Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
REPORT
Report prepared for:
GREATER WELLINGTON REGIONAL COUNCIL
Report prepared by:
Tonkin & Taylor Ltd
T&T Ref: 85484.004
Greater Wellington Regional Council
Resource Consent Applications for
River Management Activities in rivers
of the Upper Wairarapa Valley
& for Dry Gravel Extraction from
selected river reaches in the Lower
Wairarapa Valley
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry
Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Table of contents
Greater Wellington Regional Council i
Resource Consent Applications for River Management Activities in rivers of the
Upper Wairarapa Valley i
& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley i
1 Introduction 1
1.1 Application for resource consents 1
1.2 Activities not requiring consent 10
1.3 Wider context of this application 13
1.4 Proposed adaptive management approach 15
1.5 Structure and terms sought for new consents 15
2 Land ownership 18
3 Mana whenua 19
4 River management context 21
4.1 River management schemes 21
4.2 Floodplain management plans 23
4.3 Current river management strategies 23
4.3.1 Gravel extraction 23
4.4 Development of annual works programmes 24
5 Existing works and activities 26
5.1 Upper Ruamahanga River 26
5.1.1 Ruamahanga – Mt Bruce Scheme 26
5.1.2 Ruamahanga – Te Ore Ore Scheme 27
5.1.3 Ruamahanga – Gladstone Scheme 27
5.2 Waingawa River 27
5.3 Waipoua River 28
5.4 Kopuaranga River 29
5.5 Whangaehu River 29
5.6 Taueru River 30
5.7 Waiohine River 30
5.8 Mangatarere Stream 30
5.9 Kaipatangata Stream 30
5.10 Enaki Stream 30
5.11 Gravel extraction – Area One 30
5.11.1 Upper Ruamahanga catchment 30
5.11.2 Waiohine River 34
5.11.3 Kaipatangata Stream 34
5.12 Gravel extraction – Area Two 34
6 Existing river environment 35
6.1 Geomorphology & sediment transport 35
6.2 Hydrology 35
6.3 Water quality 35
6.4 Riparian vegetation 35
6.5 Birds 35
6.6 Aquatic vegetation 35
6.7 Aquatic macroinvertebrates 35
6.8 Fish 35
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry
Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
6.9 Recreation 36
6.10 Heritage & sites of cultural value 36
6.11 Sites of cultural value 36
7 Proposed works 36
7.1 Management approach 36
7.2 Activities 36
7.3 Gravel extraction 36
8 Consideration of alternatives 36
9 Assessment of environmental effects 36
10 Consultation 36
11 Statutory assessment 36
12 Proposed consent conditions 36
13 Conclusions 36
14 Applicability 36
Appendix A: Application Forms i
Appendix B: Certificates of Title i
Appendix C: River management scheme plans and work records i
Appendix D: i
Appendix E: i
Annex 1: Environmental Code of Practice & Monitoring Plan (working draft) i
Figure 1: Application Area One – Upper Wairarapa Valley (for Toolbox of activities) Figure 2: Application Area Two – Lower Wairarapa Valley (for dry gravel extraction only) Figure 3: Adaptive management framework Figure 4: Location of significant gravel extraction sites in the 10 years prior to 2014. Source:
(Harley, 2014) Figure 5: Waingawa River Gravel Extraction 1977 – 2013. Source: (Harley, 2014) Figure 6: Ruamahanga River – Te Ore Ore Reach Gravel Extraction 1979 -2013 Figure 7: Waipoua River Gravel Extraction History 1998 -2013. Source: (Harley, 2014)
Table 1: Application Areas One & Two – extent details Table 2: The ‘toolbox’of activities proposed for use in accordance with the Code of Practice Table 3: Regional resource consents required Table 4: Permitted Activities Table 5: GWRC’s river management project work streams Table 6: Upper Wairarapa Valley River Management Schemes – Summary information Table 7: Annual works programme development process Table 8: Upper Ruamahanga catchment gravel extraction limits and extracted volumes 2012/13.
Source: (Harley, 2014)
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry
Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Executive summary
Greater Wellington Regional Council (GWRC) is seeking resource consents under the
Resource Management Act 1991 (RMA) to allow for the continuance of its river
management activities in two areas of the Wairarapa Valley as follows:
Area One, covering selected parts of the beds and banks of the rivers of the Ruamahanga
River catchment above the Waiohine River confluence, and parts of the beds and banks of
the Waiohine River and its tributaries (the Mangatarere, Kaipatangata and Enaki Streams).
Six drain management systems located in the upper Ruamahanga River catchment which
are managed by GWRC are also included in this application area.
Area Two, covering only the dry beaches in selected reaches of several rivers in the Lake
Wairarapa and Lake Onoke catchments and Ruamahanga River catchment below the
Waiohine River confluence.
The new consents being sought are intended to replace six existing resource consents held
by GWRC which are due to expire. These existing consents currently allow for flood
protection activities in parts of the Waiohine River, Mangatarere and Kaipatangata Streams,
the Waingawa, Waipoua and Upper Ruamahanga Rivers, and also gravel extraction from
beaches throughout the entire Ruamahanga River catchment. GWRC seeks for the new
consents to cover these areas and also to include parts of the Kopuaranga, Whangaehu and
Taueru Rivers, Enaki Stream (a tributary of Mangatarere Stream) and six drainage schemes
in the upper Wairarapa Valley which are not currently subject to any resource consents for
flood protection activities.
This application for new consents offers GWRC river managers the opportunity to set in
place a revised approach to the management of the rivers of the upper Wairarapa Valley,
which provides for greater commitment to improvement of the river environment, in
conjunction with necessary and on-going flood protection and erosion control to protect
the productive land and urban areas through which the rivers flow.
To date, GWRC’s river management activities have been controlled by consents that have
contained a wide array of prescriptive conditions, and in particular, detailed limits on
activities such as the length of rock lining, bed recontouring and amounts of gravel
extraction in any one year. GWRC seeks an improvement to this regime, and thus is
proposing a slightly different approach to the structure of the new consents, which aims to
put in place meaningful controls on adverse effects while allowing for an increase in
understanding of those effects.
GWRC’s river management approach is based fundamentally on the concept of a design
alignment for the river, which consists of a ‘fairway channel’ (i.e. the channel that would be
fully covered by water in a large flood event) and buffer zones containing edge protection
works and plantings either side of the fairway. All the activities that GWRC undertakes in
the rivers are primarily focused on the establishment and maintenance of this design
alignment.
In recent years, it has been increasingly recognised by GWRC river managers that although
the design alignment imposes a level of unnatural control on the river form, it is possible to
design it in such a way that allows the river to form channels within the design alignment in
a way that reflects the river’s natural character. This can be achieved by using both the
edge protection works and instream works to guide the form of the river channels into a
desired meander pattern that has been calculated from actual measurements of the river’s
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry
Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
form in unmanaged reaches. This is regarded as desirable because improvement in the
geomorphic form or ‘natural character’ of a river is assumed to have flow-on benefits for
the aquatic habitat diversity within the river, and by extension, the fish and invertebrates
using that habitat. If such benefits can be achieved, then this may also deliver positive
outcome in terms of cultural and recreational values.
GWRC is committed to improving its practices to achieve better environmental outcomes,
and to collecting information which will inform decisions relating to this. To this end, it has
revised and updated its Code of Practice (COP), particularly the ‘how to’ descriptions for
individual river management activities, which collectively form it’s ‘toolbox’. GWRC is
seeking for the new consents to allow for the full toolbox of activities to be available for
use, with decisions on the particular ‘mix’ of activities to be made by river managers, taking
into account the particular values or sensitivities of the river and/or reach/site in question.
This requires on-going information gathering and data collection to identify and quantify
those ‘values’ and include them in the COP.
GWRC has also developed an Environmental Monitoring Plan (EMP), which forms part of
the COP. This contains proposals for on-going investigations into the effects of selected
activities, so as to build a database of information over time which can be used to evaluate
those activities and make decisions about their on-going effectiveness and use.
To enable improvement and innovation over time, GWRC needs to have the ability to
respond to the outcomes of monitoring and to new information or research by changing its
practice, once that information has been appropriately considered and evaluated.
This would more easily be facilitated if the new consents were to authorise the continuance
of its river management activities, not according to a set of prescriptive consent conditions
that are fixed in time, but according to the Code of Practice and Environmental Monitoring
Plan, and the regular review process that forms part of it. This review process will involve
science advisers, mana whenua and other interested parties or stakeholders, and will
inform updates and changes to the Code and EMP over time. With such a ‘rolling review’ in
place, the need to continually review the actual consent becomes redundant, provided that
commitment to the review of the Code and EMP is assured. Hence the term of the consent
becomes far less important than the process that it authorises – and hence GWRC is
seeking the maximum allowable term of 35 years for the new consents.
A key issue for the EMP is the testing of the idea that an improvement in the overall
‘natural character’ of the river leads to overall environmental and ecological benefits,
despite the fact that individual activities may produce short-term adverse effects at specific
sites within the river environment. To enable this, a means of measuring ‘natural character’
in a quantitative way is required, and to this end GWRC has been supporting work
undertaken by Massey University to develop a ‘natural character index” or NCI which can
be used for this purpose. Although in its developmental phases, GWRC is keen to progress
this work as a new and innovative tool for river management and monitoring.
As well as providing opportunities for increased collaboration between interested groups,
adoption of the adaptive management approach will require compromises from all parties.
For example, it requires ratepayers to accept that there may be increased costs involved
with river management; it requires river managers to accept greater scrutiny of their
practices and to be open to change; it requires ecologists and mana whenua to accept that
some short-term adverse effects may be unavoidable in the achievement of longer term
improvement.
GWRC is very hopeful that the new resource consents can deliver a mechanism for
achieving real improvements in both river management and environmental outcomes going
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry
Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
forward, which may well provide a model for other river managers around the country to
emulate.
1
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
1 Introduction
1.1 Application for resource consents
Greater Wellington Regional Council (GWRC) seeks resource consents under sections 9, 13, 14
and 15 of the Resource Management Act 1991 (RMA) to undertake activities in two areas of the
Wairarapa Valley as follows:
Area One, covering:
• selected parts of the beds and banks of the rivers of Te Kauru (i.e. the catchment of the
Ruamahanga River above the Waiohine River confluence)
• parts of the beds and banks of the Waiohine River and its tributaries (the Mangatarere,
Kaipatangata and Enaki Streams)
Area Two, covering:
• Dry beaches in selected reaches of several rivers in the Lake Wairarapa and Lake Onoke
catchments and Ruamahanga River catchment downstream of the Waiohine River
confluence.
The two application areas are shown in Figure 1 and Figure 2. Area One includes the beds and
banks of the rivers covered by nine current river management schemes, and a few river reaches
outside these scheme areas which are also maintained by GWRC under its isolated works or
gravel management policies1. Area Two includes the entire main stem of the Ruamahanga River
bed below the Waiohine confluence, plus reaches of three of its tributaries (Huangarua River
catchment, Dry River and Tauanui River), reaches within four rivers flowing to Lake Wairarapa and
reaches of two rivers flowing to Lake Onoke. Further details are given in Table 1.
The new consents are intended to replace six existing resource consents that currently allow for
flood protection activities in parts of the Waiohine River, Mangatarere and Kaipatangata Streams,
the Waingawa, Waipoua and Upper Ruamahanga Rivers, and also gravel extraction from beaches
throughout the entire Ruamahanga River catchment. The new application covers these areas and
also extends over parts of the Kopuaranga, Whangaehu and Taueru Rivers and Enaki Stream (a
tributary of Mangatarere Stream), which are not currently subject to any resource consents for
flood protection activities.
The activities proposed in Area One are as follows:
Flood protection and erosion control works and maintenance activities (including gravel
extraction), and river corridor management activities.
GWRC requests that the resource consents for Area One will provide for the complete
‘toolbox’ of flood protection operations and maintenance activities, as listed in Table 2, to
be available for use. It is proposed that the consent conditions relating to these activities
will require them to be selected and undertaken in accordance with GWRC’s
Environmental Code of Practice and Monitoring Plan for Flood Protection Activities (COP),
with details around limits and restrictions on activities to be prescribed in the COP rather
than in the conditions of consent. In addition, GWRC also seeks for the consent conditions
to require the adoption of an adaptive management approach which involves a
programme of on-going monitoring of the effects of selected activities (as presented in an
1 Note that maintenance works in the Drainage Schemes within the Wairarapa Valley are not included in the
application.
2
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Environmental Monitoring Plan or EMP which is incorporated in the COP). This will enable
better understanding of the effects of the activities undertaken and will inform changes
to the COP over time via an agreed consultative review process, which is explained
further in Section 1.4. A term of 35 years is proposed for these consents, as explained
further in Section 1.5.
Flood protection activities in the ‘toolbox’ that must be authorised by resource consent
under rules in the operative regional plans are given in Table 3. A working draft of the
COP & Environmental Monitoring Plan is attached to this report as Annex 1.
It is stressed that in seeking authorisation of the full toolbox GWRC does not intend to
create an expectation that all methods available in the toolbox will necessarily be
employed over the life of the consent; nor does it imply that the level of service currently
provided under each current river management scheme will necessarily alter. Rather, the
primary intention is to ensure that the Council is able to select the most appropriate
method or methods at any time over the life of the consent to provide appropriate and
environmentally acceptable responses to flood and erosion control issues.
The activities proposed in Area Two are limited to:
Gravel extraction from dry river beds.
This application seeks to authorise the continuation of gravel extraction in the Lower
Ruamahanga catchment from beaches above the actively flowing channels (‘dry
extraction’). A term of approximately 12 years is proposed for this consent so that its
expiry coincides with the expiry of the current resource consent for flood protection
activities in the lower Ruamahanga River and Lake Wairarapa catchments2. This will allow
for gravel extraction in this area to be reconsidered as part of the renewal of these ‘Lower
Valley’ consents and in the context of a Lower Valley Floodplain Management Plan
process, which has yet to commence.
The prescribed resource consent Application Forms are included in Appendix A, and the following
report contains the information necessary to support these applications and fulfil the
requirements of section 88 of the RMA, including an assessment of environmental effects (AEE).
Administrative details are included below.
Applicant Wellington Regional Council3
Owners of application site The Crown, Wellington Regional Council, Masterton,
Carterton & South Wairarapa District Councils and
others. Certificates of Title are included in Appendix
B4.
Site address / map reference Area One: The beds and banks of rivers in the selected
rivers of the Upper Wairarapa Valley – see Table 1 for
details
Area Two: Dry beaches within the beds of selected
rivers in the Lower Wairarapa Valley – see Table 1 for
2 Consent WAR 070049 authorises flood protection works and maintenance activities within the Lower Wairarapa Valley
Development Scheme area. It expires on 30 September 2027. 3 Note that this is the correct legal name for the regional council. Elsewhere in this application document, the council is
referred to by its promotional name of ‘Greater Wellington Regional Council’. 4 The official copy of the application includes a Schedule of the Certificates of Title and copies of each title; other copies
only include the Schedule.
3
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
details
RMA Regional Plans Regional Freshwater Plan for the Wellington Region
Regional Soil Plan for the Wellington Region
RMA District Plans Combined Wairarapa District Plan (Masterton,
Carterton & South Wairarapa District Councils)
Address for service and invoicing Greater Wellington Regional Council
Flood Protection Department
Attention: Tracy Berghan
1
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Figure 1: Application Area One – Upper Wairarapa Valley (for Toolbox of activities)
1
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Figure 2: Application Area Two – Lower Wairarapa Valley (for dry gravel extraction only)
2
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Table 1: Application Areas One & Two – extent details
Area
River
Managed Reach/Scheme
Upstream extent
NZTM Grid
reference
Downstream extent
NZTM Grid
Reference
Length of
waterway (km)
Easting Northing Easting Northing
One Ruamahanga River Upper Ruamahanga -Mt Bruce Scheme 1820075 5484340 1826285 5463335 25
Upper Ruamahanga – Te Ore Ore Scheme 1826285 5463335 1824700 5457285 9
Upper Ruamahanga – Gladstone Scheme 1824700 5457285 1810081 5446279 24
Kopuaranga River Kopuaranga Scheme 1827625 5481635 1826895 5469325 27
Waipoua River Waipoua Scheme 1820670 5475140 1825286 5462380 18
2.5 km section upstream of Scheme 1820687 5477082 1820670 5475140 2.5
Waingawa River Waingawa Scheme 1813255 5469940 1824125 5456915 17
Whangaehu River Whangaehu Scheme 1829900 5462080 1826260 5458975 9
Taueru River Taueru Scheme 1828555 5455460 1821245 5450300 17
Waiohine River Waiohine/Mangatarere Scheme 1801481 5453181 1810481 5446779 17
1.5 km upstream of Scheme 1801360 5454415 1801481 5453181 1.5
Mangatarere Stream Waiohine/Mangatarere Scheme 1810620 5456445 1810481 5446779 6
Upstream scheme 1811635 5464985 1810620 5456445 13
Kaipatangata Stream Waiohine/Mangatarere Scheme 1808530 5455645 1810620 5456445 3
Gravel management reach 1809170 5454765 1809380 5454265 0.6
Enaki Stream Waiohine/Mangatarere Scheme 1809270 5457167 1809960 5455325 2.4
3
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Two Ruamahanga River Main stem from the end of Area One to
Lake Onoke
1810081 5446279 1778890 5417925
Huangarua River & tributaries Forest Park to Ruamahanga confluence Whole catchment*
Dry River Limeworks to Ruamahanga confluence 1799570 5423755 1799315 5431430 12
Tauanui River Upper catchment to Ruamahanga
confluence
Whole catchment*
Waiorongomai River (Lake Wairarapa catchment) Western Lake
Rd to delta
Whole catchment*
Tauherenikau River (Lake Wairarapa catchment) Gorge to Lake
Wairarapa
Whole catchment*
Donalds Creek/Abbots Creek (Lake Wairarapa catchment) Featherston to
Lake Wairarapa
Whole catchment*
Cross Creek (Lake Wairarapa catchment) Western Lake
Rd to delta
Whole catchment*
Turanganui River (Lake Onoke catchment) Whakatomotomo
Rd end to delta
Whole catchment*
Pounui Stream (Lake Onoke catchment) Western Lake Rd to
delta
Whole catchment*
* In this context ‘whole catchment’ means the catchment from the point at which the river emerges from the steep hill country
4
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Table 2: The ‘toolbox’of activities proposed for use in accordance with the Code of Practice
Activity Location General Activity Type Individual Activities
In or on the beds of rivers in Area One –
full toolbox
Construction & maintenance of
“Impermeable” Erosion Protection
Structures
• Rock & block groynes
• Gravel groynes & training banks
• Rock lining (rockline, rip-rap, toe rock)
• Gabion baskets
• Gabion structures
• Reno mattresses
• Grade control structures
Construction & maintenance of
“Permeable” Erosion Protection
• Debris fences
• Permeable groynes
• Debris arrester
Demolition and removal of existing
structures
• Impermeable structures
• Permeable structures
Maintenance of existing outlet structures Structural repairs to, cleaning and clearance of:
• Existing culverts and floodgate structures that discharge directly to the
river/waterbody
Channel shaping or realignment Mechanical:
• Beach ripping
• Beach recontouring
• Channel diversion cut
• Ripping of the bed in the active (flowing) channel
• Bed recontouring in the active (flowing) channel
• Bank contouring & reconstruction
Channel capacity maintenance • Beach scalping
• Removal of flood debris
• Gravel extraction from ‘dry’ beaches
• Gravel extraction from the active (flowing) channel
• Mechanical clearing of drains
• Mechanical clearing of minor watercourses
5
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Activity Location General Activity Type Individual Activities
Planting • Willow poles & stakes
Construction & maintenance of vegetative
(willow) structures
• Layered willows
• Tree groynes
• Tethered willows
Maintenance of riparian vegetation • Mechanical mowing of banks & berms from the river bed
• Trimming & mulching of bankside vegetation (while operating from the river bed)
Outside the beds of rivers in Area One –
full toolbox
Construction of structures and tracks on
berms
Construction of:
• Floodwalls
• Footbridges
• Fences
• Access ways
• Cycle ways
• Walk ways
and associated new stormwater drains and culverts
Maintenance of berms, structures and
tracks
Structural repairs to, and maintenance of:
• Berms
• Stopbanks & training banks
• Floodwalls
• Footbridges
• Fences
• Access ways, cycle ways, walk ways
• Stormwater drains
• Stormwater culverts (including clearance of debris)
Planting on berms • Tree planting – native
• Tree planting - willow
Maintenance of riparian vegetation • Trimming and mulching of trees (from outside the river bed)
• Removal of old trees
• Mowing stopbanks & berms (not involving machinery in river bed)
In the beds of the river reaches in Area Channel capacity maintenance Gravel extraction from beaches in the river bed, above actively flowing channels
6
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Activity Location General Activity Type Individual Activities
Two – dry gravel extraction only
7
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Table 3: Regional resource consents required
Location Type of resource
consent sought
Relevant Regional Plan &
Rule(s)
Activities covered by Regional Plan rules
Area One Land Use
Regional Freshwater Plan
(RFP):
Rule 43 – Maintenance,
repair, replacement
extension, addition to, or
alteration of any structure
Rule 44 – Removal or
demolition of structures
Rule 47 – Placement & use of
any river crossing on specified
rivers
Rule 48 – Placement of
impermeable erosion
protection structures (which
are part of an FMP or river
control scheme)
Rule 49 – All remaining uses
of river beds
� Construction in/on river beds of:
- impermeable erosion protection structures (rock groynes, riprap or gabion)
- rock/concrete grade control structures
- drainage channels and minor culverts associated with walkway developments
� Construction of gravel groynes, training banks in river bed
� Construction in/on river beds of permeable erosion protection structures:
- debris fences
- debris arresters
� Maintenance, repair, replacement, extension, addition, alteration of structures on river beds
(including associated disturbance of, or deposition on, river beds & temporary diversion of
water)
� Demolition and removal of structures from river beds (including associated disturbance of,
or deposition on, river beds)
� Placement of river crossings (including disturbance of, deposition on river beds or diversion
of water) on specified rivers – Kaipatangata Stream, Kopuaranga River, Mangatarere Stream,
Ruamahanga River, Waingawa River, Waiohine River, Waipoua River, Whangaehu River,
Taueru River)
� Layering & tethering of willows in the river beds
� Placement of cabled willows/tree groynes in river beds
� Mechanical ripping of river beds (including in the flowing channel)
� Cutting of diversion channels (excavation) in river beds
� Mechanical recontouring of the river beds (including in the flowing channel)
� Mechanical shaping and repair of bank edges (including deposition of material on river bed)
� Removal of sediment and aquatic vegetation from the beds of streams not classified as
‘drains’
8
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Location Type of resource
consent sought
Relevant Regional Plan &
Rule(s)
Activities covered by Regional Plan rules
� Extraction of gravel:
- from above the flowing channel (dry beaches) and flowing channels in rivers above
the Waiohine confluence
� Construction of footbridges > 6 m long
� Operation of machinery in river beds for all the above purposes (and for permitted activities)
� Entry & passage on river beds for operations & maintenance purposes (including by
machinery)
� Disturbance of river beds & deposition of material on river beds associated with all of the
above activities (including for formation of access)
� Undertaking of urgent works in river beds
Land Use Regional Soil Plan (RSP):
Rules 1 ,2 & 4
� Any works on banks & berms (i.e. not in river bed) that do not meet permitted activity rules
& conditions; this may include:
- Repairs etc. of banks, berms and stopbanks
- Construction of earth training banks (not in river bed)
- Construction of walkways or cycle ways on the river berms
- Disturbance of vegetation on berms
- Removal of material from river berms for the purpose of increasing flood carrying
capacity
Water Permit RFP Rule 16 � Damming or diversion of water associated with the above activities as necessary
Discharge Permit RFP Rule 5 � Discharge to the river of silt and sediments associated with:
- all construction works
- all maintenance works
- all demolition works
- all permitted activity works (including planting, beach recontouring & ripping,
vegetation & flood debris removal)
- all urgent works
in the river beds.
� Discharge of stormwater into surface water associated with works on banks & berms outside
the river bed
9
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Location Type of resource
consent sought
Relevant Regional Plan &
Rule(s)
Activities covered by Regional Plan rules
Area Two Land Use RFP Rule 49 – All remaining
uses of river beds
� Extraction of gravel from dry’ beaches only in river beds below the Waiohine confluence,
and associated disturbance of bed.
10
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
1.2 Activities not requiring consent
The flood protection ‘toolbox’ includes some activities for which resource consent is not required.
These include some of the activities in Table 3 which are classified in the operative regional plans
as permitted activities below a certain threshold, and/or activities that are prescribed as
permitted activities provided that certain conditions are met. These activities are listed in Table 4.
Table 4: Permitted Activities
Relevant Plan & Rules Activities covered
RFP Rule 1
Discharge of water (other than stormwater) and minor
contaminants
Cleaning & water blasting of structures
RFP Rule 2
Discharge of stormwater into surface water
Stormwater discharges arising from works
areas on berms (provided it doesn’t originate
from an area of bulk earthworks greater than
0.3 ha)
RFP Rule 9
Minor diversion of water from intermittently flowing
stream
Diversion of less than 1.5 m3/s of fresh water
& associated disturbance of river bed,
associated with placement of a structure in
an intermittently flowing stream
RFP Rule 9A
Diversion of water from an artificial watercourse or drain
Diversion of water from an artificial
watercourse or drain associated with
construction or maintenance work in the
drain
RFP Rule 22 Maintenance, repair etc. of structures Minor maintenance works on structures &
associated disturbance of river bed
RFP Rule 23 Extensions of linear rock protection Minor extensions of width & length to
existing riprap & associated river bed
disturbance
RFP Rule 24 Placement of vegetative bank protection
structures
Placement of cabled willows extending no
more than the lesser of 5 m or 10% of the
total stream width. (NB - Crack willow is
allowed if already predominant on river
margin)
RFP Rule 25 River crossings in intermittently flowing
streams
Placement of culverts, weirs, fords, small
bridges in intermittently flowing streams,
including any associated disturbance of or
deposition on bed or temporary diversion.
(NB – a ford is defined as ‘any modification of
the bed … to establish a crossing by which
any vehicle … or persons may traverse)
RFP Rule 27 Sediment retention weirs in intermittently
flowing streams
RFP Rule 31
The erection and maintenance of any bridge over a river
bed (less than 6m in length)
11
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
RFP Rule 33
Removal or demolition of structures
Removal or demolition of structures provided
they are not being replaced, or involving
disturbance of < 10 m3 of river bed material
RFP Rule 35
Entry or passage across river bed not covered by any use
specified in Rules 22 - 48 or s13 of the Act
Passage across a river bed for access
RFP Rule 36
Clearance of flood debris
Disturbance of river beds associated with
clearance of flood debris
RFP Rule 37
“Beach” recontouring
Recontouring of beaches in the river bed to
remedy or mitigate effects of flood or
erosion. Would include ‘ripping’.
RFP Rule 39
Maintenance of drains (as defined by RFP)
Removal of vegetation & associated sediment
from drains for the purpose of maintaining
original grade or cross section of the channel
RFP Rule 40
Removal of vegetation from river bed (& any associated
disturbance of, deposition on, river bed or temporary
diversion)
Removal of vegetation from river bed
(including cutting of stakes and poles for re-
planting)
Trimming, cutting or removal of trees on river
margins (and that are rooted in the river bed)
Would include ‘scalping’ to remove
vegetation on the surfaces of river beaches
RFP Rule 41
Planting (& any associated disturbance of, deposition on,
river bed or temporary diversion)
Planting in river beds for flood protection
purposes. (NB – crack willow is permitted on
river margins where already predominant)
RFP Rule 42
Urgent Works
Urgent works within 10 days of a natural
hazard event, including:
• Repair of any bank protection works
• Recontouring of the river beds
& associated disturbance of or deposition on
the river beds
RSP Rule 1
Roading & tracking east of Ruamahanga River resulting in
new upslope batter less than 200 m or less than 1.5 m
vertical height
Roading & tracking west of the Ruamahanga River resulting
in new upslope batter less than 200 m or less than 2 m
vertical height
Construction of walkways or cycle ways on
the river berms (outside of the river beds)
RSP Rule 2
Soil disturbance on erosion prone land ( > 23⁰ east of
Ruamahanga River ; > 28⁰ west of Ruamahanga River),
other than that associated with roading & tracking, that
disturbs less than 1000 m3 of soil within any 10,000 m
2 area
Repairs of stopbanks and berms (outside the
river beds)
Recontouring on berms
Lowering berms
12
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
RSP Rule 3
Vegetation disturbance on erosion-prone land, provided
vegetation is re-established within 18 months
Clearance of vegetation on steep banks,
mowing of some berms
In addition, the ‘toolbox’/COP includes some activities not restricted by the RMA or regulated by
the operative regional plans; these include:
• Erection of fences & other structures on berms
• Track creation on land under the RSP Rule 1 thresholds
• Vegetation clearance & soil disturbance on slopes lower than the ‘erosion-prone land’
thresholds.
It is GWRC’s intention that all flood protection activities will be undertaken in accordance with
good environmental practice, as outlined in the COP, regardless of whether the activities are
permitted or require resource consent.
13
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
1.3 Wider context of this application
This application for resource consents is one component of a wider GWRC consent renewal and
river management project, which covers eight current flood protection operations and
maintenance consents and three gravel extraction consents, all due for renewal between April
2013 and September 2016. The existing consents are spread between rivers in the western and
eastern parts of the Wellington Region.
The project comprises five work streams as detailed in Table 5. This application falls within the
ambit of Work Stream 1.
Table 5: GWRC’s river management project work streams
Work
Stream
Description Details Timetable & progress
1 Re-consenting
GWRC’s existing
operations and
maintenance
resource consents
in the western and
eastern parts of the
region.
The existing western rivers consents cover:
• Hutt River [WGN 980255 and WGN 060334]
• Stokes Valley Stream [WGN 060291]
• Waikanae River [WGN 980256]
• Otaki River [WGN 980254] and
• Wainuiomata River [WGN 020143]
The existing eastern rivers consents cover:
• Waingawa River [WAR 130142]
• Waiohine River, Mangatarere Stream,
Kaipatangata Stream [WAR 000363]
• Waipoua River [WAR000364]
• Upper Ruamahanga River [WAR000365]
• Ruamahanga River [WAR 990026]
• Kaipatangata Stream [WAR 990313]
Work on re-consenting the
western consents started in
April 2012; seven smaller
tributaries of the Hutt,
Waikanae and Otaki Rivers
are included. All consent
applications were lodged as
at October 2014.
Work on the eastern
consents commenced in late
2014 and is the subject of
this application.
2 Waingawa River
Short-term
Resource Consent
Application was made in 2012 and consent
granted in May 2013 for a short-term consent to
enable flood protection works in the Waingawa
River to continue until the Floodplain
Management Plan (FMP) work for this river
(currently underway – see Work Stream 5) is
sufficiently advanced to support a long-term
consent application.
This consent [WAR 130142]
expires 30 September 2015
and the re-consenting of it is
included in this application
(see Work Stream 1 above).
3 Monitoring of
environmental
effects of activities
and development
of a regional
Environmental
Monitoring Plan
This is to enable better understanding of the
effects of flood protection works and activities.
A Science Group drawn from external and
internal parties, including representatives from
Department of Conservation, Fish & Game NZ,
Massey University, GWRC Biodiversity and
Science staff, and involving a consultant ecologist
and a consultant river engineer, has been
established by GWRC to assist development of
the EMP and provide feedback and input into the
consent applications noted in Work Stream 1.
GWRC funded annual trout
surveys by Fish & Game NZ
in the Hutt and Waikanae
Rivers have continued.
A draft EMP has been
produced that expands on
initial environmental
monitoring of aquatic
ecology associated with
gravel extraction activities in
the Hutt River, and regional
river bird surveys.
Investigations are underway
14
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
into the development of a
‘Natural Character Index’ or
NCI.
Work on it continues and
the EMP forms part of the
COP that is also under
development.
4 Environmental
Code of Practice
Update of GWRC’s existing Environmental Code
of Practice. The new Code of Practice (COP) will
be region-wide and will inform all activities
undertaken by GWRC.
A draft COP was prepared
for inclusion with the
western rivers consent
applications, and is included
as Annex 1 to this
application. Initial comment
from iwi and some key
stakeholders has been
sought and considered in
the development of this
draft, and it is anticipated
that further development of
the Code will continue in
response to on-going
consultation throughout the
processing of the resource
consent applications, and
beyond.
5 Floodplain
Management Plans
FMPs already exist for the Hutt, Waikanae and
Otaki Rivers.
Development of FMPs for the Waiohine River,
Mangatarere Stream & tributaries (Enaki &
Kaipatangata Streams) and those rivers in Te
Kauru (the upper part of the Wairarapa Valley) –
including the Kopuaranga, Waingawa, Waipoua,
Whangaehu, Taueru Rivers and the upper
reaches of the Ruamahanga River)
The Waiohine FMP process
commenced in 2009 and
Phase 3 (selection of a
sustainable solution) was
signed off in late 2013.
Refinement of the preferred
option is currently
underway.
Scoping for the Te Kauru
Floodplain Management
Plan (TKFMP) was
undertaken in 2012, and
Phase 1 of the FMP process
investigations &
establishment of context)
was approved in October
2014. Phase 2 (identification
& assessment of
management options) is
underway. The FMP is
expected to be in place by
late 2016.
The TKFMP includes the
Waingawa River, for which a
separate FMP was initially
being developed.
15
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
1.4 Proposed adaptive management approach
The need for operations and maintenance work in many of Wellington’s rivers is constant and on-
going. However, the type of work that is undertaken has changed over time, and will continue to
change, in response to the changing needs of the particular flood protection scheme or floodplain
management plan (based on community expectation, any established agreements between local
government agencies and on the dynamics of the river) and in response to different management
philosophies. Over time, it has been increasingly recognised that operational works can often be
undertaken in ways that reduce impacts on the ecology of the river and on recreational uses.
The individual types of operational activities collectively form a ‘tool-box’ available for GWRC to
use in the day-to-day management of the river. The specific methods to address an individual
issue are selected by river managers based on experience and knowledge of the suitability of
those methods in that particular situation.
GWRC proposes an ‘adaptive management’ approach to the undertaking of flood protection
works under the new resource consents, to reflect its commitment to develop and improve its
river management practices in response to new knowledge. Central to the proposal is the idea
that the new and comprehensive COP (noted in Work Stream 4 above) will be used in conjunction
with the updated EMP to guide and direct GWRC’s works and maintenance activities that are
currently undertaken under the annual plans for individual river schemes, and which will
eventually be undertaken under the Te Kauru/Upper Ruamahanga and other FMP’s. In particular,
the COP will provide specific detail and direction on the methodology to be adopted for individual
activities. It will be a living document that reflects current good practice.
GWRC proposes that the programme of research and monitoring of the environmental effects of
activities (such as bed recontouring and gravel extraction in particular) in the rivers it manages,
noted in Work Stream 3 above, will be on-going. The outcomes of this monitoring will be subject
to evaluation and review which in turn will lead to adjustments to the COP, via an agreed process,
which is illustrated in Figure 3 and described in further detail in the COP & EMP in Annex 1.
For the adaptive management approach to work effectively, GWRC seeks for the new resource
consents to acknowledge and require its adoption, including the requirement for activities to be
undertaken in accordance with the COP rather than by detailed consent conditions5. It is
therefore intended that much of the detail and prescription for the methods to be employed will
be included in the COP, rather than in the resource consent itself. The COP will be a living
document representing good environmental practice. It will be supported by an on-going
programme of investigation and monitoring and amended accordingly. Such an approach will
allow greater flexibility to test and refine methods, allow for innovation and improvement of
practice over time without the need to vary and/or seek new resource consents.
1.5 Structure and terms sought for new consents
Area One
Since the introduction of the Resource Management Act (RMA) in 1991, GWRC has been required
to undertake its rivers works and maintenance activities according to resource consents that have
been used to prescribe and set the parameters for these activities. To date, the terms granted for
these consents have been less than the maximum 35 year term allowed under the RMA.
5 It is acknowledged that consent conditions for gravel extraction in the Lower Wairarapa Valley may need to be more
specific until this activity is addressed in more detail as part of FMP development for this area.
16
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
The rationale for limiting previous consents to shorter terms appears to have been principally to
allow for a significant re-evaluation of them, and particularly the environmental effects of the
activities they relate to, every 15 or so years. If the new consents authorise activities to be
undertaken in accordance with the COP and allow for the proposed adaptive management
process, the need for periodic review of the consents themselves is significantly reduced.
Adoption of the proposed adaptive management process will also enable relevant information
and decisions arising from the Waiohine FMP & TKFMP processes currently underway to be
incorporated into the COP & EMP on a progressive basis. For these reasons it is therefore
considered appropriate to apply the maximum allowable term of 35 years to the new consents for
the rivers of the Upper Ruamahanga & Waiohine catchments.
Area Two
Development of an FMP for the rivers in the lower parts of the Wairarapa Valley has not yet
commenced. It is considered more appropriate at this stage therefore, to adopt a more traditional
approach to gravel extraction in this area by limiting this management tool to the current practice
of extraction from dry beaches only, until such time as it can be considered in more detail as part
of the FMP development for the Lower Wairarapa Valley. For this reason, a term of approximately
12 years is proposed for the new dry gravel extraction consent for Area Two, to coincide with
expiry of resource consent WAR 070049 for flood protection works in the lower part of the
Wairarapa Valley on 30 September 2027.
17
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Figure 3: Adaptive management framework
18
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
2 Land ownership
Certificates of Title for the application area are included in Appendix B.
Further details to be added once titles are available
19
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
3 Mana whenua
There are two iwi with mana whenua6 status in the Wairarapa Valley: Ngati Kahungungu ki
Wairarapa and Rangitane o Wairarapa. The relationship that both iwi have to the rivers, wetland
and floodplains of the area is both physical and spiritual and encompasses interests that are both
historic and contemporary (Carter, 2014).
Rangitane o Wairarapa is represented by Rangitane o Wairarapa Inc., which is a mandated iwi
authority for purposes of the RMA. Kahungungu ki Wairarapa Inc. is a legally established
organisation responsible to the Ngati Kahungungu people of Wairarapa, which receives its
mandate to operate from the collective Ngati Kahungungu marae and hapu, known as Te
Kotaihitanga.
Both iwi are currently in the process of settling Treaty of Waitangi claims.
Prior to the arrival of Europeans, Maori had a clearly structured system of resource management.
Today tangata whenua seek to continue to manage resources in accordance with these traditional
practices and values. Kaitiakitanga is a holistic management framework for ensuring human
interaction with the natural environment occurs in a respectful way, consistent with the
whakapapa connections between all things. Exercised effectively, it ensures that resources are
utilised in a way that provides for both current and future generations and show respect for those
who came before (Carter, 2014). A key way that kaitiakitanga is given effect to is through the
interactions (both formal and informal) between tangata whenua and GWRC.
Formal interaction between tangata whenua and GWRC is currently conducted through the
following:
• A Memorandum of Partnership (MOP - which sets out the principles for conduct of the
relationship between tangata whenua and GWRC that stems from the Treaty of Waitangi
and is prescribed in legislation including the Treaty of Waitangi Act (1975) and the
Resource Management Act (1991).
• Ara Tahi Leadership Committee – a formal partnership of tangata whenua and council
leaders, dealing with high level and strategic issues
• Te Upoko Taiao – Natural Resource Management Committee – consisting of an equal
number of iwi nominated members and councillors, providing oversight of the
development and monitoring of regional plans and regulatory matters
• Ruamahanga Whaitua – one of five catchment based ‘whaitua’ or ‘zone’ groups set up in
response to the National Policy Statement on Freshwater Management 2011, to identify
water quality and flow limits and develop recommendations for their achievement.
• The Wairarapa River Management Agreement (2011) – an agreement between tangata
whenua and GWRC (Flood Protection Department), Department of Conservation and Fish
& Game NZ – to provide for an agreed way of working to support the monitoring and
improvement of recreation, cultural and wildlife values of the Waiohine, Waingawa,
Waipoua and Upper Ruamahanga Rivers while providing also for ongoing flood and
erosion protection work through their scheme reaches.
• The Gravel Guardians - a group to promote the sustainable management of gravel
resources, set up as a result of a protocol between the Wellington Regional Council,
tangata whenua and Federated Farmers that arose from the Council’s 2001 resource
consent for gravel extraction from the Ruamahanga River system. The protocol has now
expired.
6 Mana whenua refers to the people who have local tribal or sub-tribal authority over an area.
20
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
• The Te Kauru and Waiohine Floodplain Management Committees (which include iwi
representatives).
The adaptive management approach to this consent, described in Section 1.4 above, provides
another important way in which kaitiakitanga can be expressed. The proposed approach includes
a formal and on-going process of consultation with iwi, whereby information from environmental
monitoring and iwi experience and knowledge can be shared and discussed, and decisions made
as to changes to the COP over time.
21
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
4 River management context
The requirement to address the flood and erosion hazards associated with rivers is enshrined in
legislation7, with GWRC assuming responsibility for this function in the Wellington Region. Flood
protection and control works make up 6% (or $17.1 M) of GWRC expenditure for the current
(2014/15) financial year.
GWRC’s flood protection and erosion control programme and funding for the Region is outlined in
the Council’s Long Term Plan & Infrastructure Strategy and it is supported by Floodplain
Management Plans, Asset Management Plan and annual work programmes for individual river
management schemes. The level of service provided is determined by:
• the level of need as determined through a variety of processes, described further in the
following sections
• the need to maintain established flood protection assets
• agreed performance measures for individual river schemes, and
• the available funding.
Review of the level of service to be provided in future in the Upper Wairarapa and
Waiohine/Mangatarere catchments will be an outcome of the FMP processes. In seeking
authorisation for the toolbox of methods to be available for use in service delivery, GWRC is
seeking to enhance its ability to respond in an environmentally appropriate way to changes and
events in the river system that may occur over the life of the new consents, without the need to
continually seek variations for innovation and improvement in its management methods. This
approach is consistent with that adopted for GWRC’s applications for resource consents in other
rivers in the western part of the Wellington Region. It should be stressed also that making the full
toolbox available is not intended to create an expectation that all methods available in the
toolbox will necessarily be employed over the life of the consents.
4.1 River management schemes
To date the management of Wairarapa Rivers has been structured largely around individual River
Management Schemes, which are governed by individual Advisory Scheme Committees and
funded from a rating system that reflects both the direct benefits to the landowners from the
scheme (the ‘targeted river rate’) and the overall contribution that river management and
development on the floodplains make to the whole region (the general GWRC rate). GWRC
provides the management support for the Schemes and undertakes the work that is required, as
explained further in Section 4.4.
The river management schemes currently operating in the upper Wairarapa Valley (i.e.
Application Area One) are shown in Table 6.
7 GWRC has statutory responsibility for the minimising and preventing of flood and erosion damage under the Soil
Conservation and Rivers Control Act 1941 (sections 10 and 126), and avoidance or mitigation of natural hazards under
section 30 of the Resource Management Act 1991 (RMA). By definition, ‘natural hazards’ include flooding.
22
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Table 6: Upper Wairarapa Valley River Management Schemes – Summary information
Source: (Harley, 2014) and GWRC
8 Scheme reserves have been established to enable repairs to be made following flood events. The Scheme Reserves are utilised for floods in a 5 to 25 year return period.
9 The Major Flood Investment Reserve caters for flood events greater than a 25 year return period.
10 The Kopuaranga Scheme is still servicing the original loan taken out to initiate the scheme in 2007 and therefore has a negative scheme reserve.
Scheme Length
(km)
Year Established Annual Expenditure
(June 2013)
Value of Assets
(June 2012)
Scheme Reserve8
(June 2013)
Major Flood
Investment Fund9
Upper Ruamahanga – Mt Bruce 25 1982 (2001 - split) $123,900 $1,448,577 $80,034 $7,373
Upper Ruamahanga – Te Ore Ore 9 1982 (2001 - split) $151,000 $2,365,289 $192,919 $7,373
Upper Ruamahanga – Gladstone 24 1982 (2001 - split) $155,000 $2,796,066 $76,568 $7,373
Waipoua 18 1950's $108,500 $3,664,087 $94,807 $21,686
Waingawa 17 1992 $179,900 $1,415,406 $100,257 $21,686
Kopuaranga 27 2007 $23,346 $0 -$44,59310
$0
Whangaehu 9 1997 $6,979 $0 $10,123 $0
Taueru 17 1994 $5,500 $0 $10,351 $0
Waiohine/Mangatarere 17 1950s $346,400 $7,391,000 $589,030 $35,227
23
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
4.2 Floodplain management plans
A Floodplain Management Plan provides a wider and more comprehensive approach to river
management than the individual river management schemes allow. Floodplain Management
Planning is a three stage process involving extensive consultation with the whole community,
which aims to:
• understand the issues of the flood hazard posed to communities by a river or rivers, the
levels of risk to life and property and the conflicts between the flood hazard and the
activities and aspirations of the community
• engage with the community to identify options for management of these issues
• reach agreement on the implementation of sustainable measures for management of
these issues, based on an agreed level of flood risk.
Although not a statutory document, a Floodplain Management Plan is an important tool for
establishing the level of service desired or expected by a community in respect of river
management works, together with the methods of achieving this outcome and the environmental
values that must also be taken account of.
Currently, as noted in Table 5, FMPs are under development for the Waiohine/Mangatarere and
Te Kauru/Upper Ruamahanga catchments. Identification of a sustainable strategy for
management of the flood hazard and agreement on the governance structure and funding
arrangements around the current river management schemes going forward will be key outcomes
of these FMP processes.
4.3 Current river management strategies
Currently the primary goal in the management of Wairarapa gravel bed rivers is to maintain a
stable channel alignment through the establishment of a design channel ‘fairway’ with vegetative
buffers on either side. This is generally achieved with the use of both engineered structures and
vegetative systems, with a heavy reliance on the use of vegetation buffers to reduce lateral
erosion of the river bank and to absorb and/or redirect the energy of flowing water.
Significant work is carried out in the rivers using bulldozers, excavators and dump trucks to both
extract and move gravel around, both in channel and on the dry beaches, to achieve the design
alignment and to provide the opportunity and necessary condition to plant vegetation buffer
required to provide edge protection. Ripping of gravel beaches is also used extensively to manage
areas where gravel accumulation (which results in increased beach heights and island areas) puts
pressure on the opposite banks of outside bends. Ripping, which is done with bulldozers, breaks
up the hard compacted armour layer of the bed and allows the built up material to be mobilised
more easily during freshes (i.e. less than annual return period flood events) and larger floods.
(Harley, 2014) notes that there has been an improvement in consistency of approach over the last
few years in terms of working towards the established fairway/channel alignment design. The
ability to carry out planned work, is greatly affected by the flood events that occur during the
year. Since around 2006 large flood events have been relatively infrequent and this has meant
that maintenance programmes have not been interrupted, for the most part, by the need to
remedy flood damage. However, there is always the risk that a flood event will occur, which
severely damages work done over previous years to the scheme. This may affect the council’s
ability to work to a long term plan to achieve the designed management alignments.
4.3.1 Gravel extraction
The removal of excess gravel, by extraction, is also used as a method to assist with the
management of river capacity and alignment. This occurs mainly on the Ruamahanga, Waingawa,
24
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Waipoua Rivers and Waiohine, although limited extraction also occurs in a small section of the
Kaipatangata Stream to address a specific problem there. Gravel extraction from the rivers of the
Wairarapa Valley is managed directly by GWRC.
The benefits of a managed gravel extraction regime are to reduce river management costs and
improve the effectiveness of flood and erosion control works. However, over-excavation of
gravels or extraction from degrading river beds can create a risk of undermining of flood
protection and erosion control works. To achieve the correct management balance therefore
requires an ongoing review and monitoring programme, and an ability to target gravel extraction
in terms of location, quantity and timing. Where possible GWRC uses the commercial demand for
gravel as a means of excavating excess gravel that it needs removed for river management
purposes. To date this has worked well and GWRC has not had to undertake significant extraction
itself.
The current gravel management system in the Wairarapa has been in operation since 2001, when
GWRC obtained resource consent WAR 990026 to enable extraction ofgravel from the
Ruamahanga River system for river management purposes, and assumed responsibility for
managing gravel extraction by third parties undertaking the extraction on GWRC’s behalf via a
licensing process. Prior to this, individual extractors were required to obtain resource consents
for each extraction site.
The current process for gravel licencing involves the following steps:
• Extractor applies to GWRC for a “Gravel extraction licence”
• GWRC checks database to ensure it fits within the allowable extraction volumes
prescribed by resource consent WAR 990026
• A site visit is undertaken by the Extractor and River Supervisor, in order to identify areas
that have most benefit to river alignment
• GWRC issues a Licence – either long term, annual or one-off
The licence year runs from 1 July to 30 June in following year; extractors are charged an annual
licence fee and are required to submit a return each quarter specifying the extracted amounts.
These are used to calculate royalties payable (currently $1.30 per m3). Revenue from gravel
royalties is used to offset the costs of flood protection works pertaining relevant Scheme and the
costs of GWRC’s river monitoring survey work.
4.4 Development of annual works programmes
A works programme is prepared annually, prior to the start of the financial year on 1 July, for each
of the Wairarapa river management schemes11
according to the process outlined in Table 7.
Table 7: Annual works programme development process
Month Action Components
March/April Work Programme
draft
1. Inspections are carried out to identify condition ratings
for individual assets.
2. Scheme finances are examined and appropriate
operational budgets are set with consideration of
targeted rate increases, and flood reserve contribution
3. Scheme work budget allocations: A draft plan is set up
using typical expenditure for work types and budget is
11 Currently for the Upper Ruamahanga ,Waingawa, Waipoua Schemes and the Waiohine Schemes
25
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
allocated by river reach for channel work; planting;
spraying; etc. Only high priority/significant expenditure
jobs are itemised on the work programme
4. Engineer/Supervisor prioritise work from desktop
assessment, noting any critical jobs (e.g. priority channel
alignment or planting sites
5. Engineer/Supervisor conduct river inspections and/or
analyse helicopter photographs, and revise desk-top
programme draft.
6. Manager/Senior Engineer review: This provides a final
review of the draft programme. Note, this is required by
the River Agreement and must take into account
environmental considerations in the review.
May Work Programme
presentation to
Scheme Advisory
Committees
About 75% of the programme is generic, i.e. $ for planting, $ for
channel work O/H, etc. – without listing the site-specific locations
for expenditure. This is due to the nature of the work, which is
maintenance oriented – not permanent or capital.
The Scheme Committees are asked to pass resolutions:
(i) Accepting the annual and financial report presented
(ii) That the scheme has been maintained to the satisfaction of the
committee, and
(iii) Recommending to Council that the proposed annual works
budget and annual rate increase, if required
June/July Deferments noted
for next financial
year
This is any work that is noted during river inspections, during the
year, that is unable to completed, for a particular reason; or
anything that has been deferred due to budgetary constraints.
Flood
events
The programme of work for each river is reviewed following flood events to re-prioritise
works based on the effects of the event
26
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
5 Existing works and activities
5.1 Upper Ruamahanga River
The Upper Ruamahanga River exits the Tararua Ranges at Mount Bruce, and flows a total distance
of 58 km over the Wairarapa Plain to the Waiohine confluence.
The channel form changes from predominantly semi-braided in the upper reaches, through a
transition in the middle reaches to a single thread in the lower reaches. Significant geological
features influencing river regime and alignment are the gorges in the Mt Bruce area, the “Hidden
Lakes” slip, rock outcrops at Double Bridges and Rathkeale College, the Cliffs at Te Whiti and at
the Gladstone and Kokotau Bridges.
There has been a long history of river management associated with human settlement and the
desire for people to protect themselves and their assets from the threat of flooding. A river
control scheme was implemented in 1953 and during the next 20 years provided bank edge
protection and river alignment stabilisation, thereby reducing the incidence of flooding along
many sections of the River.
The Upper Ruamahanga River Control Scheme was established in 1982 and covers the length of
the Ruamahanga River from Mount Bruce downstream to the Waiohine confluence. The scheme
was designed to protect an area of about 2,760ha of rural land and a number of public utilities
using stopbanks, heavy bank protection, vegetation buffer zones and the Te Ore Ore grade-
control weir (which is no longer maintained).
A major review of the Scheme was undertaken in 2001/02 in response to a number of issues,
particularly the river management approach and rating classifications. This review resulted in the
Upper Ruamahanga Scheme being split into the three sections, noted in Table 6, in order to
improve scheme performance (undertake river management and structural works to appropriate
standards and meet reasonable ratepayer expectations) and rating equity (to better reflect levels
of benefit to different ratepayers/properties). These are discussed further in Sections 5.1.1 to
5.1.3 below.
5.1.1 Ruamahanga – Mt Bruce Scheme
Existing scheme assets comprise structures including stopbanks, debris fences and groynes,
together with willow plantings, with an estimated value of over $1.4M – see Table 6.
A design alignment based on a defined ‘fairway channel’ and with ‘buffer zones’ either side of this
was developed by consultant river engineer Gary Williams in the early to mid-2000s. The
alignment replicates a calculated natural meander pattern and geometry of the river within the
fairway channel. Once established, the fairway is kept clear of vegetation and debris through a
combination of machine clearance (bulldozer and excavator) and chemical spraying. The
establishment and protection of vegetated buffer strips along either side of the river bank is a key
activity in the management regime to support the establishment and maintenance of the both
design fairway and form of the active channel(s) within it.
Recent maintenance and operational works have been focused on maintaining the active channel
within the designated channel fairway through bed re-contouring and channel alignment works,
beach clearing and ripping, construction of rock/gravel groynes, and vegetation removal. Also,
the planted buffer zones have been maintained and additional planting and/or willow cabling
placed in areas subject to active bank erosion.
More detailed information is included in Appendix C, with plans showing the location of the
scheme and activities undertaken, and a table containing the work quantums.
27
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
5.1.2 Ruamahanga – Te Ore Ore Scheme
Existing scheme assets comprise structures including stopbanks, groynes, rip-rap, debris fences
(some of which are strengthened with rock heads) together with willow plantings, with an
estimated value of over $2.3M – see Table 7.
This scheme also uses a river design alignment supported by willow buffer zones as a principal
management tool. This is achieved and maintained through the use of bed re-contouring and
channel alignment works, beach clearing and ripping, construction of rock/gravel groynes
(particularly where local assets, such as Henley Lake, are in close proximity to the river and where
river re-alignment would significantly impact on these assets), and vegetation removal. Planting
and/or willow cabling is also placed in areas subject to active bank erosion.
More detailed information is included in Appendix C, with plans showing the location of the
scheme and activities undertaken, and a table containing the work quantums.
5.1.3 Ruamahanga – Gladstone Scheme
Existing scheme assets comprise structures including stopbanks, groynes, rip-rap, and debris
fences together with willow plantings, with an estimated value of over $2.7M – see Table 7.
This scheme also uses a river design alignment supported by willow buffer zones as a principal
management tool. More detailed information is included in Appendix C, with plans showing the
location of the scheme and activities undertaken, and a table containing the work quantums.
5.2 Waingawa River
The Waingawa River is a steep gravel bed river with a semi-braided channel form, originating in
the Tararua ranges and flowing to its confluence with the Ruamahanga River. The river is known
for its high energy and the river channel can be highly mobile throughout its plains reach. In this
latter area a number of active faults cut across the river, and these have displaced the river
channel over time. The floodplain of the main river is generally well defined by terraces, however
prior to the construction of stopbanks in the West Bush/Skeets Road area outflows during flood
events could occur to the Waipoua River and Masterton.
A series of floods in 1988 prompted affected landowners and the District Councils to request that
a river management scheme be set up. This led to establishment of the Waingawa River
Management Scheme in 1992. The Scheme covers a length of 17km, stretching from the
Atiwhakatu Stream to the Ruamahanga River Confluence downstream.
Over the first 15 years infrastructural assets were developed to mitigate erosion damage, course
change and flood hazard to Masterton town and floodplain. A significant aspect of the scheme
also involved the retirement of private land adjacent to the river for vegetation buffer zone
(achieved with financial incentives). Current scheme management is focused on the following
objectives:
• Establishment and maintenance of a defined channel fairway free of vegetation and
obstruction
• Establishment and maintenance of a continuous buffer zone of protective vegetation
along the fairway edges
• Sustainable gravel extraction
• Limitation of ‘heavy’ protection works to sites where serious river alignment or change of
course problems are developing
• Recognition of the importance of the river for recreation, and to enhance and extend
recreational access and opportunities in conjunction with the operation of the Scheme
28
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
• Recognition of the wildlife and fishery values of the river and maintenance or
enhancement of the wildlife and fish habitat within the management of the river and its
buffer zones.
Existing scheme assets comprise structures including stopbanks, groynes, rip-rap, and debris
fences together with willow plantings, with an estimated value of over $1.4M – see Table 7.
(Harley, 2014) notes that progress in establishing the current design fairway is ongoing, however
the current river channel is out of alignment with the design channel lines in several locations and
is approaching the outside buffer line at a few points along the scheme length. Channel re-
alignments, through a combination of bed and beach re-contouring and the use of gravel groynes,
is followed up with willow planting to continue development of the current design lines.
Over the last quarter of 2013 a series of freshes has led to increased bank erosion, particularly in
the reaches upstream of the Railway bridge leading to further deviation from the proposed design
alignment.
More detailed information is included in Appendix C, with plans showing the location of the
scheme and activities undertaken, and a table containing the work quantums.
5.3 Waipoua River
The Waipoua River has a catchment area of 149 km2. Originating in the Tararua Ranges, a large
part of the catchment is within the lower foothills of the range. The river has three major
tributaries: the Kiriwhakapapa, Mikimiki and Whakamoekau Streams, which join the Waipoua
River as it flows across the Wairarapa plain. The River then passes through the Masterton urban
area before discharging into the Ruamahanga River at Te Ore Ore.
The main river channel from its headwaters to its confluence with the Ruamahanga River is 30 km
in length. The river channel is characterised as a steep gravel phase river with a relatively stable
and narrow single thread channel. The Mikimiki reach and Masterton township reach have been
straightened, steepened and shortened.
Land use in the catchment is a mix of native forest in the upper catchment within the Tararua
Ranges, transitioning to a range of primary production activities (dairying, dry stock grazing,
cropping and plantation forestry), rural lifestyle development, and urban areas (Masterton) on
the floodplain.
Stopbanks in the Masterton urban area were first constructed in the 1940s, and the Waipoua
River Scheme was established in 1954 with the objective to mitigate flooding and erosion hazards
for rural land and the Masterton urban area. The scheme was designed to protect an area of
about 770ha from flooding and extends 18 km from the Mikimiki Bridge to the confluence with
the Ruamahanga River. Scheme assets consist of several lengths of stopbanks, rock groynes, rock
riprap, grade control weirs, and debris fences, in addition to vegetation buffer zones and
protective willow plantings. Table 6 indicates these have an estimated value of over $3.6M.
The Waipoua Scheme adopts the same “basic rural” channel management approach as the other
schemes noted above - namely maintaining a river fairway clear of vegetation while progressively
trying to establishing vegetated willow buffers margins on both banks. More detailed information
of recent work undertaken is included in Appendix C, with plans showing the location of the
scheme and activities undertaken, and a table containing the work quantums.
29
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
5.4 Kopuaranga River
The Kopuaranga River originates in the northern Wairarapa hill country to the east of Mount
Bruce, and its catchment covers 166 km². The river flows for 58 km before joining the
Ruamahanga River east of Opaki.
In its upper reaches across the Hastwells Valley, the river channel is entrenched. The river then
flows in a tightly meandering channel within a narrow valley that follows the line of the West
Wairarapa fault, before turning away from the fault line and following an old course of the
Ruamahanga River, in its lower reaches. The river joins the Ruamahanga River east of Opaki, at
Rathkeale.
The Kopuaranga floodplain contains a mix of soils formed from sandstone, limestone and
siltstone. Land use in the catchment is predominantly primary production activities (dairying, dry
stock grazing, cropping and plantation forestry) with a few scattered areas of native forest
throughout the catchment.
The Kopuaranga River Management Scheme covers 27km in length, from the bridge just
downstream of the Clark Memorial Domain at Mauriceville, to its confluence with the
Ruamahanga. It was established in 2007 in response to flood events in 2004 and 2005. The key
goal of the scheme was to fund the selected removal of willows within and near the river channel
which were impeding river flows, resulting in reduced channel capacity and more frequent
flooding, particularly on properties in the lower sections of the Kopuaranga catchment. The
Scheme also involves re-planting river banks with native and exotic species in the lower
catchment, and an on-going maintenance programme involving spraying or cutting willows as
required. Since the establishment of the Scheme, progressive removal and re-planting of willows
has been undertaken. More detailed information of recent work undertaken is included in
Appendix C. There are no structural assets located on the Kopuaranga River.
5.5 Whangaehu River
The Whangaehu River catchment covers 145 km2. The river, which is 32 km long, rises in steep hill
country near Ihuraua and flows south in a narrow valley for much of its length, before flowing
across the Te Ore Ore plains east of Masterton to join the Ruamahanga River.
The Whangaehu catchment contains a mix of soils formed from sandstone, limestone and
siltstone. Land use in the catchment is predominantly primary production activities (dairying, dry
stock grazing, cropping and plantation forestry) with a few scattered areas of native forest
throughout the catchment.
In the 1950s a 600m long diversion channel was excavated adjacent to the river’s confluence with
the Ruamahanga River to try to reduce the incidence of flooding. This diversion channel caused a
substantial amount of erosion, and to counteract it willows were planted in the diversion and the
original river course immediately upstream (a total length of about 1.5km).
In addition to this introduced planting, the river channel from the Ruamahanga confluence up to
the Masterton-Castlepoint Road was overgrown with self-established willows. These willows
physically blocked the channel, and encouraged silt deposition, reducing the river channel
capacity. Works were undertaken in 1997/98 to remove the largest areas of willows and debris
from the river channel.
The Whangaehu River Management Scheme was established in 1995 in response to worsening
flooding resulting from increased congestion of the river channel from willows and other debris.
It covers 9km in length from Castlepoint Road to the Ruamahanga confluence. The Scheme does
not contain any physical flood protection assets. The main works undertaken consist of an annual
30
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
spraying regime to control willow re-growth, with tree removal undertaken when required.
Limited pole planting to manage erosion near the confluence is also undertaken. More detailed
information of recent work undertaken is included in Appendix C.
5.6 Taueru River
The Taueru River is 69 km long and has a catchment area of 498 km2. In its lower reaches it has a
relatively low gradient with a meandering pattern. Soils in the catchment are derived from the
sandstone, limestone and siltstones of the eastern Wairarapa hill country. Land use in the
catchment is predominantly primary production activities (dairying, dry stock grazing, cropping
and plantation forestry) with a few scattered areas of native forest throughout the catchment.
The existing Lower Taueru River Scheme extends for a length of approximately 18 km from the
confluence with the Ruamahanga River just north of the Gladstone Road bridge upstream to a
location near the end of Te Kopi Road. It was established in 1994 to reduce the incidence of
flooding in this area due to excessive willow growth within the river channel.
Scheme works have comprised original removal of willows and debris, followed by spraying to
control re-growth and tree removal when required - which has many similarities to the
Whangaehu River Scheme. The Scheme does not contain any physical flood protection assets.
More detailed information of recent work undertaken is included in Appendix C.
5.7 Waiohine River
FP to provide further information – inside & outside scheme
5.8 Mangatarere Stream
FP to provide further information; for areas inside & outside scheme
5.9 Kaipatangata Stream
FP to provide further information
5.10 Enaki Stream
FP to provide further information – inside & outside scheme
5.11 Gravel extraction – Area One
5.11.1 Upper Ruamahanga catchment
The amount of gravel that can potentially be extracted for river management purposes under the
existing resource consent WAR 990026 is determined from bed level trends and gravel volume
changes which are derived from five yearly surveys of river cross-sections. The most recent
extraction limits are compared with the volumes that were actually extracted for the 2012/13
financial year in Table 8. It can be seen that over this year only 41% of the potentially available
volume was extracted.
31
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Table 8: Upper Ruamahanga catchment gravel extraction limits and extracted volumes 2012/13. Source: (Harley, 2014)
River/Reach Annual Maximum
Limit (m³)
Volume Actually
Extracted (m³)
Waingawa River 20,000 19,400
Waipoua River & Tributaries 4,000 2,466
Ruamahanga River - Upstream of Double Bridges 20,000 3,500
Ruamahanga River - Double Bridges to Wardells 40,000 14,157
Ruamahanga River - Wardells to Waiohine 50,000 15,715
TOTAL 134,000 55,238
Figure 4 shows the location of the main gravel extraction sites in the 10 years prior to 2014, along
with an indication of the extracted volumes. Figure 5 to Figure 7 shows further details of the
extraction history in the Waingawa, Upper Ruamahanga (Te Ore Ore reach) and Waipoua Rivers.
Boulder and gravel extraction has been undertaken at various locations within the Waingawa
River, but the Figures show that gravel extraction from the river over the last 20 years has been
significantly lower than the period through the 1980s. This reflects both a moratorium on
extraction in the reach between the road and rail bridges which was imposed by GWRC in 1992 to
reduce bed degradation, and introduction of the new gravel licencing system under WAR 990026
in 2001 which limited annual extraction to below 10,000 m3. Since then, extraction limits have
been increased, in 2005 and again in 2009, via variations of the resource consent.
It can also be seen that extraction rates from the Ruamahanga River upstream of the Te Ore Ore
bridge were significantly reduced in 1995/96 - this occurred when a new gravel extraction consent
was granted. This quantity was again reduced to its current rate of 5000 m3 in 2009 in response
to on-going concerns relating to the effects of gravel extraction.
Gravel extracted from the Waipoua River has generally been used much more locally to the river
than with gravel extracted from the Waingawa and Ruamahanga rivers. This means that demand
has been driven by what is being built in close proximity to the river at a particular time. The
extraction limit is currently 4000 m3/year based on a three yearly rolling average, which means
that this annual limit can be exceeded (by up to 25%) in any one year, as long as it does not
exceed 12,000 m3 for any three year period.
32
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Figure 4: Location of significant gravel extraction sites in the 10 years prior to 2014. Source: (Harley, 2014)
33
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Figure 5: Waingawa River Gravel Extraction 1977 – 2013. Source: (Harley, 2014)
Figure 6: Ruamahanga River – Te Ore Ore Reach Gravel Extraction 1979 -2013
34
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Figure 7: Waipoua River Gravel Extraction History 1998 -2013. Source: (Harley, 2014)
5.11.2 Waiohine River
FP to provide further information
5.11.3 Kaipatangata Stream
FP to provide further information
5.12 Gravel extraction – Area Two
FP to provide further information
35
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
6 Existing river environment
6.1 Geomorphology & sediment transport
Summary to be added
6.2 Hydrology
Summary to be added
6.3 Water quality
Summary to be added
6.4 Riparian vegetation
Summary to be added
6.5 Birds
Summary to be added
6.6 Aquatic vegetation
Summary to be added
6.7 Aquatic macroinvertebrates
Summary to be added
6.8 Fish
Summary to be added
36
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
6.9 Recreation
Summary to be added
6.10 Heritage & sites of cultural value
Summary to be added
6.11 Sites of cultural value
Summary to be added
7 Proposed works
7.1 Management approach
7.2 Activities
7.3 Gravel extraction
8 Consideration of alternatives
9 Assessment of environmental effects
10 Consultation
11 Statutory assessment
12 Proposed consent conditions
13 Conclusions
14 Applicability
This report has been prepared for the benefit of Greater Wellington Regional Council with respect
to the particular brief given to us and it may not be relied upon in other contexts or for any other
purpose without our prior review and agreement.
37
Resource Consent Applications for River Management Activities in rivers of the Upper Wairarapa Valley& for Dry Gravel
Extraction from selected river reaches in the Lower Wairarapa Valley
Greater Wellington Regional Council T&T Ref. 85484.004
Tonkin & Taylor LTD
Environmental and Engineering Consultants
Report prepared by: Authorised for Tonkin & Taylor Ltd by:
.......................................................... ...........................….......…...............
(Type Name here) (Type name here)
(Title) (Title)
pl
C:\Users\allana\AppData\Roaming\OpenText\DM\Temp\WGN_DOCS-#1441254-v1-Application_Document_-_Working_DRAFT_V3_-
_SENT_OUT_21-12-14.DOCX
Appendix A: Application Forms
Appendix B: Certificates of Title
Appendix C: River management scheme plans and work
records
• To be sourced from Harley (2014) – Appendix A
• WGN_DOCS-#1255672-UWVFMP Area - River Management
Expenditure (2003/04 to 2012/13)
Appendix D:
Appendix E:
Annex 1: Environmental Code of Practice &
Monitoring Plan (working draft)