39
“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations

WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

“WHY ARE PROJECTS ALWAYS LATE?”(what can the Project Manager DO about that?)

Craig Henderson, MBA, PMPARVEST Bank Operations

Page 2: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Introduction

PM Basics• FIO

• GID

• KISS

Predictable Project Delivery- Quality product- On time- On budget

(Figure it out)

(Get it done)

(Keep it simple, )sweetie

Page 3: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Planning• “FIO”

• Detailed, precise SCOPE• Create WBS structure• Estimate activity durations• Sequence activities

• Network diagram• Develop schedule

With all this wonderful work,WHAT COULD POSSIBLY GO WRONG??

Page 4: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Planning• Estimate Errors?• Scope Creep?• Execution?• Risks?

Page 5: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Estimate Errors?• Factors influencing estimate quality

• Planning horizon• Immediate events more accurate than distant events

• Project duration• Shorter durations more accurate than long

• People• Resource skill levels• Team experience• Turnover• Productive time (5-6 hours/day?)

• Project structure & organization• Estimate padding (or Understating?!)• Organization culture

Page 6: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Estimate Errors?• Estimate Errors?• Tradeoffs

• “Nothing” is free (but everything else Costs!)• Estimates are not free• “Better” estimates are more expensive

• Must balance accuracy/cost tradeoff

Don’ t underestimate the estimate

Page 7: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

task pred 1 pred 2 EstimateA 3B A 2C A 5D A 4E B 3F C 2G D 8H E F 4I H 4J G 4K I J 7

Task Data

What is your project duration estimate?

Page 8: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

(network diagram reminder)

ES ID EF

SLACK

LS Dur LF

“AON” (Arrow on Node)ES ID EF

SLACK

LS Dur LF

ES ID EF

SLACK

LS Dur LF

ES ID EF

SLACK

LS Dur LF

Page 9: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

3 C 8

1

4 5 9

3 B 5

3

6 2 8

5 E 8

3

8 3 11

3 D 7

0

3 4 7

14 I 18

115 4 19

8 F 10

1

9 2 1119 K 26

0

19 7 26

10 H 14

111 4 15

15 J 19

0

15 4 19

7 G 15

0

7 8 15

0 A 3

0

0 3 3

Network Diagram

What is the Critical Path?

Page 10: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

3 C 8

1

4 5 9

3 B 5

3

6 2 8

5 E 8

3

8 3 11

3 D 7

0

3 4 7

14 I 18

1

15 4 19

8 F 10

1

9 2 1119 K 26

0

19 7 26

10 H 14

1

11 4 15

15 J 19

0

15 4 19

7 G 15

0

7 8 15

0 A 3

0

0 3 3

Critical Path

Page 11: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

task pred 1 pred 2 EstimateA 3B A 2C A 5D A 4E B 3F C 2G D 8H E F 4I H 4J G 4K I J 7

Tot CP Est 26CP= A-D-G-J-K

Task Data

What are our odds of finishing on time, P(26)?100%? 50% (50/50)? (Something else?)

Page 12: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Not So Fast!

• Task Duration• One point?• Three point?• Distribution?

“95% Payback, BEST IN TOWN!”

(Fitzgerald’s Casino, Reno, NV)

“Feeling lucky, Sucker?!”

Page 13: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

PERT

• “Program Evaluation Review Technique”• Assumes activity duration is a range statistically following

a beta distribution. • 3 time estimates for each activity:

• Expected• Optimistic• Pessimistic

• Weighted average represents activity duration distribution.• Weighted average and variance for each activity allows computed probability for various project durations.

Page 14: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Activity and Project Frequency Distributions

Page 15: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Activity Time CalculationsThe weighted average activity time is computed by the following formula:

Page 16: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Activity Time Calculations (cont’d)

Activity time estimate variability approximated by:

Standard deviation for activity:

Standard deviation for project:

Note standard deviation of activity is squared in this equation; also called variance. This sum includes only activities on the critical path(s) or path being reviewed.

Page 17: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

task pred 1 pred 2 a m bA 2 3 4B A 1 2 3C A 4 5 12D A 3 4 11E B 1 3 5F C 1 2 3G D 1 8 9H E F 2 4 6I H 2 4 12J G 3 4 5K I J 5 7 8

CP= A-D-G-J-K

Task Data

Page 18: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

task a Est (m) b T(e) sigma sigma^2A 2 3 4 3 0.333333 0.111111B 1 2 3 2 0.333333 0.111111C 4 5 12 6 1.333333 1.777778D 3 4 11 5 1.333333 1.777778E 1 3 5 3 0.666667 0.444444F 1 2 3 2 0.333333 0.111111G 1 8 9 7 1.333333 1.777778H 2 4 6 4 0.666667 0.444444I 2 4 12 5 1.666667 2.777778J 3 4 5 4 0.333333 0.111111K 5 7 8 6.833333 0.5 0.25Totals: 26 25.83333 4.027778CP= A-D-G-J-K CP sigma = 2.006932

Task Times

66% of the time, this project will complete in the range of??

Page 19: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Probability of Completing the Project @ XCompute the “Z” value (Z = number of standard deviations from the mean)Then find probability of Z

Page 20: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Z Values and Probabilities

Page 21: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Possible Project Duration ExampleProbability project is completed before

scheduled time (TS) of 67 daysProbability project is completed

by the 60th day (TS)

Page 22: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Probability of finish by Est?

%53)26(083.

01.2/)83.2526(/)(

==

−=−=

p

StndDevvalueMeanZ

Page 23: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Possible Project DurationProbability project is completed before

scheduled time (TS) of 26 units

%53)26(083.

01.2/)83.2526(/)(

==

−=−=

p

StndDevvalueMeanZ

Total

25.8326

53%

Page 24: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Monte Carlo Simulation• Randomize task times

• Random normal number• Adjusted for µ & σ of each task’s distribution

• Add resulting task times per network diagram• Do this “many” times!• Calculate average (expected value) and σ

Page 25: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Monte Carlo Simulationin Excel

• Generate random results for each task• Analysis Tool Pack, Random Number Generator

• Following CP, add times• Remember “IF” statement to check CP length!

• Calculate average project time/stnd dev• Compare to previously computed result

Page 26: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Monte Carlo Results• Te = 27.57• Stnd Deviation = 1.83

• (Remember, Computed• Te = 25.83• Stnd Dev = 2.0)

% change (mean)= 6.36%

% change (sigma)= -8.72%

How can this be?

Page 27: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Monte Carlo• CP = A-D-G-J-K

BUTMonte Carlo runs showed• CP finish of A-C-F-H-I-K = 61.3%

ObservationCP shifted from original path about 2/3 of the time!

The CP shift prevented us from gaining full advantage when the original randomized CP was very early.

CP Results # %A-B-E-H-I-K= 15 1.5%A-C-F-H-I-K= 613 61.3%A-D-G-J-K= 372 37.2%

What is the term for a network like this?

Page 28: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

3 C 8

1

4 5 9

3 B 5

3

6 2 8

5 E 8

3

8 3 11

3 D 7

0

3 4 7

14 I 18

1

15 4 19

8 F 10

1

9 2 1119 K 26

0

19 7 26

10 H 14

1

11 4 15

15 J 19

0

15 4 19

7 G 15

0

7 8 15

0 A 3

0

0 3 3

Critical Path, and others

Page 29: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Monte Carlo Result - Beta Distribution?Total

Count of beta

beta

CP Results # %A-B-E-H-I-K= 15 1.5%A-C-F-H-I-K= 613 61.3%A-D-G-J-K= 372 37.2%

Page 30: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

task pred 1 pred 2 a m bA 2 3 4B A 1 2 3C A 4 5 12D A 3 4 11E B 1 3 5F C 1 2 3G D 1 8 9H E F 2 4 6I H 2 4 12J G 3 4 5K I J 5 7 8

CP= A-D-G-J-K

Task Data

Page 31: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Management’s Project TargetTotal

Count of Random Z

Random Z

Est CP = 26, Te(computed) = 25.83, Te (simulation) = 27.57

Page 32: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Confidence and Completion

• 95% confidence project will complete by time “X”

57.3057.2783.1*64.1

)(*

=+=

+= MeanStndDevZ

“95% Payback, BEST IN TOWN!”

(Fitzgerald’s Casino, Reno, NV)

“Feeling lucky, Sucker?!”

Page 33: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Possible Project Duration95% confidence Project Duration

Total

27.57

30.57

95%

57.3057.2783.1*64.1

)(*

=+=

+= MeanStndDevZ

Page 34: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Probability of finish by Est?

%20)26(858.

83.1/)57.2726(/)(

≈−=

−=−=

p

StndDevvalueMeanZ

“Feeling lucky, Sucker?!”

P(26)?

Page 35: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Probability of finish by Est?

%20)26(858.

83.1/)57.2726(/)(

≈−=

−=−=

p

StndDevvalueMeanZ

Total

27.57

26

20%

Page 36: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

CP T(e)= 25.83CP sigma = 2.00Project 95% con= 29.12P(26) = 53.32%

Monte Carlo T(e)= 27.57sigma = 1.83Project 95% con= 30.58P(26) = 20%

Project Result Summary

Page 37: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Remember• Activity definition and precedence• Network diagram• Task estimates, and ranges/distributions• Calculate Expected Durations on CP• Consider Monte Carlo simulation

Finally:• Calculate “Management Duration” based on desired

confidence/predictability• Add this to your Risk Plan and Risk Budget

Page 38: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

“Why are projects always late?”Project Managers frequently fail to understand and account for

Actual result distributions vary from (point) estimatesIn their Risk Plans and Budgets

“Feeling lucky, Sucker?!”

Page 39: WHY ARE PROJECTS ALWAYS LATE?...“WHY ARE PROJECTS ALWAYS LATE?” (what can the Project Manager DO about that?)Craig Henderson, MBA, PMP ARVEST Bank Operations Planning • “FIO”

Questions!

“Feeling lucky, Sucker?!”