zone-1 and zone-2 relays, zone-3
(As in Figure 3.1 ) of a distance relay is used to provide the remote backup protection in
case of the failure of its primary protection and is typically set to cover about 120-180% of
the longest adjacent line. This zone is given a delay time twice that associated with zone-2
operating time to achieve time selectivity, and the time delay is typically set in the range
of 1-2 seconds. Sometimes it is necessary to coordinate the zone-3 relay with over-current
relays on tapped distribution load. The relay should detect any fault for which it is expected
to provide backup and not limit the load carrying capability of the line. The setting of the
zone-3 relay ideally will cover (with adequate margin and with consideration for in-feed, if
required) the protected line, plus all of the longest line leaving the remote station [20].
In this study, 100% of the line in question and 150% of the adjacent longest line are used
as the setting of the zone-3 of the distance relays.
3.3 Load-encroachment and Supervision of Back-up
Protection
Distance relays are usually designed on the basis of fixed impedance setting and this setting
is called a relay reach. In conventional distance relaying the impedance between the relay and
the location of the fault is measured, which indicates whether a fault is internal or external
to its protection zone. However, the disadvantage of using relays is that their settings have
to be reset for changes in the network configuration. The relay either overreaches or under
reaches depending on the operating conditions of the power system and the location of
the fault [25]. In case of long transmission lines the back-up protection relay reach can
be significantly large and the apparent impedance seen by this relays approaches the relay
protective boundary while the loading of the line increases as demonstrated in Figure 3.2.
Impedance characteristics may enter the tripping zone of the relay under very heavy loads
and lead to tripping. This condition where impedance characteristic observed by distance
relay enters the relay protective zone due to the power shift in the transmission lines is
referred to as load encroachment.
Chapter 3. Supervisory Control for Back-Up Zone Protection 36
Figure 3.2: Effect of Load Encroachment on Zone-3 Characteristics
Remote back-up protection is only supposed to operate as a last resort in situations
where all other devices have failed as a measure against the loss of system integrity. Load
encroachments of back-up zones of protection are an unwanted side effect of these types
of protection schemes. WAMS data can give the additional perspective for determining if
there are truly needs to take preventive actions. Multiple views of the system allow relays
to differentiate between trip and block. In this example demonstrated in Figure 3.3, relay
A can identify a violation of loadability limit with respect to a system fault i.e. whether a
zone-3 pick up is appropriate using information from PMUs at neighboring buses B and C.
Chapter 3. Supervisory Control for Back-Up Zone Protection 37
Figure 3.3: Supervision of Backup Protection
3.4 Study Model Description
The proposed protection scheme is developed and tested using full WECC and CA heavy
summer models prepared in GE’s PSLF software.
3.4.1 WECC Full Loop Model
The PSLF model of full WECC heavy summer system that was created in February 2008.
This study system encompasses 15,700 buses with a wide range of interconnected transmis-
sion system connecting over 3000 generators to their loads across almost 1.8 million square
miles of territory. Along with a steady-state load-flow model, the study-system includes
a dynamic representation of WECC system. Generators included in the model are mostly
represented as thermal units and all machines contain appropriate dynamic elements such as
Chapter 3. Supervisory Control for Back-Up Zone Protection 38
governor models, excitation system, power system stabilizer, static VAR compensator, static
synchronous condenser and some protection models to accurately represent the real system
and also improve the dynamic stability of the study system. The total system demand is
over 150GW represented by mostly constant current loads & frequency-dependent loads and
some constant impedance & constant power loads distributed within 18 partners or utilities
in the Western Interconnect. The Pacific high voltage DC link and WECC-Eastern Interface
DC tie are also included in this model.
3.4.2 California Model
California study system is a reduced model created from the WECC full loop model. This
model consists of over 4000 buses that are spread around within 6 main electric utilities in
the CA region. Over thousand generators supporting almost 56 GW of load demands and
power injections from outside California are represented with two large equivalent generators
in the Northern and the South-eastern interfaces. Seven 500 kV tie-lines are also included
to interconnect California power system with the external buses of the remaining WECC
system. Table 3.1 contains the list of inter-ties for the CA system.
500 kV Lines Linking utilities Interfaces
Navajo - Crystal AZ Public Service Co. - L.A. Dept. of Water & Power AZMoenkopi Eldorado AZ Public Service Co. - Southern CA Edison AZHassyampa- N.Gila AZ Public Service Co. - San Diego Gas & Electric Co. AZPaloverde- Devers AZ Public Service Co. - Southern CA Edison AZ
Mead- Marketplace NV Power Company - L.A. Dept. of Water & Power NVCapt. Jack- Olinda Bonneville Power Admin. - Pacific Gas & Electric ORMalin- Round Mt. PacifiCorp - Pacific Gas & Electric OR
Table 3.1: 500 kV Links in CA System
3.5 Selection of Appropriate Location for Back-up
Protection
To implement the supervisory protection scheme, the critical locations are to be detected
where the back-up will be needed. This opts for a detailed understanding of the study system
Chapter 3. Supervisory Control for Back-Up Zone Protection 39
and critical elements of the system. Critical elements are those that if lost or tripped the
stability of the power system will be on stake. Identifications of critical lines are crucial
because when a line trips in the system other lines try to make up for the power loss by
transmitting power to the load to be fed by the tripped line. If a line is tripped which has a
large portion of total power flow here referred as a critical line, this loss may not be quickly
restored by the others as over-loading may occur. As a result, the back-up zone-3 protection
of these overloaded lines may seen impedance characteristics within its protection boundary
which can be identified by the relay as an in-zone fault instead of load-encroachment. In
this case operation of the relay by tripping the line to clear zone-3 fault is a mistake. This
unnecessary outage of heavy loaded lines can initiate cascading failure in the system and
cause blackouts.
As a part of the load-encroachment study, the method of line outage distribution factor
(LODF) is applied here perform first screening of the critical lines. The goal is to find the
line with large LODF, for one or multiple contingencies which may cause over-loads at lines
near an outage.
3.5.1 Line Outage Distribution Factors
LODF gives the percent of flow from the outage line that ends up flowing on another line.
As discussed before for a line outage, loss of power flow on that line will be carried by
other lines. Figure 3.4(b) shows line1−3, from bus 1 to 3 is out of service, part of the flow
S1−3 of line1−3 (Figure 3.4(a)) is being carried by other lines; the percentage of S1−3 is the
distribution factor for that line1−3.
Chapter 3. Supervisory Control for Back-Up Zone Protection 40
Figure 3.4: Principle of LODF (a) L13 in service. (b)L13 out of service (unknown source)
3.5.1.1 Technique for Determining Line Outage Distribution Factor
Before the line outage contingency occur, the impedance matrix, [Z] ans system susceptance
matrix [X] are computed considering the initial topology of the system as described in Section
2.1.3. Distribution factor Krs,pq represents the fraction of the power in the line p-q that goes
out which ends up in line r-s after the outage.
drs,pq =xpqxrs
(Xrp −Xsp −Xrp +Xsq)
xpq − (Xpp +Xqq − 2Xpq)(3.1)
Where xpq is the impedance of the line p-q and Xpq is the pqth element of susceptance
matrix, X [15]. If the power on line r-s and line p-q is known, the flow on the line r-s, due
to the outage of line p-q can be determined using the drs,pq factors.
frs = f 0rs + drs,pq ∗ f 0
pq (3.2)
Where f 0rs and f 0
pq are the pre-outage flows on the lines r-s and p-q, respectively frs is
the flow on line r-s after line p-q out.
Chapter 3. Supervisory Control for Back-Up Zone Protection 41
3.6 Implementation of LODF to California
(Heavy Summer) Model
To apply the distribution factor analysis to the full California power system model, under-
standing of the system parameters and familiarization with PSLF (GE Positive Sequence
Load Flow Software)are necessary as the system is modelled using the software. As LODFs
are to be found in terms of bus suceptance matrix or [X] matrix which is computed from
bus admittance matrix, [Ybus] for the California network, with around 4000 buses and 4474
lines as described in Section 2.1.3.
3.6.1 Formation of LODF Matrix for CA System and
Identification of Critical Lines
Using Equation 3.1, distribution factors for each single line contingencies are calculated and
a 4474 x 4474 dimensional LODF matrix is formed. As LODF gives the percent of flow from
the outage line that ends up flowing on another line, distribution factor, drs,pq represents
the fraction of the power in the line p-q that goes out which ends up in line r-s after the
outage. Using the Equation 3.2, post-contingency power flows in the lines are calculated.
Considering a power factor (0.8 0.9), the thermal capacity of the lines are compared with
the post-contingency power flows in the lines and overloads are detected. Lines with 30% or
more overloads are considered as critical lines.
3.6.2 Identification of Zone 3 Settings for Critical Lines after
Single Contingency
(n − 1) contingencies are created and the corresponding critical lines are monitored. The
zone-3 setting of critical lines were identified considering Mho relays, i.e. the apparent
impedances is seen by the relays in normal condition. The apparent impedances seen by the
relays due to the pre-determined overloads are determined. As the load on a line increases,
the apparent impedance locus approaches the origin of the R-X diagram. For some value of
line loading, the apparent impedance may cross into the zone of protection of a relay, and
may cause the relay to trip, this is called an encroachment of protective zone.
Chapter 3. Supervisory Control for Back-Up Zone Protection 42
3.6.2.1 Relay Settings for Multi-Terminal Lines
When the multi-terminal lines have sources of generation behind the tap points, or if there
are grounded neutral wye-delta power transformers at more than two terminals, the pro-
tection system design requires careful study of infeed currents. Consider a three-terminal
transmission line as shown in Figure 3.5 for this study.
Figure 3.5: Effect of Infeeds on Zone Settings of Distance Relays
For a fault at F , there is a contribution to the fault current from each of the three
terminals. (For simplicity, it is assumed that this is a single-phase system and the actual
distance evaluations for each type of fault must be considered. This aspect of multi-terminal
line protection is no different from the usual considerations of faults on a three-phase system.)
The voltage at bus 1 is related to the current at the same bus by Equation 3.3,
E1 = Z1I1 + Zf (I1 + I2) (3.3)
and the apparent impedance seen by relay R1 can be computed as,
Zapp =E1
I1
= Z1 + Zf (1 +I2
I1
) (3.4)
where the true impedance to the fault is,
Ztrue = Z1 + Zf (3.5)
Chapter 3. Supervisory Control for Back-Up Zone Protection 43
The current I2, the contribution to the fault from the line tap which is referred as
the infeed current when it is approximately in phase with I1, completely arbitrary phase
relationships are also possible, but in most cases the phase relationship is such that the
current I2 is an infeed current.
The apparent impedance seen by relay R1 that is shown in Equation 3.4 demonstrates
that it results in being larger than the actual value if the tap current is an infeed. As the
setting of zone-1 of relay R1 is usually about 80 90% of the actual line length(impedance)
1-2, for many of the faults inside the zone of protection will appear to be outside the zone of
the relay, and the relay will not detect such faults. It would also be insecure to set zone-1 of
the relay to higher value, in order to retain the apparent impedances for all faults inside the
zone-1 setting. For, such a setting, if the tap source should be out of service for some reason,
faults beyond the 80 90% point may cause zone-1 operation of this relay. In this case, the
infeed current should not be considered for defining zone-1 settings /citePhadke1994.
Subsequently, zones-2 and -3 of relay R1 are set to reach beyond buses 2 and 3, respec-
tively, under all possible configurations of the tap. As a result, these over-reaching zone
settings must consider contributions of all the infeeds. Then, even if some of the infeeds
should be out of service, the apparent impedances seen by the relay will be smaller, and will
definitely reside inside the protective zones.
3.7 Multiple Contingency Studies
Since no encroachment of zone 3 protective zones was found with single contingencies, over-
loads for multiple contingencies were studied. The study was started with contingencies like
500 kV line outage which created heavy overloads (30% or more of line capacity, maximum
MVA rating) along with generator outages. Performing this contingency analysis, it was ob-
served that for all generator outages, PSLS load flow add the MW losses in the system with
the Swing Generators. In the CA Study system there are 2 swing generators, one located in
the Northern boundary and the other in the Eastern boundary of CA. These swing genera-
tors are also modelled as equivalent generators outside CA. As a result of normal load-flow
in PSLF, all generation mismatches were picked up by these two equivalent generators, but
in the real system, the outage generations are to be distributed to the rest of the genera-
tors (in-service) according to their machine inertia. Inertial re-dispatch was performed for
Chapter 3. Supervisory Control for Back-Up Zone Protection 44
generator outage contingencies.
3.7.1 Inertial Re-Dispatch of Generators
Inertia of generators indicate the amount of reserved rotating energy in the system. Under
steady state conditions the mechanical and electrical energy must be balanced. When the
system has a generation loss, the electrical demand at each remaining generator terminal
lacks the mechanical energy supplied, as result the system frequency rises. The rate of change
of frequency increase dependant upon the initial power mismatch and system inertia. The
speed of each machines will continue to reduce until the total mechanical power supplied to
the whole system matches to the electrical demand. The stored kinetic energy of the rotating
machines are delivered to grid as MW power.
For a synchronous machine inertia constant H is frequently specified. It is defined as the
ratio of the stored kinetic energy at rated speed to the rated apparent power of the machine
(MVA rating). This yields,
H =stored kinetic energy at synchronous speed in mega-Joules
generator MVA rating=Wk
SB(3.6)
where WK is the kinetic energy of the rotating mass(generator) and SB is the rated MVA of
the machine which indicates the size of the machine.
Since most of the generators in the CA system is represented as thermal units, similarity
in machine inertia constants are observed. So, H can be defined as a constant in Equation 3.5.
Then the amount of energy stored in each rotating machines become directly proportional to
the size of that machine(generator base/rated MVA) and it can be inferred that the bigger
the generators are the larger contributions to make-up for a generation loss.
For steady state analysis, it is agreed that ∆P at a generator will be ∝ Srated to that
machine. So after a generator outage contingency, the MW mismatch is accounted for by
re-dispatching the other generators(in service) based on their machine base, Srated . In the
post-contingency, change in real power output in generators using Equation 3.7,
∆Px =Srated,xSrated,total
∆Ptotal (3.7)
Chapter 3. Supervisory Control for Back-Up Zone Protection 45
Where, ∆Px is the change in MW in machine x, after re-dispatch, ∆Ptotal is the total gener-
ation loss in MW in the whole system, before re-dispatch, Srated,x is machine base of machine
x, Srated,total is the total of machine bases in whole system. A multiple contingency analysis
was performed based on this concept utilizing the following algorithm to find overloads and
encroachments of back up zone (zone-3).
Figure 3.6: Flow-Chart for Inertial Re-dispatch of Generators
Chapter 3. Supervisory Control for Back-Up Zone Protection 46
3.7.2 Comparison between CA and Full-Loop Study System
To verify our generator inertial re-dispatch algorithm, the same generator outage contin-
gencies were performed in both the Full-loop study system, which is a complete model of
WECC power system, it has the actual generators outside CA included in it. But these
generators are modelled as equivalents in the CA study system. It was observed that in the
Full-loop model 66-70% of make-up generations come from generators outside CA and in
the CA model 70-73% of losses were picked up by the equivalents modelled as generators
outside CA. After validating the algorithm with the testing in both systems, the multiple
contingency studies were performed.
3.8 Load-Encroachment Examples in CA System
The apparent impedance entering the protective zone due to the shifting of power flows
as result of changes in transmission network structure. This is especially true in the case
of long transmission lines or zone-3 elements that have to provide backup protection for
lines outgoing from substations with significant in-feed as the back-up zone protection char-
acteristic circle reaches very far. Again, zone-3 protective circle of a relatively short line
encloses a large protection area which makes the back-up zone to over-reach and be prone
to load-ability violation. Such a line between Captain Jack (500kV) and Olinda (500kV) is
demonstrated in the WECC map in Figure 3.7 which follows by a long transmission line
from Olinda (500kV) to Tracy (500kV). Hence, the zone-3 setting of Mho relay located at
Captain Jack looking toward Olinda is significantly larger than its primary zones as shown
in Figure 3.8.
Chapter 3. Supervisory Control for Back-Up Zone Protection 47
Figure 3.7: WECC Map, Relay at Captain Jack (500kV Bus) [23]
Captain Jack- Olinda is a segment of path 66 is an inter-tie between PG&E and Pacifi-
Corp 500 kV lines. This route technically starts at Captain Jack station close to Malin, very
close to California-Oregon border, near the Malin substation, where the other 500 kV lines
start another link between PacifiCorp & PG&E. These substations also link to Bonneville
Power Administration (BPA) grid in the Pacific Northwest and brings large amount of power
to CA system through the PG&E high voltage lines. Consider, the loss of one of these links
due to maintenance or faults which stresses and increase loading in Captain Jack-Olinda
line. Such heavy loads causes apparent impedance seen by the Mho relay located at Cap-
tain Jack enter the zone-3 margin of this relay as shown in Figure 3.8 and may lead to an
inappropriate relay tripping. Both 500 kV lines between Round Mt. and Table Mt. are
taken out-of-service to simulate the loss of the tie-line between California and the Pacific
Northwest.
Chapter 3. Supervisory Control for Back-Up Zone Protection 48
Figure 3.8: R-X Characteristics of Relay at Captain Jack (500kv bus), Monitoring Line fromCaptain Jack to Olinda
In this section the area of focus is the Midway- Vincent 500 kV lines with three parallel
circuits which are high voltage corridors between PG&E and S. California two major utilities
in WECC system. Scenarios are considered where Mho distance relays are located both end
of the lines and observe the characteristics of the over-reaching back-up zone protection.
Using the California Study System, power flow is monitored through this important link.
Power flow congestion is created in these corridors to simulate the impedance trajectories
observed by the relays and identify scenarios where the impedance plots encroach the back-up
zones of protection.
Transient studies are performed which determined the R-X characteristics observed by
the Mho relays protecting Midway-Vincent lines. The MVA ratings for Midway-Vincent
lines are listed in Table 3.2 as gathered from PSLF system model.
Chapter 3. Supervisory Control for Back-Up Zone Protection 49
Midway-Vincent Line Current Rating ACircuit No. (MVA)
1 1848.12 2309.73 1848.1
Table 3.2: Midway-Vincent Line Ratings
As mentioned in Table 3.2, the circuit 2 between Midway-Vincent line (500kV) has the
highest flow capability among all three circuits where circuit 1 and 3 has the same rating.
Either of the lower rated circuit 1 or 3 is able to sustain losses of both circuit 2 and one of
the lower rated circuits in the heavy summer model of the California Study System. So some
of the adjacent lines to Midway 500 kV bus is tripped to increase power flow in the single
in-service line between Midway and Vincent to simulated load encroachment scenarios and
impedance characteristics seen by relays are monitored. But impedance plot (Figure 3.9 )
still remains far away from the zone of protection. As a result, total loads in S.California
area are increased to create flow over-loads in the single in-service MidwayVincent line (500
kV). Some examples are presented below to portray the R-X behaviors to be observed by
the relays: (zone-1, -2 & -3 protections are shown with blue circles; the red circle around the
zone 3 represents the supervisory boundary which is set at 150% of zone-3 protection).
Multiple contingencies listed below are applied and impedance trajectory due to load
increase in Midway-Vincent line is monitored as shown in Figure 3.9 where distance relay is
located at Midway bus (500kV) looking toward Vincent (500kV).
• 500 kV Lines out-of-service from Midway to Vincent, circuit 1 & 3 for maintenance at
1.0 sec.
• 500 kV Line out-of-service between Midway & Losbanos to fault at 2.0 sec.
• 500 kV Lines out-of-service between Gates & Losbanos to fault both circuits at 2.5 sec.
• Transformer failure from Gates (500kV) to Gates(230kV) at 3.0 sec.
Chapter 3. Supervisory Control for Back-Up Zone Protection 50
Figure 3.9: R-X Characteristics of Relay at Midway (500kV bus), Monitoring Line fromMidway to Vincent, ck 2
Another example of impedance trajectory during load increase in Midway-Vincent line is
monitored is illustrated in Figure 3.10 where distance relay is again located at Midway
bus(500kV) looking toward Vincent(500kV). In this scenario, a 40% increase of S. California
loads are simulated to further over-load the monitored line than the previous case so that
impedance characteristics observed by distance relay at Midway approaches the supervisory
boundary of the back-up protection margin of the relay. The Step by step contingencies
which are applied to simulated the R-X trajectory in Figure 3.10 are listed below.
• 500 kV Lines out-of-service from Midway to Vincent, circuit 1 & 3 for maintenance at
1.0 sec.
• 500 kV Line out-of-service between Midway & Losbanos to fault at 2.0 sec.
• 500 kV Lines out-of-service between Gates & Losbanos to fault both circuits at 2.5 sec.
• Transformer failure from Gates (500kV) to Gates(230kV) at 3.0 sec.
• 40% load increase in S. California area(24) at 3.5 sec.
Chapter 3. Supervisory Control for Back-Up Zone Protection 51
Figure 3.10: R-X Characteristics of Relay at Midway (500kV Bus), Monitoring Line fromMidway to Vincent, ck 2
If the total loads in S. California Edison is increased up to 75% of the base case scenario along
with the other contingencies in the previous case, the Midway-Vincent line is furthermore
overloaded. The load-ability limit of this line imposed by the zone-3 of the distance relay
at Midway is violated as the impedance trajectory seen by this relay enters the back-up
protection boundary or tripping zone of the relay as demonstrated in Figure 3.11. But the
relay at Vincent Mho characteristic is oriented towards the first quadrant as in Figure 3.12,
which is in the direction of forward faults toward Midway and the apparent impedance lies
in the third quadrant during the flow overload so this relay protection is not violated.
Chapter 3. Supervisory Control for Back-Up Zone Protection 52
Figure 3.11: R-X Characteristics of Relay at Midway (500kV Bus), Monitoring Line fromMidway to Vincent, ck 2
Figure 3.12: R-X Characteristics of Relay at Vincent (500kV Bus), Monitoring Line fromMidway to Vincent, ck 2
Chapter 3. Supervisory Control for Back-Up Zone Protection 53
3.9 Summary
Zone-3 distance relays are key elements in power system protection that are implemented
to detect faults on the protected transmission line and beyond to cover remote elements.
Besides providing back-up protection to its primary zones, these relays are often utilized for
equipment protection further ahead of the line and also used as an alternative protection to
equipment failure communication systems. As these relays over-reach to protect transmission
lines against remote faults, these may become susceptible to loadability violations. As seen
in the simulation cases in CA system, back-up relays can see the apparent impedance to be
within the impedance circle or the zone-3 reach of these relays due to increased loading in the
lines. Inclusion of a supervisory boundary to the back-up protection improves the distance
protection scheme which allows notification of approaching line over-loads and provision of
adjustment to avoid cascading line failures.
Chapter 4
Adaptive Loss-of-Field Protection
In the field of power system protection there are a great variety of protection schemes which
act to prevent damage to critical parts of the electric infrastructure. And just as there are
many types of protection schemes, there are many types of relays which act to physically
implement the protection schemes created by protection engineers. This chapter focuses on a
specific type of relaying called loss-of-field (LOF) relaying. This type of relaying is important
for protecting generators from a particular instability condition where the generator loses its
rotor field. A generator may lose its excitation due to inadvertent field breaker tripping, a
field open circuit, a field short circuit, voltage regulator failure, or loss-of-excitation system
supply [27]. While a typical LOF condition is partial, a complete loss-of-excitation can occur
in rare instances.
When a synchronous generator incurs a LOF condition it draws reactive power from the
system which damages rotor. This is caused by heavy loading of the generator windings due
to the excessive reactive power consumption which dictates heating of the rotor windings
and potentially a loss of magnetic coupling between the rotor and the stator. Because this
condition creates an increasing reactive power demand on the neighbouring area it has the
potential to cause the bus voltages to decline near the generator experiencing the loss-of-field
condition. This condition at a large generator such as major fossil plants can quickly cause
voltage collapse at nearby system and can even endanger the voltage stability of the rest of
the power system [28]. Therefore, LOF condition on a generator is a critical state of the
power system which should be identified as fast as possible, and the effect of loss-of-field on
the power system stability has to be assumed and investigated in order to prevent voltage
54
Chapter 4. Adaptive Loss-of-Field Protection 55
collapse or cascading failure of the network [29].
4.1 LOF Relaying Background
Impedance type loss-of-field relays are applied at the generator terminals to detect failure
of the generator excitation in the form of DC voltage or short circuit. The LOF relay is
designed to recognize this condition and trip the generator within one second of the failure.
The LOF relay settings consists of two concentric circles; the inner circle is the impedance
boundary criterion of actual steady state stability limit, which if encroached, will lead to
loss of synchronization of the generator, pole slipping and its eventual tripping. The outer
circle is used to create an alarm for system operators if the apparent impedance seen by
the relay indicates an operating condition which requires immediate action to mitigate an
impending problem. As described in the following section, the steady state stability limit
circle is affected by the system operating conditions, which has the potential to result in a
mis-operation of the LOF relay. In this chapter, an approach for creating coherent groups
of generators and finding the LOF settings for the generator members of the group which
allows on-line identifying system conditions based on wide area measurements. Thus the
steady state stability limit circle can be adaptively fit for different operating conditions.
The limits of stability are expressed as settings in the R-X plane for distance relays.
The setting of the loss-of-field relays is based upon generator voltage, generator impedance,
and the Thevenin impedance of the system as seen from the generator terminals. Clearly
the generator impedance is constant, but the system Thevenin impedance changes as the
structure of the power system changes and the terminal voltage of the generator may also
vary. However, because the changes due to the generator voltage are minimal, it can be
assumed that the only varying quantity in the equation is the Thevenin impedance which
changes most dramatically when there is a discrete change in impedance due to a topology
change (example: line outage). Consider a scenario where the power system is in a vulnerable
state because of a particular line outage or multiple line outages. In this scenario, the system
Thevenin impedance will increase; this reflects the evolving weakness of the power system.
As the Thevenin impedance increases, the steady-state stability margin will shrink, and the
LOF relay settings in place on the generators are then inappropriate [26]. In certain cases
of cascading failures, this may lead to a generator trip without getting a warning, further
exacerbating the situation.
Chapter 4. Adaptive Loss-of-Field Protection 56
The goal of this research is to determine adaptive LOF relay settings for generator
protection with remote phasor measurements so that these generator protection schemes are
not allowed to operate when it is not appropriate [23] [13]. This chapter aims to develop
an adaptive LOF relaying criteria for generators using the system Thevenin impedance as a
varying element with respect to the current system operating mode. California study system
in PSLF is used for testing and simulations to identify adaptive LOF protection settings for
generators in the system and validate the adjustment of relay based on system changes due
to events or disturbances.
4.2 Loss-of-Field Relay Protection Criteria
This section explains the reason that a loss-of-field condition is considered as a steady-state
instability. Figure 4.1 demonstrates the phasor diagram of the terminal voltage E1, stator
current I1, and the internal voltage of the generator Es. Also shown is the field circuit with
a field current If .
Figure 4.1: Phasor Diagram of Generator Voltage and Current during Reduced Excitation
If the effects of generator saturation is neglected, the voltage Es and the field current
If are proportional to each other. As a result the phasor Es (magnitude) can be used to
Chapter 4. Adaptive Loss-of-Field Protection 57
represent the field current. If the field current of the generator decreases which causes the
loss-of-field condition, the output real power P is not affected. Since the power P is equal
to EI cos θ, where θ is the power factor angle and in normal operating condition, current
lags voltage. The projection of the stator current vector I1 on the axis of E1 is a constant
parameter even if the field current changes. This is represented by x in Figure 4.1.
Now consider a decrease of field current If which causes the internal voltage of the
generator Es to drop. In order to maintain the phasor relationship between Es, E1 and I1
under these conditions, as Es reduces in magnitude the vector must move along the dashed
horizontal line and the current I1 must move along the dashed vertical line. This relationship
retains the output real power constant at P , while the stator current moves from I1 position
to I1′, the power factor goes from a lagging to a leading angle. The machine absorbs reactive
power from the system when the field current reduces or generator loses excitation [30] [26].
Figure 4.2: Loss-of-Field as an Instability Condition
The ratio of E1 to I1 is the apparent impedance Z or (R + jX) seen by LOF relay (a
distance relay) connected at the terminals of the generator. If x is constant, the apparent
impedance travels along the circle, crossing over from the first quadrant to the fourth quad-
rant. The characteristics of the impedance relays which define the steady stability margin
and a supervisory boundary for alarm are also shown in Figure 4.2. It is clear that as the field
Chapter 4. Adaptive Loss-of-Field Protection 58
current of the generator drops, the generator goes from a lagging power factor to a leading
power factor, and the apparent impedance seen by a distance relay quickly approaches the
steady-state stability boundary which is discussed in the following sections [26].
4.2.1 Steady State Instability as a Consequence of LOF Condition
Consider a simple system consisting of one machine connected to a power system where the
rest of the system is condensed into a single machine and impedance as shown in Figure 4.3
Figure 4.3: Simple System for Steady-State Stability Analysis
The internal voltage of the machine is Es and the machine reactance isXs. The equivalent
impedance (Thevenin) of the power system is Xt and power system equivalent voltage is E2.
Since steady-state analysis is considered here, the voltage Es is the field voltage Ef , and the
reactance Xs is the the synchronous reactance Xd. The total reactance between the machine
internal bus and E2 is X = Xs + Xt. The electric power output at the machine terminals
(at bus S or at bus 2) is given by Equation 4.1.
Pe =EsE2
Xsin δ (4.1)
where δ is the angle by which the machine internal voltage Es leads E0. The mechanical
power input to the machine is Pm, and in steady state electrical power and mechanical power
are in balance at a rotor angle δ0 which is zero when the machine is operating in steady state
at δ0. The rate of change of the output power Pe with respect to δ is given by Equation 4.2.
∂Pe∂δ
=EsE2
Xcos δ (4.2)
which remains positive for −π/2 ≤ δ ≤ π/2. This is the range of steady-state stability for
the system. Because the generator must have a positive output, the steady-state stability
Chapter 4. Adaptive Loss-of-Field Protection 59
limit of interest is δ = π/2. This remains positive for −π/2 ≤ δ ≤ π/2. This is the range of
steady-state stability for the system.
Figure 4.4: Steady-State Stability Limit (a) A Circle in the P-Q Plane (b) A Circle in theR-X Plane [26]
The real and reactive power outputs of the machine (as measured at the machine termi-
nals) are given by Equation 4.3.
P1 + jQ1 = E1I1 (4.3)
At the steady-state stability limit of the machine, the rotor angle is π/2, and it can be shown
that, at the stability limit, P1 and Q1 satisfy Equation 4.4.
P 21 +
[Q1 −
E21
2
(1
Xt
− 1
Xs
)]2
=
[E2
1
2
(1
Xt
− 1
Xs
)]2
(4.4)
This is an equation of a circle in the P -Q plane, as shown in Figure 4.4(a). The response of
the distance relay is determined when the machine is operating at its steady-state limit. It
can be shown that a circle in the P -Q plane maps into a circle in the apparent R-X plane.
Whether or not a machine approaches a limit (such as a steady-state stability limit) defined
by a circle in the P -Q plane can then be detected by the corresponding circle in the R-X
plane, using a distance relay. Let us take a general circle in the P -Q plane, with its center
at (P0, Q0), and a radius of S0. This is given in Equation 4.5.
(P − P0)2 + (Q−Q0)2 = S20 (4.5)
Chapter 4. Adaptive Loss-of-Field Protection 60
For example, in the case of the steady-state stability limit given in Equation 4.4, these
values are given by Equation 4.6-4.8.
P0 = 0 (4.6)
Q0 =E2
1
2
(1
Xt
− 1
Xs
)(4.7)
S0 =E2
1
2
(1
Xt
− 1
Xs
)(4.8)
Figure 4.5: Apparent Impedance Seen by an Impedance Relay (a) Generator Connectedto Power System (b) Generator Supplying the Same Power to Parallel Load (c) GeneratorSupplying the Same Power to a Series-Connected Load [26]
Consider the three circuits shown in Figure 4.5 where Figure 4.5(a) shows a generator
with output P + jQ with a terminal voltage, E. Figure 4.5(b) shows the generator with
the same terminal conditions but now supplying an impedance load R and X connected in
parallel at the generator terminal. The parallel impedances are next converted to series-
connected R and X, which are related to the terminal conditions by Equation 4.9-4.10.
P =E2R
R2 +X2(4.9)
Q =E2X
R2 +X2(4.10)
Substituting Equation 4.9 & 4.10 into Equation 4.8 results in Equation. 4.11.
(R−R0)2 + (X −X0)2 = Z20 (4.11)
This is an equation of a circle in the R-X plane with its center at (R0, X0) and a radius of
Chapter 4. Adaptive Loss-of-Field Protection 61
Z0 as in Figure 4.4(b) where these parameters are given by Equation 4.12-4.14.
R0 =P0E
2
P 20 +Q2
0 − S20
(4.12)
X0 =Q0E
2
P 20 +Q2
0 − S20
(4.13)
Z0 =S0E
2
P 20 +Q2
0 − S20
(4.14)
The circle in the impedance R-X plane for the steady-state stability limit is shown in Figure
4.4(b). For this case, the values can be substituted for P0, Q0 and S0 from Equation 4.6-4.8
using E for the machine terminal voltage, rather than E1. The LOF relay settings are then
given in Equation 4.15-4.17 [26].
R0 = 0 (4.15)
X0 =Xt +Xs
2(4.16)
Z0 =−(Xt −Xs)
2(4.17)
4.2.2 Steady State Stability Limit Circle
The steady state stability limit, as explained in the previous section, reflects the ability of the
generator to adjust for gradual load changes. The steady state stability limit is a function of
the generator voltage and the impedances of the generator, step-up transformer and system
(Thevenin equivalent impedance). This method assumes field excitation remains constant
(no AVR) and is conservative. When calculating, all impedances is converted to the same
MVA base, as the generator base. The steady state stability limit is a circle defined by the
equations shown in Figure 4.6 below where xt=xtrans+xthev [31]:
Chapter 4. Adaptive Loss-of-Field Protection 62
Figure 4.6: Graphical Method for Steady State Stability Limit
In traditional LOF protection, the size of the steady state stability limit circle is un-
changed once the relay is commissioned. However, in a practical system, the size of the
steady state stability limit circle is related with the system operating modes and changes
from time to time as the loading of the system changes or due to an event [32].
As previously mentioned, the steady state stability limit boundary impedance locus is
a circle as shown in Figure 4.6. The center of the impedance circle is located at the point
(0, −j(Xt−Xs)2
) and the radius is (Xt+Xs)2
. From Figure 4.6, it can be seen that the center and
the radius of the steady state stability limit circle are actually dependent on the system’s
Thevenin equivalent impedance since the impedance of the generator and the transformer
remain constant. When the system impedance increases, the radius gets larger and the center
moves up. At the same time, the new steady static stability impedance circle becomes larger,
covering the previous area. When the system impedance decreases, the radius gets smaller
and the center moves down.
Chapter 4. Adaptive Loss-of-Field Protection 63
4.3 Development Adaptive LOF Relay Scheme
This section and the rest of the chapter describe the work related to a study to implement
an adaptive LOF relaying scheme for generator protection using wide area measurements to
prevent mis-operation of the LOF relays when the steady-state stability limit changes due
to a topology change. This includes exhaustive testing using the California study system
to develop the group settings for the LOF relays and to test the relaying schemes through
simulations. The scheme as explained in the previous section uses an impedance relay as
the measuring element for loss-of-field for a generator. The application for this project is
based on the behavior of the system impedance as seen from the generator terminals for
various under-excited conditions or contingencies in the system. The primary indicator that
a generator or a machine has lost its excitation is the high reactive flow into the machine
[26]. So the final impedance after an under-excitation condition lies in the fourth quadrant
of the R-X diagram. Any relay characteristic that will initiate an action in this quadrant is
applicable [33]. Once again, the question of whether to trip or to alarm for this condition
must be addressed. In almost every case, an alarm is provided early in the locus of the
impedance swing so the operator can take the appropriate corrective action.
In order to make the relay settings adaptive, different system conditions (line outages)
are identified and the corresponding settings are calculated for each discrete condition. The
LOF relay settings depend on the synchronous reactance Xd and Thevenin reactance of
the power system, Xt at the generator terminal. Since any topology change close to that
terminal will change the value of Xt, the relay will be trained to adapt to these topology
changes and create a LOF relay setting group for each generator or generator groups. Each
member of LOF relay setting group will be correspond to the LOF settings for a specific
operation condition. After identifying the current operation condition using the wide area
knowledge of the topology of the network, the relay will adapt to the system and change
its setting. In the California study system, generators are connected to the system through
their step-up transformers which are referred as the generator groups.
Chapter 4. Adaptive Loss-of-Field Protection 64
Figure 4.7: LOF Relay at Diablo Machine Terminal
Figure 4.7 shows an example of the relay settings at the terminal of generators at Diablo.
The radius increased showing that the LOF relay setting changed from its normal conditions
after a contingency. This contingency was created by taking a line out-of-service adjacent
to bus Diablo (This example is elaborated in Section 4.3.2. With this scenario, the pre-
contingency and post-contingency Xt values need to be calculated. Additionally, it should
be noted that the Thevenin reactance of the power system at the machine terminal changes
significantly. LOF relay setting are determined by simulations using GE’s PSLF on California
Study System.
4.3.1 LOF Group Settings
The proposed adaptive LOF relay setting consists of two concentric circles for a specific
system operating mode as seen in Figure 4.8. The inner circle is the impedance boundary
criterion of actual steady state stability limit. Encroachment of this limit circle leads to loss
of synchronization of the generator, pole slipping and its eventual tripping. The outer circle
is used to create an alarm for the system operator if the apparent impedance seen by the
relay creates operating condition which requires mitigation. If the power system can supply
reactive power to the generator without a significant drop in voltage, an alarm is set off for
possible corrective action, followed by a shut-down trip after a particular time delay. Typical
Chapter 4. Adaptive Loss-of-Field Protection 65
delays used vary with machine and system, but are 10 sec to 1 min.
Figure 4.8: LOF Relay Settings
Simulation results gathered from California study system demonstrate that the steady
state stability limit circle is affected by the system operating conditions, which may cause the
LOF relay to mis-operate. Hence, this research calls for LOF protection for each generator
which is provided by a group of settings instead of individual one where each setting corre-
sponds to a different operating mode. This setting group allows on-line identification and
selection correct LOF settings for each generator depending on the current system conditions.
Consider, the example of generator Dibalo1 in CA system as seen in the previous section.
From the analysis above, it can be seen that the LOF protection is not accurate if the
steady state stability limit circle cannot adapt to the change of the system impedance when
the system operating mode varies. So, the LOF settings for the generator Dibalo1 should
consider for all possible scenario which causes system the Thevenin reactance to change
as result generator’s stability will change. The system impedance is calculated considering
generator Dibalo1 connected to a power system where the rest of the system is condensed
into a single machine and impedance as shown in Figure 4.9.
Chapter 4. Adaptive Loss-of-Field Protection 66
Figure 4.9: Dibalo1- One Machine Infinite Bus
All contingency cases (one bus away) that may affect the system’s reactance for Dibalo1
is considered and each Thevenin reactance calculated using short circuit analysis in GE’s
PSLF per scenario. So, LOF protection for Dibalo1 generator is provided by multiple of
settings with respect to the system’s current condition instead of one fixed setting as seen
in Figure 4.10. If the current operating mode can be provided on-line, then it is possible for
the relay located at Dibalo1 to select and modify the appropriate settings according to the
change of the system which may allow reliability of protection and operating speed of the
LOF relay to be improved.
Figure 4.10: LOF Relay Settings
Chapter 4. Adaptive Loss-of-Field Protection 67
4.3.2 Adaptive LOF Relay Application in CA System
To demonstrate an implementation of these group settings that has just been discussed, an
example scenario is shown below where loss-of-field relay is located at Diablo1 generator. The
generator step up transformer is connected to the Diablo 500 kV bus. It has two adjacent
paths; one transmission line to Gates and parallel sub-transmission lines going to Midway.
Diablo2 generator is also connected to the 500 kV bus as in Figure 4.11 one-line diagram.
Figure 4.11: Network Diagram near Diablo
The steady state stability limit of a generator defines the LOF relay characteristics is
calculated based on the generator voltage, the impedances of the generator, step-up trans-
former and system’s Thevenin equivalent impedance. In traditional LOF protection, the
size of the steady state stability limit circle is a fixed value once the relay is commissioned
which is determined for a specific system impedance calculated from a base operating con-
dition. However, in a practical system, the size of the steady state stability limit boundary
changes with the system operating modes as the loading of the system changes or due to
disturbances. The traditional LOF relay setting for a relay located at Diablo1 generator
terminal is represented by the red circle as shown in Figure 4.12. This setting is calculated
considering a system Thevenin impedance for the normal operating scenario where all of the
power system elements in Figure 4.11 remain in-service.
Chapter 4. Adaptive Loss-of-Field Protection 68
Figure 4.12: Apparent Impedances Seen by Traditional Relay after LOF Conditions
As demonstrated in Section 4.3, system’s Thevenin reactance becomes larger when the
connection between the generator and the rest of the network is weaken due to outages of
adjacent transmission lines, as a result the steady state stability limit circle for the generator
gets bigger also. Figure 4.13 exhibits loss-of-field relay settings for two scenarios which
compares conventional LOF schemes with the proposed adaptive LOF protection. The red
circle here represents the traditional setting calculated based on the normal operating mode
and the blue circle corresponds to the adaptive relay setting which is dictated by the current
system condition where a contingency is created by tripping the 500 kV line between Diablo
and Gates. The apparent impedances seen by the relays during the generator’s loss-of-field
conditions are also compared in Figure 4.13 for these two operation modes. The impedance
trajectory is different during the contingency case (purple) than the normal condition(cyan).
The system reactance becomes larger for the contingency case, as a result the steady state
stability limit circle gets bigger for the adaptive relay condition. But the traditional method
still sets the protective device according to the smaller circle and does not identify the system
change which eventually results in false tripping of the generator. In this case, the impedance
locus enters the stability boundary 300 ms before the traditional could detect it. Hence the
generator trips due to instability sooner that its traditional LOF relay can even identify
loss-of-excitation scenario which is harmful to the security of system and the generator. In
Chapter 4. Adaptive Loss-of-Field Protection 69
addition, adaptive LOF scheme provides an supervisory boundary to the stability limit for
alarms which allows provision to take preventive measures as demonstrated in Figure 4.14.
Figure 4.13: Apparent Impedances Seen by Relay after LOF Conditions - Relay at Diablo1
Figure 4.14: Apparent Impedances Seen by Relay after LOF Conditions - Relay at Diablo1
Chapter 4. Adaptive Loss-of-Field Protection 70
Loss-of-field relay settings for conventional relays is again compared with the adaptive
LOF protection setting which determined based on the present system condition where both
of the 500 kV lines from Diablo to Midway are taken out-of-service, as seen in Figure 4.15.
The red circle represents the traditional setting calculated based on the normal operating
mode, similar to the previous example and the green circle corresponds to the adaptive relay
setting which is dictated by the contingency scenario. The system reactance becomes even
larger than previous example during line outage case due to the severity of the event, as a
result the steady state stability limit circle gets even bigger for the adaptive relay condition.
Again, the impedance locus is different, when the system’s operating condition changes due
to outage of both the lines between Diablo and Midway (purple trajectory). With traditional
LOF relay, the generator may lose synchronization well before it encroaches its stability limit
(which is not adjusted for system change) which may cause the generator to be tripped almost
700ms earlier than it is predicted.
Figure 4.15: Apparent Impedances Seen by Relay after LOF Conditions - Relay at Diablo1
Chapter 4. Adaptive Loss-of-Field Protection 71
4.4 Summary
A static impedance boundary criterion of steady state stability limit is widely used to identify
loss-of-field conditions in the conventional LOF protection. This boundary is truly dependent
on the system’s operating condition, specifically the local topology of the network. This static
boundary of steady-state stability is prone to mis-operation is it doesn’t have the capability
of adjustment based on the changes in the network. If an adaptive LOF approach is desired,
the system conditions can be identified on-line using wide area measurements provided by
PMU devices and adaptive relay settings can be realized. This improves the reliability and
the operating speed of the LOF protection, which is advantageous for the security of the
generator and the power system as a whole. The simulation results from the California
Study system demonstrate that the proposed ideas can improve the performance of these
protective relays.
Chapter 5
Impact of Generation Re-distribution
Immediately after Generation Loss
At any point in time, the total power output of all of the generators must balance with the
total system load including losses. This idea is clearly evident during steady-state conditions.
However, consider a scenario where some type of discrete change on the network such as a
loss of load, or (more specific to this chapter) a forced generator outage occurs abruptly. In
any of these scenarios, the balance of the network is disrupted instantaneously. However,
it follows that due to conservation of energy that the network must also instantaneously
compensate for the balance disruption by (in the case of a generator outage) increasing the
power out of the terminals of remaining generators and decreasing the power into loads
who’s value depends on system conditions such as frequency or current. The energy used
to instantaneously balance the network after a discrete disruption in the generation-load
equilibrium comes from the stored kinetic energy in the rotors of all of the generators that
are connected to the network. After a negative step change in generation in the network,
generators all across the network responds by increasing the power output at the terminals
by converting stored kinetic energy into electrical energy with the side effect of slowing
the rotation of the rotors thereby decreasing the system frequency. Following this reaction
generator control systems increases the mechanical input power to the rotor to bring the
system frequency back to nominal. The amount of compensation by each generator just
after a step change in the operating point is much different than the contributions once the
network has again reached a steady-state condition.
72
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 73
The obvious question which follows this observation is how much kinetic energy in each
generator is converted to electrical energy and subsequently injected onto the network to
balance the load demand. Note that this is different than using several steady-state tech-
niques to find generator contributions after contingencies because these techniques dictate
that the system will have already reached steady-state. Power flows out of the terminals of
the generator directly after a discrete disruption in the power balance of the network is a
function of the condition of the network before the contingency (operating point & network
topology), the particular contingency that occurred (the network topology right after the
contingency). The control systems of generators do not have enough time to react for the
factors used in steady-state analysis to take effect.
A detailed dynamic analysis of the system is indeed the appropriate method here which
is obviously the multi-time-scale simulation of short- and long-term dynamics of system
parameters. Such simulations remain quite computationally demanding as well in terms of
computing time, data maintenance and output processing [34].
To ease the computational burden, approximations can be made using an inertial re-
dispatch to determine the re-distribution of power after a generation loss or load increase.
An inertial re-dispatch considers the current output of the generator when assigning changes
in generation output. While this approach is useful in its own right, in the context of
steady-state analysis. It does not serve the purpose of efficiently and simplistically evaluat-
ing the power re-distribution across the network on a time scale just slightly following the
change even before the system attains the next steady-state. Additionally, redistribution of
generation based on generator inertia may not consider the topology of the system.
In this chapter a non-computationally intensive method (an alternative to comprehensive
dynamic simulations) is discussed for finding the re-distribution of power in a network just
slightly after a contingency (before generators’ primary control systems can operate) and
to observe how the electrical distances from generators to the location of initial change or
contingency may affect this re-distribution. This study aims to investigate the effect of a
system change such as a generation loss just slightly after the change which uses a Kron
network reduction method to remove non-generator buses from the system and determine
relation of redistributed injections with electrical distance between the generator buses. To
visualize the role of the network impedances in the re-distribution of power in this scenario,
illustrative examples are presented which discusses the contributions of generators based on
their location in the system with respect to a contingency location.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 74
To determine the generator injections just slightly after a contingency, dynamic simula-
tion is performed using GE’s PSLF on study systems. The goal is to demonstrate that the
redistribution of the MW output of the generation is affected by the electrical distance to
each of the remaining in-service generators which are responsible for loads being served in
the system. These new injections of the remaining generators cause changes in transmission
flows and may create threat to protection.
5.1 Generation Re-distribution with Respect to Loca-
tion
This section discusses the ideas surrounding what happens to the balance of power in a
network the instant after a discrete disruption to the power balance. The ideas herein are
discussed at a very high level for the presentation of the general concept. Later sections
present mathematical metrics for evaluating many of the ideas discussed in this section.
Consider the generic scenario of the network portrayed in Figure 5.1. There is a generator
in the Northern part (which is referred to as the northern generator G1 for this discussion)
which serves load in the northern part of the grid and is then connected via a long transmis-
sion corridor with the larger network in the south. In the southern network, there are four
generators (which is referred to as the north-western (G2) , north-eastern (G3), south-western
(G3), and south-eastern (G4) generators) which all serve loads in the southern network.
Figure 5.1: Abstract Power System
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 75
Using superposition of the flow of electrical power in a network it can be stated that
each generator actually serves each load in some amount. However, for the purposes of
this discussion, it is assumed that the distribution of each generators contribution to the
network favors those loads which are electrically closest to the source. The footprint of each
generator (the loads which are served heavily by the respective generator) are demonstrated
in Figure 5.2. Each generator serves loads which are electrically closest to it and some loads
are served by multiple generators when the electrical distance between the load and each of
the generators is close in value.
Figure 5.2: Distribution of Generation in an Abstract Power System
Such a perspective on the contributions of individual generators allows the proper vi-
sualization of the effect of a generator in a system. Consider the scenario shown in Figure
5.3 where the G5 is suddenly tripped out of service. The impact of the loss of the generator
can be thought of as depriving those loads which were served in majority by that particular
generator source. Thus it is left up to the remaining generators to supply this energy to
these loads.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 76
Figure 5.3: Loss of Generator G4 in an Abstract Power System
It can be taken that the amount of power provided by each remaining generators for
each load left by the outage is inversely proportional to the electrical distance between
those generators and each of the loads which needs to be served. Generators which are
electrically closest to the power deficient loads provide a larger portion of that energy than
those generators which are farther from other loads. This is illustrated in Figure 5.4 by the
resizing of the circles which represent the footprints of each of the generators in the abstract
power system discussed in this section.
Figure 5.4: Re-distribution of Generation in an Abstract Power System, Just after theContingency
A parallel can be drawn between the generic system described in this section and a real
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 77
system such as WECC power system. Consider, generator at Diablo Canyon Nuclear Power
Station in California (Northwest of Los Angeles) and generation units in Moss Landing,
Morro Bay, Kern are nearby machines. If the outage of the generations at Diablo Canyon
is considered all the mentioned generations in the contingency vicinity mostly pick-up the
instantaneous changes in output power (Map included in Figure 5.15 ). Even though there
are large generation units located at southern part of Washington State such as generations
at Benton county, Tacoma etc, immediate impact of the generation loss at Diablo is trivial to
theese Northern machines due to their location i.e quite large electrical distance with respect
to the event location.
The discussion in this section concerning the abstract power system shown in Figures
5.1 - 5.4 can be summarized with the following two ideas.
1. A major portion of the output of each generator serves those loads which are electrically
closest to it in proportion to the electrical distance between the generator in question
and each of the loads in the network.
2. After the loss of a generator, those generators that are electrically closer to the loads
left un-served by the contingency provide more energy to the network than those which
are farther from the loads. The amount of MW contribution is inversely proportional
to the electrical distance between each of the generators and each of the loads.
The merging of these two ideas infers that after a discrete disruption in the power balance
of the network such as a generator outage, the generators which are electrically closer to the
contingency (the generator that tripped) contribute more to serve the energy deficit in the
network proportional to their electrical distance to the contingency. Despite this being an
obvious approximation, the reason that the above inference is significant is the electrical
distance between generators can be determined using knowledge of the network topology
and lines impedances. This is discussed in detail in the proceeding section.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 78
5.2 Generator Location as a Function of Admittance
from an Event Location
As presented in the previous section, after a discrete change in the power balance of the
network, the system responds immediately depending on relative locations of sources and
demands. A generator which is close to the loads that were supported by the generator
lost due to the contingency feels the greatest impact. A metric for describing the electrical
distance between a generator and the outage location can be created using the impedance
or admittance between the generators. This process is demonstrated in this section using
the IEEE 39 bus system and the IEEE 118 bus system.
5.2.1 Network Reduction to Determine Admittance between
Generators
The bus-admittance matrix of a power network contains elements which are indicative of the
inter-connectivity of the network. A matrix element with zero value means that no direct
connection exists between two nodes in the system. However, the off-diagonal non-zero
elements represent the admittance (electrical distance) between two nodes in the network.
In order to determine the admittance between each of the generator nodes, the admittance
matrix must be reduced so that all off-diagonal elements contain some non-zero value which
represents a metric of electrical distance between generators nodes (despite the generator
nodes not sharing a direct connection).
Consider the network equations which can be formulated using the node-voltage method
for a power system[16] with m number of generator buses and n number of non-generator
buses. [Ig
In
]=
[Ygg Ygn
Yng Ynn
]∗
[Vg
Vn
](5.1)
Where Ig and In represent the complex current injections at the generator and non-generator
buses. Also, Vg and Vn represent the complex voltages at the generator/injection buses and
non-injection buses, respectively. The load buses can considered as non-injection as they are
represented as impedances and included in the admittance matrix so that these buses have
zero injections. The admittance matrix can reduced to only relate the buses with injections
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 79
i.e. the generator buses which is presented with Equation 5.1 ,
[Ig] = [Yreduced][Vn] (5.2)
Where
[Yreduced] = [Ygg] + [Ygn][Ynn]−1[Yng] (5.3)
[Yreduced] has the dimensions m x m, as the system has m number of generators. If the
loads are not considered to be constant impedances, the identity of the load buses must be
retained. For this study all loads are converted into constant impedances using the load bus
voltages and currents, also eliminated from the network equation. An elaborated description
of network reduction and derivation of this desired reduced matrix are provided in Chapter
2.
5.2.2 IEEE 39 Bus System Examples
This section presents a numerical example of the algorithm described in the previous section
implemented on the IEEE 39 Bus System. The IEEE 39 bus system has 10 generators and
will therefore yield a reduced matrix, [Yreduced] which has dimensions 10 x 10. Figure 5.5
shows the one-line diagram of the IEEE 39 bus system.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 80
Figure 5.5: One Line Diagram of IEEE 39 Bus System
The equivalent system created using network reduction technique presents an exact re-
production of the self and transfer impedances of the reduced system as seen from its gener-
ator buses. So, each non-diagonal element represents the admittance between each generator
buses. The bus admittance matrix of the IEEE 39 bus system was reduced to only include
the generator nodes in the network and therefore all of the off-diagonal elements represents
the effective admittance between each of the generator nodes in the network. The numerical
value of [Yreduced] is shown below.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 81
Yreduced =
32.517 2.250 2.542 1.842 0.813 1.949 1.070 11.432 3.123 7.248
2.250 26.119 10.221 1.429 0.630 1.512 0.830 1.269 0.763 5.569
2.542 10.221 27.393 2.022 0.892 2.140 1.174 1.467 0.955 4.401
1.842 1.429 2.022 33.631 16.209 4.745 2.604 1.309 1.374 1.060
0.813 0.630 0.892 16.209 24.759 2.093 1.149 0.578 0.606 0.468
1.949 1.512 2.140 4.745 2.093 31.311 13.867 1.386 1.454 1.122
1.070 0.830 1.174 2.604 1.149 13.867 23.464 0.761 0.798 0.616
11.432 1.269 1.467 1.309 0.578 1.386 0.761 26.251 3.975 3.647
3.123 0.763 0.955 1.374 0.606 1.454 0.798 3.975 14.596 1.154
7.248 5.569 4.401 1.060 0.468 1.122 0.616 3.647 1.154 24.243
In order to compare the power injections at generators and admittances between the
each of the generators and a particular generator which is abruptly taken out of service,
a dynamic simulation was conducted. Generator 3 located at bus 32 in the IEEE 39 bus
system was taken out of service 1 second into the dynamic simulation. The number which is
of importance here is the step change in the value of the power coming out of the terminals
of each of the other generators. The power output of each of the generators is shown in
Figure 5.6.
Figure 5.6: MW Outputs of Remaining Generators after Generator 3 at Bus 32 Outage
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 82
Figure 5.7 shows the change in MW output of the generator after the contingency at two
different times. The red shows the change in MW output at the instant of the contingency.
This is a measure of the amount of the generators’ stored kinetic energy which is converted
to electrical energy to instantaneously balance the discrete change in generation. The blue
shows the change in MW output of the generator from the pre-contingency state to the post-
contingency steady-state condition. The purpose of this graph is to demonstrate that the
change in power output directly after the contingency is not the same as the power output
once the system has reached steady state. In fact, the two are not even proportional to each
other.
Figure 5.7: Histogram of MW Outputs of Remaining Generator after Generator 3 at Bus 32Outage
Previously, it has been stated that the distribution of the pick-up of each of the generators
directly after the loss of another generator is dictated by the electrical distance between
each of the generators which remain in service and the generator which is lost. From the
[Yreduced] matrix calculated above, the distance between all of the generators left in service
and generator 3 (the machine which was lost) can be evaluated. To do this, the 3rd column
of the matrix is used because it corresponds to generator 3. Now, a column vector, each
of the elements of the column are associate by their row number with a particular bus and
therefore a particular generator. When those values are mapped to the corresponding change
in MW (just after the contingency) calculated using the dynamic simulation it can be seen
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 83
that the two sets are approximately linearly proportional to each other. Figure 5.8 shows
this as a plot of the admittances between each of the generators and generator 3 has been
superimposed on a plot of the transient change in MW of each of the respective generators.
Figure 5.8: MW Output at Remaining Generator after Generator 3 at Bus 32 Outage
The same procedure was repeated by removing generator 7 instead of generator 3. The
results of the dynamic simulation are shown below in Figure 5.9.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 84
Figure 5.9: MW Output at Remaining Generator after Generator 7 at Bus 36 Outage
As in the previous example, Figure 5.10 shows the transient change in MW output of
the generator in red. In blue, the difference between the pre-contingency MW output and
the post-contingency steady-state output is shown. Again, there is a dramatic difference
between the two and they are not proportional to each other.
Figure 5.10: Histogram of MW Outputs of Remaining Generator after Generator 7 at Bus36 Outage
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 85
Similarly, column 7 of the [Yreduced] matrix was used to determine the admittance between
each of the generators and generator 7 (the machine which was lost) and a plot of this was
superimposed on a plot of the transient change in MW output of the generator. Again, the
results in Figure 5.11 show that the two sets are approximately linearly proportional to each
other.
Figure 5.11: MW Output at Remaining Generator after Generator 7 at Bus 36 Outage
5.2.3 IEEE 118 Bus System Examples
In order to demonstrate that this observation is ubiquitous among different networks and not
just a special property of the IEEE 39 bus system the above procedure have been repeated
here on three different examples in the IEEE 118 bus system. The IEEE 118 bus system
contains 118 buses, 186 branches, 91 loads, and 54 generators. The generators at bus 10,
80, and 66 were the subject of these three examples, respectively. As with the previous
demonstration on the IEEE 39 bus system, the results show that admittance between each
of the generators and the generator which tripped are approximately linearly proportional
to the transient changes in MW just after the loss of the generator. Only the results are
shown in this section (Figures 5.12 - 5.14 ) to avoid unnecessary redundancy.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 86
Figure 5.12: MW Output at Remaining Generator after Generator at Bus 10 Outage
Figure 5.13: MW Output at Remaining Generator after Generator at Bus 80 Outage
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 87
Figure 5.14: MW Output at Remaining Generator after Generator at Bus 66 Outage
5.2.4 WECC System Examples
Again, dynamic simulation is performed on WECC system by tripping two generator units
at Diablo, in order to illustrate the linear proportionality of the transient changes in MW
at generators with the admittances of each of these generators from a particular generator
which is abruptly tripped. Figure 5.15 shows the change in MW output of the generator
after this contingency at two different time scales. The red shows generators that has the
most change in MW output at the instant of the contingency. The blue shows the generators
that has biggest changes in MW output of the generator from the pre-contingency state to
the post-contingency steady-state condition. This graph again demonstrates that the major
changes in power output directly after the contingency occurs in the contingency area even
though the next steady-state power re-distribution might not be the same.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 88
Figure 5.15: Generators Dibalo 1 & 2 Outage in WECC System
5.3 Linear Regression to Predict Power Injection
Changes at Generators after Contingency
In the previous section, it was established that immediately after a generation loss, the real
power generation pick-up by the remaining generators are approximately linearly propor-
tional to the admittances between those generators and the out-of-service generator. All the
nodes in the system except for the internal generator nodes are eliminated to obtain the
admittance matrix, [Yreduced], for the reduced network. The larger the admittance between
two generator buses, the smaller the impedance or electrical distance between them. There-
fore, the approximate linear proportionality of the admittances between generators and the
contingency with the transient change in MW directly after the contingency verifies the as-
sumptions in the discussion in Section 5.1. It then follows that with the knowledge of the
network impedances & topology, the size in MW of the contingency, and most importantly
the knowledge of the aforementioned linear relationship, an educated guess can be made of
the transient response of the of the generators which remain in the network. The question
then becomes how to quantify the linear relationship. This can be done using a simple linear
regression on the admittances and the transient changes in MW.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 89
If the ith generator trips in a system with N generators and the admittance between each
of the remaining N-1 generator buses and the ith generator bus is represented by [y]i. The
vector [y]i contains the off-diagonal elements of ith column of the reduced admittance matrix
therefore it has (N-1) number of rows. The corresponding real power injection changes at
each of these generators immediately after the loss of ith generator is represented by the
vector [∆Pdyn]i. A simple linear regression illustrates the relation between the dependent
variables of [∆Pdyn]i and the independent variables of [y]i based on the regression equation,
[∆Pdyn]i = β0i + β1i ∗ [y]i + [r]i for ith= 1st, 2nd,...N th generator outage (5.4)
Where, β0i and β1i are the regression coefficients and ri is the residual matrix. The linear
regression can determine the values of the coefficients β0i and β1i which are the y-intercept
and the slope, respectively, of the line which represents the best linear approximation of the
linear relationship between the two data sets.
5.3.1 IEEE 39 Bus System Examples
Consider an example in the IEEE 39 bus system with 10 generator buses (System data and
one line diagram for this study model is shown in Appendix A.1 ). If the generator 1 is
taken out-of-service and the admittances between each of the remaining nine generators and
generator 1 are shown in [y]1. Vector [y]1 has all nine of the off-diagonal elements in 1st
column of the reduced admittance matrix. The corresponding real power injection changes
at each of these nine generators immediately after the loss of generator 1 is shown here by
the vector [∆Pdyn]1. Both [y]1 and [∆Pdyn]1 are normalized by dividing each element of these
vectors by the sum of all elements of the respective vector. Now the following relationship
can be derived using regression as in Equation 5.6,
[∆Pdyn]1 = β01 + β11 ∗ [y]1 + [r]1
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 90
Where,
0.103
0.090
0.079
0.061
0.075
0.054
0.250
0.107
0.181
= β01 + β11 ∗
0.070
0.079
0.057
0.025
0.060
0.033
0.354
0.097
0.225
+ [r]1
Performing the regression yields β01=0.045 and β11=0.589 when generator 1 is out-of-service.
Figure 5.16 demonstrates the linear relationship between [y]1 and [∆Pdyn]1, after generator
1 at bus 30 is taken out-of-service, where both vectors are normalized.
Figure 5.16: Immediate Injection Changes at Generators Buses after Generator 1 Outage
Consider another example in the IEEE 39 bus system. In this case, generator 3 is
tripped and the admittances between each of the remaining nine generators and generator
3 are similarly represented by [y]3 which contains all nine of the off-diagonal elements in 3rd
column of the reduced admittance matrix. The respective real power injection changes at
each of these nine generators immediately after the loss of generator 3 is represented by the
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 91
vector [∆Pdyn]3. Similar to the previous case, both [y]3 and [∆Pdyn]3 are also normalized by
dividing each element of these vectors by the sum of all elements of the respective vector.
So, the following relationship can be derived using the regression equation in Equation 5.6,
[∆Pdyn]3 = β03 + β13 ∗ [y]3 + [r]3
In this case, β03=0.044 and β13=0.612 when generator 3 is out-of-service. The linear rela-
tionship between [y]3 and [∆Pdyn]3 are shown in Figure 5.17, after generator 3 at bus 32 is
taken out-of-service, where both vectors are again normalized.
Figure 5.17: Immediate Injection Changes at Generators Buses after Generator 3 Outage
Similarly, immediately after generator 10 is lost from the IEEE 39 bus system a linear
relationship can be seen between the admittances of the generators that remain in-service
from the contingency location and the change in real power injection at those generators. For
generator 10 outage case, the regression coefficients are, β010=0.033 and β110=0.798. Figure
5.18 demonstrates the linear relationship between [y]10 and [∆Pdyn]10 after the outage of
generator 10 at bus 39, where both vectors are normalized.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 92
Figure 5.18: Immediate Injection Changes at Generators Buses after Generator 10 Outage
In Figure 5.19, each of the 10 generators contingency is considered except for the swing
generator case. All of the nine cases demonstrates a linear relationship between the ad-
mittances of the remaining generators in-service from the tripped generator and the change
in real power injection at those generators, immediately after each respective generator is
lost from the IEEE 39 bus system. In Figure 5.19 the actual admittances and MW values
are shown for better visualization where each color shows results from individual generator
outage case. Figure 5.20 demonstrates the linear relationship between the admittances and
change in power injections where both vectors are normalized after each of the generators is
taken out-of-service individually (except for the swing generator).
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 93
Figure 5.19: Immediate Injection Changes at Generators Buses after Each Generators Outage
Figure 5.20: Immediate Injection Changes at Generators Buses after Each Generators Outage
If the linear relationship in Equation 5.6 can somehow be determined without the knowl-
edge of the transient change in MW then contribution of each of the generators (transient
change in MW) can be predicted right after a generator loss. This seems evident and of no
value. However, an observant individual should notice that while it is true that the rela-
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 94
tionship between the admittances and transient MW changes is approximately linear for all
contingencies, the quantitative linear relationship (slope and y-intercept of the best fit line)
is different for different contingencies. Table 5.1 shows the slopes and y-intercepts alongside
the MW size of the contingency. It can be observed that the size of the contingency is pro-
portional to the slope of the line. This observation makes sense in that a larger contingency
requires more stored kinetic energy to be injected into the network.
Gen No. MW Slope y-intercept
1 205.9 0.589 0.0453 561.8 0.612 0.04410 824.2 0.798 0.033
Table 5.1: Slopes & y-Intercepts of Best Fitted Lines alongside Transient MW Changes
With this knowledge, only a sample of simulations should be done and the slopes and y-
intercepts of the best fits lines of those contingencies should be calculated as described in the
previous section. Then, another linear regression can be performed where the independent
variable is the MW size of the aforementioned sample of contingencies and the dependent
variable is the slope of the best fit lines of each of the respective contingencies. This process
should also be repeated using the y-intercepts as the dependent variable.
For example, from Table 5.1, when generator 1 supplying 205.9 MW is lost from the sys-
tem, β01=0.045 and β11=0.589. Again, for generator 3 contingency case which supplies 561.8
MW, β03=0.044 and β13=0.612. The regression coefficients are, β010=0.033 and β110=0.798
for generator 10 outage contingency case which generates 824.2 MW power. So, it can be
considered that β0 and β1 are two dependent variables where Ploss, the MW loss of the
contingency generator is the dependent variable. Two separate simple linear regression il-
lustrates the relation between the dependent variable β0 and the independent variable Ploss,
also the relation between the another dependent variable β1 and the independent variable
Ploss based on the following two regression equations.
[β0] = κ0 + κ1 ∗ [Ploss] + [r0] (5.5)
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 95
or, β01...
β0N
= κ0 + κ1 ∗
Ploss1
...
PlossN
+
r01
...
r0N
[β1] = γ0 + γ1 ∗ [Ploss] + [r1] (5.6)
or, β11...
β1N
= γ0 + γ1 ∗
Ploss1
...
PlossN
+
r11
...
r1N
These two sets of regression coefficients, κ0, κ1 and γ0, γ1 can be derived using data from three
individual generator outage contingency cases for IEEE 39 bus system using the previous
two equations and predict the effect of individual outage of the rest of the six generators in
the system. As the contingency cases are considered, reduced admittance matrix, Yreduced is
calculated using network reduction, which allows the admittance of each generator from the
contingency generator i, [y]i, to be known. Then respective changes in real power injection
at each of the nine generators immediately after the loss of a generator, vector [∆Pdyn]i,
is calculated from simulation. Using the [y]i - [∆Pdyn]i relation from Equation 5.6 three
sets of β0i, β1i are calculated considering outage of generator 1, 3 and 10. The real power
output data for all of the ten generators in IEEE 39 bus system are attached in Appendix A.1
which demonstrates that these three generators are chosen from different ranges of power
output. The two sets of regression coefficients, κ0, κ1 and γ0, γ1 are then calculated from
β0i, β1i for the mentioned generator outage contingency case. Vector Ploss, the MW loss of
the contingency generator is normalized by diving each elements of this vector by the total
generation of the system which is 5081.76 MW β01
β03
β010
= κ0 + κ1 ∗
Ploss1
Ploss3
Ploss10
+
r01
r03
r010
(5.7)
or numerically, 0.045
0.044
0.033
= κ0 + κ1 ∗
0.041
0.111
0.162
+
r01
r03
r010
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 96
β11
β13
β110
= γ0 + γ1 ∗
Ploss1
Ploss3
Ploss10
+
r11
r13
r110
(5.8)
or numerically, 0.589
0.612
0.798
= γ0 + γ1 ∗
0.041
0.111
0.162
+
r11
r13
r110
The regression coefficients, κ0=0.051, κ1=-0.097 and γ0=0.495, γ1=1.643 are calculated from
β0i, β1i for individual outage contingency case of generator 1, 3 and 10. Using κ0, κ1 and
γ0, γ1 coefficients, β0i and β1i are predicted for contingency case for generator 4, 5, 6, 7,
8, 9 (generator 2, swing generator is not included). The predicted values of β0i, β1i are
represented as β0i, β1i in the following equation.
β04
β05
β06
β07
β08
β09
= κ0 + κ1 ∗
Ploss4
Ploss5
Ploss6
Ploss7
Ploss8
Ploss9
(5.9)
Therefore,
β04
β05
β06
β07
β08
β09
= 0.051 + (−0.097) ∗
0.107
0.083
0.111
0.093
0.089
0.146
=
0.041
0.043
0.040
0.042
0.042
0.037
Again,
β14
β15
β16
β17
β18
β19
= γ0 + γ1 ∗
Ploss4
Ploss5
Ploss6
Ploss7
Ploss8
Ploss9
(5.10)
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 97
and therefore,
β14
β15
β16
β17
β18
β19
= 0.495 + 1.643 ∗
0.107
0.083
0.111
0.093
0.089
0.146
=
0.671
0.631
0.676
0.647
0.641
0.735
Where, predicted β0i, β1i values less (minus) some residuals r0i, r1i, the actual coefficients
β0i, β1i of the regression Equation 5.6, can be calculated.
β04
β05
β06
β07
β08
β09
=
β04
β05
β06
β07
β08
β09
−
r04
r05
r06
r07
r08
r09
and,
β14
β15
β16
β17
β18
β19
=
β14
β15
β16
β17
β18
β19
−
r14
r15
r16
r17
r18
r19
Here, β0i, β1i values are used in linear regression Equation 5.6 to predict the vector [∆Pdyn]i,
respective change in real power injections at each of the nine remaining generators in IEEE
39 bus system immediately after the loss of ith generator where i= 4, 5, 6, 7, 8 and 9. For
example, the linear regression equation to predict power injection changes at all generators
except generator 4, right after generator 4 is lost can be written as following,
[ ˆ∆Pdyn]4 = β04 + β14 ∗ [y]4
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 98
ˆ∆Pdyn at gen1
ˆ∆Pdyn at gen2
ˆ∆Pdyn at gen3
ˆ∆Pdyn at gen5
ˆ∆Pdyn at gen6
ˆ∆Pdyn at gen7
ˆ∆Pdyn at gen8
ˆ∆Pdyn at gen9
ˆ∆Pdyn at gen10
for gen4 outage
= 0.041 + 0.671 ∗
0.057
0.044
0.062
0.497
0.146
0.080
0.040
0.042
0.033
=
0.078
0.070
0.082
0.374
0.138
0.094
0.068
0.069
0.062
The Figure 5.21 demonstrates the actual and predicted change in injections at all in-service
generators, right after the loss of generator 4 of 543.5 MW. The magenta star represents the
MW value from the dynamic simulation (assumed actual value) and the blue star represents
the MW value predicted by the regression. Figures 5.22, 5.23, 5.24, 5.25 & 5.26 show
similar results for a contingency at generators 5 (419.9 MW), 6 (561.7 MW), 7 (471.8 MW),
8 (451.8 MW) & 9 (741.7 MW), respectively.
Figure 5.21: Actual and Predicted Changes in Injections at Generator Buses after Generator4 (543.5 MW) Outage
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 99
Figure 5.22: Actual and Predicted Changes in Injections at Generator Buses after Generator5 (419.9 MW) Outage
Figure 5.23: Actual and Predicted Changes in Injections at Generator Buses after Generator6 (561.7 MW) Outage
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 100
Figure 5.24: Actual and Predicted Changes in Injections at Generator Buses after Generator7 (471.8 MW) Outage
Figure 5.25: Actual and Predicted Changes in Injections at Generator Buses after Generator8 (451.8 MW) Outage
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 101
Figure 5.26: Actual and Predicted Changes in Injections at Generator Buses after Generator9 (741.7 MW) Outage
5.3.2 Accuracy of Regression Model
The coefficient of determination, R2, is a measure used in regression model analysis to assess
how well a model explains and predicts future outcomes. it is useful because it indicates the
level of the variance (fluctuation) of one variable that is predictable from the other variable.
It is a gauge that allows determination of how accurate predictions can be achieved from a
certain model/graph. The coefficient of determination is the ratio of the explained variation
to the total variation.
The coefficient of determination is such that 0 < R2 < 1, and denotes the strength of the
linear association between the outcomes and the values of the single regressor being used for
prediction (the dependent and the independent variables). The coefficient of determination
represents the percent of the data that is the closest to the line of best fit. It is a measure
of how well the regression line represents the data i.e. how well the linear regression acts as
a predictor of the independent variable. If the regression line passes exactly through every
point on the scatter plot, it would be able to explain all of the variation. The further the
line is away from the points, the less it is able to explain.
For this study, the linear regression equation acts as a predictor of actual ∆Pdyn for a
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 102
generator outage case which can be written as the following,
[ ˆ∆Pdyn] = β0 + β1 ∗ [y] (5.11)
The coefficient of determination for this regression model computes as,
R2 = 1− SSerrSStot
(5.12)
SStot represents total sum of squares, the deviations of the observations from their mean:
SStot =n∑k=1
(∆Pdynk − ¯∆Pdyn)2 (5.13)
Where k, n, ∆Pdynk,¯∆Pdyn represent sample observation data, the total number of sample,
kth observation and mean of observations. If we were to use ¯∆Pdyn to predict ∆Pdyn, then
SStot measures the variability of the ∆Pdyn around their predicted value. SSerr measures
the deviations of observations from their predicted values:
SSerr =n∑k=1
(∆Pdynk − ˆ∆Pdyn)2 (5.14)
Table 5.2 shows this calculation of coefficient of determinations of regression models to pre-
dict changes in power injection performed on one of the contingencies previously shown from
the IEEE 39 bus system. The admittance between each generator & the contingency and
Contingency Case MW Loss from Outage R2
Gen 4 at bus 33 Outage 543.55 0.99Gen 5 at bus 34 Outage 419.84 0.97Gen 6 at bus 35 Outage 561.86 0.94Gen 7 at bus 36 Outage 471.85 0.98Gen 8 at bus 37 Outage 451.84 0.45Gen 9 at bus 38 Outage 741.73 0.40
Table 5.2: Coefficient of Determinations of Regression Models to Predict Power InjectionChanges for IEEE 39 Bus Study
the transient MW change following the contingency is approximately a linear relationship.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 103
This section has illustrated this linear relationship as a method to use a small sample set
of all of the possible generator contingencies to predict the response of the remainder of the
generators. The right-most column of Table 5.2 shows the coefficients of determination for
the generator contingencies where a prediction of real power output was attempted. The
majority of the coefficients are in the 90% range while there are two as low as 40%.
It indicates that almost 90% of the variability observed in sudden MW changes at gener-
ators can be explained by the admittances between each generator & the contingency. Thus,
the location of the remainder generators of the system contributes a lot of information how
power is re-distributed to them, immediately after a generation loss. It is further discussed
at the end of the next section.
5.3.3 IEEE 118 Bus System Examples
IEEE 118 bus system is used as another sample study system to predict changes in real power
injection at generator buses after a single generation loss where linear relationship between
injection changes at generators and the admittances of these generators from the out-of-
service generator for some sample generator outage cases act as predictors. The original
IEEE 118 bus has 54 generators and only 19 out of them are injecting power to the system
during normal operating condition. For simplicity, statuses of all generators with zero power
injections are set to zero. As a result, this modified IEEE 118 bus system has 19 generators
in operation. System data and one line diagram for this study model is shown in Appendix
A.2.2.
Consider the example in the IEEE 118 bus system (modified) with 19 generator buses.
The network reduction is performed again to find admittance between each of these 19 gener-
ators. So [Yreduced] for this system is a 19 x 19 dimensional matrix. This reduced admittance
matrix determines the admittance of each generator from the contingency generator i, vector
[y]i. Generator contingency cases are considered individually and the respective changes in
real power injection at each of the nine generators immediately after the loss of a generator,
vector [∆Pdyn]i, is calculated from simulation.
For the generator 1 outage contingency case, the admittances between each of the re-
maining 18 generators and generator 1 are shown in [y]1. Vector [y]1 has all eighteen of the
off-diagonal elements in 1st column of the reduced admittance matrix. The corresponding
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 104
real power injection changes at each of these 18 generators immediately after the loss of
generator 1 is demonstrated here by the vector [∆Pdyn]1. Both [y]1 and [∆Pdyn]1 are normal-
ized by dividing each element of these vectors by the sum of all elements of the respective
vector as in previous section. Now the following relationship can be derived using the linear
regression Equation 5.6,
[∆Pdyn]1 = β01 + β11 ∗ [y]1 + [r]1
Where,
0.4123
0.1024
0.1652
0.1079
0.0179
0.0308
0.0101
0.0124
0.0184
0.0416
0.0281
0.0271
0.0163
0.0008
0.0027
0.0037
0.0019
0.0004
= β01 + β11 ∗
0.5117
0.0627
0.1786
0.1064
0.0103
0.0162
0.0026
0.0066
0.0129
0.0477
0.0173
0.0182
0.0076
0.0001
0.0003
0.0008
0.0003
0.00002
+ [r]1
β01=0.0061 and β11=0.908 when generator 1 at bus 10 is out-of-service. The Figure 5.27
demonstrates the linear relationship between [y]1 and [∆Pdyn]1, after generator 1 at bus 10
is taken out-of-service , where both vectors are normalized.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 105
Figure 5.27: Immediate Injection Changes at Generator Buses after Generator 1 Outage
Similarly, individual outage contingency cases are considered for Generator 9 (at bus
59), 11 (at bus 65),& 16 (at bus 89) which demonstrates the approximate linear relationship
between power injections at all generators and their location in terms of admittance from
the tripped generator which are shown in Figure 5.28, 5.29 & 5.30.
Figure 5.28: Immediate Injection Changes at Generator Buses after generator 9 Outage
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 106
Figure 5.29: Immediate Injection Changes at Generator Buses after Generator 11 Outage
Figure 5.30: Immediate Injection Changes at Generator Buses after Generator 16 Outage
It is seen that β0 and β1 are two dependent variables of Ploss, which are dependent
on the MW loss of the contingency generator. Two separate linear regressions represent
the relation between the dependent variable β0 and the independent variable Ploss, also the
relation between the another dependent variable β1 and the independent variable Ploss based
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 107
on the following two regression equations.
[β0] = κ0 + κ1 ∗ [Ploss] + [r0] (5.15)
and,
[β1] = γ0 + γ1 ∗ [Ploss] + [r1] (5.16)
This two sets of regression coefficient, κ0, κ1 and γ0, γ1 are derived using data from 5
individual generator outage contingency cases (Table 5.3 ) for IEEE 118 bus system from
these equations. The effect of individual outage of the rest of the 14 generators in the
system are predicted using the predictor data. Using [y]i - [∆Pdyn]i relation from Equation
Contingency Case MW Loss from Outage
Gen 2 at bus 12 outage 85Gen 5 at bus 31 outage 7Gen 9 at bus 59 outage 155Gen 11 at bus 65 outage 391Gen 16 at bus 89 outage 607
Table 5.3: List of Contingency Cases Used for Prediction
5.6, 5 sets of β0i, β1i are calculated considering outage of generators listed in Table 5.3. The
real power output data for these predictor cases demonstrates that these five generators are
chosen from different ranges of power output. The two sets of regression coefficients, κ0, κ1
and γ0, γ1 are then calculated from β0i, β1i for the mentioned generators’ contingency cases.
Vector Ploss, the MW losses of the tripped generator are normalized by diving each elements
of this vector by the total generation of the system which is 4345.14 MW.β02
β05
β09
β011
β016
= κ0 + κ1 ∗
Ploss2
Ploss5
Ploss8
Ploss11
Ploss16
+
r02
r05
r09
r011
r016
(5.17)
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 108
β12
β15
β19
β111
β116
= γ0 + γ1 ∗
Ploss2
Ploss5
Ploss8
Ploss11
Ploss16
+
r12
r15
r19
r111
r116
(5.18)
The regression coefficients, κ0=0.017, κ1=-0.061 and γ0=0.57, γ1=2.29 are calculated from
β0i, β1i for individual outage contingency case of generators listed in Table 5.2. Using κ0,
κ1 and γ0, γ1 coefficients, β0i and β1i are predicted for contingency case for generator rest of
the 14 generators (generator 13, swing generator is not included). The predicted values of
β0i, β1i are represented as β0i, β1i in the following equations.
β01
β03
β04
β06
β07
β08
β010
β012
β014
β015
β017
β018
β019
= κ0 + κ1 ∗
Ploss1
Ploss3
Ploss4
Ploss6
Ploss7
Ploss8
Ploss10
Ploss12
Ploss14
Ploss15
Ploss17
Ploss18
Ploss19
(5.19)
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 109
β11
β13
β14
β16
β17
β18
β110
β112
β114
β115
β117
β118
β119
= γ0 + γ1 ∗
Ploss1
Ploss3
Ploss4
Ploss6
Ploss7
Ploss8
Ploss10
Ploss12
Ploss14
Ploss15
Ploss17
Ploss18
Ploss19
(5.20)
β0i, β1i values are used in linear regression Equation 5.6 to predict the vector [∆Pdyn]i,
respective change in real power injections at each of the remaining generators in IEEE 118
bus system right after the loss of ith generator where i= 1, 3, 4, 6, 7, 8, 10, 12, 14, 15, 17,
18 and 19. For example, the linear regression equation to predict power injection changes
at all generators except generator 13 (swing bus), after generator 1 is lost can be written as
following,
[ ˆ∆Pdyn]1 = β01 + β11 ∗ [y]1
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 110
ˆ∆Pdyn at gen1
ˆ∆Pdyn at gen2
ˆ∆Pdyn at gen3
ˆ∆Pdyn at gen5
ˆ∆Pdyn at gen6
ˆ∆Pdyn at gen7
ˆ∆Pdyn at gen8
ˆ∆Pdyn at gen9
ˆ∆Pdyn at gen10
ˆ∆Pdyn at gen11
ˆ∆Pdyn at gen12
ˆ∆Pdyn at gen14
ˆ∆Pdyn at gen15
ˆ∆Pdyn at gen16
ˆ∆Pdyn at gen17
ˆ∆Pdyn at gen18
ˆ∆Pdyn at gen19
hat∆Pdyn at gen1
for gen4 outage
= 0.0104 + 0.8064 ∗
0.51170
0.06268
0.17857
0.10637
0.01026
0.01616
0.00260
0.00660
0.01285
0.04771
0.01725
0.01823
0.00756
0.00009
0.00026
0.00081
0.00026
0.00002
=
0.4230
0.0609
0.1544
0.0962
0.0187
0.0234
0.0125
0.0157
0.0207
0.0489
0.0243
0.0251
0.0165
0.0104
0.0106
0.0110
0.0106
0.0104
Figure 5.31, 5.32, 5.33 & 5.34 demonstrate the actual and predicted change in injections at
all in-service generators, right after the loss of generator 1 (450 MW at bus 10), 7 (204 MW
at bus 49), 10 (160 MW at bus 61) & 14 (477 MW at bus 80), respectively.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 111
Figure 5.31: Actual and Predicted Changes in Injections at Generator Buses after Generator1 (450 MW) at Bus 10 Outage
Figure 5.32: Actual and Predicted Changes in Injections at Generator Buses after Generator7 (204 MW) at Bus 49 Outage
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 112
Figure 5.33: Actual and Predicted Changes in Injections at Generator Buses after Generator10 (160 MW) at Bus 61 Outage
Figure 5.34: Actual and Predicted Changes in Injections at Generator Buses after Generator14 (477 MW) at Bus 80 Outage
It has been said that the relationship between the admittance between each generator &
the contingency and the transient MW change following the contingency is approximately
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 113
linear. This section has demonstrated this as well as the ability to use this knowledge and a
small sample of all of the possible generator contingencies to predict the response of the rest
of the generators. The right-most column of Table 5.4 shows the coefficients of determination
for the generator contingencies where a prediction of real power output was attempted. The
majority of the coefficients are in the 90% range while there is one in the high 80% range
and one as low as 39%.
Contingency Case MW Loss from Outage R2
Gen 1 at bus 10 outage 450 0.99Gen 3 at bus 25 outage 220 0.97Gen 4 at bus 26 outage 314 0.98Gen 6 at bus 46 outage 19 0.92Gen 7 at bus 49 outage 204 0.95Gen 8 at bus 54 outage 48 0.93Gen 10 at bus 61 outage 160 0.96Gen 12 at bus 66 outage 392 0.87Gen 14 at bus 80 outage 477 0.93Gen 15 at bus 87 outage 4 0.39Gen 17 at bus 100 outage 252 0.94Gen 18 at bus 103 outage 40 0.90Gen 19 at bus 111 outage 36 0.94
Table 5.4: Coefficient of Determinations of Regression Models to Predict Power InjectionChanges for IEEE 118 Bus Study
It is believed that divergences from the linear model are due to ideas presented in Section
5.1 where an abstract power system was presented. Consider two scenarios, both where the
same generator in the network trips out abruptly causing a discrete change in the power
balance of the system. In the first scenario, imagine a load profile in which the majority
of the load served by the generator in question is electrically close. This means that the
electrical distance between this generator and every other generator in the network is a good
approximation of the electrical distance between each generator and the loads in need of
energy after the contingency. The second scenario places the loads served by the generator
in question farther away. Then, the electrical distance between each generator and the
generator in question is no longer a good approximation of the electrical distance between
each generator and the loads in need of energy after the contingency.
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 114
5.4 Potential Application in Protection Studies
Chapters 3 & 4 presented the summary of computationally intense protection studies per-
formed on the WECC and CA systems. One of the biggest challenges in performing studies
such as this is to try to identify the weak points in the system so that they can be scrutinized
and evaluated to ensure if appropriate protection scheme is implemented. Consider the po-
tential scenario where the loss of a generator in a large network. As discussed previously in
this chapter, the response of the system will be to convert stored kinetic energy from the
rotors of the machines into electrical energy which will be subsequently injected into the
network. There may exist a scenario in which the amount of transient MW change in the
output of a generator could be misinterpreted as a fault by a distance relay. It is desirable
to identify these scenarios in order to prevent mis-operation of a relay in the field.
One way to study this would be to take each generator out one by one and run a dynamic
simulation for each. For a sufficiently large system this could be time consuming. It makes
sense that most contingencies would not even come close to causing a relay mis-operation.
Therefore, an ideal scenario would be one in which the contingencies that could potentially
cause an inappropriate relay operation (depending on the relative size of the transient MW
output) could be quickly identified in a first pass. Once potential candidate scenarios are
identified, a comprehensive dynamic study can be performed for those scenarios to check for
violations.
This chapter has demonstrated that the transient MW output of the generators after a
loss of a generator can be reasonably predicted using network admittances, a small subset of
contingencies run as dynamic simulations, and knowledge of the linear relationship between
admittances and transient MW output. This procedure can be used as screening technique
for a protection study of a large network where it is impractical to perform all of the dynamic
simulations or to manually search for weakness in the grid. Shown in the next few sub-
sections are examples of the above hypothesis demonstrated on the IEEE 118 bus system
and the WECC system.
IEEE 118 Bus System Examples
As discussed earlier potential load encroachment scenarios for back-up protection relays are
evaluated in this section for generator outage contingencies in IEEE 118 bus system. Figure
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 115
5.35 demonstrates impedance trajectory (on R-X plane) seen by the Mho relay located at
bus 90 monitoring 138 kV line between bus 90 & 91. Generator supplying 607 MW at bus
89 is tripped which followed by outages of two adjacent 138 kV lines from bus 89 to 90
and 150% Load increase at bus 90. This condition does not create load encroachment for
the monitored line but the impedance trajectory of the relay approaches very close to the
supervisory boundary of the back-up protection within 4 seconds of the event occurrence.
Figure 5.35: Impedance Trajectory Seen by Relay at Line between Bus 90 and 91
Another example is shown here in Figure 5.36 which illustrates the impedance trajectory
seen by relay at bus 68 that monitors 345 kV line between bus 68 and 65. In this case a 392
MW generator is taken-of-service at bus 66 and another 391 MW generator at bus 65 trips,
a second later the previous outage which brings the impedance trajectory seen by this relay
close to the boundary of the back-up protection within 5 seconds of the first contingency.
This sudden and drastic movement of R-X point toward the protection boundary occurs as
a result of high flow in that line due to sudden MW injection changes of generators in the
area of contingency(such as generator at bus 49).
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 116
Figure 5.36: Impedance Trajectory Seen by Relay at Line between Bus 68 and 65
WECC System Examples
In this section, a back-up protection example is shown for 500 kV line from Hassayampa
to North Gila as seen in the map of southern WECC system in Figure 5.37. This line is
owned by Arizona Public Service (APS) and it is a segment of the South-West power link
(SWPL), a major transmission corridor that transports power in an east-west direction, from
generators in Arizona, through the service territory of Imperial Irrigation District (IID), into
the San Diego area. This is a major inter-tie for supplying loads in San Diego. The loss of
this 500 kV transmission line initiated widespread outage during the San Diego Blackout in
2011.
Figure 5.37: Generators at SONGS 1 & 2 in WECC System [23]
Figure 5.38 illustrates impedance presented to the distance relay at Hassayampa to
North Gila when two units (2350 MW generators) of San Onofre Nuclear Generating Station
(SONGS) in southern California trip and cause sudden increase of tie flow in the 500 kV
Chapter 5. Impact of Generation Re-distribution Immediately after Generation Loss 117
SWPL. Such heavy loading causes the impedance trajectory of distance relay to move away
from the normal load area and approach close to relay characteristic.
Figure 5.38: Impedance Trajectory Seen by Relay at Line between Hassayampa to NorthGila in WECC System
5.5 Summary
This chapter presents the concept of an approximately linear relationship between the elec-
trical distances between generator nodes in a network and the transient changes in MW
output of each respective generator directly after the loss of a generator. The approxima-
tion is due to the fact that it is not exactly the electrical distance between the generator
nodes but rather the electrical distance between the loads that are served in majority by the
generator lost during the contingency. When those loads are electrically farther from the
generator, then the linear approximation will not be as good. These ideas are demonstrated
on the IEEE 39 bus system as well as the IEEE 118 bus system yielding similar results which
indicates that the linear relationship is not a special property of one network but rather an
idea that can be applied to any network. Additionally, the efficacy of the linear regression is
evaluated by calculating the coefficients of determination for each contingencies. A discus-
sion of the application of such concept is presented for power system protection and a few
examples are shown from the IEEE 118 bus system and the WECC system.
Chapter 6
Conclusion & Future Work
Some of the recent blackouts in power system have shown that losing important system ele-
ments like critical transmission lines during stressed system conditions due to over-reaching
or inappropriate protection schemes can be detrimental to the system integrity and can cause
potentially cascading failures. When the system is operating in a stressed condition, it is
crucial to operate in a secure and reliable manner and retain all functioning and contributing
elements in the network (especially key generation units and transmission corridors) without
jeopardizing the overall security of the network. Every power system contains many pro-
tective relays identify abnormal system conditions and disturbances and initiate corrective
actions in order to recover the normal operating state of the system. Most of the protective
schemes in the systems are set to be very dependable so that system faults are always de-
tected and cleared by some relay. As a result, protection zones of some relays extend beyond
its necessary protective zone providing back-ups to a remote element and may eliminate
system elements unnecessarily. In other cases, relays are designed to operate on a specific
system condition fail to evolve with the system changes and result in tripping of important
network components inappropriately. The goal of this dissertation is to demonstrate avenues
to improve such power system protection schemes utilizing WAMS technology.
6.1 Summary
Chapter 3 discussed incorporation of a supervisory boundary the back-up distance protection
scheme to alert system stress and avoid possible false tripping of zone-3 due to violations of
118
Chapter 6. Conclusion & Future Work 119
load limits in transmission lines referred as load encroachment. WECC full loop model and
California study system is used as a bench-mark for this protection scheme. Line outage
distribution factor sensitivity analysis is utilized to determine the initial impact of N-1 line
outage contingencies in the sample systems. An inertial dispatch algorithm for generators
is developed to re-distribute power after generator losses to identify possible transmission
congestion and over-loads. Contingency analyses of multiple critical elements are performed
to obtain results that demonstrate the utilization of supervisory control to aid back-up zone
protection schemes. The research shows that the inter-ties between utilities in WECC are
prime locations of possible load encroachment.
The steady state stability limit of a generator and its significance during reduced field
excitation scenarios is explained in Chapter 4. The insufficient field excitation of a generator
is referred as loss-of-field condition which can be identified with impedance type relay. The
critical LOF conditions of the generator characteristics lie in the fourth quadrant of P-
Q of the generator capability curve that is represented with R-X impedance plane of the
monitoring LOF relay. The purpose of the LOF protection is to provide safety against the
generators steady-state limit which is a function of generator voltage, impedances of the
machine and step-up-transformer and most importantly the system’s Thevenin equivalent
impedance. But the system impedance is a variable quantity that changes with the system,
as seen from WECC simulation results. When the power system becomes weaker due to line
outages the system’s impedance increases and causes the generator load limit to drop; as a
result generator becomes susceptible to tripping. Hence an adaptive LOF protection scheme
is suggested to adjust the relay setting with prevailing system conditions and also provides
additional security with a regulatory margin to allow preventive measures by creating alarms.
In Chapter 5, a screening technique is introduced which aims to predict possible power
contribution of the generators remaining in the system after an immediate outage of a gener-
ator. An approximate linear relationship is derived between the changes in generators’ power
injections and their electrical distance from the event location i.e. the nearby a generator
to a tripped generator in terms of admittance between them, the more power is injected by
that generator to satisfy system demands and alleviate the MW mismatch in the system
that is imposed by the generator loss. Kron network reduction is used to reduce the system
admittance matrix to determine the direct admittance between each of the generators in the
system. This method of generator outage contingency analysis method helps determine pos-
sible overloads in transmission lines that are adjacent to a generator that is expected to inject
Chapter 6. Conclusion & Future Work 120
large amount of power right after a generator outage. This procedure can be incorporated
with system remedial action schemes (a corrective method for N-2 or worse contingencies)
to flag areas which can potentially suffer heavy loading when the system is operating under
stressed conditions to avoid inappropriate tripping of key system elements.
6.2 Future Work
As technologies such as phasor measurement units, smart-grid communication infrastruc-
tures, sub-station automation system proliferate, more applications of the wide-area mea-
surement systems are worthy of further investigation in the areas addressed in this disser-
tation. This final section outlines some of the potential avenues for further research in the
area of wide-area protection and automation.
• The analysis of protection improvement techniques applied in WECC system can be
continued to study Eastern Interconnections, ERCOT and Quebec systems as more
PMUs are being employed in these systems to enable wide area control. The 2008
study model demonstrates sufficient capacity of transmission corridors to deliver power
demand. But the rapid growth of system demands in the CA region in the last few years
could result in less capacity in the WECC lines and susceptible to load encroachment.
Further inquiry of back-up protection scheme can be performed on a new system model
of WECC.
• Development of method for on-line computation of system impedance accurately will
allow adjustment of LOF relay settings to adapt with prevailing power system con-
ditions. As discussed in this dissertation, the LOF relay settings can be identified
from off-line studies and the steady state stability can grow or shrink to adapt with
system changes such as variation in topology, change in loading/generation. However,
this technique can be utilized to identify relay settings for LOF conditions which is a
function of system’s Thevenin equivalent impedance by performing short-circuit anal-
ysis to identify the current system impedance at specific time intervals based on the
updated snapshots of the system extracted from the EMS (Energy Management Sys-
tem)/ SCADA system. Then the derived LOF settings will be even more precise and
appropriate for an evolving power system.
Chapter 6. Conclusion & Future Work 121
• This dissertation assumed continuous data availability for on-line analysis of protec-
tion schemes from all PMU units installed in the field. The impact of loss of wide
area measurements required for supervision of back-up protection and LOF protection
schemes can be investigated. Any default settings or alternate solutions to adjust to
the prevalent system criteria should any supporting devices such as PMU elements,
communication network parameters fail or mis-operate.
• The generation re-distribution technique post generator outage, described in Chapter
5, can be applied to existing protection schemes which will provide wide area knowledge
of impending generation imbalance in the system. In the case of a generator trip, the
trip signal can be made available as a flag to relays who’s zones of protection may
be violated due to over-loading of transmission lines by the immediate redistribution
of power amongst the remaining generators. The relays may then subsequently block
their trip signal or obtain information from other relays to determine if what is seen is
actually a fault, or a transient redistribution of power amongst the remaining generators
that resulted in load encroachment scenarios and being interpreted as a system fault.
• A study of communication structures and requirements to deploy WAMS for adaptive
relaying can be advised. As efficient information gathering from various devices in
system and prompt distribution of these data are essential for WAMS technology,
appropriate investigation is required to identify how the communication conventions
behave and comply with power system protection protocols. This calls for analysis of
various system architecture to determine whether to provide centralized or distributed
control to avoid latency and allow reliable & optimal operation of system protection
schemes.
Bibliography
[1] NERC Steering Group. Technical Analysis of the August 14, 2003, Blackout: What
Happened, Why, and What Did We Learn? Technical report, North American Electric
Reliability Council, Princeton, New Jersey, July 2004.
[2] Damir Novosel, Miroslav M. Begovic, and Vahid Madani. Shedding Light on Blackouts.
IEEE power & energy magazine, 2004.
[3] Enquiry Committee of India Ministry of Power. Report of the Enquiry Committee on
Grid Disturbance in Northern Region on 30th July 2012 and in Northern, Eastern &
North-Eastern Region 31st July 2012. Technical report, Ministry of Power, Govt. of
India, New Delhi, India, August 2012.
[4] IEEE Power System Relay Committee. Performance of Relaying during Wide-Area
Stressed Conditions. Technical report, May 2008.
[5] System Protection and NERC Planning Committee Control Task Force. Increase Line
Loadability by Enabling Load Encroachment Functions of Digital Relays. Technical
report, North American Electric Reliability Council, December 2005.
[6] System Protection and NERC Planning Committee Control Task Force. Methods to
Increase Line Relay Loadability. Technical report, North American Electric Reliability
Council, June 2006.
[7] John Berdy. Loss of Excitation Protection for Modern Synchronous Generators. IEEE
Transactions - Power Apparatus and Systems, 94(5):1457– 1463, September 1975.
[8] Rakesh B. Bobba, Jeff Dagle, Erich Heine, Himanshu Khurana, William H. Sanders, Pe-
ter Sauer, and Tim Yardley. Enhancing Grid Measurements - Wide Area Measurement
Systems, NASPInet, and Security. IEEE power & energy magazine, December 2011.
122
Bibliography 123
[9] J. F. Hauer, W. A. Mittelstadt, K. E. Martin, J. W. Burns, and Harry Lee. Interim
Report of the WECC Disturbance Monitoring Work Group. Technical report, December
2005.
[10] U.S.- Canada Power System Outage Task Force. Final Report on the August 14, 2003
Blackout in the United States and Canada: Causes and Recommendations. Technical
report, U.S. Secretary of Energy & Minister of Natural Resources Canada, April 2012.
[11] FERC/NERC Staff Report. Arizona-Southern California Outages on September 8, 2011
- Causes and Recommendations. Technical report, FERC/NERC, April 2012.
[12] Mutmainna Tania. Adaptive Relaying Technology Development & Measurements -
Methods for Supervising Back-up Zones. Technical report, Virginia Polytechnic Insti-
tute, CIEE Electric Grid Research Program, November 2011.
[13] Mutmainna Tania. Adaptive Relaying Technology Development & Measurements - Use
of WAMS to Automatically Adjust the Settings of Generator Protecting Loss-of-Field
Relays. Technical report, Virginia Polytechnic Institute, CIEE Electric Grid Research
Program, November 2011.
[14] H. D. Limmer. Techniques and Applications of Security Calculations Applied to Dis-
patching Computers. Third PSCC, June 1969.
[15] A. J. Wood and B. F. Wollenberg. Power Generation, Operation and Control. Wiley,
New York, 1984.
[16] H. Saadat. Power System Analysis. McGraw-Hill, New York, 2002.
[17] A. G. Ejigu. Implementation of Noord-Holland grid in RTDS. Master’s thesis, Delft
University of Technology, July 2009.
[18] GE - Concorda PSLF Simulation Engine. GE Product (PSLF) website, 2012. Accessed:
1/10/2012.
[19] SEL University. Power System Protection Fundamentals. The University of Tennessee
website: web.eecs.utk.edu/courses/spring2012/ece522/Protection%20primer.ppt, 2008.
[20] IEEE Guide for Protective Relay Applications to Transmission Lines, September 1999.
Bibliography 124
[21] A. M. Kulkarni, S. A. Soman, Yogesh Bijpuria, and Prashant Navalkar. On Grid Dis-
turbances in India (30/July/2012 and 31/July/2012). Invited lecture at Virginia Tech,
October 19, October 2012.
[22] A. G. Phadke, D. Novosel, and S.H. Horowitz. Wide Area Measurement Applications
in Functionally Integrated Power Systems. CIGRE B-5 Colloquium, Madrid, Spain,
September 2012.
[23] CIEE Electric Grid Research Program. Adaptive Relaying Technology Development &
Measurements. http://uc-ciee.org/downloads/ARTD FactSheet.pdf, October 2008.
[24] S. Dechphung and T. Saengsnwan. Three Zones Adaptive Characteristic of the Mho
Distance Relay by KU Method. IEEE International Conference on Sustainable Energy
Technologies, 2008.
[25] A. N. Sarwade, P.K. Katti, and J.G. Ghodekar. Adaptive Solutions for Distance Relay
Settings. IEEE 9th International Power and Energy Conference, Suntec, pages 493–498,
October 2010.
[26] S. H. Horowitz and A. G. Phadke. Power System Relaying. Research Studies Press
Ltd., Baldock, Hertfordshire, England, second edition, 1992.
[27] R. Sandoval, A. Guzman, and H.J. Altuve. Dynamic Simulations Help Improve Gener-
ator Protection. SEL, 2006.
[28] IEEE Committee Report. IEEE Guide for AC Generator Protection. IEEE Trans. on
PWRD, 4(2):957–964, 1989.
[29] Ran Xu. Loss of Field Protection and Its Impact on Power System Stability. PhD thesis,
Washington State University, December 2009.
[30] C. R. Mason. A New Loss-of-Excitation Relay for Synchronous Generators. AIEE
Trans., Part II(68).
[31] Walter A. Elmore, editor. Protective Relaying Theory and Applications. ABB Power
T&D Company Inc., Coral Springs, FL, March 1994.
[32] Bi Tianshu, Sui Jiayin, Yu Hao, and Yang Qixun. Adaptive Loss-of-Field Protection
Based on Phasor Measurements. IEEE, Power and Energy Society General Meeting,
2011, October 2011.
Bibliography 125
[33] W. F. Mackenzie, J. A. Imhof, C. Dewey, S. H. Horowitz, and et al. Loss-of-Field Relay
Operation during System Disturbance Working Group Report - June 1971. Technical
Report PAS-94, no. 5, IEEE Transactions on Power Apparatus Systems, September/
October 1975.
[34] Florin Capitanescu and Thierry Van Cutsem. Unified Sensitivity Analysis of Unstable
or Low Voltages Caused by Load Increases or Contingencies. IEEE Trans on Power
Systems, 20(1):321–329, 2005.
Appendix A
Sample Study Systems
A.1 IEEE 39 Bus System Data
Figure A.1: One Line Diagram of IEEE 39 Bus System with 10 Generators
126
Appendix 127
Bus Data
Bus Bus Pd Qd Vm Va Vmax Vmin
No. Type (MW) (MVAR) (pu) (degrees) (pu) (pu)
1 1 0 0 1 0 1.06 0.94
2 1 0 0 1 0 1.06 0.94
3 1 322 2.4 1.0341 -9.73 1.06 0.94
4 1 500 184 1.0116 -10.53 1.06 0.94
5 1 0 0 1.0165 -9.38 1.06 0.94
6 1 0 0 1.0172 -8.68 1.06 0.94
7 1 233.8 84 1.0067 -10.84 1.06 0.94
8 1 1022 276.6 1.0057 -11.34 1.06 0.94
9 1 0 0 1.0322 -11.15 1.06 0.94
10 1 0 0 1.0235 -6.31 1.06 0.94
11 1 0 0 1.0201 -7.12 1.06 0.94
12 1 8.5 88 1.0072 -7.14 1.06 0.94
13 1 0 0 1.0207 -7.02 1.06 0.94
14 1 0 0 1.0181 -8.66 1.06 0.94
15 1 320 153 1.0194 -9.06 1.06 0.94
16 1 329.4 32.3 1.0346 -7.66 1.06 0.94
17 1 0 0 1.0365 -8.65 1.06 0.94
18 1 158 30 1.0343 -9.49 1.06 0.94
19 1 0 0 1.0509 -3.04 1.06 0.94
20 1 680 103 0.9914 -4.45 1.06 0.94
21 1 274 115 1.0337 -5.26 1.06 0.94
22 1 0 0 1.0509 -0.82 1.06 0.94
23 1 247.5 84.6 1.0459 -1.02 1.06 0.94
24 1 308.6 -92.2 1.0399 -7.54 1.06 0.94
25 1 824 147.2 1.0587 -5.51 1.06 0.94
26 1 139 17 1.0536 -6.77 1.06 0.94
27 1 281 75.5 1.0399 -8.78 1.06 0.94
28 1 206 27.6 1.0509 -3.27 1.06 0.94
29 1 283.5 26.9 1.0505 -0.51 1.06 0.94
Continued on next page
Appendix 128
Table continued from previous page
Bus Bus Pd Qd Vm Va Vmax Vmin
No. Type (MW) (MVAR) (pu) (degrees) (pu) (pu)
30 2 200 0 1.0475 0 1.06 0.94
31 3 9.2 4.6 0.982 0 1.06 0.94
32 2 0 0 0.9831 1.63 1.06 0.94
33 2 0 0 0.9972 2.18 1.06 0.94
34 2 0 0 1.0123 0.74 1.06 0.94
35 2 0 0 1.0493 4.14 1.06 0.94
36 2 0 0 1.0635 6.83 1.06 0.94
37 2 0 0 1.0278 1.27 1.06 0.94
38 2 0 0 1.0265 6.55 1.06 0.94
39 2 100 0 1.03 -10.96 1.06 0.94
Table A.1: IEEE 39 Bus System - Bus Data
Branch Data
Branch From To R R B
No. Bus Bus (pu) (pu) (pu)
c 1 2 0.0035 0.0411 0.6987
2 1 39 0.001 0.025 0.75
3 2 3 0.0013 0.0151 0.2572
4 2 25 0.007 0.0086 0.146
5 3 4 0.0013 0.0213 0.2214
6 3 18 0.0011 0.0133 0.2138
7 4 5 0.0008 0.0128 0.1342
8 4 14 0.0008 0.0129 0.1382
9 5 6 0.0002 0.0026 0.0434
10 5 8 0.0008 0.0112 0.1476
Continued on next page
Appendix 129
Table continued from previous page
Branch From To R R B
No. Bus Bus (pu) (pu) (pu)
11 6 7 0.0006 0.0092 0.113
12 6 11 0.0007 0.0082 0.1389
13 7 8 0.0004 0.0046 0.078
14 8 9 0.0023 0.0363 0.3804
15 9 39 0.001 0.025 1.2
16 10 11 0.0004 0.0043 0.0729
17 10 13 0.0004 0.0043 0.0729
18 13 14 0.0009 0.0101 0.1723
19 14 15 0.0018 0.0217 0.366
20 15 16 0.0009 0.0094 0.171
21 16 17 0.0007 0.0089 0.1342
22 16 19 0.0016 0.0195 0.304
23 16 21 0.0008 0.0135 0.2548
24 16 24 0.0003 0.0059 0.068
25 17 18 0.0007 0.0082 0.1319
26 17 27 0.0013 0.0173 0.3216
27 21 22 0.0008 0.014 0.2565
28 22 23 0.0006 0.0096 0.1846
29 23 24 0.0022 0.035 0.361
30 25 26 0.0032 0.0323 0.513
31 26 27 0.0014 0.0147 0.2396
32 26 28 0.0043 0.0474 0.7802
33 26 29 0.0057 0.0625 1.029
34 28 29 0.0014 0.0151 0.249
35 12 11 0.0016 0.0435 0
36 12 13 0.0016 0.0435 0
37 6 31 0 0.025 0
38 10 32 0 0.02 0
39 19 33 0.0007 0.0142 0
Continued on next page
Appendix 130
Table continued from previous page
Branch From To R R B
No. Bus Bus (pu) (pu) (pu)
40 20 34 0.0009 0.018 0
41 22 35 0 0.0143 0
42 23 36 0.0005 0.0272 0
43 25 37 0.0006 0.0232 0
44 2 30 0 0.0181 0
45 29 38 0.0008 0.0156 0
46 19 20 0.0007 0.0138 0
Table A.2: IEEE 39 Bus System - Branch Data
Generator Data
Generator Pg Qg Qmax Qmin Vg mBase Pmax Pmin
Bus (MW) (MVAR) (MVAR) (MVAR) (pu) (MVA) (MW) (MW)
30 0 103.3 9999 -9999 1.0475 100 350 031 572.9 170.3 9999 -9999 0.982 100 1145.55 032 900 175.9 9999 -9999 0.9831 100 750 033 632 103.3 9999 -9999 0.9972 100 732 034 508 164.4 9999 -9999 1.0123 100 608 035 650 204.8 9999 -9999 1.0493 100 750 036 560 96.9 9999 -9999 1.0635 100 660 037 540 -4.4 9999 -9999 1.0278 100 640 038 830 19.4 9999 -9999 1.0265 100 930 039 1000 68.5 9999 -9999 1.03 100 1100 0
Table A.3: IEEE 39 Bus System - Generator Data
Appendix 131
A.2 IEEE 118 Bus System Data
A.2.1 IEEE 118 Bus System Data with 54 Generators
Figure A.2: One Line Diagram of IEEE 118 Bus System with 54 Generators
Appendix 132
A.2.2 IEEE 118 Bus System with 19 Generators
Figure A.3: One Line Diagram of IEEE 118 Bus System with 19 Generator
Appendix 133
Bus Data
Bus Bus Pd Qd Vm Va Base Vmax Vmin
No. Type (MW) (MVAR) (pu) (degrees) KV (pu) (pu)
1 1 51 27 0.955 10.67 138 1.06 0.94
2 1 20 9 0.971 11.22 138 1.06 0.94
3 1 39 10 0.968 11.56 138 1.06 0.94
4 1 39 12 0.998 15.28 138 1.06 0.94
5 1 0 0 1.002 15.73 138 1.06 0.94
6 1 52 22 0.99 13 138 1.06 0.94
7 1 19 2 0.989 12.56 138 1.06 0.94
8 1 28 0 1.015 20.77 345 1.06 0.94
9 1 0 0 1.043 28.02 345 1.06 0.94
10 2 0 0 1.05 35.61 345 1.06 0.94
11 1 70 23 0.985 12.72 138 1.06 0.94
12 2 47 10 0.99 12.2 138 1.06 0.94
13 1 34 16 0.968 11.35 138 1.06 0.94
14 1 14 1 0.984 11.5 138 1.06 0.94
15 1 90 30 0.97 11.23 138 1.06 0.94
16 1 25 10 0.984 11.91 138 1.06 0.94
17 1 11 3 0.995 13.74 138 1.06 0.94
18 1 60 34 0.973 11.53 138 1.06 0.94
19 1 45 25 0.963 11.05 138 1.06 0.94
20 1 18 3 0.958 11.93 138 1.06 0.94
21 1 14 8 0.959 13.52 138 1.06 0.94
22 1 10 5 0.97 16.08 138 1.06 0.94
23 1 7 3 1 21 138 1.06 0.94
24 1 13 0 0.992 20.89 138 1.06 0.94
25 2 0 0 1.05 27.93 138 1.06 0.94
26 2 0 0 1.015 29.71 345 1.06 0.94
27 1 71 13 0.968 15.35 138 1.06 0.94
28 1 17 7 0.962 13.62 138 1.06 0.94
29 1 24 4 0.963 12.63 138 1.06 0.94
Continued on next page
Appendix 134
Table continued from previous page
Bus Bus Pd Qd Vm Va Base Vmax Vmin
No. Type (MW) (MVAR) (pu) (degrees) KV (pu) (pu)
30 1 0 0 0.968 18.79 345 1.06 0.94
31 2 43 27 0.967 12.75 138 1.06 0.94
32 1 59 23 0.964 14.8 138 1.06 0.94
33 1 23 9 0.972 10.63 138 1.06 0.94
34 1 59 26 0.986 11.3 138 1.06 0.94
35 1 33 9 0.981 10.87 138 1.06 0.94
36 1 31 17 0.98 10.87 138 1.06 0.94
37 1 0 0 0.992 11.77 138 1.06 0.94
38 1 0 0 0.962 16.91 345 1.06 0.94
39 1 27 11 0.97 8.41 138 1.06 0.94
40 1 66 23 0.97 7.35 138 1.06 0.94
41 1 37 10 0.967 6.92 138 1.06 0.94
42 1 96 23 0.985 8.53 138 1.06 0.94
43 1 18 7 0.978 11.28 138 1.06 0.94
44 1 16 8 0.985 13.82 138 1.06 0.94
45 1 53 22 0.987 15.67 138 1.06 0.94
46 2 28 10 1.005 18.49 138 1.06 0.94
47 1 34 0 1.017 20.73 138 1.06 0.94
48 1 20 11 1.021 19.93 138 1.06 0.94
49 2 87 30 1.025 20.94 138 1.06 0.94
50 1 17 4 1.001 18.9 138 1.06 0.94
51 1 17 8 0.967 16.28 138 1.06 0.94
52 1 18 5 0.957 15.32 138 1.06 0.94
53 1 23 11 0.946 14.35 138 1.06 0.94
54 2 113 32 0.955 15.26 138 1.06 0.94
55 1 63 22 0.952 14.97 138 1.06 0.94
56 1 84 18 0.954 15.16 138 1.06 0.94
57 1 12 3 0.971 16.36 138 1.06 0.94
58 1 12 3 0.959 15.51 138 1.06 0.94
Continued on next page
Appendix 135
Table continued from previous page
Bus Bus Pd Qd Vm Va Base Vmax Vmin
No. Type (MW) (MVAR) (pu) (degrees) KV (pu) (pu)
59 2 277 113 0.985 19.37 138 1.06 0.94
60 1 78 3 0.993 23.15 138 1.06 0.94
61 2 0 0 0.995 24.04 138 1.06 0.94
62 1 77 14 0.998 23.43 138 1.06 0.94
63 1 0 0 0.969 22.75 345 1.06 0.94
64 1 0 0 0.984 24.52 345 1.06 0.94
65 2 0 0 1.005 27.65 345 1.06 0.94
66 2 39 18 1.05 27.48 138 1.06 0.94
67 1 28 7 1.02 24.84 138 1.06 0.94
68 1 0 0 1.003 27.55 345 1.06 0.94
69 3 0 0 1.035 30 138 1.06 0.94
70 1 66 20 0.984 22.58 138 1.06 0.94
71 1 0 0 0.987 22.15 138 1.06 0.94
72 1 12 0 0.98 20.98 138 1.06 0.94
73 1 6 0 0.991 21.94 138 1.06 0.94
74 1 68 27 0.958 21.64 138 1.06 0.94
75 1 47 11 0.967 22.91 138 1.06 0.94
76 1 68 36 0.943 21.77 138 1.06 0.94
77 1 61 28 1.006 26.72 138 1.06 0.94
78 1 71 26 1.003 26.42 138 1.06 0.94
79 1 39 32 1.009 26.72 138 1.06 0.94
80 2 130 26 1.04 28.96 138 1.06 0.94
81 1 0 0 0.997 28.1 345 1.06 0.94
82 1 54 27 0.989 27.24 138 1.06 0.94
83 1 20 10 0.985 28.42 138 1.06 0.94
84 1 11 7 0.98 30.95 138 1.06 0.94
85 1 24 15 0.985 32.51 138 1.06 0.94
86 1 21 10 0.987 31.14 138 1.06 0.94
87 2 0 0 1.015 31.4 161 1.06 0.94
Continued on next page
Appendix 136
Table continued from previous page
Bus Bus Pd Qd Vm Va Base Vmax Vmin
No. Type (MW) (MVAR) (pu) (degrees) KV (pu) (pu)
88 1 48 10 0.987 35.64 138 1.06 0.94
89 2 0 0 1.005 39.69 138 1.06 0.94
90 1 163 42 0.985 33.29 138 1.06 0.94
91 1 10 0 0.98 33.31 138 1.06 0.94
92 1 65 10 0.993 33.8 138 1.06 0.94
93 1 12 7 0.987 30.79 138 1.06 0.94
94 1 30 16 0.991 28.64 138 1.06 0.94
95 1 42 31 0.981 27.67 138 1.06 0.94
96 1 38 15 0.993 27.51 138 1.06 0.94
97 1 15 9 1.011 27.88 138 1.06 0.94
98 1 34 8 1.024 27.4 138 1.06 0.94
99 1 42 0 1.01 27.04 138 1.06 0.94
100 2 37 18 1.017 28.03 138 1.06 0.94
101 1 22 15 0.993 29.61 138 1.06 0.94
102 1 5 3 0.991 32.3 138 1.06 0.94
103 2 23 16 1.001 24.44 138 1.06 0.94
104 1 38 25 0.971 21.69 138 1.06 0.94
105 1 31 26 0.965 20.57 138 1.06 0.94
106 1 43 16 0.962 20.32 138 1.06 0.94
107 1 50 12 0.952 17.53 138 1.06 0.94
108 1 2 1 0.967 19.38 138 1.06 0.94
109 1 8 3 0.967 18.93 138 1.06 0.94
110 1 39 30 0.973 18.09 138 1.06 0.94
111 2 0 0 0.98 19.74 138 1.06 0.94
112 1 68 13 0.975 14.99 138 1.06 0.94
113 1 6 0 0.993 13.74 138 1.06 0.94
114 1 8 3 0.96 14.46 138 1.06 0.94
115 1 22 7 0.96 14.46 138 1.06 0.94
116 1 184 0 1.005 27.12 138 1.06 0.94
Continued on next page
Appendix 137
Table continued from previous page
Bus Bus Pd Qd Vm Va Base Vmax Vmin
No. Type (MW) (MVAR) (pu) (degrees) KV (pu) (pu)
117 1 20 8 0.974 10.67 138 1.06 0.94
118 1 33 15 0.949 21.92 138 1.06 0.94
Table A.4: IEEE 118 Bus System - Original Bus Data
Additional Bus Data
Bus Bus Pd Qd Vm Va Base Vmax Vmin
No. Type (MW) (MVAR) (pu) (degrees) KV (pu) (pu)
119 1 0 0 0.966 10.98 138 1.06 0.94
120 1 0 0 1.02 15.58 138 1.06 0.94
121 1 0 0 1.03 13.29 138 1.06 0.94
122 1 0 0 1.03 21.06 138 1.06 0.94
123 1 0 0 1.0605 35.88 138 1.06 0.94
124 1 0 0 1.01 12.49 138 1.06 0.94
125 1 0 0 0.99 11.48 138 1.06 0.94
126 1 0 0 1 11.79 138 1.06 0.94
127 1 0 0 0.98 11.3 138 1.06 0.94
128 1 0 0 1 21.11 138 1.06 0.94
129 1 0 0 1.06 28.18 138 1.06 0.94
130 1 0 0 1.03 29.96 138 1.06 0.94
131 1 0 0 0.99 15.61 138 1.06 0.94
132 1 0 0 0.99 13.01 138 1.06 0.94
133 1 0 0 0.98 15.06 138 1.06 0.94
134 1 0 0 1.01 11.51 138 1.06 0.94
135 1 0 0 1 11.08 138 1.06 0.94
136 1 0 0 0.99 7.52 138 1.06 0.94
Continued on next page
Appendix 138
Table continued from previous page
Bus Bus Pd Qd Vm Va Base Vmax Vmin
No. Type (MW) (MVAR) (pu) (degrees) KV (pu) (pu)
137 1 0 0 1.01 8.67 138 1.06 0.94
138 1 0 0 1.01 18.58 138 1.06 0.94
139 1 0 0 1.04 21.03 138 1.06 0.94
140 1 0 0 0.97 15.35 138 1.06 0.94
141 1 0 0 0.965 15.06 138 1.06 0.94
142 1 0 0 0.97 15.24 138 1.06 0.94
143 1 0 0 1.01 19.45 138 1.06 0.94
144 1 0 0 1.01 24.12 138 1.06 0.94
145 1 0 0 1 23.51 138 1.06 0.94
146 1 0 0 1.01 27.72 138 1.06 0.94
147 1 0 0 1.01 27.56 138 1.06 0.94
148 1 0 0 1.04 29.99 138 1.06 0.94
149 1 0 0 0.995 22.62 138 1.06 0.94
150 1 0 0 0.99 21.11 138 1.06 0.94
151 1 0 0 1.01 21.99 138 1.06 0.94
152 1 0 0 0.968 21.67 138 1.06 0.94
153 1 0 0 0.963 21.8 138 1.06 0.94
154 1 0 0 1.015 26.75 138 1.06 0.94
155 1 0 0 1.05 28.99 138 1.06 0.94
156 1 0 0 0.996 32.55 138 1.06 0.94
157 1 0 0 1.025 31.44 138 1.06 0.94
158 1 0 0 1.01 39.73 138 1.06 0.94
159 1 0 0 0.996 33.33 138 1.06 0.94
160 1 0 0 0.98 33.35 138 1.06 0.94
161 1 0 0 1 33.85 138 1.06 0.94
162 1 0 0 1.02 27.08 138 1.06 0.94
163 1 0 0 1.027 28.07 138 1.06 0.94
164 1 0 0 1.01 24.48 138 1.06 0.94
165 1 0 0 0.982 21.74 138 1.06 0.94
Continued on next page
Appendix 139
Table continued from previous page
Bus Bus Pd Qd Vm Va Base Vmax Vmin
No. Type (MW) (MVAR) (pu) (degrees) KV (pu) (pu)
166 1 0 0 0.976 20.62 138 1.06 0.94
167 1 0 0 0.962 17.58 138 1.06 0.94
168 1 0 0 0.983 18.14 138 1.06 0.94
169 1 0 0 0.99 19.78 138 1.06 0.94
170 1 0 0 0.985 15.04 138 1.06 0.94
171 1 0 0 1.03 14 138 1.06 0.94
172 1 0 0 1.015 27.16 138 1.06 0.94
Table A.5: IEEE 118 Bus System - Additional Bus Data
Branch Data
Branch From To R R B
No. Bus Bus (pu) (pu) (pu)
1 119 2 0.0303 0.0999 0.0254
2 119 3 0.0129 0.0424 0.01082
3 120 5 0.00176 0.00798 0.0021
4 3 5 0.0241 0.108 0.0284
5 5 121 0.0119 0.054 0.01426
6 121 7 0.00459 0.0208 0.0055
7 122 9 0.00244 0.0305 1.162
8 122 5 0 0.0267 0
9 9 123 0.00258 0.0322 1.23
10 4 11 0.0209 0.0688 0.01748
11 5 11 0.0203 0.0682 0.01738
12 11 124 0.00595 0.0196 0.00502
13 2 124 0.0187 0.0616 0.01572
Continued on next page
Appendix 140
Table continued from previous page
Branch From To R R B
No. Bus Bus (pu) (pu) (pu)
14 3 124 0.0484 0.16 0.0406
15 7 124 0.00862 0.034 0.00874
16 11 13 0.02225 0.0731 0.01876
17 124 14 0.0215 0.0707 0.01816
18 13 125 0.0744 0.2444 0.06268
19 14 125 0.0595 0.195 0.0502
20 124 16 0.0212 0.0834 0.0214
21 125 17 0.0132 0.0437 0.0444
22 16 17 0.0454 0.1801 0.0466
23 17 126 0.0123 0.0505 0.01298
24 126 127 0.01119 0.0493 0.01142
25 127 20 0.0252 0.117 0.0298
26 125 127 0.012 0.0394 0.0101
27 20 21 0.0183 0.0849 0.0216
28 21 22 0.0209 0.097 0.0246
29 22 23 0.0342 0.159 0.0404
30 23 128 0.0135 0.0492 0.0498
31 23 129 0.0156 0.08 0.0864
32 130 129 0 0.0382 0
33 129 131 0.0318 0.163 0.1764
34 131 28 0.01913 0.0855 0.0216
35 28 29 0.0237 0.0943 0.0238
36 30 17 0 0.0388 0
37 122 30 0.00431 0.0504 0.514
38 130 30 0.00799 0.086 0.908
39 17 132 0.0474 0.1563 0.0399
40 29 132 0.0108 0.0331 0.0083
41 23 133 0.0317 0.1153 0.1173
42 132 133 0.0298 0.0985 0.0251
Continued on next page
Appendix 141
Table continued from previous page
Branch From To R R B
No. Bus Bus (pu) (pu) (pu)
43 131 133 0.0229 0.0755 0.01926
44 125 33 0.038 0.1244 0.03194
45 127 134 0.0752 0.247 0.0632
46 35 135 0.00224 0.0102 0.00268
47 35 37 0.011 0.0497 0.01318
48 33 37 0.0415 0.142 0.0366
49 134 135 0.00871 0.0268 0.00568
50 134 37 0.00256 0.0094 0.00984
51 38 37 0 0.0375 0
52 37 39 0.0321 0.106 0.027
53 37 136 0.0593 0.168 0.042
54 30 38 0.00464 0.054 0.422
55 39 136 0.0184 0.0605 0.01552
56 136 41 0.0145 0.0487 0.01222
57 136 137 0.0555 0.183 0.0466
58 41 137 0.041 0.135 0.0344
59 43 44 0.0608 0.2454 0.06068
60 134 43 0.0413 0.1681 0.04226
61 44 45 0.0224 0.0901 0.0224
62 45 138 0.04 0.1356 0.0332
63 138 47 0.038 0.127 0.0316
64 138 48 0.0601 0.189 0.0472
65 47 139 0.0191 0.0625 0.01604
66 137 139 0.0715 0.323 0.086
67 137 139 0.0715 0.323 0.086
68 45 139 0.0684 0.186 0.0444
69 48 139 0.0179 0.0505 0.01258
70 139 50 0.0267 0.0752 0.01874
71 139 51 0.0486 0.137 0.0342
Continued on next page
Appendix 142
Table continued from previous page
Branch From To R R B
No. Bus Bus (pu) (pu) (pu)
72 51 52 0.0203 0.0588 0.01396
73 52 53 0.0405 0.1635 0.04058
74 53 140 0.0263 0.122 0.031
75 139 140 0.073 0.289 0.0738
76 139 140 0.0869 0.291 0.073
77 140 141 0.0169 0.0707 0.0202
78 140 142 0.00275 0.00955 0.00732
79 141 142 0.00488 0.0151 0.00374
80 142 57 0.0343 0.0966 0.0242
81 50 57 0.0474 0.134 0.0332
82 142 58 0.0343 0.0966 0.0242
83 51 58 0.0255 0.0719 0.01788
84 140 143 0.0503 0.2293 0.0598
85 142 143 0.0825 0.251 0.0569
86 142 143 0.0803 0.239 0.0536
87 141 143 0.04739 0.2158 0.05646
88 143 60 0.0317 0.145 0.0376
89 143 144 0.0328 0.15 0.0388
90 60 144 0.00264 0.0135 0.01456
91 60 145 0.0123 0.0561 0.01468
92 144 145 0.00824 0.0376 0.0098
93 63 143 0 0.0386 0
94 63 64 0.00172 0.02 0.216
95 64 144 0 0.0268 0
96 38 146 0.00901 0.0986 1.046
97 64 146 0.00269 0.0302 0.38
98 139 147 0.018 0.0919 0.0248
99 139 147 0.018 0.0919 0.0248
100 145 147 0.0482 0.218 0.0578
Continued on next page
Appendix 143
Table continued from previous page
Branch From To R R B
No. Bus Bus (pu) (pu) (pu)
101 145 67 0.0258 0.117 0.031
102 146 147 0 0.037 0
103 147 67 0.0224 0.1015 0.02682
104 146 68 0.00138 0.016 0.638
105 47 148 0.0844 0.2778 0.07092
106 139 148 0.0985 0.324 0.0828
107 68 148 0 0.037 0
108 148 149 0.03 0.127 0.122
109 128 149 0.00221 0.4115 0.10198
110 149 71 0.00882 0.0355 0.00878
111 128 150 0.0488 0.196 0.0488
112 71 150 0.0446 0.18 0.04444
113 71 151 0.00866 0.0454 0.01178
114 149 152 0.0401 0.1323 0.03368
115 149 75 0.0428 0.141 0.036
116 148 75 0.0405 0.122 0.124
117 152 75 0.0123 0.0406 0.01034
118 153 154 0.0444 0.148 0.0368
119 148 154 0.0309 0.101 0.1038
120 75 154 0.0601 0.1999 0.04978
121 154 78 0.00376 0.0124 0.01264
122 78 79 0.00546 0.0244 0.00648
123 154 155 0.017 0.0485 0.0472
124 154 155 0.0294 0.105 0.0228
125 79 155 0.0156 0.0704 0.0187
126 68 81 0.00175 0.0202 0.808
127 81 155 0 0.037 0
128 154 82 0.0298 0.0853 0.08174
129 82 83 0.0112 0.03665 0.03796
Continued on next page
Appendix 144
Table continued from previous page
Branch From To R R B
No. Bus Bus (pu) (pu) (pu)
130 83 84 0.0625 0.132 0.0258
131 83 156 0.043 0.148 0.0348
132 84 156 0.0302 0.0641 0.01234
133 156 86 0.035 0.123 0.0276
134 86 157 0.02828 0.2074 0.0445
135 156 88 0.02 0.102 0.0276
136 156 158 0.0239 0.173 0.047
137 88 158 0.0139 0.0712 0.01934
138 158 159 0.0518 0.188 0.0528
139 158 159 0.0238 0.0997 0.106
140 159 160 0.0254 0.0836 0.0214
141 158 161 0.0099 0.0505 0.0548
142 158 161 0.0393 0.1581 0.0414
143 160 161 0.0387 0.1272 0.03268
144 161 93 0.0258 0.0848 0.0218
145 161 94 0.0481 0.158 0.0406
146 93 94 0.0223 0.0732 0.01876
147 94 95 0.0132 0.0434 0.0111
148 155 96 0.0356 0.182 0.0494
149 82 96 0.0162 0.053 0.0544
150 94 96 0.0269 0.0869 0.023
151 155 97 0.0183 0.0934 0.0254
152 155 98 0.0238 0.108 0.0286
153 155 162 0.0454 0.206 0.0546
154 161 163 0.0648 0.295 0.0472
155 94 163 0.0178 0.058 0.0604
156 95 96 0.0171 0.0547 0.01474
157 96 97 0.0173 0.0885 0.024
158 98 163 0.0397 0.179 0.0476
Continued on next page
Appendix 145
Table continued from previous page
Branch From To R R B
No. Bus Bus (pu) (pu) (pu)
159 162 163 0.018 0.0813 0.0216
160 163 101 0.0277 0.1262 0.0328
161 161 102 0.0123 0.0559 0.01464
162 101 102 0.0246 0.112 0.0294
163 163 164 0.016 0.0525 0.0536
164 163 165 0.0451 0.204 0.0541
165 164 165 0.0466 0.1584 0.0407
166 164 166 0.0535 0.1625 0.0408
167 163 106 0.0605 0.229 0.062
168 164 166 0.00994 0.0378 0.00986
169 166 106 0.014 0.0547 0.01434
170 166 167 0.053 0.183 0.0472
171 166 108 0.0261 0.0703 0.01844
172 106 167 0.053 0.183 0.0472
173 108 109 0.0105 0.0288 0.0076
174 164 168 0.03906 0.1813 0.0461
175 109 168 0.0278 0.0762 0.0202
176 168 169 0.022 0.0755 0.02
177 168 170 0.0247 0.064 0.062
178 17 171 0.00913 0.0301 0.00768
179 133 171 0.0615 0.203 0.0518
180 133 114 0.0135 0.0612 0.01628
181 131 115 0.0164 0.0741 0.01972
182 114 115 0.0023 0.0104 0.00276
183 68 172 0.00034 0.00405 0.164
184 124 117 0.0329 0.14 0.0358
185 75 118 0.0145 0.0481 0.01198
186 153 118 0.0164 0.0544 0.01356
Table A.6: IEEE 118 Bus System - Branch Data
Appendix 146
Additional Branch Data
Branch From To R X Branch From To R XNo. Bus Bus (pu) (pu) No. Bus Bus (pu) (pu)
1 119 1 0 0.025 28 146 65 0 0.0252 120 4 0 0.02 29 147 66 0 0.023 121 6 0.0007 0.0142 30 148 69 0.0007 0.01424 122 8 0.0009 0.018 31 149 70 0.0009 0.0185 123 10 0 0.0143 32 150 72 0 0.01436 124 12 0.0005 0.0272 33 151 73 0.0005 0.02727 125 15 0.0006 0.0232 34 152 74 0.0006 0.02328 126 18 0 0.0181 35 153 76 0 0.01819 127 19 0.0008 0.0156 36 154 77 0.0008 0.015610 128 24 0 0.025 37 155 80 0 0.018111 129 25 0 0.02 38 156 85 0.0008 0.015612 130 26 0.0007 0.0142 39 157 87 0 0.02513 131 27 0.0009 0.018 40 158 89 0 0.0214 132 31 0 0.0143 41 159 90 0.0007 0.014215 133 32 0.0005 0.0272 42 160 91 0.0009 0.01816 134 34 0.0006 0.0232 43 161 92 0 0.014317 135 36 0 0.0181 44 162 99 0.0005 0.027218 136 40 0.0008 0.0156 45 163 100 0.0006 0.023219 137 42 0 0.025 46 164 103 0 0.018120 138 46 0 0.02 47 165 104 0.0008 0.015621 139 49 0.0007 0.0142 48 166 105 0 0.02522 140 54 0.0009 0.018 49 167 107 0 0.0223 141 55 0 0.0143 50 168 110 0.0007 0.014224 142 56 0.0005 0.0272 51 169 111 0.0009 0.01825 143 59 0.0006 0.0232 52 170 112 0 0.014326 144 61 0 0.0181 53 171 113 0.0005 0.027227 145 62 0.0008 0.0156 54 172 116 0.0006 0.0232
Table A.7: IEEE 118 Bus System - Additional Branch Data
Appendix 147
Generator Data
Generator Pg Qg Qmax Qmin Vg mBase Pmax Pmin
Bus (MW) (MVAR) (MVAR) (MVAR) (pu) (MVA) (MW) (MW)
10 450 0 200 -147 1.05 100 550 012 85 0 120 -35 0.99 100 185 025 220 0 140 -47 1.05 100 320 026 314 0 1000 -1000 1.015 100 414 031 7 0 300 -300 0.967 100 107 046 19 0 100 -100 1.005 100 119 049 204 0 210 -85 1.025 100 304 054 48 0 300 -300 0.955 100 148 059 155 0 180 -60 0.985 100 255 061 160 0 300 -100 0.995 100 260 065 391 0 200 -67 1.005 100 491 066 392 0 200 -67 1.05 100 492 069 516.4 0 300 -300 1.035 100 805.2 080 477 0 280 -165 1.04 100 577 087 4 0 1000 -100 1.015 100 104 089 607 0 300 -210 1.005 100 707 0100 252 0 155 -50 1.017 100 352 0103 40 0 40 -15 1.01 100 140 0111 36 0 1000 -100 0.98 100 136 0
Table A.8: IEEE 118 Bus System - Generator Data