Upload
trinhliem
View
217
Download
0
Embed Size (px)
Citation preview
www.rpacan.com Rock Solid Resources. Proven Advice.
Why Mines Fail
March 6, 2017
Seeking Better Mining Outcomes in the Next Cycle
Presented by: Richard J. Lambert, MBA, P.E., P.Eng.
www.rpacan.com Rock Solid Resources. Proven Advice.
2
About RPA
• Advice to the mining industry for 30 years • The specialty firm of choice for resource and reserve work • All stages:
• exploration and resource evaluation • scoping, prefeasibility and feasibility studies • financing, permitting, construction, operation, closure and rehabilitation.
• Clients are financial institutions, governments, major mining companies, exploration and development firms, law firms, individual investors, and private equity ventures
• Offices in Canada, United States and United Kingdom • Head office in Toronto • 100% employee owned
www.rpacan.com Rock Solid Resources. Proven Advice.
3
Outline
• Why Do Mines Fail? • Common Threads • Fatal Flaws • Non-Fatal Flaws that can be overcome
www.rpacan.com Rock Solid Resources. Proven Advice.
4
Why do Mines Fail?
• Poor Management • Built to be more than it really was • Mineral Resource not there • Prices (up or down) • Level of Study (moving too fast) • Insufficient funds
www.rpacan.com Rock Solid Resources. Proven Advice.
5
Failed/Troubled Projects Since 1985
• RPA review identified 75 projects that failed to meet expectations in a material way.
35 Grade Related
10 Mining Method
16 Processing
8 Capital Cost
7 Operating Cost
6 Social/Permitting/Government
5 Prices/Timing
www.rpacan.com Rock Solid Resources. Proven Advice.
6
Common Threads
• Head Grade - Resource Reserve models. • Basic errors or incorrect assumptions in resource estimation.
• Productivity and misapplication of mining method • Mining extraction overestimated and mining dilution underestimated.
• Processing, including metallurgy, equipment selection, and ramp up.
• Capital costs underestimated.
• Operating costs underestimated.
• People and Technology. • Lack of experience / Team size • Substituting software for judgment.
• External Pressures.
• Time and cost constraints.
www.rpacan.com Rock Solid Resources. Proven Advice.
8
Resource Head Grade
• Geology – understand the deposit, do not let the software drive the interpretation and replace judgement
• Collect enough data
• Database integrity – QA/QC.
• Capping.
• Specific Gravity or Bulk Density?
• Cut-off grades – break even or incremental? • Checkerboarding
• Low grade deposits and accuracy of estimation.
• Reconciliation.
• Grade smearing
www.rpacan.com Rock Solid Resources. Proven Advice.
9
LEGEND: Grey = Blocks Below Cut-Off Red = Blocks Above Cut-Off
The Effect of Cut-Off Grade = 1.0 g/t
www.rpacan.com Rock Solid Resources. Proven Advice.
10
LEGEND: Grey = Blocks Below Cut-Off Red = Blocks Above Cut-Off
3.0 g/t
www.rpacan.com Rock Solid Resources. Proven Advice.
11
LEGEND: Grey = Blocks Below Cut-Off Red = Blocks Above Cut-Off
5.0 g/t
www.rpacan.com Rock Solid Resources. Proven Advice.
12
Dilution
• Mining method and production rate.
• Minimum width.
• Ground conditions.
• Equipment selection.
• Mining skills.
• Technical and supervisory skills.
• Grade Control and sampling.
• Assay turnaround.
• Most underestimated of all technical parameters.
www.rpacan.com Rock Solid Resources. Proven Advice.
13
MineralizationOutline
0.8
3.43.7
0.5
3.5
0.24.4
0.50.5
4.52.5
2.63.6
1.5
0 .8
3 .40 .7
0.5
3.5
3. 4
0.3
0.5
0. 5
0.5
0.7
0.8
1 .1
1.5
InternalDilution
Dilution & Extraction
www.rpacan.com Rock Solid Resources. Proven Advice.
14
PlannedDilution
PlannedDilution
Drift
Drift
DesignedStope
MineralizationOutline
PlannedLoss
PlannedLoss
Dilution & Extraction
www.rpacan.com Rock Solid Resources. Proven Advice.
15
Drift
Drift
DesignedStope
MineralizationOutline
UnplannedDilution
UnplannedDilution
Actual Stope
Dilution & Extraction
www.rpacan.com Rock Solid Resources. Proven Advice.
16
Minimum Mining Width
• Vein width vs. equipment requirements – dilution.
• Block size for resource model. Narrow vein with big blocks or bulk mining with small blocks.
www.rpacan.com Rock Solid Resources. Proven Advice.
18
5 x 5 m 2.5 x 2.5 m Considerations include: - Ability to locate individual blocks in BH pattern - Excavate entire block cleanly – loading unit - From a shot-rock pile that has moved
Selective Unit – Open Pit Mine
www.rpacan.com Rock Solid Resources. Proven Advice.
19
Head Grades - Actual Production vs PFS and FS Studies
Based on 70 Projects
www.rpacan.com Rock Solid Resources. Proven Advice.
20
Productivity
• Not enough workplaces = less flexibility in production plan = higher dilution.
• Mine operators will generally always deliver the required tonnes, but sometimes there is no ore in them.
• Zero base – use cycle times, not factors.
• Lay out entire mine at the start, including all development.
• Schedule in detail – monthly, quarterly, annually, life of mine.
• Detailed 3 month plan for operations.
• Underground – 50 metres vertical per year.
• Open pit – 8 to 12 benches per year.
www.rpacan.com Rock Solid Resources. Proven Advice.
21
Processing
• Metallurgical assumptions.
• Enough testwork to establish recoveries, con grades and impurities.
• Bench scale, Locked cycle tests, Grinding tests, Pilot Plant.
• Bulk Sample.
• Non Standard or new technology.
• Plant ramp up.
• Can range from two weeks to never.
• Should forecast four to six months at the FS level, for standard technology.
• Allow for experienced startup team and many people.
• Ensure assay lab is running and can turnaround samples quickly.
www.rpacan.com Rock Solid Resources. Proven Advice.
22
Capital Costs
• RPA database from 2002.
• EMJ Gypton Jan 2002 and recent work by RCF from 2005.
• RCF also gathered historical data from 1965.
• Mining Engineering Bullock Apr 2011.
• Close to 200 projects.
• General average overrun 20% to 25%.
• Much higher in times of high metal demand and prices.
• Not just mining – analysis of other projects pre-2002 showed an average overrun of 28% - going back 90 years.
www.rpacan.com Rock Solid Resources. Proven Advice.
23
Capital Cost Overruns - Experience
-50%
0%
50%
100%
150%
200%
250%
300%
$10 $100 $1,000
Cos
t Ove
rrun
Original Project Estimate ($M)
Capital Cost Overruns in Mine Construction
www.rpacan.com Rock Solid Resources. Proven Advice.
24
Capital Cost Overruns – By Project
-20%
0%
20%
40%
60%
80%
100%
120%
140%
160%
180%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Actu
al C
apita
l Cos
t C
ompa
red
to B
udge
t
www.rpacan.com Rock Solid Resources. Proven Advice.
25
Costs Example – How Reliable are Study Estimates
• 73% Increase of Capital Costs from Prefeasibility Study (PFS) to Updated Feasibility Study (UFS).
• Operating Cost increase not as dramatic, but still 37% higher than PFS.
• Source of cost escalation largely in labour, consumables, equipment.
• This is not atypical for recent mining projects, across all commodities, mine types, locations, and company sizes.
0
0.2
0.4
0.6
0.8
1
1.2
1.4
$-
$5
$10
$15
$20
$25
Oct-09 PFS Jun-10 FS Oct-12 UFS Feb-14 ACT
Hea
d G
rade
(gpt
)
OPE
X ($
/t pr
oces
sed)
Operating Costs and Grade - OP Gold in Canada
OpEx ($/t processed) Head Grade (gpt)
$-
$0.5
$1.0
$1.5
$2.0
$2.5
$3.0
Oct-09 PFS Jun-10 FS Oct-12 UFS Oct-13 ACT
Cap
ital C
osts
Bill
ions
Large OP Gold in Canada
INIT CAP SUST CAP
www.rpacan.com Rock Solid Resources. Proven Advice.
26
Changes in Study Estimates
$-
$50
$100
$150
$200
$250
$300
$350
$400
$450
$500
Oct-06PEA
Sep-07PFS
May-08FS
Sep-09UFS
Aug-10ACT
Initi
al C
apita
l Cos
t (M
illio
ns)
Capital Cost Escalation - Mid Size OP Gold in W. Africa
$-
$50
$100
$150
$200
$250
Feb-06 PEA Aug-07 FS Dec-07 UFS Mar-09 ACT
Initi
al C
apita
l Cos
ts (M
illio
ns)
Mid Size OP & UG Gold/Silver in Mexico
15% increase in CAPEX from PEA to Actual
52% increase in CAPEX from PEA to Actual
www.rpacan.com Rock Solid Resources. Proven Advice.
27
Operating Costs
• Larger is lower unit cost.
• Smaller is higher unit cost.
• Complexity is higher cost.
• Remote areas are higher cost.
• The key cost drivers will change from area to area, mine to mine and process to process. What was key for a remote Canadian operation may not be key to a remote operation in another country.
www.rpacan.com Rock Solid Resources. Proven Advice.
28
Where Do Operating Cost Estimates Go Wrong?
• Productivity assumptions in every separate unit operation
• Tonnes per manhour
• Tonnes per hour of equipment
• Metres of development per day
• Productivity less at high elevations
• Understanding fixed vs variable costs.
• Missing the impact of administration on a unit cost basis especially in low tonnage operations (administration is fixed not variable).
• Believing that a zero base budget (or cost estimate from first principles) is correct just because there is a huge amount of detail in the calculations.
www.rpacan.com Rock Solid Resources. Proven Advice.
29
Where Do Operating Cost Estimates Go Wrong?
• Omitting items (administration, benefits, fees, head office, warehousing, support functions).
• Factoring based on other operations with similar methods.
• Not including costs for “high end” products that may be needed – winter diesel, biodiesel, galvanized bolts, stainless steel products.
• Over complicated spreadsheets resulting in logic and arithmetic errors that defy auditing
• Failure to keep track of edits and changes to costs including the rationale for such changes.
• Believing that a fixed price contract passes the risk to the contractor or supplier.
www.rpacan.com Rock Solid Resources. Proven Advice.
31
People and Technology
• Knowledge and experience gap.
• Lack of skilled people at all levels.
• Majors have abandoned the traditional role of training engineers and managers.
• Reliance on software in replacement of judgment = precision over accuracy.
• Statistical analysis is overrated. Should I really feel more comfortable if someone tells me the project is P90?
• Process related analysis can lead to a false sense of security, e.g. risk assessments.
• Team Size Matters - Project complexity is the primary driver
• Teams are commonly too small (especially for mega projects).
• Very common to see vacant positions on the org chart.
www.rpacan.com Rock Solid Resources. Proven Advice.
32
Non-Fatal Areas That Can Be Overcome
• Schedule Delay • Ramp-Up Delay
Discussed Previously • Capital Cost Overruns • Management and People • Level of Study
Individually these problem areas can usually be overcome, when combined, may again be fatal.
www.rpacan.com Rock Solid Resources. Proven Advice.
33
Schedule Delay
• The primary purpose of the schedule developed by the EPCM firm is to provide a target for project completion.
• The Master Schedule typically excludes any contingency.
www.rpacan.com Rock Solid Resources. Proven Advice.
34
Ramp-Up
From: Terry McNulty
Mining Engineering Oct 1998
www.rpacan.com Rock Solid Resources. Proven Advice.
35
More Observations
1. Precision vs Accuracy - believing that detail makes it all correct. 2. Believing that cheap labour means lower cost . 3. Not benchmarking. 4. Truisms that aren’t.
• We can do better than everyone else – we have a better team.
• If that’s all the money we can raise, then that’s what we will build it for.
• The contractors should carry the risk – or - don’t worry, we have fixed price contracts.
• The EPCM people have promised us their best team.
www.rpacan.com Rock Solid Resources. Proven Advice.
36
Summary
• Objective: • Provide background on why mining projects fail • Describe fatal and non-fatal failures • Describe problem areas to understand impact
• Outcome • Understanding risks for mining projects • Know when to get out
www.rpacan.com Rock Solid Resources. Proven Advice.
Toronto Denver London Vancouver Quebec City
Richard J. Lambert, P.E. Tel: +1 (303) 800-8104 Email: [email protected]